You are on page 1of 1

Reach-1 Viaduct August Target v/s progress

Contractor :- M/s NCC Ltd.

Description Target for August Progress %


the month target during achieved Progress
of August first 10days during first Achieved
10days
Piles 110 35 44 125.71
Pile Cap 26 8 1 12.50
Open Foundation 1 1 1 100.00
Pier 26 8 6 75.00
Pier Caps 25 8 2 25.00
Portals 1 0 0 0.00
Segment Casting
185 61 38 62.29
(Metro)
Spine Segment
60 20 9 45.00
Casting (NHAI)
Segment
16 5 2 40.00
Launching(Metro)
Pier arm 4 1 0 0.00
Wing/RIB casting
50 16 1 6.25
(NHAI)