DRAWING NO.

DM/GACE/D7/2021/03/01

DM/GACE/D7/2021/03/02

DM/GACE/D7/2021/04/01
CORRECTIONS

front elevation has to be replaced with side elevation in side elevation diagram.
in stirrups diagram of plinth beam the dimension 10mm should be replaced by 8mm.
in the section general notes point no 1. "and elevation are in metre" has to be removed.
in the section general notes point no 12 the spelling of mechanical has to be corrected.
in the section general notes point no 8 which is related to "false ceiling" has to be removed.
in the section legends the hatch of aac block work and compacted earth has to be corrected.
in the section A-A diagram the thickness of pcc and compacted earth should be of 100mm and
150 mm respectively.
in the section legends the hatch of RCC M25/M30 and IBR ROOFING SHEET has to be corrected.
the colour of all dimensions should be same.