Professional Documents
Culture Documents
Clark
Coil-Type
STEAM
GENERATORS
Equipment helps realize significant fuel savings
Efficiency (percent)
year.3
50
For the typical industrial user of
natural gas or No. 2 fuel oil, this
40
translates to a cost of 50 to 60-plus
cents per therm (100,000 Btu). At
this price level, alternative technolo- 30
gies that offer improvements in effi-
ciency—even if initially more expen- 20
sive—must be examined. The
coil-type steam generator is one 10
such technology. Along with alter-
native technologies, steam-system 0
0 10 20 30 40 50 60 70 80 90 100
maintenance and its impact on en- Firing rate (percent)
ergy conservation must be exam-
ined.
FIGURE 1. Efficiency of coil-type steam generators and natural-circulation firetube
At the current price levels of fuel,
boilers over firing range.
it is imperative to properly maintain
existing equipment and compo-
nents. For example, although much be lost through a 3⁄8-in. sharp-edged • There are significant cyclical or
has been written on the subject, and orifice. At today’s costs, this results seasonal load fluctuations.
all steam-boiler users know (or in an economic loss of more than • The operation experiences
should know) the consequences if it $40,000 per year. short-duration load swings.
is not practiced, proper steam-trap So how can steam-boiler users de- • The boiler operation is in a
maintenance still is a significant termine if they should replace an standby mode.
problem.4 At 60 cents per therm, older firetube boiler with another So, assuming something other
the cost of 1,000 lb of steam (based type of firetube boiler or with a coil- than a 24/7, constant-load condi-
on a boiler efficiency of 80 percent) type steam generator? And what tion, how can a user determine if a
is approximately $7.29, as shown about the potential for substantial steam generator is economically fea-
below: savings of a new application? Can sible?
coil-type steam generators better re- The first consideration, of course,
1,000 lb steam (33,520 Btuh alize those savings? Obviously, users usually is the initial capital cost of
34.5 lb per hour steam) = 971,594 Btu first must determine if: (1) a coil- the equipment. The “typical” sell-
type steam generator is suitable for ing price of a coil-type steam gener-
(971,594 Btu 1 105 Btu per therm) their application and, (2) if so, the ator generally is higher than that of
60 cents per therm 0.80 = $7.29 economic payback justifies that se- a firetube boiler. However, the in-
lection. stallation cost may be somewhat
Using the data in French’s Table As mentioned above, coil-type lower because steam generators of-
1,4 and substituting $7.29 (for fuel steam generators are most effective ten can be disassembled and rigged
only) in his calculations, which were in heating applications in which one through existing access ways, reduc-
based on an average cost of $5 per or more of the following conditions ing or eliminating the need for de-
1,000 lb of water, feedwater treat- exist: molition and reconstruction. And,
ment, and fuel, the results are dra- • Additional steam capacity is unlike most other field-erected boil-
matic. For example, French demon- needed, and available floor space, ers, coil-type steam generators can
strated that almost half-a-million headroom, and/or physical access is be reassembled without welding,
pounds of dry steam per month can limited or restricted. eliminating the need for code
welders and fire-watch provisions. Suppose we have three 400-bhp With the list price of a 400-bhp
The most significant savings with firetube boilers in an older heating coil-type steam generator in the
a steam generator, though, may be plant with a 16-week heating sea- range of $80,000 (compared with
realized in applications in which all son. The boilers are configured so $60,000 for a firetube boiler), the
or part of the boiler operation is in a that two of them run while the third payback in replacing the older
standby mode. Because of its rela- is in a low-fire “standby” mode. firetube boiler in this scenario
tively long startup time, the firetube This third boiler operates in other with a new coil-type steam gener-
boiler generally will be kept in a than standby mode only 10 percent ator will be less than two years. If
“hot” standby condition by main- of the four-month heating season you also consider installation
taining low fire. This results in fuel and has an average “fuel-to-steam” costs, utilization of the other two
consumption without the effective efficiency of 80 percent. The aver- boilers, and the maintenance im-
use of the energy produced. With its age ambient-heat losses from the plications of running a firetube
fast steaming characteristics—typi- shell only (“vessel losses”) are 5 per- boiler at low-fire hold for long pe-
cally, cold startup to full output in cent. Just in making up for those riods of time, the quick-steaming
approximately five minutes—the ambient-heat losses, the standby advantage of the coil-type steam
coil-type steam generator, on the boiler will waste more than $12,000 generator becomes even more at-
other hand, can be started only as per heating season, as shown below: tractive and the economic justifi-
needed. Because most existing fire- cation even more compelling.
tube-boiler steam-heating plants 400 bhp 33,520 Btuh per bhp Another application with much
will have at least five minutes of re- 0.80 efficiency 0.05 average heat loss potential for fuel savings is a new
serve steam in their system, this = 838,000 Btuh installation in which a substantial
“boiler-on-demand” concept can be portion of the steam load remains
practical even for critical steam re- 16 weeks 7 days per week constant during continuous
quirements. And the coil-type steam 24 hr per day 90 percent = 2,419 hr (24/7) operation, but still may
generator’s inherent immunity from exhibit swings during certain
failures caused by thermal shock en- 838,000 Btuh 2,419 hr 1 higher- or lower-use periods. In
sures long life even with frequent 105 Btu per therm 60 cents per therm this case, the most-efficient con-
starts and stops. = $12,163 figuration might call for coil-type