Professional Documents
Culture Documents
Solving A Major Odor Problem in A Chemical Process
Solving A Major Odor Problem in A Chemical Process
To cite this article: J. F. Byrd , H. A. Mills , C. H. Schellhase & H. E. Stokes (1964) Solving a
Major Odor Problem In a Chemical Process, Journal of the Air Pollution Control Association, 14:12,
509-516, DOI: 10.1080/00022470.1964.10468324
Fig. 1. Medical syringe used for odor sampling Fig. 2a. Odor panel observer preparing to
and measurement. eject odorous sample into nostrils. Fig. 2b. Odor panel.
fluctuating loads from our process flows. ever, it was possible that due to certain flame whipped about in the wind (the
A flare stack obviated these objections. incomplete products of combustion of tests were run outdoors for safety
However, for effective elimination of the amines such as, say, oxides of nitro- reasons). Inadvertently, as the tube
the nuisance problem, almost total de- gen, a mild odor problem could remain. was moved around in an attempt to
struction of the amines is necessary We, therefore, took gas samples from keep it in the dancing flame, some of the
because of the extremely low odor the periphery of the flame with our odor sample was drawn from the cool inner
threshold of DMA. syringe. These samples were taken to core of the flame where the amines still
an odor-free room for dilution as neces- existed in an undecomposed state.
Flare Stack Design— sary and observation by our odor panel. Nevertheless, these quantitative anal-
Pilot Plant Work A barely discernible odor was noted, yses for the amines with all their short
To determine the effectiveness of a probably some oxide of nitrogen, but comings did confirm at least the near-
flare stack we built a small model pilot the fish odor was, fortunately, con- absence of amine. The possibility of
stack for test purposes. A bunsen spicuous by its absence. the formation of a black plume at our
burner was rigged to the stack to simu- (3) Being engineers, however, we were flare stack consisting of unburned carbon
late the pilot flame. This model handled not completely satisfied with subjective particles formed from thermal decom-
flows of Vsoo the actual design flows. approaches. Engineers like to express postition of the gaseous compounds and
A maximum of 7.0 cfm of the several facts with numbers. So we actually incomplete combustion of these parti-
constituents of the exhaust gases were drew samples from the outer periphery cles appeared to us as highly unlikely
metered to the pilot model flare stack. of the flame through a midget impinger because of the small ratio of carbon
These flows included various combina- sampling train consisting of a midget atoms to hydrogen atoms and the low
tions of hydrogen, di-methyl amine, impinger containing .01 normality HC1, molecular weight of the gaseous com-
ammonia, nitrogen, and fuel gas. Fuel a rotameter for measuring the gas sam- pounds.7- 9 In practice this assump-
gas is considered a necessary ingredient pling rate, and an eductor to provide the tion proved entirely correct. The flare
at all times. Hydrogen normally pres- motivating force for the gas sample stack has not smoked.
ent would support combustion. How- (Fig. 10). Amine hydrochlorides were
ever, we could foresee various process formed in the impingers. In the labo- Flare Stack Design
conditions where the waste gases might ratory, these amines were evolved over So we installed a flare stack in place
consist of no hydrogen but merely solid KOH in large excess within a of the acid scrubber and never regretted
purging nitrogen containing enough sealed chamber. The evolved gas was the decision (Fig. 11). The flare stack
amines to create a major odor problem then chromatographed. This techni- purchased from the John Zink Company
but not enough to support combustion. que did show thy presence of several is 100 feet high. The bottom section
These conditions could occur at any parts per million amines in the gases of is six feet in diameter by 10 feet high
time. Therefore, sweetening fuel gas is combustion. While this quantity would and acts as a knock-out drum to remove
required on a continuous basis in the be too insignificant to be an odor prob- liquid material. The top two feet of
total effluent streams discharged to the lem at the closest homes and represented the stack is lined with castable refrac-
flare stack. a better than 99.9% removal, we still tory on the inside for protection against
The various gases were fed from high should have detected this odor with our heat from the flame. Similarly, the
pressure gas bottles through calibrated noses since the odor threshold of amines upper eight feet is stainless steel. The
rotameters into a manifold and thence is much less than one ppm. stack is designed to handle various
to the model flare stack (Fig. 8). Feed The reason for this apparent but combinations of amines, ammonia, hy-
rates of the constituents discharged to slight inconsistency is simple. The drogen, and nitrogen plus sweetening
the flare during several test conditions gas sample collection tube had to be gas, i.e., natural gas, to assure a com-
are shown in Fig. 9. manually held in the flame since the bustible mixture under worst conditions.
We checked the efficiency of odor
removal of the amines by three
approaches:
(1) Direct a small stream of SO2 at
the tip of the flame to determine vis-
ually if there were any remnants of
unburned amines. Amines combine
with SO2 to form a thick, white visible
fume. The test is a rather sensitive
qualitative approach. At the tip of the
ilame and around the periphery no
white fumes were noticed. At the
cooler base there was only the slightest
indication of the presence of amines.
{2) Odor tests—Observers in the im-
mediate area of the flame noticed no Fig. 10. Midget impinger test unit for measur- Fig. 1 1 . Sketch—full scale flare stack as
sign of the distinctive fish odor. How- ing amine concentrations. designed.
The addition of natural gas provides a from the system the NH3 which built level in case of flame failure was not a
minimum of 350 to 400 Btu/cubic feet up in the system from a side reaction design criteria for the height of our
of exhaust gases entering the flare stack. and over-pressured some of the pro- stack because of the relatively innocuous
We had been advised that 250 Btu/cubic cessing and storage tanks. During our nature of the waste gases.
feet of exhaust gases is probably ade- first run we installed additional inter- These relief valve surge tanks nor-
quate but our pilot plant tests showed locks and alarms to avoid those mis- mally operated at two psig or so. How-
the need of a higher heat value to be operations which could over-pressure ever, the maximum allowable pressure
sure of combustion. We did not want the process vessels. However, in even of the tanks was set at 30 psig by our
to risk a flame-out and a major odor the best managed of families, relief safety people for various process safety
nuisance again. The stack was valves do discharge and once opened do considerations. Combined surge tank
equipped with four natural gas pilot not reset well. We just could not af- capacity was 3200 cubic feet. There-
lights to assure ignition of all combus- ford the risk of further major nuisance fore, at 30 psig they were capable of
tibles released from the stack. Ignition espisodes. Therefore, in our revised handling 6400 standard cubic feet of
of the pilots is accomplished by a remote system (Phase II) the discharges from emission from the relief valves. The
"flame front" ignition system. About all major relief valves are fed into a contents of these surge tanks could be
400 feet of pipeline to the pilot light 16 inch collection header and thence to discharged to the flare stack at a con-
isfilledwith a proper mixture of natural two large storage tanks which act as trolled rate so as not to exceed the
gas and air. A spark is generated by a surge tanks to contain the discharges design capacity of the flare stack.
spark plug and the flame is propogated from the relief valves. These relief The one Achilles heel in this scheme of
along the length of the pipe line to the valve surge tanks meter their contents things is the large relief valve protecting
pilot lights. About 25 cfm of natural gas slowly into the flare stack for destruc- these surge tanks. It discharges to the
is fed to the four pilots (Fig. 12 to 14). tion of the odorous organic material. atmosphere. The theoretical rate of
Aside from the elimination of a stream The normal emissions also pass through discharge from this relief valve was
pollution problem and total destruction these surge tanks which constitutes a tremendous, too large for a flare stack
of odorous compounds the flare stack wide place in the line and therefore serve of reasonable dimensions. However,
proved far more reliable than the pre- the purpose of a knock-out drum to with our alarm and interlock system for
vious odor control device, the acid remove any liquid from the gaseous vessel over-pressures, we believed that
scrubber. The latter was, of course, a stream prior to discharge to the flare the over-pressure of our surge tanks
chemical process requiring some atten- stack. We wanted to avoid the possi- would rarely, if ever, occur. A year's
tion. Several odor episodes were cre- bility of flaming particles of liquid operation confirms this reasoning.
ated by malfunctioning or misoperation dropping down toward the ground.
of the scrubber. The troubles included One might be tempted to ask why
malfunctioning of the pH control, Storage Tank Vent System
the surge tank for the relief valve dis-
failure to deliver acid to the scrubber, charges. Why not pipe the relief A number of storage tanks operating
flooding of the scrubber, clogging of the valves directly to the flare stack? at or near atmospheric pressure con-
recirculation pump with broken bits of These relief valves were designed for tain stocks normally free of odorous
berl saddles, ad infinitum. Much oper- large peak flows and the discharge amines. However, misoperation could
ating and maintenance attention was from a number of these valves could result in amine contamination of the
required by the acid scrubber. On the peak simultaneously. To have de- stocks in the tanks and odor discharges
other hand, the flare stack is given only signed the flare stack to burn the in- to the atmosphere from the vents of
a bare minimum of maintenance and stantaneous peaking of all these sources the tanks. We therefore collect the
operational time. It just keeps on at once would have resulted in a flare vents of various groupings of tanks
burning. After a year on the line there stack of record breaking height, diam- and discharge them to the atmosphere
has been no period of misoperation or eter, and cost. One of the key cal- through a water scrubber. The spent
malfunctioning, resulting in flame out culations in flare stack heights in- scrubber water normally is clean and,
and an odor nuisance. The amines volves flame lengths for given heat therefore, sent directly to the sewer and
entering the flare stack have been to- loads.7'8 Safety dictates a flare stack thence to the river at an outfall near a
tally destroyed. be of such height that the flame length heavily trafficked bridge. However,
for the design heat load will not en- short and infrequent periods of mis-
Pressure Relief Valve Discharges danger life or property. A surge tank operation could result in a scrubber
Our earlier troubles during the first to receive the relief valve discharges water discharge contaminated with
runs (Phase I) involved frequent pop- obviates the necessity for the flare stack enough amines to render the odor of the
ping of pressure relief valves. We par- to be so large and costly. Just as an spent water objectionable. Therefore,
tially solved the problem by bleeding aside, toxic concentrations at ground all spent scrubber water passes through
514 Journal of the Air Pollution Control Association
The plant manager, group manager, and STORAGE a WORK TANK VENT SYSTEMS