You are on page 1of 4

FEATURE ARTICLE by Larry S.

Clark

Coil-Type
STEAM
GENERATORS
Equipment helps realize significant fuel savings

n an article published in the Sep-

I tember 1999 issue of HPAC Engi-


neering,1 I discussed using coil-type
steam generators to supplement (or, in
some instances, even replace) firetube
(or natural-circulation watertube) boil-
ers in traditional heating-plant applica-
tions. In that article, which offers a thor-
ough description of forced-circulation
technology, primary selection criteria
were identified. Although briefly men-
tioned, the fuel savings associated with
this technology were not addressed in
detail.
Nearly two years later, following a
dramatic increase in fuel prices, the fast-
startup characteristics of coil-type steam
generators are even more significant
than before. In 1973, the average cost of
natural gas delivered to electric-utility
consumers was 38 cents per thousand
cubic feet.2 That cost increased nearly
tenfold over the next decade, reaching
$3.70 per thousand cubic feet in 1984.2
It then began a gradual decline to an av-
erage of $2.43 in 1999.2 Last year, how-
ever, prices of energy hit record highs,
with the cost of natural gas to electric
utilities reaching $4.46 in June 2000.2
The forecast for 2002 is for gas at the
wellhead to sell for $4.57 per thousand
cubic feet, which will translate to a cost
to electric utilities of $4.99 per million
Rick Fischer/Masterfile

30 June 2001 www.ABMA.com


Btu.3 So for the short term at least, 90
the price of natural gas will be a ma- Coil-type generator
jor concern to users of gas-fired 80
steam boilers. And, of course, No. 2
oil is following the same trends as
70
natural gas, with the average whole-
Natural-circulation firetube boiler (typical)
sale cost of No. 2 heating oil ex-
60
pected to be 87 cents per gallon this

Efficiency (percent)
year.3
50
For the typical industrial user of
natural gas or No. 2 fuel oil, this
40
translates to a cost of 50 to 60-plus
cents per therm (100,000 Btu). At
this price level, alternative technolo- 30
gies that offer improvements in effi-
ciency—even if initially more expen- 20
sive—must be examined. The
coil-type steam generator is one 10
such technology. Along with alter-
native technologies, steam-system 0
0 10 20 30 40 50 60 70 80 90 100
maintenance and its impact on en- Firing rate (percent)
ergy conservation must be exam-
ined.
FIGURE 1. Efficiency of coil-type steam generators and natural-circulation firetube
At the current price levels of fuel,
boilers over firing range.
it is imperative to properly maintain
existing equipment and compo-
nents. For example, although much be lost through a 3⁄8-in. sharp-edged • There are significant cyclical or
has been written on the subject, and orifice. At today’s costs, this results seasonal load fluctuations.
all steam-boiler users know (or in an economic loss of more than • The operation experiences
should know) the consequences if it $40,000 per year. short-duration load swings.
is not practiced, proper steam-trap So how can steam-boiler users de- • The boiler operation is in a
maintenance still is a significant termine if they should replace an standby mode.
problem.4 At 60 cents per therm, older firetube boiler with another So, assuming something other
the cost of 1,000 lb of steam (based type of firetube boiler or with a coil- than a 24/7, constant-load condi-
on a boiler efficiency of 80 percent) type steam generator? And what tion, how can a user determine if a
is approximately $7.29, as shown about the potential for substantial steam generator is economically fea-
below: savings of a new application? Can sible?
coil-type steam generators better re- The first consideration, of course,
1,000 lb steam  (33,520 Btuh alize those savings? Obviously, users usually is the initial capital cost of
 34.5 lb per hour steam) = 971,594 Btu first must determine if: (1) a coil- the equipment. The “typical” sell-
type steam generator is suitable for ing price of a coil-type steam gener-
(971,594 Btu  1  105 Btu per therm) their application and, (2) if so, the ator generally is higher than that of
 60 cents per therm  0.80 = $7.29 economic payback justifies that se- a firetube boiler. However, the in-
lection. stallation cost may be somewhat
Using the data in French’s Table As mentioned above, coil-type lower because steam generators of-
1,4 and substituting $7.29 (for fuel steam generators are most effective ten can be disassembled and rigged
only) in his calculations, which were in heating applications in which one through existing access ways, reduc-
based on an average cost of $5 per or more of the following conditions ing or eliminating the need for de-
1,000 lb of water, feedwater treat- exist: molition and reconstruction. And,
ment, and fuel, the results are dra- • Additional steam capacity is unlike most other field-erected boil-
matic. For example, French demon- needed, and available floor space, ers, coil-type steam generators can
strated that almost half-a-million headroom, and/or physical access is be reassembled without welding,
pounds of dry steam per month can limited or restricted. eliminating the need for code

BSE June 2001 31


COIL-TYPE STEAM GENERATORS

welders and fire-watch provisions. Suppose we have three 400-bhp With the list price of a 400-bhp
The most significant savings with firetube boilers in an older heating coil-type steam generator in the
a steam generator, though, may be plant with a 16-week heating sea- range of $80,000 (compared with
realized in applications in which all son. The boilers are configured so $60,000 for a firetube boiler), the
or part of the boiler operation is in a that two of them run while the third payback in replacing the older
standby mode. Because of its rela- is in a low-fire “standby” mode. firetube boiler in this scenario
tively long startup time, the firetube This third boiler operates in other with a new coil-type steam gener-
boiler generally will be kept in a than standby mode only 10 percent ator will be less than two years. If
“hot” standby condition by main- of the four-month heating season you also consider installation
taining low fire. This results in fuel and has an average “fuel-to-steam” costs, utilization of the other two
consumption without the effective efficiency of 80 percent. The aver- boilers, and the maintenance im-
use of the energy produced. With its age ambient-heat losses from the plications of running a firetube
fast steaming characteristics—typi- shell only (“vessel losses”) are 5 per- boiler at low-fire hold for long pe-
cally, cold startup to full output in cent. Just in making up for those riods of time, the quick-steaming
approximately five minutes—the ambient-heat losses, the standby advantage of the coil-type steam
coil-type steam generator, on the boiler will waste more than $12,000 generator becomes even more at-
other hand, can be started only as per heating season, as shown below: tractive and the economic justifi-
needed. Because most existing fire- cation even more compelling.
tube-boiler steam-heating plants 400 bhp  33,520 Btuh per bhp Another application with much
will have at least five minutes of re-  0.80 efficiency  0.05 average heat loss potential for fuel savings is a new
serve steam in their system, this = 838,000 Btuh installation in which a substantial
“boiler-on-demand” concept can be portion of the steam load remains
practical even for critical steam re- 16 weeks  7 days per week constant during continuous
quirements. And the coil-type steam  24 hr per day  90 percent = 2,419 hr (24/7) operation, but still may
generator’s inherent immunity from exhibit swings during certain
failures caused by thermal shock en- 838,000 Btuh  2,419 hr  1 higher- or lower-use periods. In
sures long life even with frequent  105 Btu per therm  60 cents per therm this case, the most-efficient con-
starts and stops. = $12,163 figuration might call for coil-type

FIGURE 2. Flow diagram of a recirculating steam generator.

32 June 2001 www.ABMA.com


steam generators backing up fire- concept—particularly for high- 0130; “Monthly Energy Review,”
tube boilers. This would allow the pressure steam applications—is a DOE/EIA-0035; and “Electric
boilers, which operate best at con- hybrid system configured with Power Monthly,” DOE/EIA-0226.
stant, full-design-load conditions, both conventional boilers and 4) French, S.A. March 2000.
to be base loaded. The steam gen- coil-type steam generators for op- “Lighting a Fire Under Steam Trap
erators, with their fast response timum efficiency. Maintenance.” HPAC Engineering.
and full-modulation characteris- With energy costs at an all-time 5) Moore, J. July 1999. “Multi-
tics, then could handle the load high and expected to remain ple-Boiler Sizing and Selection.”
swings for which they are de- there for a while, it is more im- HPAC Engineering.
signed. Because the efficiency portant than ever to look at alter-
curve of a coil-type steam genera- natives to the conventional
About the author:
tor essentially is flat over its full boiler-plant design. The coil-type
operating range (Figure 1), there steam generator is only one such Larry S. Clark is eastern-region
is no economic penalty in this alternative. Innovative heat-re- sales manager for Vapor Power
mode of operation (note that the covery systems and other ap- Group in Niles, IL With a bache-
area between the two curves rep- proaches to saving fuel also lor’s degree in electrical engineer-
resents fuel savings). Depending should be carefully examined. ing, he has 19 years of experience in
on the size and type of load, there all aspects of process equipment. He
also may be opportunities (such as References can be contacted at
during summertime operation) to 1) Clark, L. September 1999. larryscl@aol.com. n
take the firetube boilers off-line “Coil-Type Steam Generators for
and carry the full load with only Heating Plant
the steam generators. Often, this Applications.”
can result in both fuel savings and HPAC Engi-
maintenance advantages. neering.
To evaluate the potential bene- 2) U.S. En-
fits of the coil-type steam genera- ergy Informa-
tor, it is important to understand tion Adminis-
the technology’s theory of opera- tration.
tion. Referring to Figure 2, water October 2000.
at saturation temperature is drawn “Natural Gas
from a steam drum and pumped Annual 1999.”
through a set of nested, parallel- 3) Forecasts
connected coils at several times generated
the maximum desired steaming through simu-
rate. The water then is carried to a lation of the
steam lance and set of baffles and Short-Term
screens, where steam is released Integrated
and effectively separated. Dry Forecasting
steam (greater than 99.5-percent System. Data
dryness) is withdrawn from the from Energy
drum, leaving a reservoir of heat- Information
saturated feedwater. Because of its Administration
relatively low (2 to 3 percent) wa- databases sup-
ter content, the coil-type steam porting the fol-
generator will be smaller, lighter, lowing reports:
and faster in responding than will “Petroleum
a comparably rated firetube boiler. Marketing
Moore5 suggested that many Monthly,”
commercial and industrial two- DOE/EIA-
boiler designs are best replaced 0380; “Natural
with multiple-boiler systems. Per- Gas Monthly,”
haps the logical extension of that DOE/EIA-
Circle 21

BSE June 2001 33

You might also like