You are on page 1of 3

PDVSA

GAS

Project/Title: GAS ANACO – OPERACIONES CENTRALIZADAS - PDVSA Document N°: 552198345.doc


FACILIDADES DE COMPRESIÓN OTEPI Document N°: F201163-B213E-1603-ET-209
Client: PDVSA Page / File: 1 / 552198345.doc
Rev./ Date: G0/ July 14, 2003

PROYECTO GAS ANACO – INGENIERIA BASICA


OPERACIONES CENTRALIZADAS - FIELD SANTA ROSA
ELECTRICAL
SPECIFICATION FOR 480 V MOTOR CONTROL CENTER –
FACILITIES

ISSUE INDEX:

This document consists of 4 pages.

The continuous line (sideline) at the right hand indicated all amendment since the previous
revision.

REV. DATE PÁGES COMMENTS

C0 Sep. 05, 2002 1 – 13 Final Issued


N3 Jun. 06, 2003 1–4 Issued for Internal Review
D0 Jun. 12, 2003 1–4 Issued for Comments
E0 Jun. 23, 2003 1–4 Issued for Client Approval
G0 July 14, 2003 1–4 Final Issued

OTEPI PDVSA

PREPARED BY REVISED BY APPROVED BY APPROVED BY

E. SCHIAVONE (C.I.V: 94697) V. NARDI (C.I.V: 69992) L. NAVA (C.I.V. 12.713) A. MEJÍAS / M. ZAPATA
PDVSA
GAS

Project/Title: GAS ANACO – OPERACIONES CENTRALIZADAS - PDVSA Document N°: 552198345.doc


FACILIDADES DE COMPRESIÓN OTEPI Document N°: F201163-B213E-1603-ET-209
Client: PDVSA Page / File: 2 / 552198345.doc
Rev./ Date: G0/ July 14, 2003

INDEX

SECTION Nº PÁG.

1. OBJECTIVE 3

2. SCOPE 3

3. ATTACHMENT: DATA SHEET 3


PDVSA
GAS

Project/Title: GAS ANACO – OPERACIONES CENTRALIZADAS - PDVSA Document N°: 552198345.doc


FACILIDADES DE COMPRESIÓN OTEPI Document N°: F201163-B213E-1603-ET-209
Client: PDVSA Page / File: 3 / 552198345.doc
Rev./ Date: G0/ July 14, 2003

1. OBJECTIVE
The purpose of this document is to cover the minimum technical requirement for 480 V
Motor Control Center (MCC), required for Anaco Project-Operaciones Centralizadas
Campo Santa Rosa.

2. SCOPE
The document is an addendum to the Engineering specification “ Low – Voltage Circuit
Breaker Motor Control Center “, according to PDVSA N 274, rev 0 and PIP
ELSMC13D, Which is the specification shall be applied to this project.