Construction Site Layout and Logistics

Construction Methods and Technology


Module 2
Tutorial 1:
Logistic Planning
Prepare a Construction Logistic Plan
Case: Site Key Plan
Case- Logistic Planning
• ABC construction company has been awarded a contract for the construction of a residential
society located in Plot –G12, sector 143, Noida, Uttar Pradesh. Mr. Sanjay, project manager of
ABC construction company needs to propose a logistic plan of the project in the Kick-off meeting
for the approval, so that they can mobilise the resources to the site and can start the project on the
scheduled date.
• Mr. Sanjay has successfully handed over 6 high rise residential projects for which he gives credit to
efficient logistic planning of project. He have outlined below listed factors, that he always consider
before starting logistic planning:
• Safety
• Site Challenges (Such as levelness, condition of soil, groundwater, etc.)
• Site Access
• Excavation and Hauling
• Hoisting.
• Movement of Manpower, material, mobile machinery and equipment.
• Concrete Conveyance and Placement
• Project Phasing
• Demobilisation
Project Details

Site Profile Machinery/Equipment Temporary Structure


Plot Area: 10 Acres Required

Front Side: 24 mtr Expressway 2 Batching Plant-30 Cum Site Office

Back Side: Green Belt 100 mtr Concrete Pipeline Marketing Office

Right Side: Adjacent Empty Plot of 100MT Weigh Bridge Visitor View Gallery
size 5 acres (Available for Rent: Rs. 4 Bar Bending/Cutting Cement Storage – 5000
1000/M2) Machines bags
Left Side: 12 mtr wide road 2 Transit Mixer QA/QC Lab
Stories: 20 No. Tower Crane Labour Camps+ Toilets
Basement: 2 No. DG set Site General store
Club: 1 No. 2 Concrete Pump Site Boundary
Ground water: At 2.5 mtr from NGL 2 Excavator+ 4 Dumpers Labour Canteen
Foundation Bottom: At 8.5 mtr from Dewatering Pumps
Referenced Level
Constraint Related To Project Site

• Expressway on front side of project, have time restriction over entry for all category
heavy vehicle i.e 10:30pm to 7am.
• Busy City Road on Left side of project, have time restriction over entry for all category
heavy vehicle i.e 9:00pm to 7am.
• Shall not use Groundwater for Construction.
• Sound emitting construction equipment shall not be used or operated during night time in
this zone.
• Acoustic Barriers for controlling Noise in day time.
• Vehicles carrying goods such as steels bars, cement and other construction vehicles are
not allowed on City road.