NUMBER Question Correct Answer Explanation

1 Chester Inc. was contracted to install 200,000 square feet of floor tile Control Procurements The opening of a claim is in controlling procurements or the
in three food production facilities in Michigan. There was some Control Procurements process. PMBOK® p. 498
concerns raised by the customer that the total square footage was not
met and the buyer opened up a claim. The activity of opening this
claim is related to:

2 After a meeting with the financial department, there have been some Project management plan updates This would be an update to the budget.
changes to the amount of money available for the project. What will
need to be updated in the manage stakeholder engagement process?

3 Your team is working on a new project and will require training on the Cost of quality Training is a part of the cost of quality. PMBOK® p. 283
new equipment. This training is known as what?

4 The role of the project manager in an Agile environment is? Somewhat of an unknown The role of the project manager in an Agile environment is
somewhat of an unknown, because in many Agile frameworks
and approaches, they do no address the role of the project
manager. Agile Practice Guide, page 37.

5 At the end of the first month of a six month project, the project Critical path method This is the proper term for what the project manager is doing.
manager is re-analyzing the schedule. She is putting together a
sequence of activities with the least amount of scheduling flexibility.
What is this called?

6 The project manager needs to be aware of changes. In addition, the Prevent unnecessary changes This is a key responsibility of a project manager.
project manager should also do what?

7 One of the inputs to the Plan Risk Management process is the The stakeholder register allows the project This is the most appropriate answer.
stakeholder register. What is the best reason this is needed in manager to see what the roles are, of each
planning for risks? stakeholder.

8 There are three outputs in determining a budget. Which of the Project funding requirements The project funding requirements is an output. The rest are
following is one of the outputs in the process Determine Budget? inputs or tools and techniques for determining a budget using
the Determine Budget process.

9 The project manager has decided that he prefers a colocated team A sense of community with a central war room. A colocated team advantage is a sense of community. PMBOK
over a virtual team for a particular project. A senior project manager p. 340
tells him that a virtual team provides the following advantages except
which one?

10 There are four values of the Agile Manifesto. Which of the following is Ensure all risks have a response plan over just The four values of the Agile Manifesto are: Individuals and
not one of the four values of the Agile Manifesto? allowing risks to occur. interactions over processes and tools; Working software over
comprehensive documentation; Customer collaboration over
contract negotiation; Responding to change over following a
plan. Agile Practice Guide. p. 8
11 A work breakdown structure component that is below the control Planning package A planning package is a work breakdown structure or WBS
account and above the work package is known as: component that resides below the control account and is above
the work package and has known work content but does not
have detailed scheduled activities. PMBOK® p. 161

12 What is the main benefit of developing a project management plan? It creates a comprehensive document that defines This central and comprehensive document is the key benefit.
the basis of the project work and how the work PMBOK® p. 82
will be performed.

13 You are working on a construction project in a different country and Pay the fee. Since this is a legitimate request, pay the fee.
on a tight schedule. The city manager informs you that due to a local
holiday you will need to pay an additional fee for the needed road
closure that day. What do you do next?

14 The most successful project managers will spend a significant amount Communicating Communication is one of the key factors in successful projects.
of time doing which of the following: PMBOK® p. 359, 361

15 You have been asked in the hallway by the CFO which report will have Progress report The progress report will have the information from the last
an update on the project since the last meeting. You tell him that the meeting that the CFO needs. The status report will also have
information is in which report? most of that information but status reports focus on the project
overall.

16 The key tool in controlling the scope of a project is variance analysis. Determining the cause and degree of difference This is the definition as described in PMBOK® p. 170
What is the best definition of this? between the baseline and the actual performance
relative to the scope baseline.

17 The project is about halfway done and the client is looking for a 10% / -5% A definitive budget is +10% / -5% and is generally known once
definitive estimate for the rest of the project. You work up the budget the project is underway. A planning budget is +25% / -10%. An
and you are able to say that the budget is plus or minus what order of magnitude budget is +75% / -25%.
percentage?

18 Regularly analyzing as well as documenting key relevant stakeholder Identify stakeholders Identify Stakeholders is that process being described. PMBOK®
information, such as their interests, interdependencies, influence, and p. 503
their potential impact on the success of the project, occurs in which
process?

19 You have been asked to begin writing the project scope management Quality management plan The way the project and product scope will be managed can
plan. You are gathering the necessary documents to begin this have an influence and will be needed when developing the
process. Which of the following is required to do this? scope management plan. PMBOK® p. 135

20 General communications activities that are utilizing emails, social Informal General communications activities that are utilizing emails,
media, websites, and informal ad hoc discussions are: social media, websites, and informal ad hoc discussions are
informal. PMBOK® p. 361
21 The project manager must require the skills to identify, build, Develop Team Recognizing and rewarding good performance, is mainly a
maintain, motivate, lead, and inspire project team members, focus of the Develop Team process. PMBOK® p. 337
regardless of the size of the project team. Recognizing and rewarding
good performance, is mainly a focus of which Resource Management
process?

22 Kevin is presenting the project quality plan to the stakeholder Quality is the degree which the product fulfills the Quality is the degree that the product meets the requirements.
meeting. One of the stakeholders asks what the difference is between requirements while grade is technical Grade is the technical characteristics. A low-grade example is a
grade and quality. What is your best response? characteristics of the product. basic cellphone meets the need to make phone calls. A high-
grade example would be an advanced smartphone with extra
features.

23 The key benefit of a cost-reimbursable contract is which of the They provide flexibility to redirect a seller when This is the key benefit for a cost reimbursable contract
following? the scope of the project cannot be defined or
there are high risks involved.

24 While reviewing the bids from the subcontractors, the project Source selection analysis The source selection analysis step was missed, as the process
manager is trying to compare the various bids. He realizes that the Plan Procurement Management produces as an output the
planning process missed a step to allow him to rate each bid. What source selection criteria. PMBOK® p. 466
step did the planning process fail to provide?

25 In the monthly financial report, you see the following information: CPI $41 CV=EV-AC. Since these are not given, we need to calculate
=1.1, SPI=.9, PV=$500, SV=-$200. You cannot find the CV so you need these. Since EV=SPI*PV, EV=.9*$500=$450. CPI=EV/AC
to calculate it. What is the CV? therefore AC= EV/CPI= $450/1.1 = $409. Now we calculate
CV=$450-$409=$41

26 You are managing a project with budget at completion (BAC) $70,000. $97,000 Estimate at Completion , i.e. EAC = AC + bottom-up ETC, EAC =
The actual cost to date you have seen is $22,000 and earned value is $22,000 + $75,000 = $97,000.
$19,000. You calculate estimate to complete (ETC) to $75,000 by
doing bottom-up sum of all costs. After so many calculations, what is
the estimate at completion (EAC) for the project?

27 Collecting requirements encompasses a variety of areas for different Risk requirements There are no risk requirements.
reasons. Which of the following is not a type of requirement?

28 In the stakeholder engagement assessment matrix, which the project Leading Leading is the answer. PMBOK® p. 521
manager and the project team must actively manage, has different
classifications. For a stakeholder that is aware of the project and
potential impacts and is actively engaged in ensuring that the project
will be successful, would be in which classification?

29 The team is reviewing the process control charts and is concerned Close out the tests as the process is not out of The process is not out of control as it takes seven consecutive
about a run of six consecutive points that are above the mean control. points above or below the mean to signify it is out of control.
measurement. The quality manager says that the process is out of
control and these tests will need to be done over again. This will cause
extra costs that were not anticipated. What is the next best step?

30 How project requirements activities will be planned, tracked, Requirements management plan How requirements activities will be planned, tracked, reported,
reported, and where the requirements prioritization process, are and the requirements prioritization process, are defined in the
defined? requirements management plan. PMBOK® p. 137
31 Valerie has been comparing the last six weeks of performance data. CPI > 1 and SPI > 1 CPI > 1 and SPI > 1 is the best answer. As the PMBOK® Guide
She notices that the project is running under budget and ahead of states: CPI greater than 1 indicates under planned cost or
schedule. Valerie is training Susan, and Susan needs to understand under budget. SPI greater than 1 indicates ahead of schedule.
both the cost performance index (CPI) and the schedule performance PMBOK® Guide p. 267
index (SPI). Which of the following would be true regarding the cost
performance index (CPI) and the schedule performance index (SPI)
based on what was previously stated?

32 A factor considered in selecting an organizational structure includes The number of projects, contract types, and All are factors to consider in selecting an organizational
the following, except: number of employees structure, except the number of projects, contract types, and
number of employees. PMBOK® p. 47

33 During the weekly risk management meeting, your team is reviewing Plan a new response. This would be the next step.
a high risk situation. They realize that the original response will not
work as planned if the risk occurs. What should the next step be?

34 There is an urgent issue with the distribution of project reports, Communications management plan The escalation process is a component of the communications
regarding the stakeholder communication requirements, the types of management plan. PMBOK® p. 377
reports requested, their frequency and the individual stakeholders
who should receive which reports. The project manager needs to
follow the escalation process to resolve this urgent issue. Where can
the project manager find the escalation process which should be
followed to quickly resolve this issue?

35 When the communications management plan is complete and signed There is never a need to change the An effective communications management plan will change if
off, which of the following is not true? communications management plan once it is conditions require a change. PMBOK® p. 367
complete and signed off by stakeholders

36 The following are advantages of a virtual team, except: Communication planning Communication planning becomes increasingly important in a
virtual team environment. PMBOK® p. 333

37 Communications have a number of dimensions and skills. Which of Negotiation Negotiation is a skill, not a dimension of communication.
the following is not a dimension of communication?

38 For the project that William is the project manager, it has been Behind schedule and over budget The best and correct answer is: Behind schedule and over
identified through earned value analysis (EVA), that the schedule budget. Using the interpretation of results from the PMBOK®
performance index (SPI) is .77 and the cost performance index is .83. Guide, If SPI is less than 1.0 that equals "Behind schedule" and
The project is? for CPI less than 1.0 then the project is "over planned cost or
over budget." PMBOK® p. 267

39 Your project is behind schedule and the decision to contract out some ABC Contractors qualifications Although you have used them in the past, it has been on
of the work has been made. In the past you have worked with ABC smaller projects. You will want to confirm that they can do the
Contractors on smaller projects and want to use them. What should work.
be a concern?

40 There are four main tools and techniques used in the Plan Resource Organizational theory This is one of the tools and techniques in the Plan Resource
Management process. Which of the following is one of these? Management process. PMBOK® p. 312, 318
41 A series of approved changes have been made and your team is Quality audit A quality audit can confirm that approved changes have been
making sure that all of the approved changes are now in place and implemented. PMBOK® p.295
working as expected. They are engaged in what activity?

42 Which of the following validates alignment of a project to the strategy Project charter Creating of a project charter validates alignment of the project
and the ongoing operational work of an organization? to the strategy and the ongoing operational work an
organization, and the project charter is what authorizes a
project and makes a project official. PMBOK® p. 81

43 The performance measurement baseline is: An integrated scope-schedule-cost plan which is The performance measurement baseline is an integrated scope-
for the project work against which project schedule-cost plan which is for the project work against which
execution is compared so as to measure and project execution is compared so as to measure and manage
manage performance. performance. PMBOK® p. 88

44 Which of the following can use focus group sessions? Questionnaires and surveys Questionnaires and surveys, can use focus group sessions.
PMBOK® p. 511

45 A project budget which is controlled by the project manager, includes All the contingency reserves except for all The cost baseline is the approved version of the time-phased
all the funds authorized to execute the project. The cost baseline is management reserves project budget that includes all the contingency reserves
the approved version of the time-phased project budget that includes: except for all management reserves. PMBOK® p. 248

46 In Project Risk Management, the results of the processes: Perform Risk register The risk register records the information from those risk
Qualitative Risk Analysis, Plan Risk Responses, Implement Risk processes throughout the project. PMBOK® p. 417
Responses, and Monitor Risks are recorded in which document?

47 Which information in the scope baseline is used as an input in Plan Project scope statement within the Scope baseline The Scope baseline is composed of the WBS, The WBS
Quality Management? provides definition of acceptance criteria, which Dictionary and the Scope Statement. Be sure to know the
may influences, increase or decrease quality costs importance and details of all 3. See PMBOK® p. 279.
and project costs

48 The output of Identify Stakeholders is which of the following? Stakeholder register The stakeholder register is the output of the Identify
Stakeholder process.

49 The process that provides the key benefit of the overall management Direct and Manage Project Work The key benefit of the process Direct and Manage Project
of the project work and the project deliverables, is: Work, is the overall management of the project work and the
project deliverables. PMBOK® p. 90

50 Jason is managing a project that has earn value (EV) = $50,000. The Ahead of schedule and under budget Performing the calculation for schedule performance index
actual cost (AC) is $30,000. The planned value (PV) = $40,00. The (SPI) = EV/PV, we get SPI = $50,000 / $40,000 = 1.25. Having an
project is: SPI > 1 is good and indicates "Ahead of schedule" Regarding the
cost performance index (CPI) = EV/AC, we get CPI = $50,000 /
$30,000 = 1.67 and 1.67 > 1. A CPI > 1 is good and indicates
"Under planned cost or under budget." PMBOK® p. 267
51 The project management information system (PMIS) can ensure that Team charter Team charter is a document that establishes the team values,
project stakeholders can easily retrieve the project information they agreements, and the operating guidelines for the project team.
need and require in a timely way. Project information is managed and PMBOK® p. 319, 385
effectively distributed using a variety of tools. Which of the following
is not a tool?

52 You have been running the quality control tests without any Failure to follow the scope of the project This is an ethics question and is a failure to follow the scope of
problems. However, your high-priority client is asking that you run an the project.
additional test that was not covered in the project scope. This is a
fairly simple, low-cost test and you perform the test without notifying
anyone. This is an example of which of the following?

53 Two of the companies bidding on part of the construction project Hold a bidder conference. The project manager should hold a bidder conference. Since
have been asking the similar questions. Another company has two companies are asking the same questions and the third has
submitted a bid that is 50% lower than what was estimated for the submitted a bid that is unexpectedly low, there may be some
budget. What should the project manager do next? confusion on the project.

54 The virtual project team consists of people located in the seven Well defined communications and people skills These will be the most critical tools for success
different countries. What will be the most critical tools for a
successful project?

55 During a team quality meeting, it is discovered that some of the parts A defect repair which is performed during the Defect repair which is an intentional activity to modify a
failed quality control. These parts were scrapped and production was process Direct and Manage Project Work. nonconforming product or product component.
stopped. After the root cause of the problem was discovered, the
project manager issued a change order to fix the defective
manufacturing machinery. After this repair is made, the remainder of
the parts met the required quality standards. The repair to the
machinery is an example of which?

56 An Agile Mindset is: A way of thinking and behaving underpinned by The Agile Mindset is a way of thinking and behaving
the four values and twelve principles of the Agile underpinned by the four values and twelve principles of the
Manifesto. Agile Manifesto. Agile Practice Guide, p. 150

57 The project team is preparing to close the construction phase of the Complete any outstanding items on the contract. The team first needs to complete any outstanding items on the
project and prepare documentation for the start of the next phase. contract, and this is performed in the process Control
What is a critical step in closing the phase? Procurements. PMBOK® p. 499

58 The project budget is $5,000 and in month four the CPI and SPI are $5,000 The EAC = BAC / CPI. $5,000 / 1 = $5,000
equal to 1. Assuming that the remaining work continues with the
same indexes, what will be the final estimate at completion?

59 George is reviewing the latest risk assessment and notices one Reserve analysis Reserve analysis compares the contingency reserves to the
particular positive risk is becoming more likely. If it does happen, he amount of risk remaining at any time in the project in order to
can save 5% of the reserves set aside for that portion of the project. determine if the remaining reserve is adequate.
George is evaluating which of the following?

60 You are in the norming stage of the Tuckman model when a difficult Forcing Since you have decided in favor of one side, this is an example
choice needs to be made on the implementation of a scope change. of forcing power.
The senior team lead is pushing for option X because he has
experience in the area. However, the rest of the team wants to use
option Y because it will be using some new technology that will
reduce the complexity of the implementation. You decide that you
will follow the senior member's recommendation. This is an example
of what?
61 What are the main reasons for the Conduct Procurements process? Obtain seller responses, select a seller and award This is the procurement process.
a contract.

62 Peter is asking what a positive risk is as he says risks are all negative. Positive risks are those risks where the project Positive risks those risks that would have a positive effect on
You tell him what? would benefit from an event. the project, such as too many orders.

63 Once the project baselines are created, they may be changed by only When a change request has been approved Approved change requests are the only way to change the
what? through the Perform Integrated Change Control project baselines.
process.

64 As the PM, you have been very busy directing and managing project Project Scope Management The requirements documentation is an output of the process,
work and you have finally completed all of the major deliverables that Collect Requirements which occurs in the Project Scope
were documented in the requirements documentation. The Management Knowledge Area.
requirements documentation is something that is created in which
knowledge area?

65 You are beginning the development of a risk register and the intern Is a repository where the outputs of the risk The risk register contains the results of risk analysis and risk
you are working with asks what it is. You explain that a risk register is management processes are recorded. response planning for both positive and negative risks.
which of the following?

66 Victor has been instructed to build a fishbone diagram for a quality Ishikawa diagram Ishikawa diagrams were developed in the 1960s by Kaoru
problem that the project team has been dealing with. He is not Ishikawa and are also known as fishbone diagrams.
familiar with the term and asks Nancy for assistance. She tells him
that a fishbone diagram is the same thing as a what?

67 Despite detailed planning, a negative risk event occurred. The Create a work around Since the risk has already occurred, the next step is to create a
production of a critical part was delayed by several weeks. What is workaround for the critical part.
the best thing that the project team can do next?

68 At the end of the quality audit, all but which of the following are Approved change requests Approved change requests are an output of the Perform
updated? Integrated Change Control process.

69 A new motor shaft is being developed to replace the current version. Examine the manufacturing process for issues. Although the initial run is within limits, all ten results are over
The dimensions of the shaft are to be 23mm +/- 2mm. You are the specified mean of 23mm. Following the rule of seven, the
running the initial quality inspection of the first run. The first run of process needs to be inspected for problems.
ten shafts has been produced. They all have measurements between
23.0mm and 23.2mm. What should you do next?

70 The new team member works for the ABC company and it has been Make-or-buy analysis A make-or-buy analysis is used to determine whether work or
determined that the new software web interface will be built by the deliverables can best be accomplished by the project or should
XYZ company, rather the software development staff at the ABC the purchase be acquired from outside sources. PMBOK® p.
company. Which tool and technique was used? 473
71 Which is not an output of the process Plan Resource Management? Resource requirements Resource requirements is an output of the process Estimate
Activity Resources. PMBOK® p. 308

72 A change request by a key stakeholder has been rejected by the Document the result of the change request. The project manager needs to document the result of the
change control board. The next action that the project manager needs change request. This way if the issue comes up again, there is
to take is which of the following? already documentation on the request and why it was rejected.
The change log is used as a comprehensive list of all changes
submitted during the project and lists their current status.

73 You are the project manager for a construction company with a $385,000 Estimate at completion (EAC) is the expected total cost of
budget of $300,000 and two months into the project, you find that completing all work expressed as the sum of the actual cost to
there have been several changes in the project and you re-estimate date and the estimate to complete (EAC = BAC/CPI). CPI =
that the project will cost additional money. If the Earned value to date EV/AC = $175,000 / $225,000 = .778 Therefore EAC = $300,000
is $175,000 and the costs incurred are $225,000 calculate the / .778 = $385,000
estimate at completion (EAC):

74 Your project management team is working on the project scope plan The communications management plan needs to The communications management plan needs to be set up very
and the project communications management plan at the same time. be set up very early as it will allow other resources early as it will allow other resources to communicate the
One of the department heads asks why they are working on the to communicate the planning information planning information correctly to the right stakeholders at the
communications management plan even before the scope correctly to the right stakeholders at the right time right time and with the right communication method. PMBOK®
management plan is written. As the project manager, you inform the and with the right communication method. p. 367
department head:

75 Gary is preparing the project baselines. Which of the following does Risk Risk does not have a baseline. The three baselines are
not have a baseline? schedule, cost and scope.

76 The accounting functional manager in your company is asking for Expected monetary value The product of the risk times the impact of the risk is the
financial information about one of the risks in your project. You expected monetary value.
instruct your intern to multiply the 10% chance of an incident
occurring by the financial impact of the event, in this case, $5,000.
The result of $500 is known as what?

77 Risks need to be examined for their probability, impact and either Risk appetite Risk appetite is the degree of uncertainty an entity is willing to
gain or cost. What term describes an organization's willingness to take on in anticipation of a reward.
accept risk?

78 In today's increasingly complicated and competitive global Professional Discipline Today's organizations are seeking added skills besides technical
marketplace, there is much that project managers must be aware of project management skills as the core to program and project
and The PMI Talent Triangle® is key. Bill, a new project manager, is management. Thus today's organizations are seeking added
reviewing The PMI Talent Triangle®, which is not included in The PMI skills in leadership and business intelligence. PMBOK® p. 56, 57
Talent Triangle®?

79 A project team member who is a risk owner has just confirmed that Executing Implement Risk Responses is an executing process, where the
the risk that the risk owner is responsible, has occurred and he must risk plan for a specific risk will be implemented. PMBOK® p. 450
implement the agreed-upon risk plan. What process group is this risk
owner in, if he will implement his risk response plan?

80 The process that frequently occurs for the first time in a project either Identify stakeholders Identify Stakeholders is the process that frequently occurs for
prior to or at the same time the project charter is developed, the first time in a project either prior to or at the same time the
reviewed, and approved, is: project charter is developed, reviewed, and approved. PMBOK®
p. 508
81 The project charter you are working on is being changed frequently by Project sponsor The project sponsor will have the primary authority to allow or
two of the stakeholders. Who has the primary responsibility to decide refuse changes before the charter is complete.
if these changes are necessary?

82 Your project team is reviewing the work completed so far by a key Performance reviews This is a structured review of the sellers progress to deliver the
vendor. The vendor's project manager has brought in documentation requested deliverables according to the contract, and is known
on lessons learned so far in order to identify key performance as a performance review. PMBOK® p. 498.
indicators. What is the activity is currently being performing?

83 A project manager is in the Manage Quality process and has Process analysis A project manager must understand that process analysis is a
conducted a detailed analysis to identify a problem. She conducted technique to be effectively used while executing the Manage
the analysis because she wanted to discover the underlying causes Quality process. PMBOK® p. 292
that lead to the problem. After completing the analysis she developed
actions to prevent the problems from occurring again. The project
manager is most likely conducting:

84 The team is reviewing the requirements traceability matrix while This links the various requirements to their origin See PMBOK® p.165, 719
validating the scope. What is this used for? and tracks them through the project.

85 The quality measures and techniques are: Specific to the type of project deliverables that are The quality measures and techniques are specific to the type of
being produced project deliverables that are being produced. PMBOK® p. 273

86 As the project manager for a complex project you are looking at ways When all obligations have been met by both A contract can be closed by either party when all of the
to make sure nothing gets missed. Which of the following is the best parties obligations are met by both sides. PMBOK® p. 499
condition to close procurements during the project cycle without
penalty?

87 Which of the following is a 'Responsibility' of the project manager? Ensure risk audits are performed at an appropriate The project manager studies the risk management plan and
frequency ensures the proper conduct of risk audits to monitor the risks.
All the other choices relate to the responsibilities of project
sponsor

88 In what process groups should the stakeholder register be updated? All but closing The stakeholder register is used in all the process groups
except closing.

89 Due to the high technical and financial based global project that is in Communications management plan The communications management plan will contain the
progress, the project manager instructed the project team to work glossary of common terminology. PMBOK® p. 377
with the stakeholders and compile a glossary of common terminology,
to ensure anyone on the project will know the various technical and
financial based terms mean. Where will this glossary of common
terminology be located?

90 You are a project manager working on a project that is part of a five The project manager and the project management Even when a project is part of a program or portfolio, the
part program component. There have been some issues about who team project manager and the project management team have day-
should be directing the day-to-day work for the project. Who makes to-day responsibility for running the project. PMBOK® p. 92
the final decisions regarding direct and manage work in a project in a
program.
91 Ginny is reviewing the next month on her project and sees that there Call in her entire team to work overtime for the Crashing the project is bringing in additional resources to
will be a delay later on in the project but she has the authority to next few days. complete critical work faster than initially planned.
crash the project now to prevent the delay. Ginny is planning on
which of the following?

92 Allan is the project manager and is reviewing an upcoming quality The auditing team will inspect the product for Quality audits are a part of assuring that the project activities
audit with his team. Several of the members complain about the extra defects. are in compliance not the product. Inspecting the quality of the
work that will be needed to go through the quality audit. Allan tells product is a part of quality control. PMBOK p 294
the team that quality audits are good for all of the following reasons
except which one?

93 Philip is interning as an assistant to the project manager, Cindy. Cindy The process of aggregating the estimated costs of The definitions can be found in the PMBOK® p. 231
has tasked Philip to prepare the initial steps for putting the budget individual activities or work packages to establish
together. Philip asks what the definition of the budget is. Cindy tells an authorized cost baseline.
him which of the following?

94 Peter is the project manager on a major construction project. The Control Schedule Peter is currently controlling the schedule, and the process is
company uses a construction scheduling management package. Control Schedule.
Currently, Peter is using the software to compare the schedule
baseline to the latest work performance data. Peter is in what
process?

95 An activity list, a network diagram, and a bar chart are good examples Project schedule presentations An activity list, a network diagram, and a bar chart are good
of what? examples of project schedule presentations. PMBOK® p. 176

96 The team has been running into frequent problems and the current Ground rules Although all of the answers are correct, ground rule are
planning meeting has been going very poorly. One team member expectations regarding acceptable behavior by the project
accused another of not providing the agenda for the meeting on time team members. PMBOK® p. 708
and the meeting erupted in shouting and negative behaviors. What is
not being adhered to?

97 An organization is forming a new project office. The new manager has The project charter authorizes you to use The project charter is a formal authorization of the project and
decided to use formal project charters. As an experienced project organizational resources to accomplish the provides the backing to do the work.
manager, why would you encourage this practice? objectives of the project.

98 The project sponsor wants a list of key stakeholders along with their Power / Interest grid The power / interest grid groups stakeholders based on their
level of authority and their concern about the upcoming project. This power (authority) and interest (concern) in the project.
is known as what? PMBOK® p. 512

99 The team is divided between three approaches to solving a problem Identify the causes of the conflict and actively Since the team is not making forward progress, but no one is
and there is a lot of discussion about the methods. A couple of manage the discussion. out of control, the project manager should identify the causes
members are arguing on the side but no one is upset, just very of the conflict and work with the team to manage a
passionate about their viewpoint. The project manager should do collaborative solution. PMBOK® p.348
which of the following?

100 You have identified all of the key stakeholders on a project you have Summary milestone schedule By reviewing the documented milestones or summary
recently been assigned. One key stakeholder is a program manager milestone schedule you are more likely to understand this
from another department and after meeting with her you realize that stakeholders concern and then be able to analyze the impact
she does not want this project to succeed. Apparently there are and come up with a strategy for approaching this situation.
certain requirements on the project that if completed and delivered,
will have a negative impact on her business unit. To understand the
situation better you go back to the project charter. To help you with
this situation you should look at the charter and pay close attention to
101 William is managing a computer programming project and is Analogous estimation Analogous estimation is using a similar previous project to
attempting to evaluate the time required to write part of the estimate work on a current project.
program. Steve and Judy worked on a similar program a few months
ago and it took them a week to complete the work. William uses that
as his estimate. This type of estimation is known as what?

102 The project has been suffering from a variety of problems in reporting A quality audit to review the reports that the The stakeholders are reporting that there is a problem about
work performance data back to key stakeholders. These stakeholders stakeholders are getting against the reports the reports themselves. By starting a quality audit to compare
are getting the reports but they have all complained that the data has specified in the quality management plan. the reports to the standards in the quality management plan,
been confusing. The project manager should start implementing the cause of the problem should be identified.
which of the following?

103 What is the difference between programs and portfolios? A program is a group of related projects, Review PMBOK® p. 13
subsidiary programs, and program activities that
are managed in a coordinated way to obtain
benefits not available from managing them
individually. A portfolio is a collection of projects,
programs, subsidiary portfolios, and operations
managed as a group to achieve strategic
objectives.
104 Regarding the number of resources in the process Estimate Activity Does not always reduce the time to half of the Does not always reduce the time to half of the scheduled time
Durations, doubling the number of resources from the original scheduled time and it may increase extra duration and it may increase extra duration due to the added risk.
number of resources does what? due to the added risk PMBOK® p. 197

105 After Bobby has completed a scheduled network diagram, which is Within data analysis, the simulation tool of the In the process Develop Schedule, and within the tools and
needed to provide the duration of the project, the best way to look at Monte Carlo analysis techniques of data analysis, the simulation tool of the Monte
individual project risks and other sources of uncertainty in this Carlo analysis would be the best tool. PMBOK® p. 213
schedule network diagram and to evaluate their potential impact on
achieving the project objectives, would be:

106 Which process could use tools and techniques such as a "contact me" Manage Project Knowledge Manage Project Knowledge process uses tools and could use
function where users can get in touch with the originators of the tools and techniques such as a "contact me" function where
lessons learned and ask for advice specific to their project and users can get in touch with the originators of the lessons
context? learned and ask for advice specific to their project and context.
PMBOK® p. 103

107 You and the project sponsor are developing requirements for an Detailed timeline The project charter only includes a broad view of the project
internal project. The charter will include all except the following? timeline such as milestones.

108 Steven was engaged in selecting his resources for the quality team he Prevention is about keeping errors out the process A major tenant of Total Quality Management (TQM) is
will lead in on a major project the following calendar year. During the and inspection is about keeping errors out of the emphasizing Prevention over Inspection.
selection process one of the resources asked a quick question hands of the customer.
attempting to clarify understanding related to prevention versus
inspection as it relates to the context of Total Quality Management
(TQM). What is the difference between the terms that is correct?

109 The project team has developed a project schedule. However, they Critical chain method The critical chain method allows the team to place buffers on
find out that a number of key resources will be limited during the the project schedule path to account for limited resources.
project. What method of scheduling should they consider using to
help with this?

110 Who must give the required level of effort so as to implement the Risk owner The risk owner is responsible to implement the agreed-upon
agreed-upon responses to an identified risk? responses for an identified risk. PMBOK® p. 450
111 The project manager informs the team that they need to plan how to Quality management plan This is the plan that will change.
implement the quality policy. If this plan changes, which plan will also
have to change?

112 The company is being bought out and the project that was just started Complete closed procurements as part of the You need make sure that closed procurements are completed,
has been terminated. What should the next step be by the project process Control Procurements. which is part of the process Control Procurement, and then
manager? move to the process Close Project or Phase. PMBOK® p. 499,
123

113 Larry is reviewing the resource management plan and begins to Virtual teams Virtual teams is the tool Larry wants to use.
acquire his team. The project is on a short schedule and Larry is
looking to maximize the time and take advantage of teams that work
in different time zones and different days of the week. The tool that
Larry should be considering is what?

114 One of the sellers has completed their work as specified in the Close out the procurement and start a new The question states that the work is done to specifications. If
contract and you are proceeding to close out the purchase. Your contract for any rework. you need to have some parts reworked a new contract needs
quality team is not satisfied with the work as the machining to be written up. PMBOK® p. 499
tolerances are not as close as they had hoped for. You need to do
which of the following with the seller?

115 Chris is a stakeholder with moderate power and high interest in the Involve Chris as soon as possible and keep him Involving Chris as early as possible and keeping him appraised
project. He supports the project but is concerned about possible appraised throughout the project. of the project is the best course of action.
negative impacts that will happen while the project is going on. The
best course of action for the project manager to take with Chris is
which of the following?

116 When considering a model for suitability of an Agile approach, which Costs The three main categories are: culture, team, and project. Agile
category is not part of the three main categories that are considered? Practice Guide, p. 126, 127

117 Stakeholder analysis includes all but which of the following? Stakeholder register The stakeholder register is the output of the identify
stakeholder process.

118 Nick is preparing to open a new location for his business and is very Develop a quality policy for his business. Nick's focus should be to develop a quality policy as this will
concerned about the quality of the new location. The previous help set the standard for selecting a new site.
location had a number of issues and he does not want to repeat the
mistakes again. He is planning the quality management plan but has
no specifics on the new location. What should he be doing?

119 Tim's team is working on the Control Costs process. They are currently Project funding requirements The project funding requirements is the one item from the
gathering the information they need to work on this. They have the project cost management planning processes (it is an output of
project management plan, work performance data, and the necessary the Determine Budget process) that is used as an input for the
financial organizational assets. What output of the project cost Control Costs process. See PMBOK® p.257
management planning processes do they need?

120 Tina is the purchasing manager for a project management company. Invitation to Bid Since they know what they need and are ready to purchase,
She is working with the PM and together they have a firm list of what they would issue an invitation to bid.
is needed and want to select one vendor with a firm price. What form
of document does she need to send to the vendors?
121 The project manager is reviewing the approved baselined schedule Mark these changes as a proposal and submit a She should not be making these changes as approved without a
diagram and removes a step required to complete another task. She change request. change request.
then changes that task to include the activities for the previous task.
What should she do next?

122 You are into the third phase of a project and your core project team Forming Since they will be adding new members, the best choice is
will be taking on four new members. What stage of the Tuckman forming PMBOK® p. 338, 339.
ladder will they be on when they start this phase?

123 All of the following are outputs from the process Plan Resource Resource requirements Resource requirements is an output of the process Estimate
Management, except: Activity Resources. PMBOK® p. 308

124 Your team is working on providing the initial budget estimate of $200,000 with a range of -5% to +10% The PMBOK defines a definitive budget to be-5% to +10%
$200,000 now that the project is approved. The team is working from
a previous project and are able to present a definitive budget. How
much is the budget?

125 All of the following are examples of 'cost of nonconformance' Destructive testing loss Destructive testing loss is an example of cost of conformance
EXCEPT? while all the other options are examples of cost of
nonconformance. PMBOK® p.283

126 Belinda an experienced project manager is training Sally, a new At greater risk Activities with divergence and convergence are at greater risk
project manager. They have just completed a project schedule for the reason that they are affected by multiple activities or
network diagram and there are several activities with divergence and can even affect multiple activities. PMBOK® p. 194
convergence. Belinda tells Sally, that these activities with divergence
and convergence are?

127 In an Agile/Adaptive environment when is risk considered? When selecting the content of each iteration and Risk is considered when selecting the content of each iteration,
during each iteration and the risks will also be identified, analyzed, and even
managed during each iteration. PMBOK® p. 400

128 You are currently working on validating the scope on your project. Reviewing the performance of an installed Validate Scope process looks at the verified deliverables that
Which of the following will you be doing? software module with the customer have been produced on the project and makes sure that they
match up against what was documented in the requirements.

129 During the procurement process, you discover that a college friend is Tell the selection committee that you have a Letting the committee know about the relationship and
the project manager for her company's portion of the project. She personal relationship with the vendor and request requesting that you be excused from the decision making
tells you that if her company is selected, she will get a much deserved that you not be involved in the selection process is the ethical thing to do. PMI Code of Ethics
promotion. You need to do which of the following? committee.

130 The project team is having their retrospective review and determining Agile Velocity is an Agile term and can be used in regards for the
the velocity. What type of approach are they using? Control Schedule process. PMBOK® p. 224
131 Risk appetites refers to what? The degree of risk which a stakeholder can take in If there is a known reward for the risk taken, it is referred as
anticipation of a reward the appetite for taking that risk.

132 One of the key functions of the project manager during directing and Communicate This is the main activity for the project manager.
managing the project is to do what?

133 The project was approved but a large number of minor requirements Have weekly meetings to review the work that will There is no need to have weekly meetings.
that stakeholders wanted were not included in the project. The not be done.
project manager is concerned about scope creep as stakeholders try
to slip in these unapproved requirements in the change control
process. Which of the following would not be a method of preventing
these change requests?

134 You are working on a new public building and are reviewing the Prioritize the register by influence and interest. Classify and prioritize the register with a influence and interest
stakeholder register. It contains over fifty people and organizations. grid. PMBOK® p. 512
Managing the stakeholder expectations on an individual basis will be
very impractical. What should your next step be?

135 Your time will be limited to spend with the stakeholders. Which The head of the department that will be using the This is the key stakeholder that you need to engage to improve
stakeholder would be most important to work with? product. He is not actively engaged in the project. his/her interest.

136 How often is the Perform Qualitative Risk Analysis process done As many times as is listed in the risk management Performing qualitative risk analysis can be done a number of
during a project? plan times and this frequency is found in the risk management plan.
PMBOK® p. 421

137 Which project document will be created early in the planning of the Lessons learned register The lessons learned register is being described here and is
project, and include impacts, recommendations, as well as proposed created early in project planning. PMBOK® p. 104
actions within a given situation?

138 Which of the following is used as an important tool and technique Facilitation Facilitation is the ability to effectively guide a group event to a
while developing a project charter? successful decision, solution, or a conclusion. A facilitator will
ensure that there are effective participation and that
participants achieve a mutual understanding, and that all
contributions are considered, so that conclusions or results
have a full buy-in according to whatever decision process has
been established for the project. PMBOK® p.80

139 The Control Procurements process is tied closely to other monitoring Perform Integrated Change Control This is the process that the contract change control is
and controlling processes. Which process is the contract change integrated with. PMBOK p.493
control system integrated with?

140 You are going to be negotiating the contracts in the next few days. Creating and maintaining a relationship so that the The main consideration is to create a successful relationship to
What is your main objective with the negotiations with the seller? project succeeds. make the project successful.
141 A stakeholder wants more functionality for a product added that was Management reserves are reserved for Management reserves are reserved for unforeseen work that is
not included in the original scope for the project. This stakeholder unforeseen work that is within the scope of the within the scope of the project. As this stakeholders request is
who is very important to the project, states that management project. clearly out-of-the project scope, then management reserves
reserves can be utilized for this request, even though they were not could not be used. Although the project manager does not
part of the original project scope. As the project manager, how would control the management reserves, the project manager must
you answer what the purpose of management reserves are? manage the scope of the project. PMBOK® p. 202

142 The triple constraint of project management is composed of the Cost, Schedule, Scope The triple constraint or iron triangle of project management
following? are cost, schedule and scope.

143 You are a project manager for XYZ. You are working on a project to The project sponsor at XYZ Although ABC will be doing the work and they will have a
expand the manufacturing capacity for your department. The project manager for the construction, the sponsoring
construction of the new facility will be outsourced to ABC. Who organization is XYZ The charter will be approved by the sponsor
approves the project charter for this project? at XYZ.`

144 You have been asked to provide a budget estimate. However, you are The project scope is poorly defined. The difficulty with having a basis for the estimate will most
having extreme difficulty coming up with a basis for the estimate. likely come from a poorly defined scope.
What is a likely reason for your difficulty?

145 If a project has management reviews to identify various points in the Project management plan Project management plan is the correct answer where
project when the project manager and the relevant stakeholders will management reviews would placed, maintained, and updated.
review the progress of the project so as to determine if the project PMBOK® p. 88
performance is as expected, or whether preventive or corrective
actions are deemed necessary. Where would this information be
placed, maintained, and updated, according to the PMBOK® Guide?

146 In an Agile environment, a feature chart, would contain all of the Number of features that are risks Features Complete, Remaining and Total are what the Feature
following, except: Chart will contain. Agile Practice Guide, p. 67

147 In which process groups are stakeholders identified? Initiating, planning, executing, and monitoring and Stakeholders can be identified in all process groups but closing.
controlling.

148 In the planning of procurements, make-or-buy analysis is used to: Determine whether deliverables can be most Determine whether deliverables can be most appropriately
appropriately done internally or externally done internally or externally is the best answer. PMBOK® p.
473

149 Tim's project team is diligently working and have a deadline to Just accept the changes as there is no need for a As the PMBOK® Guide states: "Before the baselines are
complete all the planning work in the 30 days. The various project formal change control process to be followed since established, changes are not required to be formally controlled
baselines have not yet been established. There are several cost re- the various project baselines have not yet been by the Perform integrated Change Control process. Once the
estimates as the previous cost estimates were incorrect and had to be established project is baselined, change requests go through this process."
re-done. Since the team is working in the Perform Integrated Change p. 115
Control process, what should happen next:

150 While writing a report, you discover that a business user never Recommend a preventative action to reduce the Preventative actions reduce the possibility from risks. As this
performed the test that was required. This employee wrote an email possibility of this occurring again. incident was not a risk, a preventative action is not required.
to his supervisor that you need to have one of your team members do
this test. You are now concerned that having to divert one of your key
team members to do the work will prevent the project from meeting
its next milestone. All of the following are true except which of the
following?
151 During the process Collect Requirements, there are data-gathering Requirements documentation Requirements documentation is an output of the process
techniques that are utilized. Of the following, which is not a data- Collect Requirements and describes how individual
gathering technique used by the Collect Requirements process? requirements will meet the business needs of the project.
PMBOK® p. 147

152 The project charter has been changed multiple times since the project The project sponsor Normally the project charter does not change once approved.
was first proposed. Who has to make the decision if the changes are However, changes to the project charter are managed by the
to be approved? project sponsor, while the change control board approves
changes to the project plan.

153 The process that brings objectivity to the acceptance process as well Validate Scope The Validate Scope process brings objectivity to the acceptance
as increases the probability of the final product, service, or result process as well as increases the probability of the final product,
acceptance, is: service, or result acceptance by validating each deliverable.
PMBOK® p. 163

154 There has been a change to the cost baseline. What portion of the Management reserve The management reserve is not part of the cost baseline.
budget does not necessarily change? PMBOK® p. 255

155 Tim is concerned about one of the unions on the bridge building Level of influence The level of influence is the amount of power and resources
project. They are not very involved in the project, and this is the cause that a stakeholder can use on a project. This should be
of his concern. This particular union could make the project very determined during the stakeholder analysis.
difficult or very easy depending on how they get involved. The degree
to which this stakeholder may be able to affect a project is known as
what?

156 In flow-based Agile, the team: Pulls features from the backlog on its capacity to In flow-based Agile, the team pulls features from the backlog
start work. based on its capacity to start work rather than on an iteration-
based schedule. Agile Practice Guide, p. 25

157 A project has a CPI of .9 and a SPI of .78. Of the following, what is the The critical path took longer and cost more than Since the CPI and SPI are under 1.0, this means the schedule
best explanation for this occurring? expected. took longer and is behind schedule and the cost were more
than planned for and thus costs were over the planned cost.
PMBOK® p. 267.

158 The project team have had a number of problems with the vendor Hire a mediator to help resolve the issue. Having a mediator is the best course of action without having
and it has been decided and supported by senior management to to enter into a formal legal proceeding. PMBOK® p. 498
terminate the contract. The vendor is demanding full payment but the
deliverables were not completed. What is the next best action?

159 There are three risk themes or attitudes that can affect an Risk register The risk register documents the results of risk analysis and risk
organization and stakeholders. Which one of these is not considered response planning.
an attitude regarding risk?

160 Your team has been working extensively over the phone regarding a Written communications Your team would benefit from written communications in this
problem on the project. Everyone has become frustrated because of case. Written communications could include charts or pictures
the lack of progress at resolving the issue. Everyone has a different as well as a statement that everyone can use and eliminate
perspective on it and there is no clear understanding. What type of misinterpretation.
communication would help in this situation?
161 In an Agile environment, software product development, like other Scope and Schedule baselines According to the Agile Practice Guide, learning takes place by
knowledge work in project management, is all about learning and experimenting, delivering small increments of value, and
learning while delivering value. Learning in Agile takes place by all, getting feedback on what has been accomplished thus far.
except: Agile Practice Guide. P. 61

162 Which is not an input to the Direct and Manage Project Work process? Work performance data Work performance data is an output of the Direct and Manage
Project Work process. PMBOK® p. 90

163 The project is implementing a new quality system and the quality Perform a quality audit A quality audit is an independent process to determine if a
department is doing its own investigation of this new system. What project activities comply with organizational and project
action does this department take to make sure the new system is policies, processes, and procedures. PMBOK® p. 294
working?

164 The cost of quality is the cost to produce the product with the quality Actual costs Actual costs are part of the EVM and not used in the cost of
standards in the project. There are three costs of quality, which of the quality.
following is not among them?

165 The final deliverables have been accepted by the internal department. Benchmarking Benchmarking is not a tool used in closing the project.
What is not a tool of project closure?

166 Your city building commission has hired your company to research the Risk management plan During the initiation phase of stakeholder management, you
construction of a new park. As the project manager, you are preparing will not have the risk management plan developed yet.
a list of potential stakeholders. Which document will you not need?

167 There are a number of complicated issues that will need to be Formal and written Dealing with complex issues should be formally written
communicated. What is the best way to handle this?

168 Your company's key project was delivered on time and on budget. You Audit the procurements from all vendors. Procurement audits from all vendors is a requirement to
are finally closing out the procurements. One of them was a cost- complete the Control Procurements process.
reimbursable contract. What do you need to do first?

169 You are writing the regular project document updates for the project. Project communications This is an output of Project Communications Management.
What tool would not be useful? PMBOK® p. 360, 387

170 Sylvia is working on identifying risks. Her team has some experience Delphi technique The Delphi technique provides an anonymous summary of
in the field they are working on. However, she is concerned about the experts.
team missing risks that someone with more experience would be
familiar with. She would like to get reviews from unbiased experts
that are otherwise anonymous to the team in order to keep the team
focused on the risk management plan. What would be the best
method for this situation?
171 Your CEO has handpicked your team on the project you are managing. Formal power It is not stated that you are an expert in your field or that you
He tells everyone that he believes that your team is among the best in yourself were handpicked by the CEO. Therefore, your only
the company. The power you have as project manager is best power is formal power as the project manager.
described as which of the following?

172 Adam Burger was leading a special project at his organization. He Conducting inspection(s) and identifying defects Adam was engaged in using the tools and techniques of the
hired a group of quality experts with manufacturing engineering using quality tools Control Quality process.
expertise. The manufacturing process being used by the team was still
resulting in products that had many defects. Adam was able to
determine this by:

173 Planned value (PV) is also known as: Budgeted Cost of Work Scheduled (BCWS) Planned value (PV) and Budgeted Cost of Work Scheduled
(BCWS) are synonymous. However, BCWS is an older acronym
that could appear on the exam. The calculation for BCWS =
hourly rate x total hours planed or scheduled. Although BCWS
is the older acronym, it is a description of PV.

174 Amber the project manager just realized her project is running over CPI < 1 and SPI < 1 Over budget is CPI < 1 and behind schedule is SPI < 1. PMBOK®
budget and behind schedule. Amber wants to make sure that her p. 267
project team understands how to interrupt the cost performance
index (CPI) and the schedule performance index (SPI). Given the
situation presented, which would be true regarding the cost
performance index (CPI) and the schedule performance index (SPI)?

175 The team is meeting regarding a new feature that another part of the Gold plating. Gold plating is adding features that are not requested.
company is using. This feature is not referenced in the project scope.
What is this known as?

176 In an Agile environment, what is a daily scrum? A brief daily collaboration meeting in which the A "Daily Scrum" also known as a "Daily Standup" is a brief daily
team reviews progress from the previous day and collaboration meeting in which the team reviews progress from
declares intentions for the current day, and the previous day and declares intentions for the current day,
highlights any obstacles encountered or even and highlights any obstacles encountered or even anticipated.
anticipated. Agile Practice Guide. p. 151

177 For a project lasting 12 months, how often should the stakeholder It should be reviewed on a regular basis but The stakeholder engagement plan should be reviewed on a
engagement plan be reviewed during the execution of the project? determined by the project manager regular basis. The project manager might need to adjust the
timing depending on what is going on during the project.

178 In an Organic organization structure, the project manager's authority Little or none In an Organic or Simple organization structure, the project
is? manager's authority is little or none. PMBOK® p. 47

179 You are working as a part-time project coordinator for a software Functional Since you are a project coordinator, you are most likely in a
company. You find, however, that a significant part of your effort is to functional organization and staff reports to their functional
get a certain developer from another department. What type of manager. PMBOK® p. 47
company are you working for?

180 Which of the following human resource theories states that human Maslow's hierarchy of needs This was proposed by Abraham Maslow in 1943.
beings have basic needs and that people need to meet lower-level
needs before they can move onto the next level of needs?
181 Which of the following is the most commonly used contract and most Firm fixed price This is the most common contract and the seller has to deal
advantageous to the buyer? with any risks

182 A manager in your project has changed and the new person is Project Management Information System (PMIS) This PMIS would allow the team to produce a custom report for
requesting a progress report. Which tool should you direct your staff the new manager.
to use to provide this for him?

183 Which is the following represents all the product and project work, The WBS The WBS represents all the product and project work, including
including the project management work? the project management work. PMBOK® p. 161

184 What is the definition of decomposition? Decomposition is a technique used to break down This is the correct definition.
the project scope and project deliverables into
more manageable parts.

185 Janice, a new project manager and working on her project, has just Crashing Crashing a schedule compression technique is used to shorten
been informed by the project sponsor, to shorten the schedule the schedule duration for the least incremental cost by adding
duration for the least incremental cost by just adding resources. resources. PMBOK® p. 215
Which is the best technique for Janice to apply in this situation?

186 Your project is on budget and on schedule. Your team has come up Report on the project status that it is on budget This is the objective of the status meeting.
with a demo for the sales team to use for making their presentations and on schedule and inform them that demo
to prospective customers. You will do which of the following at the presentation is complete.
next stakeholder project status meeting?

187 Project stakeholders are: People, groups, or organizations that could impact Identify Stakeholders. The process of identifying the people,
or be impacted by a decision, activity, or outcome groups, or organizations that could impact or be impacted by a
of the project. decision, activity, or outcome of the project; and analyzing and
documenting relevant information regarding their interests,
involvement, interdependencies, influence, and potential
impact on project success. PMBOK® p. 507

188 The project manager is reviewing the latest change requests from the Project charter If a requested change is going to fundamentally change the
quality management stakeholders. He believes that some of their nature of a project or should be reviewed as a separate project,
requested changes modify the overall scope of the project and should the project charter should be checked.
be its own project. He should refer to which document to confirm his
findings?

189 The building has passed the final fire inspection. What should the next Update the stakeholder register and mark the fire The stakeholder register should be updated when a
step be? warden as no longer involved. stakeholder is no longer impacted by the project.

190 In an Agile environment, using the Kanban Method, what is the most Done According to the Agile Practice Guide, in the Kanban Method, it
important column in a Kanban Board? is more important to complete work, than it is to start new
work. There is no value derived from work that is not
completed. The team works together to implement and adhere
to the work in progress (WIP) limits and to get each piece of
work through the system to "done". Thus "Done" is the most
important column in a Kanban Board. Agile Practice Guide p.
105
191 The budget for your project was based on historical data and you Start a change request. Any change to the authorized budget needs to go through the
discover that the cost would be less than what your contingencies formal Perform Integrated Change Control Process. The only
would allow for. You have determined that the approved budget will way to start that is to submit a change request. PMBOK® p. 259
need to be increased but you are aware that another critical project
just gained approval. Your next action should be?

192 Janice a new project manager, asks her mentor Ryan, which part of Prevention Costs Thoroughly documented processes within the Cost of Quality
the Cost of Quality (COQ) are thoroughly documented processes? (COQ) are part of the Cost of Conformance under Prevention
Costs, which is money spent during the project to avoid
failures. PMBOK® p. 283

193 Inspection is a technique used in the 'Validate Scope' process. The Acceptance of the deliverables In 'Validate Scope' process, the customer reviews the
main purpose of using this technique in this process is to deal with: deliverables in the user acceptance test environment and if
'PASS', will accept the deliverables.

194 The team external to the project is preparing for a quality audit and Quality control measurements This is an input to the Manage Quality process. PMBOK® p. 291
they are gathering the materials for this. What do they need?

195 Bryant has been asked to help choose one of the four potential Project A requires making an initial investment of A is the best candidate as its ANNUAL return is $60,000 per
project candidates. Management normally uses the internal rate of $100,000 and will give monthly return of $5,000. year for the investment of $100,000. Make sure to convert
return technique for project selection. Which of the following projects months into annual.
is the one he should recommend?

196 As part of the communication process, who is responsible for the The sender The sender is responsible for the transmission of the message
transmission of the message and must ensure that the information and must ensure that the information that is being
that is being communicated is both clear and complete and must communicated is both clear and complete and must confirm
confirm that the message is correctly interpreted? that the message is correctly interpreted. PMBOK® p. 372

197 What type of management will utilize the tools and techniques of: Information management Information management used the tools and techniques listed.
lessons learned register, library services, information gathering, and PMBOK® p. 103
the PMIS?

198 The bridge has been completed and is now undergoing validation by Formal acceptance Scope validation results in formal acceptance
the state authorities. If successful, this will lead to which of the
following?

199 The team has announced that they added a much needed but not Gold plating Gold plating is adding unrequested features to the product.
requested feature to the product. This is known as what? This can result in the product being out of scope or adding risk
as these new features may require further testing.

200 Diagrams which are meant to link underlying causes to effects are Ishikawa diagrams A cause and effect diagram, also known as a Ishikawa diagram
known as is a tool for categorizing the causes of a problem so that we can
identify the root causes.