Prepared by the Municipality of Kitaotao, Province of Bukidnon for the Department of Natural
Resources and the Asian Development Bank.
This Indigenous Peoples Plan is a document of the borrower. The views expressed herein do not
necessarily represent those of ADB's Board of Directors, Management, or staff, and may be
preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation
of or reference to a particular territory or geographic area in this document, the Asian
Development Bank does not intend to make any judgments as to the legal or other status of any
territory or area.
ii
CURRENCY EQUIVALENTS
(as of 29 August 2019)
Currency unit – peso (PhP)
PhP 1.00 = $ 0.019
$1.00 = PhP 52.27
ABBREVIATIONS
AD Ancestral Domain
ADSDPP Ancestral Domain Sustainable Development and Protection Plan
ADB Asian Development Bank
BDP Barangay Development Plan
BWFAI Bobong Watershed Farmers Association, Inc.
COE Council of Elders
DENR Department of Environment and Natural Resources
EMP Environmental Management Plan
GRM Grievance Redress Mechanism
ICC Indigenous Cultural Communities
IEC Information Education and Communication
INREMP Integrated Natural Resources and Environment Management Project
IP Indigenous People
IPMR Indigenous Peoples Mandatory Representative
IPP Indigenous Peoples Plan
IPRA Indigenous People's Rights Act
IRA Internal Revenue Allotment
LGU Local Government Unit
MOA Memorandum of Agreement
NCIP National Commission on Indigenous Peoples
NPCO National Project Coordinating Officer
NRM Natural Resources Management
RI Rural Infrastructure
RPCO Regional Project Coordinating Office
SPMU Sub Project Management Unit
SPS Safeguard Policy Statement
GLOSSARY
Affected person – Means any person or persons, household, firm, private or public
(AP) institution that, on account of changes resulting from the Project, will have
its (i) standard of living adversely affected; (ii) right, title or interest in any
house, land (including residential, commercial, agricultural, forest, salt
mining and/or grazing land), water resources or any other moveable or
fixed assets acquired, possessed, restricted or otherwise adversely
affected, in full or in part, permanently or temporarily; and/or (iii) business,
occupation, place of work or residence or habitat adversely affected, with
or without displacement. In the case of a household, the term AP includes
all members residing under one roof and operating as a single economic
unit, who are adversely affected by the project or any of its outputs.
Ancestral Lands – Refers to land occupied, possessed and utilized by individuals, families
and clans who are members of the ICCs/IPs since time immemorial, by
themselves or through their predecessors-in-interest, under claims of
individual or traditional group ownership, continuously, to the present
except when interrupted by war, force majeure or displacement by force,
deceit, stealth, or as a consequence of government projects and other
iv
voluntary dealings entered into by government and private
individuals/corporations, including, but not limited to, residential lots, rice
terraces or paddies, private forests, swidden farms and tree lots.
(Adopted from R.A. 8371)
Certification – It is a document issued by the NCIP attesting that the applicant or project
Precondition proponent has complied with the requirements for securing the consent
of affected ICCs/IPs in accordance to the Free, Prior and Informed
Consent Guidelines of 2006.
Customary Law – It refers to a body of written and/or unwritten rules, usages, customs and
practices traditionally and continually recognized, accepted, and
observed by the IPs.
Free and Prior – The consensus of all members of the affected IP group is to be
Informed Consent determined in accordance with their respective customary laws and
practices, free from any external manipulation, interference and coercion,
and obtained after fully disclosing the intent and scope of the activity, in
a language and process understandable and appropriate to the
community. Broad community support may exist even if some individuals
or groups object to the project.
Meaningful – A process that (i) begins early in the project preparation stage and is
consultation carried out on an ongoing basis throughout the project cycle; (ii) provides
timely disclosure of relevant and adequate information that is
understandable and readily accessible to affected people; (iii) is
undertaken in an atmosphere free of intimidation or coercion; (iv) is
gender inclusive and responsive, and tailored to the needs of
disadvantaged and vulnerable groups; and (v) enables the incorporation
of all relevant views of affected people and other stakeholders into
decision making, such as project design, mitigation measures, the
sharing of development benefits and opportunities, and implementation
issues.
v
TABLE OF CONTENTS
vi
LIST OF TABLES
Table 1: Sex-Disaggregated Data of the Project Influence Area per Ethnic Group ...................... 9
Table 2: Barangay Bobong Revenue and Expenditure ............................................................... 10
Table 3. Number of Participants in the Consultation Meetings during IPP Preparation .............. 13
Table 4. Summary of Consultation Meetings Conducted during the IPP Preparation ................ 13
Table 5. Summary Matrix of Impacts and Enhancement/Mitigation Measures ........................... 16
Table 6. Implementation Schedule of the IPP ............................................................................. 22
Table 7. Proposed Budget for the Implementation of the IPP ..................................................... 22
LIST OF FIGURES
Figure 1. February 2017 Field Validation Result of the Proposed Subproject .............................. 4
LIST OF APPENDICES
Appendix 1. Minutes of the Public Consultation held on August 08, 2017 at Bobong, Kitaotao,
Bukidnon ..................................................................................................................................... 24
Appendix 2. Internal Monitoring Indicators (Adapted from ADB’s Handbook on Resettlement: A
Guide to Good Practice, 1998) ................................................................................................... 37
Appendix 3. External Monitoring Indicators (Adapted from ADB’s Handbook on Resettlement: A
Guide to Good Practice, 1998) ................................................................................................... 39
Appendix 4. Executive Order Creating the SPMU for the Implementation of the Rehabilitation of
Bobong Access Road ................................................................................................................. 41
Appendix 5. Excerpt from the 2019 Municipal Annual Investment Plan ..................................... 43
vii
I. EXECUTIVE SUMMARY
1. This Indigenous Peoples Plan (IPP) intends to address the indigenous peoples’ (IPs’)
concerns/issues on the proposed Rehabilitation of Bobong Access Road in Barangay Bobong,
Municipality of Kitaotao, Bukidnon Province under the Integrated Natural Resources and
Environmental Management Project (INREMP). The subproject will involve the rehabilitation of
an existing access road with a total distance of 3.89 km comprising of three (3) components: (i)
re-graveling a length of 2.4 km; (ii) concreting a length of 402 m including the installation of a
concrete line canal along the existing 240-m concrete road, and (iii) concreting of a foot trail with
a length of 803 m with 1 m carriageway, 1 m shoulder on both sides, and 0.5 m concrete line
canal. The road will have a 4m carriageway, 1 m shoulder and 0.5 m earth/ concrete canal on
both sides. The subproject will be implemented by the Local Government Unit (LGU) of Kitaotao
with an estimated amount Php15,800,000.00 for the duration of 240 calendar days.
2. There are no ancestral domain claims in Barangay Bobong based on the NCIP’s data.
The proposed subproject will benefit 33% of the barangay’s total population or 208 IPs who belong
to the Manobo Tribe. Around 5% of the members of the people’s organization (PO) beneficiary of
INREMP’s Natural Resource Management subproject - Bobong Watershed Farmers Association,
Inc. (BWFAI), also belong to the Manobo Tribe.
3. Consultations with the affected IPs and PO were conducted by the LGU of Kitaotao,
Department of Environment and Natural Resources (DENR) - INREMP and its consultant on
February 8-10, 2017 and August 8, 2017. The information discussed in the meetings include (i)
subproject design; (ii) potential positive and negative impact of the subproject and (iii) proposed
measures to mitigate negative impact and enhance positive impacts. There was a total of 126
participants in the consultations, of which majority are IPs (38 female and 28 male).
4. The subproject is classified as Category B for IPs based on the ADB Safeguard Policy
Statement (SPS) 2009, given that the subproject has limited negative and positive impacts on the
Manobo Tribe that will be affected.
5. The proposed subproject will provide all year round easy and affordable access of basic
services, improving delivery of basic government services, reducing hauling and transportation
cost including travel time resulting to increase in family income, business and trade opportunities
and increasing economic opportunities and conditions for the upliftment of the quality of life of the
residents, especially the IPs/ Indigenous Cultural Communities (ICCs) of the Manobo Tribe. The
subproject will also support the Natural Resources Management (NRM) project activities of the
BWFAI. The participants during the consultations agreed with the subproject implementation
since it will have positive impacts on the IP community including (i) increased household income;
(ii) ease in the transport of produce to the market; (iii) enhanced access to healthcare and other
government services and (iv) provision of jobs to the IPs as contractual laborers. Proposed
measures to enhance the positive impacts include (i) provision of trainings on basic financial
management and support to the IPs who want to open a bank account; (ii) passage of a barangay
ordinance to regulate traffic flow, vehicular volume, hauling cost of farm produce to the market,
farm produce pricing and hauling cost of seedlings to farm/ plant sites; (iii) IEC and consultations
that will consider responsiveness and sensitivity to the traditional culture of the IP community; and
(iv) development of local first hiring policy, provision of skills training to the IPs and disclosure of
employment information.
6. Although there are no significant negative impacts identified during these consultations,
the beneficiaries of the subproject mentioned some concerns that may bring about negative
1
impacts to the community if not mitigated such as: (i) garbage; (ii) noise, dust, mud, smoke during
road rehabilitation; (iii) possibility of increase in road accidents upon completion of the
rehabilitation; (iv) demand for use of water supply and (v) possible negative impact on the IP
culture. During the consultations, the participants perceived that there will be no long-term
adverse impacts as long as mitigating measures to address these potential negative impacts are
implemented. The mitigation measures identified are: (i) compliance of the contractor on the
mitigation measures before, during and after construction as stated in the Environmental
Management Plan (EMP); (ii) the ordinances of the barangay LGU on speed limit and curfew
hours will be disclosed regularly and strictly implemented including installation of speed limit
boards along the road and (iii) any other development project that will be implemented as a result
of the rehabilitation of the road, the LGU will closely observed the process of engaging the IPs as
provided for under IPRA and NCIP Administrative Order No. 3. The LGU will also work closely
with the different schools to ensure that cultural revival and enhancement activities in the
community are observed in close coordination with the NCIP.
7. All participants in the meetings agreed and support the subproject implementation and
underscored the benefits that will be derived by the community in the rehabilitation of the access
road. The IP participants manifested the IP community’s preference for the conduct of a tribal
ritual before the implementation of the subproject.
9. The IPP implementation will be internally monitored by the LGU Sub Project Management
Unit (SPMU) and externally by an external monitoring agency (EMA). The EMA will submit semi-
annual reports to the DENR-INREMP through the National Project Coordinating Office (NPCO),
who in turn will submit the reports to ADB for review and disclosure.
10. In terms of capacity building initiatives, the municipality outlines various training with
respect to all affected IPs, including women and youth. These trainings are meant to be held
collectively for the tribe and/or the barangay at a time and place chosen by the participants and
will be specifically customized for each target participant. Training on IP related issues based on
ADB SPS and the Indigenous Peoples Framework of INREMP will be provided to the LGU. The
Municipality of Kitaotao allocated about Php 200,000.00 for support to IPs in collaboration with
other government agencies.
11. The estimated cost for the IPP implementation of the subproject is Php 40,000.00. This
cost will be covered from either INREMP and/or LGU funds activities.
1. The INREMP, implemented by DENR with funding from Asian Development Bank (ADB),
International Fund for Agricultural Development (IFAD), and Climate Change Fund (CCF),
addresses the unsustainable watershed management in four (4) priority river basins: (i) the Chico
2
Upper River Basin in the Cordillera Administrative Region, Northern Luzon; (ii) the Wahig–
Inabanga River Basin on the island of Bohol in Region 7; (iii) the Lake Lanao River Basin in the
province of Lanao del Sur in the Autonomous Region of Muslim Mindanao; and (iv) the Bukidnon
Upper River Basin in Bukidnon and Misamis Oriental provinces in Northern Mindanao (Region
10).
2. The INREMP has four (4) outputs namely: (i) River basin and watershed management
and investment plans established; (ii) Smallholder and institutional investments in conservation
increased and URB productivity enhanced in the forestry, agriculture and rural sectors; (iii) River
basin and watershed management capacity and related governance mechanisms strengthened;
and (iv) Project management and support services delivered.
3. Under Output 2, the LGU of Kitaotao, Bukidnon has proposed the Rehabilitation of Bobong
Access Road as one of the subprojects under INREMP. The subproject will involve the
rehabilitation of an existing access road with a total distance of 3.89 km comprising of three (3)
components: (i) re-graveling a length of 2.445 km; (ii) concreting a length of 402 m including the
installation of a concrete line canal along the existing 240-m concrete road and (iii) concreting of
a foot trail with a length of 803 m with 1 m carriageway, 1 m shoulder on both sides and 0.5 m
concrete line canal. The portions of the road which will be re-graveled and concreted will have a
4m carriageway, 1 m shoulder and 0.5 m earth/ concrete canal on both sides (Figure 1).
4. The road network is in a state of disrepair due to insufficient funds of the barangay. Farm
inputs and products coming out and other goods coming in are very difficult to transport during
rainy season since the most common mode of transportation is habal-habal. Farmers are obliged
to sell their farm produce to the nearby business district (Don Carlos) which is 25 km away at low
price rate due to high maintenance cost. The present road network is from Bobong to Barangay
Bershiba where the provincial road is located up to the paved national highway connecting the
Municipality of Don Carlos to the Municipality of Kadingilan. The populace of barangay Bobong
can reach Poblacion, Kitaotao via Don Carlos municipality with a distance of 25 km. The other
alternative route is from Barangay Bobong to Barangay Kauyonan passing through a hilly trail
and crossing the Muleta River through a foot bridge. Although this route is only nine (9) km away
going to the Poblacion, this would require opening and constructing of new access road and not
just mere road rehabilitation. This would also entail considerable amount of needed budget and
would greatly cover extensive areas which are classified as alienable and disposable areas.
5. The Bobong access road rehabilitation is much needed by the LGU of Kitaotao which
cannot afford to construct such project due to insufficient funds. The LGU has always been
seeking for financial assistance to address this problem of the populace. The farmers in the area
produce corn, sugarcane and other crops as their income sources. The rehabilitation of access
road will encourage the farmers to increase their production and also encourage them in
supporting programs initiated by the government. With the rehabilitation of the access road, the
farmers will be able to transport their farm produce at any time and at a lower cost.
3
Figure 1. February 2017 Field Validation Result of the Proposed Subproject
7. Based on Barangay Bobong’s 2016 BDP, it has a total population of 631 of which 343 are
males and 288 are females. The IPs in the barangay has a total of 208 individuals or 33% of
which 113 or 54% constitute the males and 95 or 46% are females. They are mostly residing at
Purok 1 and Purok 2 where the proposed subproject is located. These indigenous people belong
to the Manobo tribe. On the other hand, about 5% of the members of the PO of BWFAI also
belong to the Manobo Tribe.
4
III. SOCIAL IMPACT ASSESSMENT
8. In accordance to the Philippine law and ADB safeguards policy, all proposed subprojects
must undergo the procedures required in social impact assessment. This is to ensure that IPs will
benefit from a subproject, and that adverse impacts will be avoided, or where this is not possible,
can be mitigated. Looking at the Philippine history, the indigenous communities including the
original settlers in the country were deprived of their rights and displaced since the pre-
colonization. Many forms of injustices such as discrimination, marginalization and oppression to
the IPs continued even after the colonial rule. The injustices to the IPs pushed them to resist
projects intended to benefit them. With that, the rights of the IPs were recognized through the
passage of the Indigenous Peoples Rights Act (IPRA) law.
9. The ADB, Philippine Government and proponents shall recognize the vital role of IPs as
autonomous partners in development and shall fully support the development and empowerment
of indigenous people or associations to pursue and protect their legitimate and collective interests
and aspirations. Thus, all involved in the project will recognize, protect and promote the rights of
indigenous cultural communities/indigenous peoples establishing implementing mechanisms,
appropriating funds therefor, and for other purposes.
10. Under the Constitution of the Philippines a number of Articles have been included for the
protection of the indigenous cultural communities (ICCs). These are:
a. Article II of Section 22 recognizes and promotes the rights of indigenous cultural
communities within the framework of national unity and development.
b. Article XII of Section 5 empowers the State, subject to the provisions of this
Constitution and national development policies and programs, shall protect the rights
of indigenous cultural communities to their ancestral lands to ensure their economic,
social, and cultural well-being.
c. Article XIII of Section 6 confers the State shall apply the principles of agrarian reform
or stewardship, whenever applicable in accordance with law, in the disposition or
utilization of other natural resources, including lands of the public domain under lease
or concession suitable to agriculture, subject to prior rights, homestead rights of small
settlers, and the rights of indigenous communities to their ancestral lands.
d. Article XIV of Section 2(4) encourages non-formal, informal, and indigenous learning
systems, as well as self-learning, independent, and out-of-school study programs
particularly those that respond to community needs.
e. Article XIV of Section 17 stipulates that the State shall recognize, respect, and protect
the rights of indigenous cultural communities to preserve and develop their cultures,
traditions, and institutions. It shall consider these rights in the formulation of national
plans and policies.
f. Article XVI of Section 12 empowers the Congress to create a consultative body to
advise the President on policies affecting indigenous cultural communities, the
majority of the members of which shall come from such communities.
11. The Indigenous Peoples (IP) in the Philippines remain as the most marginalized sector of
society. This status continues despite the tremendous inroads achieved by communities, partners
5
and advocates through years of struggle. In 1997, as result vigilance and the sustained advocacy
of the IP sector and its partners, the Indigenous Peoples Rights Act (IPRA) was enacted. This
provided venues and legal backbone for the recognition of the Traditional Rights of communities
over their ancestral domain.
12. The IPRA provides for the recognition of the traditional rights of Indigenous Peoples over
their ancestral domains through the issuance of Certificates of Ancestral Domain Title (CADT). It
recognizes the rights of ICC’s to define their development priorities through their own Ancestral
Domain Sustainable Development and Protection Plan (ADSDPP) and exercise management and
utilize the natural resources within their traditional territories.
13. The NCIP AO 3 underscores the policy of the state that no concession, license, permit or
lease or undertaking affecting ancestral domains will be granted or renewed without going through
the free, prior and informed consent (FPIC) process, which is needed in the issuance of a
Certification Precondition by the National Commission on Indigenous Peoples (NCIP).
14. The DENR and NCIP entered into a Memorandum of Agreement (MOA) for the
implementation of INREMP to ensure that provisions of the NCIP Administrative Order No. 3,
Series of 2012 or the Revised Guidelines on Free and Prior Informed Consent and Related
Processes of 2012, are fully considered and complied.
16. ADB Policy on Safeguards requirement for Indigenous peoples recognizes the right of
Indigenous People to direct the course of their own development. Indigenous people are defined
in different countries in various ways. For operational purpose, the term Indigenous people is
used to refer to a distinct, vulnerable, social and cultural group with following characteristics:
a. Self-identification as members of a distinct indigenous cultural group and recognition
of this community by others;
b. Collective attachment to geographically distinct habitats or ancestral territories in the
project area and to the natural resources in the habitats;
6
c. Customary, cultural, economic, social or political institutions that are separate from
those of dominant society and culture; and
d. A distinct language, often different from the official language of the country or region.
17. According to ADB policy Indigenous people’s safeguards are triggered if a project directly
or indirectly affects the dignity, human rights, livelihood systems or culture of Indigenous people
or affects the territories, natural or cultural resources that Indigenous people own, use, occupy or
claim as their ancestral property.
18. The SPS sets out the following principles for IP safeguards in all projects in which ADB is
involved:
a. Screen early on to determine (i) whether Indigenous Peoples are present in, or have
collective attachment to, the project area; and (ii) whether project impacts on
Indigenous Peoples are likely.
b. Undertake a culturally appropriate and gender-sensitive social impact assessment or
use similar methods to assess potential project impacts, both positive and adverse, on
Indigenous Peoples. Give full consideration to options the affected Indigenous
Peoples prefer in relation to the provision of project benefits and the design of
mitigation measures. Identify social and economic benefits for affected Indigenous
Peoples that are culturally appropriate and gender and inter-generationally inclusive
and develop measures to avoid, minimize, and/or mitigate adverse impacts on
Indigenous Peoples.
c. Undertake meaningful consultations with affected Indigenous Peoples communities
and concerned Indigenous Peoples organizations to solicit their participation (i) in
designing, implementing, and monitoring measures to avoid adverse impacts or, when
avoidance is not possible, to minimize, mitigate, or compensate for such effects; and
(ii) in tailoring project benefits for affected Indigenous Peoples communities in a
culturally appropriate manner. To enhance Indigenous Peoples’ active participation,
projects affecting them will provide for culturally appropriate and gender inclusive
capacity development. Establish a culturally appropriate and gender inclusive
grievance mechanism to receive and facilitate resolution of the Indigenous Peoples’
concerns.
d. Ascertain the consent of affected Indigenous Peoples communities to the following
project activities: (i) commercial development of the cultural resources and knowledge
of Indigenous Peoples; (ii) physical displacement from traditional or customary lands;
and (iii) commercial development of natural resources within customary lands under
use that would impact the livelihoods or the cultural, ceremonial, or spiritual uses that
define the identity and community of Indigenous Peoples. For the purposes of policy
application, the consent of affected Indigenous Peoples communities refers to a
collective expression by the affected Indigenous Peoples communities, through
individuals and/or their recognized representatives, of broad community support for
such project activities. Broad community support may exist even if some individuals or
groups object to the project activities.
e. Avoid, to the maximum extent possible, any restricted access to and physical
displacement from protected areas and natural resources. Where avoidance is not
possible, ensure that the affected Indigenous Peoples communities participate in the
design, implementation, and monitoring and evaluation of management arrangements
for such areas and natural resources and that their benefits are equitably shared.
f. Prepare an Indigenous Peoples plan (IPP) that is based on the social impact
assessment with the assistance of qualified and experienced experts and that draw
7
on indigenous knowledge and participation by the affected Indigenous Peoples
communities. The IPP includes a framework for continued consultation with the
affected Indigenous Peoples communities during project implementation; specifies
measures to ensure that Indigenous Peoples receive culturally appropriate benefits;
identifies measures to avoid, minimize, mitigate, or compensate for any adverse
project impacts; and includes culturally appropriate grievance procedures, monitoring
and evaluation arrangements, and a budget and time-bound actions for implementing
the planned measures.
g. Disclose a draft IPP, including documentation of the consultation process and the
results of the social impact assessment in a timely manner, before project appraisal,
in an accessible place and in a form and language(s) understandable to affected
Indigenous Peoples communities and other stakeholders. The final IPP and its
updates will also be disclosed to the affected Indigenous Peoples communities and
other stakeholders.
h. Prepare an action plan for legal recognition of customary rights to lands and territories
or ancestral domains when the project involves (i) activities that are contingent on
establishing legally recognized rights to lands and territories that Indigenous Peoples
have traditionally owned or customarily used or occupied, or (ii) involuntary acquisition
of such lands.
i. Monitor implementation of the IPP using qualified and experienced experts; adopt a
participatory monitoring approach, wherever possible; and assess whether the IPP’s
objective and desired outcome have been achieved, considering the baseline
conditions and the results of IPP monitoring.
19. The section describes general socio-economic profiles of the IPs in Barangay Bobong.
The information was collected from the 2015 PSA survey which became the basis of Barangay
Bobong’s 2016 Barangay Development Plan (BDP).
20. To ensure that a baseline data of the IPs is obtained to be able to monitor and evaluate if
all the impacts by the subproject are effectively managed, a data gathering on the IPs will be
conducted before monitoring. Similarly, the LGU will also gather available baseline information
from the Municipal Social Welfare and Development Office (MSWDO), Municipal Health Office
(MHO), and Municipal or Barangay Indigenous People’s Mandatory Representative’s (IPMR)
Offices.
1. Population
21. Table 1 shows that Barangay Bobong has a total population of 631 of which 343 are male
and 288 are female. The IPs in the barangay has a total of 208 individuals or 33% while the
Cebuanos total 423 or 67%. Among the IPs, 113 or 54% constitute the male and 95 or 46% are
female and among the Cebuanos, 230 or 54% comprise the male and 46%, the female. Given
the 2016 total population of 631 and the total land area of 1,597 ha, the population density for
2016 is 2.53 or 3 persons per ha. The common medium of communication in the barangay is
Cebuano, just like in other barangays of the municipality. Although there are Manobos in the area,
still Cebuano is the commonly used language by the people of Barangay Bobong.
8
Table 1: Sex-Disaggregated Data of the Project Influence Area per Ethnic Group
Ethnic Groups No. of Population
Male Female Total Percentage
Cebuano 230 193 423 67%
Manobo 113 95 208 33%
TOTAL 343 288 631 100%
Source: 2016 BDP of Barangay Bobong
22. The Manobo is a group of IPs that inhabit most of Mindanao Island. The anthropologist E.
Arsenio Manuel believed that the proto-Manobo were the original people of Mindanao and this
explains why they are scattered throughout Mindanao, including the Agusan provinces, Bukidnon,
Cotabato provinces, Davao provinces, and Sarangani1. There are several subgroups among the
Manobo due to linguistic and cultural differences. The Manobo speak a language categorized into
three (3) dialects, namely Ilentungen, Kiriyenteken, and Pulangiyen. Livelihood of the Manobo is
land-based including upland cultivation of rice, corn, legume, yams, and sweet potato, hunting
and food gathering. Their settlements are generally kin-oriented nuclear groups located along
mountain ridges.
23. Although there are no ancestral domain claims in Barangay Bobong based on the NCIP’s
data, the proposed subproject will benefit 33% of the barangay’s total population or 208 IPs who
belong to the Manobo Tribe. Around 5.13% of the members of the people’s organization (PO)
beneficiary of INREMP’s Natural Resource Management subproject—Bobong Watershed
Farmers Association, Inc. (BWFAI), also belong to the Manobo Tribe.
3. Education
24. Due to the geographic location and considerable number of school age population, the
Bobong Elementary School has been established at the barangay proper catering school children
from its four (4) puroks/sitios. There is also a Day Care center for pre-school children. Currently,
the elementary school has 109 students of which 33% or 26 students are IPs while the Day Care
has 22 IP students. For the secondary education, some children proceed to high school at the
nearest school located at Masimag, Municipality of Don Carlos since it is more accessible, around
16 km away from the barangay.
25. Due to lack of access to decent affordable housing, poor residents are forced to live in
makeshift dwellings. Observations revealed that relocation or the provision of residential lots or
housing units for the poor segment of population has not been successful because of low financial
affordability level. The average proportion of 27% or 35 households are living in informal
settlements or makeshift houses. At present, the barangay allocated 1 ha lot for the provision of
residential houses for the low-income families of the barangay through the assistance of the
provincial government. The major economic activity in the barangay is on agriculture, wherein
100% of the people are engaged in farming. Some of the IP residents of the barangay are working
9
in Dole, Philippines located at Don Carlos, Bukidnon while others are working in sugar plantations
in the area and other nearby barangays.
26. Barangay Bobong has a total tax revenue of Php 1,537,827.61 in 2015 which is derived
from the Internal Revenue Allotment (IRA), share on real property tax, business tax, share on
community tax, clearance & certification fee, miscellaneous income, grants and donations. Table
2 shows the three (3) year comparative tax revenues and expenditures of Barangay Bobong.
27. Barangay Bobong at present is IRA dependent. Without this allotment, the barangay could
not implement any PPAs intended for them. Evaluating the tax revenues including the IRA against
the expenditures of the barangay, it was observed the surplus could not contribute any
considerable amount or budget for the rehabilitation of Bobong access road. As mentioned above,
some IP residents of the barangay are working at Dole Philippines and according to the LGU, has
a monthly salary of around Php 8,788.00. However, the IPs hired in sugar plantations are usually
during planting and harvesting seasons only.
28. Based on the Community Base Monitoring System (CBMS) survey in the municipality of
Kitaotao in the year 2008, the annual per capita food threshold and per capita poverty threshold
of Barangay Bobong is Php 8,675.00 and 10,450.00 respectively. This would mean that 60% of
the people in barangay Bobong live below the given food and poverty threshold.
30. The consultations which involved the key stakeholders are discussed in the succeeding
sections.
10
D. Gender-Sensitive Assessment of IP Perceptions
31. During the IPP preparation, consultations with both IP men and IP women regarding the
impacts on the IPs by the subproject implementation were conducted on August 8, 2017. To
ensure that the gender perspective is addressed, 57% or 54 IP women were also consulted during
this activity out of 95 IP women living in Barangay Bobong based on the 2016 BDP of the
barangay. Significantly, the women have also been consulted regarding their perspective on the
subproject’s anticipated impacts on their livelihood, travelling, transportation of inputs/outputs of
farming, etc., and corresponding measures to mitigate the adverse impacts as well as to enhance
the positive impacts.
32. The proposed subproject will encourage the involvement of both the males and females.
New employment opportunities for the subproject during the construction phase will be created
for both IP men and women. Men are to carry out manual and unskilled tasks while women can
work as a timekeeper, caretaker of the bunkhouse or to check the attendance of the workers.
Moreover, increased productivity, increase in additional income and more opportunities for IP
women are the tangible benefits to women with the proposed subproject. Reduction in
transportation costs will translate into extra cash for women who do the family budget. Saved
extra cash can be spent to other needs of families such as healthcare and education. Ease of
transport will directly impact on the improved safety and health of women and children, as
healthcare services will be more accessible.
33. The women will also be involved in the planning, consultation, monitoring and evaluation
activities as well as during the operation and maintenance of the completed subproject.
34. During the consultation with the IPs and other stakeholders during the IPP preparation,
the participants identified the positive impacts and possible negative impacts of the subproject on
the IPs. With reduction in the post-harvest losses, travel time, hauling and fare costs once the
road will be rehabilitated, household income will likely increase. This will in turn provide the
community, including the IPs, opportunities to engage in other sources of income and will also
generate more employment for farm workers from outside investors. To ensure that the possible
negative impact of increased household income among the IP communities is managed, trainings
on basic financial management will be made part of the capability building intervention. Further,
IP families who would want to avail of services on how to open a bank account will be assisted
by the LGU in close coordination with NCIP.
35. Once the road is rehabilitated, hauling of farm inputs and farm produce such as high-value
crops, root crops, corn and abaca will be easily transported to the nearest market once the access
road is rehabilitated. It will most likely boost the cycle of economic activities in the influence area;
hence, public utility vehicles may also increase their number of trips to serve the increasing
demand of transportation services. The barangay LGU can come up with an ordinance to regulate
the traffic flow, vehicular volume and transportation/ hauling cost of farm produce to the market.
The SPMU can provide the necessary inputs/ training/ guidance on this to the barangay.
36. During the public consultation, a participant said that emergency situations could easily
be responded to due to the rehabilitation of the road. In the same manner, Health Service
Providers can easily disseminate and acquire vital information on health issues and respond to
concerns on time. Government agencies including the LGU will be able to regularly visit and
11
monitor the area to deliver the needed services particularly provision of skills trainings and
capability building to enhance the IP community’s capacity to engage in livelihood, financial
assistance and marketing linkages. Due to this, the IEC and consultations that will be conducted
will consider responsiveness and sensitivity to the traditional culture of the IP community.
37. To enhance the positive impacts, trainings on other sources of livelihood will be provided
to the IPs according to their interest, this activity will be made part of the capability building
program. With the provision of job hiring scheme in the implementation of the subproject, “local
first hiring policy” will be developed to ensure that hiring of local IP laborers and workers including
women must be prioritized through Memorandum of Agreement (MOA) between Contractor and
the procuring entity. Provision of priority for IP laborers will be included in the contractor bidding
documents and civil work contracts. Recruitment information should be disclosed to local people,
including IPs, by being posted in tribal halls and barangay Bobong office or be informed to the IPs
by the CoE. During the consultation meeting, the women participants perceived that they could
be the timekeeper, caretaker of the bunkhouse or to check the attendance of the workers.
Additionally, skills training will be provided to the IPs so that they can have better opportunities to
be qualified for employment. IEC materials will be prepared in English and the language spoken
by and understandable to the IPs.
38. Although there are no significant negative impacts identified during these consultations,
the beneficiaries of the subproject mentioned some concerns that may bring about negative
impacts to the community if not mitigated such as: (i) garbage; (ii) noise, dust, mud, smoke during
road rehabilitation; (iii) possibility of increase in road accidents upon completion of the
rehabilitation; (iv) demand for use of water supply and (v) possible negative impact on the IP
culture. During the consultations, the participants perceived that there will be no long-term
adverse impacts as long as mitigating measures to address these potential negative impacts are
implemented. The mitigation measures identified are: (i) compliance of the contractor on the
mitigation measures before, during and after construction as stated in the Environmental
Management Plan (EMP); (ii) the ordinances of the barangay LGU on speed limit and curfew
hours will be disclosed regularly and strictly implemented including installation of speed limit
boards along the road and (iii) any other development project that will be implemented as a result
of the rehabilitation of the road, the LGU will closely observed the process of engaging the IPs as
provided for under IPRA and NCIP Administrative Order No. 3. The LGU will also work closely
with the different schools to ensure that cultural revival and enhancement activities in the
community are observed in close coordination with the NCIP. During the consultation, the
barangay’s Indigenous Peoples Mandatory Representative (IPMR), Datu Mario A. Sulatan, said
that the subproject will not have any negative impact on the IP’s culture. However, he simply
emphasized the need to have a ritual before the project starts. He also said that there are no
important cultural or archeological sites in the subproject area.
39. During the IPP preparation, three (3) public consultations/meetings in Barangay Bobong
were conducted with the IP communities and relevant stakeholders by DENR/INREMP and
Community Environment and Natural Resources Office (CENRO) Don Carlos and LGU of
Kitaotao. The consultations provided venue for the discussion of the subproject description,
proposed civil works and the anticipated positive and negative impacts and corresponding
measures to mitigate the negative and enhance the positive impacts. All the participants
12
confirmed that the Rehabilitation of the Bobong Access Road is essential for the economic
development of Barangay Bobong.
40. As mentioned, 57% or 54 IP women were also consulted out of 95 IP women living in
Barangay Bobong based on the 2016 BDP of the barangay. The women have also been consulted
regarding their perspective on the subproject’s anticipated impacts on their livelihood, travelling,
transportation of inputs/outputs of farming, and corresponding measures to mitigate the adverse
impacts as well as to enhance the positive impacts.
41. The table below summarizes the consultation activities which were carried out during the
IPP preparation.
42. On February 8-10, 2017, the INREMP technical team arrived at the Municipality of
Kitaotao and initiated an orientation with the LGU of Kitaotao, SPMU and field implementing units
to discuss the objectives of the visit. After the orientation, a site inspection was conducted to
validate the scope of works and location of the subproject. A write shop subsequently conducted
which was attended by the Local Chief Executive, SPMU and INREMP focal persons.
43. On August 8, 2017, another public consultation meeting with the assistance of the
consultant was conducted with the IP communities, officers and members of BWFAI in the
subproject area by DENR/INREMP and CENRO Don Carlos and LGU of Kitaotao. All in all, a total
of 126 participants participated in the meetings, of which women account for 48%. Among 126
participants, 66 or 52% belong to the Manobo Tribe.
44. The consultations were conducted in the Cebuano and binukid language which are both
understood and spoken by the Manobo and the discussions were documented. The minutes of
the meeting is attached in Appendix 1. The results of the consultation were positive, with local
people considering that the road rehabilitation will bring significant economic benefits to the
barangay and increase trade flows.
45. The table below summarizes the concerns and opinions raised by the participants during
the consultation meetings and how the concerns and opinions have been addressed.
13
Opinions, Suggestion and Concerns How the Opinions, Concerns and
Issues
Raised by the Participants Suggestions have been Addressed
the installation of a concrete line canal
along the existing 240-m concrete road
and (iii) concreting of a foot trail with a
length of 803 m with 1 m carriageway,
1 m shoulder on both sides and 0.5 m
concrete line canal. The portions of the
road which will be re-graveled and
concreted will have a 4m carriageway,
1 m shoulder and 0.5 m earth/ concrete
canal on both sides.
Is the subproject area in the ancestral No ancestral domain claims based on
domain area? the data from the NCIP. This has been
confirmed also by Engr. Umali.
Anticipated With reduction in the post-harvest
positive losses, travel time, hauling and fare
impacts and costs once the road will be
proposed rehabilitated, household income will
measures to likely increase. This will in turn provide
enhance the the community, including the IPs,
positive opportunities to engage in other
impacts sources of income and will also
generate more employment for farm
workers from outside investors.
Hauling of farm inputs and farm
produce such as high-value crops, root
crops, corn and abaca will be easily
transported to the nearest market once
the access road is rehabilitated.
emergency situations could easily be
responded to due to the rehabilitation
of the road. In the same manner,
Health Service Providers can easily
disseminate and acquire vital
information on health issues and
respond to concerns on time.
Government agencies including the
LGU will be able to regularly visit and
monitor the area to deliver the needed
services
Most of the IPs in the subproject area Employment priority will be given to the
who are unskilled labors wondered IPs in the barangay. Skills training will
whether they are employed by the be provided to the IPs so that the IPs
construction contractor(s). have better opportunities to be qualified
for employment.
Information on recruitment will be
posted in accessible places.
Anticipated During the construction phase, there The beneficiaries suggested that the
negative will be some environmental impacts contractor should have its own
impacts and such as noise, dust, obnoxious gas and compost pit and should practice
proposed particulate emissions, spilling diesel, segregation and composting of bio-
measures to solid waste, including garbage, etc. degradable and non-biodegradable
mitigate the caused by the construction activities. garbage. During the public
consultation, the Barangay Chairman
14
Opinions, Suggestion and Concerns How the Opinions, Concerns and
Issues
Raised by the Participants Suggestions have been Addressed
negative said that they have an ordinance
impacts regarding proper disposal of wastes.
These environmental impacts and
corresponding measures to mitigate
the impacts will be incorporated into the
EMP and the construction contractor(s)
will be required to comply with the
measures specified in the agreed
documents. Additionally, the barangay
LGU and IP community will monitor the
implementation of the measures.
Road accidents might increase due to The Barangay Chairman pointed out
over speeding of all vehicles passing that the barangay officials will formulate
by the residential areas. ordinances relating to speed and cargo
load limit.
Demand for use of water supply – both According to the participants, this
potable and non-potable particular aspect is not of any concern.
They added that, regarding the need
for non-potable water, the contractor
may just get the water from the nearest
spillway where the subproject will also
start.
Loud noise of trucks and equipment in The contractor will avoid night-time
the community especially at night might construction works considering also
cause disturbance at nighttime. that the barangay has an existing
ordinance on the observance of curfew
starting at 10:00 PM
The subproject causes no impact on The construction contractor(s) with
the IP culture, the participants, support from the Council of Elders will
however, emphasized the need to have conduct a ritual before the rehabilitation
a ritual before rehabilitation starts. activities commence.
Grievance Complaints of any member of IP
redress community will be resolved following
mechanism customary dispute resolution process
within the community.
Implementation How long will the road rehabilitation It takes about 8 months to complete the
schedule activities complete? road rehabilitation.
The IPs hope to be informed when the The implementation schedule of the
construction works start or the subproject, especially of construction
conduct of a pre-construction meeting activities will be updated to the IP
with the community community regularly.
EMP = Environmental Management Plan; IPs = Indigenous Peoples; IPMR = Indigenous Peoples Mandatory Representative; LGU =
Local Government Unit
B. Information Disclosure
46. The final IPP, updated IPP, if any, internal and external monitoring reports will be
submitted to ADB for posting on their website, DENR-Forest Management Bureau (FMB), the
LGU of Kitaotao, and the affected barangay office, DENR regional office, which will make them
15
available to the public in English or Pilipino and made available and accessible, posted if
possible, in public places such as barangay halls.
47. The table below presents the subproject impacts and corresponding enhancing and
mitigative measures identified by the beneficiaries during the consultation.
16
Subproject Impacts Enhancement or Targets Responsible Unit Estimated Cost
Mitigative Measures
Disclosure of
employment information
in accessible places such
as barangay offices,
DENR regional office and
tribal halls.
NEGATIVE IMPACTS
Garbage As mitigation measures Contractor(s) Construction Included in the
proposed in the EMP. contractor(s) budget of EMP
The barangay LGU and LGU of Barangay
the SPMU should closely Bobong
monitor the SPMU
implementation of the
contractor(s).
Noise, dust, mud, As mitigation measures Contractor(s) Construction Included in the
smoke during road proposed in the EMP. contractor(s) budget of EMP
rehabilitation. The barangay LGU and LGU of Barangay
the SPMU should closely Bobong
monitor the SPMU
implementation of the
contractor(s).
Possibility of increase Formulation and regular All residents LGU of Kitaotao Included in the
in road accidents upon disclosure of the speed and/ or LGU of budget of the
completion of the limit ordinance Bobong Municipal or
rehabilitation. Provision of speed limit Barangay LGU
boards along the road
Possible negative Conduct of a ritual prior All residents Construction For the ritual,
impact on the IP to the start of contractor(s) included in the
culture construction activities. Council of Elders contractor’s
Cultural revival and LGU of Kitaotao budget
enhancement activities in (estimated to be
the community. around Php
7,000). For
cultural revival,
included in the
budget of LGU
of Kitaotao
48. Based on the consultations conducted, certain training interventions are needed to ensure
that the community beneficiaries – both IPs and non-IPs and the barangay and Municipal LGUs
are knowledgeable and equipped with the appropriate information and skills to be able to execute
their roles in the implementation of the subproject. The capacity building initiatives for the
community are outlined with respect to all affected IPs including women and youth. These
trainings are meant to be held collectively for a tribe or barangay at a time and place chosen by
the participants and would be specifically customized for each target participant. The skills training
modules should be in their vernacular language.
49. Before arranging skill development trainings, the IP community will be organized for
orientation workshop by designated person in the SPMU with possible assistance from a non-
government organization/academe staff in the locality on expected subproject output, benefits
17
and needed skills to enhance the positive impacts and mitigate the negative impacts. The
orientation program will comprise sessions on development of the human capital especially
women and youth groups by acclimatizing them to the oncoming opportunities, enhancing
traditional and other learned skills and empowering them in a socio-culturally beneficial and
appropriate manner. Specific trainings will be identified in the orientation workshop and will be
organized at various suitably located place as per convenience of the IP community.
50. In terms of capacity building initiatives, the municipality outlines various training with
respect to all affected IPs, including women and youth. These trainings are meant to be held
collectively for the tribe and/or the barangay at a time and place chosen by the participants and
will be specifically customized for each target participant. Training on IP related issues based on
ADB SPS and the Indigenous Peoples Framework of INREMP will be provided to the LGU. The
Municipality of Kitaotao allocated about Php 200,000.00 for support to IPs in collaboration with
other government agencies.
51. The estimated cost for the capacity building activities will be source from the municipality’s
General Fund in which the Implementing Office is the Municipal Mayor’s Office as indicated in the
LGU’s 2019 Annual Investment Plan particularly on the Support to Indigenous People. It is hoped
that INREMP funds can be provided to support other capacity building initiative that may be
needed during the course of subproject implementation.
52. The LGU of Kitaotao has properly conducted the consultations with the different
stakeholders of the subproject site. However, it still has to make room for possible issues,
concerns, or grievances and disputes arising from the communities in relation to the subproject
implementation. Thus, it sets up a grievance redress mechanism (GRM) to provide a venue for
resolving grievances and disputes even at the lowest level. This will be done to resolve disputes
as early and as quickly as possible before it escalates to an unmanageable level.
53. The GRM set up by the LGU of Kitaotao generally applies when the parties involve are
non-IPs. In such a case, the BDC through the Lupon Committee will be the first group to be
approached by the aggrieved party for any complaint. In case either group cannot resolve the
matters at their level, they shall make proper documentation of the case and submit the same to
the Municipal Development Council (MDC). The MDC will be the body to resolve the grievances
endorsed to them by the BDC. In case the MDC is not able to resolve the disputes, the
Complainant may then submit his/her complaint directly to the PPMC for INREMP, which will
make every attempt to resolve the grievances at the local level. Lastly, if the complaint is not
addressed to the satisfaction of the complainant and/or the public, the Complainant may then
submit his/her complaint directly to the appropriate courts who will make every attempt to resolve
the problem.
54. Meanwhile, as traditionally done, complaints of any member off the IP communities
regarding the subproject implementation, including the IP issues will be addressed within the
community itself in the context of their customary law and customary dispute resolution process.
In resolving disputes among the IPs in the subproject area, the determination or decision is usually
reached through dialogue and consensus. There may be several conflict resolution sessions
according to the specific tribe’s customary laws before the dispute is resolved. Thus, there is no
clear definite timeline on when the conflict or dispute should be settled at the level of the clan and
the Council of Elders (CoE). The contact person for all disputes concerning IPs will be the Tribal
18
Chieftain of Barangay Bobong, Datu L. Aboy, and the barangay’s IPMR, Datu Mario A. Sulatan.
They could only be contacted through the Barangay Chairman’s contact number – 09554477719.
56. Complainants shall be exempted from all administrative and legal fees incurred pursuant
to the grievance redress procedures. The LGU of Kitaotao and the Barangay LGU will maintain
proper documentation of all complaints received and actions taken. Monthly reports on all
complaints, disputes or questions received about the subproject and corresponding actions taken
to resolve the issues will be prepared by the SPMU. These reports will be included in the semi-
annual internal monitoring reports to be submitted to ADB.
57. The IPP implementation will be monitored to (i) ensure that mitigation measures designed
to address adverse social impacts and enhance positive impacts are adequate and effective; (ii)
determine if there are any emerging issues and concerns of the IP community regarding the
subproject implementation; and (iii) propose corrective actions when needed.
A. Internal Monitoring
58. The DENR will set up an internal monitoring system comprising of an IP Safeguard Officer,
IP community and representative of the affected IPs through their respective tribe and any other
social institutions to monitor the IPP implementation. For daily monitoring of IPP, the Regional
Project Coordinating Office (RPCO) will engage one dedicated person at community level, who
will interact closely with the affected IP community on a priority basis. The staff will also disclose
project information, and IP activities and program schedule. The RPCO will also observe progress
at construction site and make plan of activities in accordance with IPP schedule in advance. The
Implementing RPCO field person will monitor this activity. The Social Safeguards Expert will
provide guidance to the RPCO, IP Safeguard Officer to carry out the tasks. Periodic internal
monitoring report will be prepared by the IP Safeguard Officer.
59. The Council of Elder (CoE) may form one participatory monitoring group from a community
who will monitor implementation activities including IPP and civil construction works. This
community level participatory monitoring group will be trained by the RPCO who will work in close
association with the community group and give necessary feedback to support internal daily
monitoring and supervision of subproject construction and IP activities.
60. The indicators for internal monitoring of the IPP implementation is presented in Appendix
2.
19
B. External Monitoring
61. An external monitoring agency (EMA) will also be engaged by the DENR. The EMA will
be either a qualified individual or a consultancy firm with qualified and experienced staff. Activities
to be undertaken by the EMA are as follows:
conduct a socio-economic baseline survey;
verify results of internal monitoring;
verify and assess the results of the subproject IEC for IPs and non-IPs;
assess efficiency, effectiveness, impact and sustainability of IPP implementation;
suggest modification in the implementation procedures of the IPP if necessary, to
achieve the principles and objectives of the INREMP IPPF; and
review of the handling of compliance and grievances cases.
62. The indicators for external monitoring of the IPP implementation is presented in Appendix
3.
C. Reporting
63. The RPCO will submit quarterly monitoring report to NPCO. The NPCO will consolidate
all reports and will prepare periodical reports for submission to ADB. In addition, NPCO will
prepare semi-annual social safeguards monitoring report (SMR). The EMA will submit semi-
annual reports to NPCO, who in turn, will be responsible for submitting the SMRs to ADB for
review and disclosure. Monitoring reports will be uploaded on the ADB and INREMP websites for
disclosure.
64. Department of Environment and Natural Resources (DENR) is the executing agency
for the INREMP and DENR has full responsibility for Project administration and management. The
National Project Coordinating Office (NPCO) has been established at the DENR Central office to
oversee the project implementation, including all safeguards compliance and technical support in
the preparation and implementation of the IPP. The tasks of NPCO are to:
Coordinate with NCIP and field implementing units in the preparation, planning, and if
needed, revision of the IPP;
Monitor the IPP implementation and fund disbursement;
Address grievances filed at its offices by the IPs for conflict mediation if these are not
resolved at the regional level; and
With NCIP, amend or complement the IPP in case problems are identified during the
internal and/or external monitoring of its implementation.
65. LGU of Barangay Bobong and the Bobong Watershed Farmers Association, Inc. will be
responsible to:
Support the LGU of Kitaotao in the IPP implementation;
Facilitate consultations with the IPs;
Conduct information disclosure of the subproject including posting the relevant
documents in accessible places and delivery of IEC materials to the IPs;
Coordinate with the SPMU in monitoring the implementation of the proposed
measures as specified in the approved IPP and follow up the resolution of complaints
and grievances raised by the IPs.
20
66. Municipal LGU of Kitaotao is the implementing agency of the subproject. The Municipal
LGU is responsible for the following tasks.
Ensure that sufficient funds are available to properly implement the IPP;
Ensure that subproject implementation complies with the ADB SPS 2009 and
regulations of the Government and tribal groups;
Obtain necessary approval(s) from NCIP and/or other concerned government
agencies prior to commencement of activities;
Ensure that tender and contract document for design, supervision and civil works
include the relevant IPP requirements;
Facilitate resolution of affected peoples' concerns;
Monitor the implementation of the measures specified in the approved IPP;
Submit periodic reports of implementation progress to the DENR;
Provide funds in capacity building needs identified to capacitate the IP stakeholders
67. Sub-project Management Unit (SPMU) was created by the LGU of Kitaotao through
Executive Order No. 33 series of 2017 (Appendix 4). The SPMU is composed of four (4) sub-
units: a) Infrastructure Management Unit; b) Social Environmental Safeguards Management Unit;
c) Finance Management Unit and d) Monitoring and Evaluation Unit. The SPMU is mainly tasked
to ensure that the implementation of the subproject and corresponding IP Plan and EMP are
properly executed. Specifically, the SPMUs is expected to:
Prepare, implement and comply with the required social, technical and environmental
safeguards, such as, but not limited to resettlement plan, acquisition of right of ways,
environmental compliance certificate/ certificate of non-coverage to ensure the
readiness of the subproject relative to these;
Incorporate social dimensions to the subproject design and implementation by
conducting public consultation, information education and advocacy to the local
development council and the communities;
Design and implement strategies and mechanisms to ensure sustainability of the
subproject to include cost recovery, among others.
Ensure that IPP provisions are strictly implemented and monitored during the various
project phases;
Adopt monitoring and evaluation system to generate baseline data and to monitor and
evaluate the benefits and impact of the subproject.
68. National Commission Indigenous Peoples (NCIP) has responsibility to observe and
comply with its duties and functions as follows.
Protect and promote the interest and well-being of the IPs with regard to their beliefs,
customs, tradition and institutions;
Issue appropriate certification as a pre-condition to the issuance of permits, leases,
grants or any other similar authority for the disposition, utilization, management, and
appropriation by any private individual, corporate entity or any government agency,
corporation or subdivision thereof on any part or portion of ancestral domains taking
into consideration the consensus approval of the IPs concerned.
Ensure all terms and conditions stipulated in the Contract of Usufruct be respected
and implemented and may impose sanctions or penalties for non-compliance with
and/or violations of the terms and conditions of the Contract of pursuant to the
pertinent provisions of the IPRA and other related Administrative orders and
issuances;
Exercise its authority to conduct visitation of the area relative to the applicant’s
program in order to secure the conditions and well-being of the ICCs/IPs;
21
Handle grievances of the IPs if the grievances are not resolved satisfactorily at the
level of CoE.
69. The Safeguards Specialist of NPCO will assist and work closely with the NPCO, and
Municipal LGU of Kitaotao as follows:
The safeguards specialist of NPCO will undertake the supervision and monitoring of
the IPP implementation and contractor’s performance.
Closely supervise and monitor the contractor’s implementation of proposed measures
specified in the IPP.
Assist the LGU in preparing semi-annual monitoring reports on the progress of the IPP
implementation.
Facilitate capacity building needs identified to capacitate the IP stakeholders.
70. The Project Management Implementation Consultants (PMIC) The PMIC will be
engaged to assist and work closely with the National Project Coordinating Office (NPCO),
Regional Project Coordinating Office (RPCO), and concerned LGU on the various activities,
including providing capacity to implement and monitor the IP activities.
71. The indicative implementation schedule of the IPP is presented in the table below.
72. The estimated budget for the implementation of the IPP including the proposed capacity
building activities is shown in the table below.
22
No. of Training Estimated cost per Estimated Budget
Activities
Sessions Training Session (Php) (Php)
B. Implementation of mitigation 1 10,000.00 10,000.00
measures
C. Implementation of 1 10,000.00 10,000.00
enhancement measures
D. Total 40,000.00
73. The Municipal LGU of Kitaotao has allocated about Php 200,000.00 for the Support to
Indigenous Peoples in collaboration with other government agencies under its General Fund in
which the Implementing Office is the Municipal Mayor’s Office as indicated in the LGU’s 2019
Annual Investment Plan (Appendix 5).
23
Appendix 1. Minutes of the Public Consultation held on August 08, 2017 at Bobong, Kitaotao,
Bukidnon
Public Consultation
Brgy. Hall, Brgy. Bobong
Kitaotao, Bukidnon
August 8, 2017
9:43am
Prayer:
Kagawad Camelo
National Anthem:
Ailine Feliciano
We all know that our road is already damage due to heavy rains and heavily loaded trucks passing
especially during harvest time. And now this Barangay consultation will be conducted pertaining
to our project, the rehabilitation of Bobong Access Road if we will agree to implement the project.
Engr. Umbal - Out of 12 Barangays only Barangay Bobong benefited the project the Rehabilitation
of Bobong Access Road. The road length is 3.386 Km. from box culvert to purok 3, and a foot trail
from purok 3 down to Muleta River to our foot bridge. The cost of this project is P15,800,000.00,
but there are many documents which are the ADB required for the project and one of them is the
Barangay consultation if the populace of this barangay will accept the project. The people want a
road from Barangay Bobong to Barangay Kauyonan but the cost of the bridge that crosses muleta
river ranging from P200-P300 million pesos which the LGU has no capability to construct the
bridge so the LGU agreed to rehabilitate the Bobong-Bersiba access road.
Engr. Paulma – Engr. Jemuel from CESM will help us in conducting this consultation and he will
ask some question pertaining to our road project.
Engr. Jem – Good Morning is there any IP member who is present here? Please raise your hands.
24
25
Engr. Jem – how about the motorcycles and the jeepney?
Engr. Jem - is there any benefits we can get if the road be rehabilitated?
Dennis Puwaw - Easily transports our patient in times of emergency, also reduces our
transportation cost, and easily transports our farm products to market.
Engr. Jem – there are three stages to construct the road. The Contractor together with the LGU
will come and meet the barangay populace and the Council of Elders to discuss the project. What
tribe resides within this barangay?
Engr. Jem (explaining the 7 tribes existing in the province and their respective locations)
Engr. Jem - If both parties will agree the Contractor come and locate areas where to install their
camps and machineries then they will hire workers. At this time who among here are interested
to work. Please raise your hand.
26
Everybody raises their hands.
Engr. Jem – It is good that also women raise their hands. The Contractor will not be accepted if
the hired less than 30% of women, and the IP member should also be hired in the construction.
At this time the Contractor will know the policies of the Barangay and the Council of Elders. The
Contractor also hired skilled worker coming from outside the barangay can it be cause trouble
from you, what is your opinion?
Engr. Jem - The Contractor will use safe water for drinking can it causes competent to you?
Engr. Jem – If they used water for pouring where did they get?
Engr. Jem – The Construction generate waste, is there any barangay ordinance in relation to
waste management?
Barangay Chairman - Every Household has its own compose pit and for those non-
biodegradables we will put in the sack. Put waste container in the area.
Engr. Jem - RA 9003 no burning of waste, so the barangay is responsible for the waste generated
during the construction. Is the barangay having curfew hour?
Barangay Chairman - We have an ordinance, and we will impose it in the camp site at 10:00PM.
27
In chorus – Bringing of woman inside the camp is not allowed.
Engr. Jem – In road construction the equipment produces dust during operation can it affect to
you? What can you suggest to the contractor?
Engr. Jem – How about the senior citizen, children and the student?
In chorus – They will use mask and also, they will not go near the construction area.
Engr. Jem – during the construction only one lane will be utilized can it cause delay in all your
transactions?
Barangay Chairman – They should have an alternative road especially during concreting.
Engr. Jem – During road construction there’s a possibility that excavated soil scattered within the
vicinity and water can be affected.
Engr. Jem – the project duration is 8 months and there’s a possibility that our project will be
delayed due to weather condition and the project will go beyond the schedule can it
be acceptable for you?
Engr. Jem – When their equipment operates it produce smoke and it cause air pollution and also
noises presence during equipment operation.
In chorus – people in affected areas will use mask and the noises produce are manageable.
Engr. Jem – the fuel and oil used by equipment can also cause pollution what can you suggest?
Engr. Jem – The last stage is what is the effect of transport vehicles that passes after the
rehabilitation of the road?
Barangay Chairman – we don’t have any ordinance pertaining to speed limit, the barangay will
pass an ordinance about speed limit.
Engr. Jem – there’s a possibility that the road will be cracked if big trucks load more than load
limit what can you say about it?
28
Barangay Chairman – Maybe the barangay can pass an ordinance pertaining to load limit.
LGU - 8 inches.
Engr. Jem – can it be affecting the IP culture if the road turns into good condition because some
people will come into this place?
Engr. Jem – Is there any animals or plant remains living in this area?
Engr. Jem – If the road is already rehabilitated some people will come and hunt down wild
animals is there any policies to give safeguard these wild animals?
Mario – the IPs and Non-IPs living in this area will give safeguards to wild life habitat.
Jem – Is barangay Bobong is part of ancestral domain? Or signed in the usufruct contract?
Prior to the implementation there should be ritual happened.
Engr. Jem – Is there any divine areas that needs for road diversion?
Engr. Jem – If the implementation will start the ADB will came here and asking you if they
conducted consultation in you regarding to our project? Then tell them that not all
of you are here during consultation.
The road design is 7 meters in width, 4 meters carriage way 1-meter shoulder on
both side and 0.5-meter earth canal and 1 meter in width foot trail. Who among you here says
that the project will continue, please raise your hand?
29
In chorus – continue the project.
Engr. Jem – Who among you here living in the road side from the box culvert down to foot
bridge?
30
Engr. Jem – Is there any of you here affected in land, plants or crops?
Councilor Robledo – there is also pipe line traversing in the road at purok 1.
Engr. Umbal – if possible there should be no plant or trees are cut and the contractor will repair
the damage pipeline.
Engr. Jem – The wages will be known to people that will be hired in the construction.
Adjournment: 10:50 AM
Prepared By:
31
Barangay Consultation Attendance
32
33
34
35
Barangay Consultation Pictures
36
Appendix 1. Internal Monitoring Indicators (Adapted from ADB’s Handbook on Resettlement: A
Guide to Good Practice, 1998)
Are IPP and MOA activities being implemented and targets achieved
against the agreed time frame?
Are funds for the implementation of the IPP/ADSDPP allocated to the
proper agencies on time?
Have agencies responsible for the implementation of the IPP/ADSDPP
received the scheduled funds?
Have funds been disbursed according to the IPP/ADSDPP?
Has social preparation phase taken place as scheduled?
Has all clearance been obtained from NCIP?
2. Public Participation and Have consultations taken place as scheduled including meetings,
Consultation groups and community activities? Have appropriate leaflets been
prepared and distributed?
Have any Aps used the grievance redress procedures? What were the
outcomes?
Have conflicts been resolved?
Was the social preparation phase implemented?
Were separate consultations done for Indigenous Peoples?
Was the conduct of these consultations inter‐generationally exclusive,
gender fair, free from external coercion and manipulation, done in a
manner appropriate to the language and customs of the affected IP
community and with proper disclosure?
How was the participation of IP women and children? Where they
adequately represented?
3. Benefit Monitoring What changes have occurred in patterns of occupation, production and
resources use compared to the pre‐project situation?
37
What changes have taken place in key social and cultural parameters
relating to living standards?
What changes have occurred for IPs?
Has the situation of the IPs improved, or at least maintained, as a result
of the project?
Are IP women reaping the same benefits as IP men?
Are negative impacts proportionally shared by IP men and women?
38
Appendix 2. External Monitoring Indicators (Adapted from ADB’s Handbook on Resettlement:
A Guide to Good Practice, 1998)
Gender of household head
Ethnic group
Access to health, education, utilities and other social services
Housing type
Land use and other resource ownership and patterns
Occupation and employment patterns
Income sources and levels
Agricultural production data (for rural households)
Participation in neighborhood or community groups
Access to cultural sites and events
Value of all assets forming entitlements and resettlement entitlements
2. Levels of AP Satisfaction How much do IPs know about grievance procedures and conflict
resolution procedures? How satisfied are those who have used said
mechanism?
How much do the affected IP communities know about the IP
framework?
Do they know their rights under the IP framework?
How much do they know about the grievance procedures available to
them?
Do they know how to access to it?
How do they assess the implementation of the IPP/ADSDPP?
3. Other Impacts Were there unintended environmental impacts?
Were there unintended impacts on employment or incomes?
39
4. IP Indicators Are special measures to protect IP culture, traditional resource rights
and resources in place?
How are these being implemented?
Are complaints and grievances of affected IPs being documented?
Are these being addressed?
Did the project proponent respect customary laws in the conduct of
public consultations, in IPP/ ADSDPP implementation, in dispute
resolution?
Were the public consultations intergenerationally inclusive?
Were women and children proportionally represented?
Were representatives of the NCIP present in the public consultations?
During the monitoring of IPP/ADSDPP implementation?
40
Appendix 3. Executive Order Creating the SPMU for the Implementation of the
Rehabilitation of Bobong Access Road
41
42
Appendix 4. Excerpt from the 2019 Municipal Annual Investment Plan
43