You are on page 1of 150

ID NO.

13
44

ERECTION GUIDELINES

FOR

500 MW

BOILER PRESSURE PARTS

{COAL FIRED CONVENTIONAL TWO PASS DESIGN)

BHARAT HEAVY ELECTRICALS LIMITED


POWER SECTOR-SOUTHERN REGION
QUALITY DEPARTMENT
CHENNAI - 600 035.
DOC. No.: PS:QLY:017
Rev. No.: ROO/09-04

Quality is the key to Productivity and Prosperity

1
ERECTION GUIDELINES
FOR

500 MW

BOILER PRESSURE PARTS


(COAL FIRED CONVENTIONAL TWO PASS DESIGN)

PREPARED BY
& B H E L : P S S R : QUALITY
APPROVED BY
AUTHORISED TO BE
HEAD - QUALITY
USED BY
PS-SR : CHENNAI

PS:QLY:017 ID No. DATE OF ISSUE


DOCUMENT No.
R00 / 09-04 1344 04-09-2004
CONTROLLED/ No. OF
COPY No: PAGES:
COPY 139
(D'Devasah m,
ISSUED TO: Dy.Manager / uality)

BHARAT HEAVY ELECTRICALS LIMITED


POWER SECTOR - SOUTHERN REGION
QUALITY DEPARTMENT
CHENNAI - 600 035
INDEX

SI.No. DESCRIPTION No. OF


SHEETS

1. INTRODUCTION 6

2. BOILER DRUM 48

3. ERECTION OF HEADERS 14
st
4. ERECTION OF 1 PASS RADIANT ROOF 5

5. ERECTION OF WATER WALL SH STEAM COOLED WALL 17

6. DOWN COMER ERECTION 5

7. ERECTION OF CONTROLLED CIRCULATION PUMPS 10

8. ERECTION OF COILS 25

9. ERECTION OF BUCKSTAY 22

10. VOIDS THAT ARE TO BE CLOSED IN PRESSURE PARTS 3

11. RECOMMENDED HYDROSTATIC TEST PROCEDURE 19


INTRODUCTION
BOILER P R E S S U R E PARTS

Introduction

The general arrangement of pressure parts of a conventional Two pass design boiler of
500 M W unit is shown in Fig.1 (First pass) and Fig.2 (second pass). The locations of
Pressure part components and assemblies are also indicated in the figures.

At job site, the main function of erection group is to receive the components, store them,
protect them from damage, preserve them during storage to sustain the original condition
and assemble them within the permissible limit/tolerance specified in the "Boiler pressure
parts Engineering Checks for Erection" (Pub.2022) to achieve pre-determined
performance during operation.

Around 4,480 tonnes of pressure parts components per unit are despatched loose to the
job site by road and rail. Hence, it becomes all the more important for the job site erection
group to take utmost care right from the receipt stage to completion of erection, so that
commissioning activities can proceed without any difficulties.

The major components in pressure parts to be erected are boiler drum, headers, water
walls and steam cooled walls, superheater, reheater coils, economiser coils and
buckstays.

Recommended hydraulic test procedure, welding & N D E are also covered in this section.

GENERAL NOTES:

1. Ensure that the component/parts are erected as per the latest applicable
contract drawings.

2. Read the drawing carefully and take care to note the specific erection points
given in the drawing.

Bharat Heavy Electricals Limited


BOILER P R E S S U R E PARTS

Fir.,1. HOI1.ER PRESSURE PARTS (1 PASS^

Bharat Heavy Electricals Limited


BOILER PRESSURE PARTS

01. DRUM
02. DOWN COMER
03.SUCTION MANIFOLD HEADER
04. CIRCULAR PUMP a.J2S3S
05. DISCHARGE LINES
06. LOWER RING HEADER
07. WW HOPPER
08. FRONT WW OUTLET HEADER
09.SIDE WW OUTLET HEADER
10. REAR 'WW HANGER OUTLET HEADER
11. REAR WW SCREEN OUTLET HEADER
12. VACANT
iJ.ECO. INLET HEADER
.ECO. COIL ASSY - LOWER
15. ECO. COIL ASSY - INTER
16. EC0. COIL ASSY - UPPER
17. EC0. OUTLET HEADER
18. EC0. LINKS TO DRUM
I9.SH. SATURATED CONNECTING TUBES
20.SH. RADIANT ROOF INLET HEADER
21.SH. RADIANT ROOF OUTLET HEADER
22. SH SIDE WALL INLET HEADER
2J.SH. SIDE WALL OUTLET HEADER
24.SH. FRONT WALL INLET HEADER
25. SH. REAR WALL INLET HEADER
26.5H/EC0 SUPPORT HEADERS
27. SH. REAR ROOF JUNCTION HEADER
28. LTSH INLET HEADER
29. LTSH COIL ASSY
30. LTSH OUTLET HEADER
31.SH. DESUPERHEATER
T
?.S«. DIVISION PANEL INLET HEADER
.3.SH. DIVISION PANELLETTES
34.SH. DIVISION PANEL OUTLET HEADER
35.SH. PLATEN INLET LINKS
36.SH. VERTICAL PLATEN INLET HEADER
37.SH. VERTICAL PLATEN ASSYS
38.SH. VERTICAL PLATEN OURET HEADER
39. RH. INLET HEADER
40. RH. FRONT ASSYS
41. RH. REAR ASSYS
42. RH. OUTLET HEAOER
43. WW TUBES
44. EXTV. SIDE WW TUBES
45.SH. RAOIANT ROOF TUBES
46. SCW TUBES
47.SH/EC0 SUPPORT TUBES
48.RISER TUBES
49.STEAM COOLED SPACER

FIG.2. BOILER PRESSURE PARTS (II PASS)

Bharat Heavy Electricals Limited


BOILER
Erection BOILER P R E S S U R E PARTS

3. All the components of pressure parts are given Mark Nos./ DU Nos. with P G M A
for the erector to identify with Mark No. indicated on erection drawings and erect
at the proper locations.

4. Take care to see from receipt at site till completion of erection the above
identification mark number /DU numbers painted on the components are
preserved properly. If necessary identification markings shall be repainted
carefully.

5. The erection welds between pressure parts to pressure parts/Non pressure


parts are shown in the erection drawings or Erection welding schedule. Erection
welding Schedule gives the details of all erection welds and cross reference to
these drawings wherein these welds are located. All butt joints in Pressure parts
are to be done with TIG root welding. All attachment welds on to pressure parts
are to be done with Basic coated low Hydrogen electrodes.

6. Comply with the field weld procedures while carrying out the welding.

7. Hydraulic test is to be conducted after all welding of pressure parts and non
pressure part attachments on to pressure parts are completed.

8. After site hydraulic test of the boiler no welding shall be performed in pressure
parts.

9. Prior to erection, all headers, lines, links, tubes, elements, panels etc. shall be
checked for clear internal passage.

Bharat Heavy Electricals Limited


BOILER
Erection BOILER P R E S S U R E PARTS

10. Erected items should be protected from workmen climbing on them and water
falling on them. Caps shall be left on tubes and links until final fit up and
welding.

11. Erection attachment/lifting attachments that are welded to the components shall
be removed / cutoff after completing the erection without damaging the
component (Eg. Panels, coils, downcomer etc.)

12. Check the entire boiler to make certain that, all temporary ties to structural steel
are removed.

13. With the help of expansion movement diagrams (released under PGMA-00-030)
check to see that thermal movement of any pressure part is not restrained.

14. Check to see that the expansion indicators are properly installed.

15. Check particularly around furnace bottom for interference from movements of
boiler. If ash hopper is installed make sure that adequate clearance is provided
for downward/side ward movement of furnace walls headers.

16. Ensure that all voids in fusion/fin welded (Peg and flat fin) panels including
erection / lifting slots are closed in furnace/roof and back pass walls.

Bharat Heavy Electricals Limited


(
* n i t m ]
BOILER
fffta Erection

BOILER DRUM

Bharat Heavy Electricals Limited


BOILER DRUM

1. TRANSPORTATION OF DRUM:

Boiler Drum is transported by a special wagon "KAVERI"


Ref. : Fig Nos. 3A & 3B

1.1 Preparation for unloading:

Before arrival of steam drum at site, the following preparation will be made
ready for unloading.

1) 2 Nos. 75 MT capacity, cranes for unloading.


2) 2 Nos. 4" wire rope slings
3) wooden sleepers - 4 inch x 8 inch x 8 ft - 300 Nos.
4) Pulling machines 6T capacity - 2 Nos.

On receipt of steam drum at site, two cranes of 75 MT capacities will be


positioned on one side. The drum will be rotated with the help of crane so as to
make erection lug on the top. Two tie members of the wagon will be removed.
Wooden sleepers around 100 Nos. will be laid below the central portion of drum
and supported at the center. Now the cranes will be positioned near rear end
and this end will be lifted by about 300 mm using 4" slings. Wooden piece tied
with manila rope may be used below the slings to avoid damages due to
slinging.

After lifting the rear end, the rear portion of wagon will be pulled out using 6MT
capacity pulling machines anchored else where. The wooden sleepers will be
stacked below the rear end as per Fig. No.4 so as to support the rear end.
Similarly the front end of the drum will be lifted with the help of cranes and this
end also will be packed with wooden sleepers so as to support the front end.

Bharat Heavy Electricals Limited


BOILER DRUM

Bharat Heavy Electricals Limited


BOILER DRUM

rt-H. AUGtO END ViCi','

FIG. m

Bharat Heavy Electricals Limited


BOILER DRUM

Bharat Heavy Electricals Limited


BOILER
Erection
BOILER DRUM

2. Preparations for Drum skidding:

1. Drum skids - 3 Nos.


2. 6 shieve pulley blocks - 80 MT capacity -2 Nos.
3. 1" wire rope.
4. 10 MT capacity Electrical winch
5. 90 lbs rails - to be laid over the sleepers up to furnace cavity.
6. Rubble soled ground for laying rails.
7. 75 MT capacity cranes - 2 Nos. - for assisting and changing direction.

Using 2 Nos. 75 MT cranes, the drum kept over the wooden sleepers will be
slowly lowered over the drum skids, which are kept over the rails. (Details of
drum skid is shown in fig.5). It is possible by lifting alternate ends and removing
the sleepers sequentially. Wire rope will be tied over the drum along with skids.

One of the 6 shieve pulley block will be connected to the front end drum skid
with one inch sling and other 6 shieve pulley block will be kept near boiler
column which are either connected with build up I beam or 4" wire rope. 10 T
electrical winch will be positioned near Boiler column in Boiler area. One-inch
wire rope on winch will be connected to both the 6 shieve pulleys through guide
pulleys. Grease will be applied over the rails (three rows) for smooth skidding of
drum.

Skidding operation will be started initially by lifting the front end of drum slightly
with crane & operating the winch.

Bharat Heavy Electricals Limited /3


BOILER DRUM

Bharat Heavy Electricals Limited


BOILER DRUM

V. Final inspection before drum lifting:

1. All the H S F G bolted connection of main structure shall be inspected as per


the procedure.

2. Rocker position shall be checked and recorded.

3. Proper anchoring of winches shall be checked and ensured.

4. Anchoring of all guide pulleys checked.

5. The insulation resistance of winch motors shall be meggered.

6. Alternate power supply shall be kept ready.

7. All four drum-lifting wire ropes shall be physically checked for any damages.

8. Communication and lighting arrangement shall be ensured.

9. Interference of wire ropes shall be checked and free movement ensured.

10. Approach for all pulley blocks and rocker plates shall be ensured.

11. Persons shall be identified for proper signaling, winch operation and
inspection during erection.

Bharat Heavy Electricals Limited


BOILER DRUM

IMPORTANT NOTE

VI. ERECTION OF STEAM DRUM:

Methodology for drum erection can be arrived at by the task performers in


consultation with Facility Engineering, PSSR-HQ

VII. MINIMUM STRUCTURE COMPLETION PRIOR TO DRUM ERECTION

Minimum structures to be erected before drum lifting shall be in line with


Field Quality Plan (FQP) for the specific project and recommendations
from Engineering, BHEL, Trichy.

Bharat Heavy Electricals Limited


BOILER
Erection BOILER DRUM

D R U M INTERNALS.

Adopt the procedure given below to assemble the drum internals at site.

1. Study the concerned contract assembly drawing before start of the internal
assembly.

A typical cross sectional view of drum internal is shown in Fig. 12A.

2. While dismantling drum internals at site, match marks to be made so that


same sub assembly component is fitted in the same place during re-
assembly.

3. seal welding is to be done only as per arrangement of drum internal drawing.

4. All bolted connections are to be used with double washers. One at the back
of nut and the other at the front of bolt and ensure that the washers cover
the holes/ slots fully.

5. Inspect all vent and drain holes in the internals to make certain they are
open.

6. Ensure that the weld joint of feed pipe are leak proof.

7. The drier sections are not to be welded together nor to the drier supporting
structure. But the supporting structures to be seal welded to the drier base
angle as per arrangement shown in Fig. 12D.

8. Ends (entry and exit) of secondary separators must be opened for steam
passage. Refer Fig. 12B.

9. Ensure that all parts of separating chamber are fitted without any gap. The
welds at the joints should be complete and leak proof.

Bharat Heavy Electricals Limited


BOILER DRUM

FIS.J2A.QRUM INTERNALS
(FOR CONTROLLED CIRCULATION)

Bharat Heavy Electricals Limited


BOILER DRUM

10. Check whether the primary separator is damped to its supports rigidly with
its axis vertical so that it does not tilt or fall during operation. Refer Fig : 12B.
A tolerance of ± 5mm is allowed in the vertically of turbo separator.

11. Check whether the passage through individual screen drier boxes are free
from foreign material. Refer Fig:12C.

12. Check whether the screen driver boxes are fixed with each other such that
the gap does not exceed 1 mm.

13. Ensure that drum is free of all foreign particles especially tools and electrode
bits may remain inside after the erection of internals.

14. Before closing the manhole door, see that manhole door gasket is in perfect
condition.

15. Check whether the downcomer cover assembly has been installed over the
downcomer openings to avoid vortex formation during operation.

16. Check for the orientation of holes in blow down pipe. These holes are to be
in the direction opposite to chemical dosing pipe.

17. The holes in the chemical dosing pipe should be facing towards the feed
distribution pipes.

Bharat Heavy Electricals Limited


BOILER DRUM

Bharat Heavy Electricals Limited


ERECTION OF HEADERS

Bharat Heavy Electricals Limited


BOILER
Erection ERECTION OF HEADERS

1. Checks on supporting structure prior to erection:

a. Check the dimensional correctness of the pressure parts supporting structures


(RBs/WBs) with respect to reference axis shown in the structural drawing.

Note : For erection of supporting structure, the drawings given in structural group
are to be followed. For the header location with respect to reference axis the
pressure parts drawings are to be followed. There will be a difference in dimension
of the centre line of supports at the top and centre line of header with respect to
reference axis. This difference is preset to accommodate thermal expansion as
shown in the Fig.1.

A - Presetting for that particular suspension depends on ' 0 '

D - Distance from origin of expansion

X - Distance of the pressure part component that is suspended


from reference structure.

X+A Distance of the suspension point on the structure from the reference
structure.

For the dimensions and the amount of presetting refer the contract
drawing.

Bharat Heavy Electricals Limited


ERECTION OF HEADERS

ORIGIN OF
EXPANSION

A - PRESETTING FOR THAT PARTICULAR SUSPENSION DEPENDS UP ON - D

D- DISTANCE FROM ORIGIN OF EXPANSION

X - DISTANCE OF THE PRESSURE PARTS COMPONENT THAT IS SUSPENDED


FROM REFERENCE STRUCTURE

FOR THE DIMENSIONS AND THE AMOUNT OF PRESETTING

REFER CONTRACT DRAWING

FIG. 1- H E A D E R S U P P O R T WITH O F F S E T ( T Y P )

Bharat Heavy Electricals Limited


j B 0 I L E R

I Erection ERECTION O F HEADERS

2. Check the following on headers:

a. Orientation of the headers.

b. Axis marking at the ends in the II & IV quadrants.

c. Left/right marking for the headers parallel to drum axis.

d. Front/Rear marking for the headers perpendicular to drum axis.

e. Flexible hose test for long stubs of the header to ensure free passage.

f. Sponge test for open-end header stubs.

g. The bow in both the planes, scarfing line and stub verticality. Clean the
weld edge preparation and apply weldable primer and fix all end caps.

h. Check the IBR inspection seal on the header.

i. Before erection of Header Ground Inspection by Boiler Inspector of


Concerned State to be completed.

3. Erection of hanger rods.

- Position the bearing plate over the support channels as per the structure
drawing dimension and tack weld as shown in the fig :2.

- Insert the hanger rods/tie rods through bearing plate and tighten with nut.

Bharat Heavy Electricals Limited ~


ERECTION OF HEADERS

F i G . 3. T E M P O R A R Y SUPPORT

Bharat Heavy Electricals Limited


BOILER
Erection ERECTION OF HEADERS

Erect all the hanger rods (for all headers) and tighten the nut in such a way to
maintain the hanger rod holes in one line to fix header easily and align.

4. Erection of header

a. Temporary support for headers with an off-set support

Temporary support arrangement (for arresting header to avoid any


possible disturbance during erection of connected pressure parts) to be
made ready as shown in the Fig. 3.

- Elevation G to be calculated as follows:

1
- G = Elevation of header - /4 the diameter of header
Center line (as per drawing) (as per drawing)

- This arrangement is to be made available in two places minimum at


L/4 distance from the end (where L is the length of the header).

- Mark the header axis with respect to reference axis as shown in


pressure parts drawings, over the temporary support arrangement as
shown in fig.4..

b. Lifting arrangement for headers

- The pulley arrangement at the top to be fixed/lashed only with welded


beams (WBs) and not to rolled beams (RBs)

Bharat Heavy Electricals Limited


ERECTION OF HEADERS

Note: Use soft materials like gunny bag while lashing the ropes over the W B s to avoid
dents, rubbing marks on the same.

The capacity, number of shieve pulleys, lifting wire rope diameter and guide
pulley location are to be decided at site based on the weight of the header and
position of the lifting winch.

Header lugs must be used for lifting as shown in the Fig. 5.

While lifting the header, use a tag line to control the load (movement of header).

Note: For headers which have an offset with the supporting structure axis - lift the
header and place it over the temporary support and match the header axis with the
centerline marked over the temporary support.

Connect the hanger rod with the header lug using the pin.

Provide the correct size cotter pin.

Check the elevation of the header, orientation, horizontality and distance from
reference axis before arresting the header.

Arrest the header as shown in the fig . 6.

Other headers like ring header which are connected with waterwall and like
SHH9 which are connected with steam cooled wall (SCW) are to be positioned,
aligned and welded with water wall / S C W etc. respectively.

Bharat Heavy Electricals Limited 2£


ERECTION OF HEADERS

Bharat Heavy Electricals Limited


ERECTION OF HEADERS

Note: 1. The end caps should be removed only during final fit up.

2. The temporary supports should be removed prior to hydraulic test only. The
temporary supports should be erected in such a way that it should not be a
hindrance to any permanent suspension/components.

Other important aspects of header suspension and header alignment are shown in
Fig. 7 A t o 7 E .

Bharat Heavy Electricals Limited


ERECTION OF HEADERS

TACK WELD AFTER FINAL ADJUSTMENT

SUPPORT CHANNELS AT
pRessose PARTS SUPPORH
L E V E L (PPSL)

HANGER ROD

.WELOING BETWEEN SUPPORT C H A N N E L AND

THE BEARING PLATE.

LENGTH OF W E L D I N G SHALL BE AS
CALLED FOR IN THE CONTRACT DRAWINGS.

AFTER FINAL ADJUSTMENT T H E NUT SHOULD BE TACKED


TO THE BEARING PLATE

''STRIKING A R C OR WELOING ON T H E LOADED HANGER RODS


SHOULD B E AVOIDED "

F I G . 7 A . BEARING PLATE WELDING OETAILS

COLLECTOR CHANNEL
S U P P O R T S TO CEILING THE COLLECTOR CHANNELS SHOULD
Sff M A I N T A I N E D H O R I Z O N T A L .

rue BOTTOM w o r s of thc COLLECTOR


CHANNEL SUPPORTS SHOULD BS
TACKKXJ H O T * WITH THE ROD A M D
THE BEAR IMS PLATE,
/COLLECTOR THE T A C K / M S SHOULD BX X O M E
CHANNELS,^ BEFORE ATTEMPTING To T I S H T E N

I TH£ W O T S A T THE C f f l L I N G T O P .

TACK WELD AFTER


FINAL ADJUSTMENT

FIG.7B. COLLECTOR CHANNEL DETAILS

Bharat Heavy Electricals Limited


ERECTION OF HEADERS

THIS HANGER LOAD IS EUFURCATEO THRO


COLLECTOR CHANNEL ARRANGEMENT AND
TAKEN TO CEILING TO AVOID INTERFERENCE

CHECK THE EQUAL LOAOING OF S T R A I G H T HANGER

BY TUNING (EQUAL PITCHED SOUND), CHECK THE

LOADING ON BIFURCATED HANGERS WITH WRENCHES.

:
I G. 7 C ._ H A N G ER ROD QF.TAI1- 3

Bharat Heavy Electricals Limited


ERECTION OF HEADERS

Bharat Heavy Electricals Limited


ERECTION OF HEADERS

B O T T O M RING H E A D E R :

Furnace water wall system has been provided with bottom ring header of 914.4 mm
OD and 95 mm thickness. Bottom ring header supplies water to various water wall
tubes.

These headers are transported to site in four pieces and each header weighs around
40 to 45 MT. Header is provided with orifice adopters which are welded at shop.
Orifices are fixed to the adopters by means of marman couplings. Orifices and
couplings are erected after steam blowing of Boiler system.

Individual piece of ring header is erected over the temporary brackets welded in the
columns with the help of 2 Nos. 75 MT cranes positioned inside the furnace cavity,
Refer Fig. No.7G.

Ring headers are erected before erection of water wall bottom hopper panels. After
erection of all four headers, headers are aligned with respect to drawing. After
alignment, headers are arrested properly before welding.

Both the front headers joints are welded simultaneously. Similarly rear header joints
are completed. This sequence is adopted to avoid any misalignment during welding.
Refer fig No.7F.

B O T T O M RING H E A D E R ORIFICE A S S E M B L Y .

Bottom ring header supplies water to various water wall^rbes. Each water wall tube is
provided with an ORIFICE A S S E M B L Y , at the Inlet, installed in the bottom ring Header
as indicated in Fig. No. 7H.

Bharat Heavy Electricals Limited


ERECTION OF HEADERS

REAR

RiGHl

G_ OF MATCH WITH
FURNACE AXIS

FRONT

Bharat Heavy Electricals Limited


BOILER
Erection ERECTION OF HEADERS

Orifice assembly consists of orifice plate, marman coupling and orifice adopter. Orifice
adopter is welded inside the header and these adopters are welded at shop itself.

Orifice assembly is installed in the ring header after completion of steam blowing
activity. Orifice size and number are checked with reference to the drawing Orifice bore
sizes are checked with " G O - N O - G O " gauge before installation. Orifice plate installed
over the orifice adopter and fixed to the adopter with marman coupling which is
tightened with stainless steel bolt and nut. After installation of orifice assembly in one
Header, Cover plate is provided around section of orifice assembly. The same
procedure is followed for all the headers, after complete installation of orifice
assemblies and cover plates, header is cleaned thoroughly and manhole doors are
closed with new gaskets.

TYPICAL DETAILS O F 500 M W BOILER H E A D E R S

S.No. DESCRIPTION ECONOMISE WATERWAL SUPER RE


R SYSTEM L SYSTEM HEATER HEATER
SYSTEM SYSTEM
1. PRODUCT PG-19 PG-05 & 07 PG-10 PG -15
GROUP
2. No. OF HEADERS 2 10 20 2
3. TOTAL WEIGHT 29 MT 211 MT 170 MT 38 MT
OF HDR
4. MAX. WT OF 16 MT 47 MT 32 MT 24 MT
SINGLE HDR
5. MAX-DIA OF 508 MM 914 MM 508 MM 558 MM.
HEADER

Bharat Heavy Electricals Limited


ERECTION OF HEADERS

MARMAN COUPLING

TYPICAI SECTIONAL VIEW


ORIFICE A S S E M B L Y ANO WATER WALL LOWER H E A D E R NIPPLE
IN T H E CONTROLLED BOILERS

3 INDEXING PINS ON
ORIFICE ADAPTER MUST
ENGAGE THE 3 MATCHING
H O L E S IN T H E ORIFICE TO
P R O P E R L Y IDENTIFY T H E
REQUIRED ORIFICE.

EIO:-7H ORIFICE IN L O W E R WW

Bharat Heavy Electricals Limited


ERECTION OF FIRST PASS
RADIANT ROOF

Bharat Heavy Electricals Limited


BOILER ERECTION OF FIRST
Erection PASS RADIANT ROOF

ERECTION OF FIRST PASS RADIANT ROOF


First pass radiant roof tubes arrangement (TYP) is shown in the Fig. No.1A.

Radiant roof consists of 150 nos. of front fin welded loose tubes and 150 nos. of rear
fin welded loose tubes.

These loose tubes with mark nos. punched on it are transported to site as loose tubes.

First pass radiant roof can be erected in there different methods.

Method -1.

Inlet and outlet headers of radiant roof are erected on permanent suspensions as per
drawing.

Roof tube supports are suspended from ceiling structure.

Front loose tubes 8 to 10 nos. are assembled as a panel in the furnace cavity.

Temporary angle stiffners are fixed at two places as shown in the fig. 1B.

Assembled panels are erected with the help of electric winches.

These panels are suspended approximately at roof elevation with the help of
temporary wire ropes which are tied to the ceiling structure.

All front panels are erected and aligned with respect to Boiler axis. Support channel is
fixed over the plate lugs already welded to the tubes. Support channel is connected to
the support rod through pin connection. Support rods are adjusted to get the proper
alignment of tubes. After alignment of temporary panels, front tubes are welded with
inlet header stubs.

Bharat Heavy Electricals Limited


BOILER ERECTION OF FIRST
Erection PASS RADIANT ROOF

Radiant roof rear tubes also erected following the same procedure mentioned above.
All rear tubes are welded with the rear outlet header supports. Middle joints of roof
tubes are welded after completion of final alignment of both front and rear tubes.

Temporary binders are removed and support lugs on tubes are welded with the end
bars at the location shown in the drawing Radiant roof tubes are erected after the
erection of all top headers, suspensions, S H links and end bar assemblies.

Method : II

Front tube is welded with corresponding rear tube in pre-assembly area. Refer fig.
No.1C.

Preassembled front and rear tubes are assembled in furnace cavity as a panel consist
of 5 to 6 tubes with temporary binder. Inlet and Outlet headers are erected on
permanent suspensions.

Preassembled panels are erected with the help of winches. Panels are suspended
from ceiling structure with the help of temporary wire ropes. After complete erection of
roof tubes, suspension channels are fixed to the tube lugs which are already welded to
the suspension rods through pin connection.

Suspension rods are adjusted so as to align the roof tubes. After final alignment, roof
tubes are welded with Inlet and outlet header stubs.

Bharat Heavy Electricals Limited


ERECTION OF FIRST
PASS RADIANT ROOF

Bharat Heavy Electricals Limited


BOILER ERECTION OF FIRST
Erection PASS RADIANT ROOF

Temporary tie channels are removed and permanent support lugs are welded with end
bars.

Method - III

Both inlet and outlet header suspension and roof tube suspensions are suspended
from ceiling structure. Front roof tubs are preassembled with front inlet header and rear
roof tubes with outlet header in furnace cavity, Ref. Fig. 1D.

Permanent support channels along with two rows of temporary stiffner channels are
fixed on both front and rear assemblies.

Front tubes are welded with inlet headers and rear tubes are welded with rear header
stubs.

Two winches are used to erect the tubes with header. One of the winch wire rope is
connected to the temporary channel through the pulley blocks connected at ceiling
structure and other winch wire rope is connected to the header. Slings are connected
through the suspension lugs of headers.

Front tubes with inlet header are connected at an inclined fashion by operating both
the winches simultaneously.

After hoisting to its final elevation support channels are fixed to permanent support
rods and headers suspension lugs to the permanent tie rods.

After completion of front tubes with inlet header erection, rigging arrangement is shifted
to rear side-ceiling structure. Preassembled rear tubes with header are erected in the
same way as indicated above.

Bharat Heavy Electricals Limited 53 .


ERECTION OF FIRST
PASS RADIANT ROOF

Front and rear tubes are aligned by adjusting the suspension rods. After final
alignment, middle joints are welded and tube support lugs are welded with end bars.

In all the above methods, precautions are taken to check the mark numbers with
reference to radiant roof assembly drawing.

Bharat Heavy Electricals Limited


BOILER
Erection

ERECTION OF
WATER WALL AND SH STEAM
COOLED WALL

Bharat Heavy Electricals Limited


BOILER ERECTION O F W A T E R W A L L AND
Erection SH S T E A M C O O L E D W A L L

I. Waterwall

- Complete the erection and alignment of waterwall outlet headers including


permanent supports. (Front waterwall header, left and right side waterwall
header, waterwall rear hanger header and waterwall rear screen outlet header).

- Waterwall tubes are made out of riffled tubes in furnace region-typical riffled
tube is shown in Fig. 1

- Carry out sponge test of all water wall panels, water hanger tubes, waterwall
arch/screen tubes and close the openings with end caps.

Note: End caps are to be removed just before final fit-up.

Check the following:

- Width of the panel

- Length of the panel

- Permanent bow (if any)

- Any damages like sling mark, deep cut, tool mark etc. (to be rectified before
lifting).

- Location of openings as per drawing.

Bharat Heavy Electricals Limited


BOILER ERECTION O F W A T E R W A L L AND
Erection SH S T E A M C O O L E D W A L L

- Edge preparation

- Preassemble the following with panel seal box as shown in Fig.2 (Optional).

- Manhole doors, peephole doors, Instrument Openings, Scot blower openings etc.

Note:- The surface of all tubes that are completely embedded in castable refractory
should be painted with two coats of bituminous paint.

Scalloped Bar Welding Detail

1. Cut the scalloped bar (only top scalloped bar of seal box) as shown in Fig.2X

2. Weld item B bottom scalloped bar and seal box with pressure parts before the
hydraulic test (refer the Fig.2Y)

3. Item A has to be welded to item B after pouring castable refractory inside the
seal box (refer Fig.2 Z).

Erect and weld waterwall hanger tube with waterwall rear hanger header
after alignment (check the verticality before welding).

Note: The lifting arrangement for waterwall hanger tube, arch/screen tubes can be
prepared as explained for LTSH and Economiser coils. (Floating pulley arrangement).

Bharat Heavy Electricals Limited


BOILER ERECTION O F W A T E R W A L L AND
Erection SH S T E A M C O O L E D W A L L

- Erect and weld waterwall screen tubes with waterwall rear screen outlet
header.

- All the burner blocks shall be preassembled with burner panel and kept in
four corners respectively and temporarily arrested with main structure. The
lifting arrangement shall be made as shown in Fig.3.

- The lifting arrangement is to be suitably decided at site based on the location


of winch.

- Waterwall/SCW panels are to be handled with care to avoid permanent bow


and damage.

- The suggested panel handling method is shown in Fig. 4 (for both lifting and
alignment).

- Lift all the top waterwall panels and align the panels within permissible
tolerance by adjusting panel to panel welding gap. (Refer Fig. 5A to 5C)

- Complete the welding after alignment.

Notts : Figure : 5C

1. Field to align panel edge bars, not tube centers in wall assembly.

2. While assembling the panels, ensure that this pitch tolerance is not
cumulated. The tolerance on width & depth is to be maintained as per
specified Tolerance.

Bharat Heavy Electricals Limited


BOILER ERECTION O F WATERWALL AND
Erection SH S T E A M C O O L E D W A L L

- After erecting all top water wall panels, erect the buckstays coming in that panel
and align (this will help in maintaining verticality of the waterwall panels and furnace
dimension within permissible limit).

- After erecting the first row of rear waterwall panel (welding with waterwall hanger
tubes) the arch tubes can be erected and welded with waterwall panel and
waterwall screen tube. Care should be taken in erection and alignment of the rear
arch tubes so that the gap required between them and R H rear coils can be
achieved. The formation of rear arch tubes is shown in Fig. No.5D.

Note: Before the erection of Rear waterwall all Reheater coils are to be erected.

- Erect all other panels and complete the welding following the
above procedure.

Note : Care should be taken while erecting the "Z" panel. Additional temporary
supports are to be provided with main structural members to position them.

- All the buckstays are to be erected before taking up the next level
water wall erection.

- Erect and align the riser tubes taking following care :

a) The drum to header connecting riser tubes are to be routed first and matching with
drum and header stub shall be carried out.

b) Weld the middle joint after routing the riser tubes between drum stub and water wall
header stub.

c) Now simultaneously weld the riser tubes joints with drum and header stub.

Bharat Heavy Electricals Limited "


BOILER
Erection

d) Wooden blocks can be used for avoiding touching of riser tubes with coils, on both
sides as shown in Fig. 6A, This would help to get a final fit up after welding of riser
tubes as shown in Fig. 6B.

- Complete the erection of all permanent supports. Release the boiler and furnace
from all temporary supports.

- Recheck the furnace alignment fireball checking and full welding of all Burner
panels,

- Complete the erection, alignment and welding of all upper and lower corner
transition tubes (UCT and LCT).

- Release the boiler first pass for furnace hopper measurements.

II. S H Steam Cooled Wall (Method -1)

- Erect and align the S H rear roof junction header on permanent support.

- Erect all the rear roof supports.

- Lifting arrangement is to be decided as per the site condition.

- Lift all the rear roof panels and fix them on the permanent support.

- Align the rear roof panel,

- Complete the welding with junction header.

Bharat Heavy Electricals Limited


BOILER ERECTION O F W A T E R W A L L AND
Erection SH S T E A M C O O L E D W A L L

- Erect and align the left and right side top headers of second pass (SH
side wall inlet headers) on permanent support.

Method - 2

- Second pass roof panels are pre-assembled with rear junction header on the pre-
assembly bed located at second pass furnace cavity.

- All the joints with the header end for welding completion in pre-assembly itself.

- Suspension channels also welded on the ground itself.

- Three Nos. temporary stiffener channels are fixed to the panels to avoid buckling of
panels during erection.

- After completion of pre-assembly, the entire panel with header is lifted with the help
of two winches rigged through the ceiling structures.

While lifting, the panel is tilted by about 30 degree to avoid fouling with the
middle columns structures.

After crossing top of middle column structure, panel is made horizontal and
raised to the final elevation.

After reaching final position, panel load is taken in permanent supports and
temporary supports are removed.

Erect all the S H steam cooled wall (erection method to be followed as


explained for waterwall).

Bharat Heavy Electricals Limited " ~ " '


6
BOILER ERECTION O F WATERWALL A N D
Erection SH S T E A M C O O L E D W A L L

Complete the erection of buckstay.

Align the LTSH inlet header and complete the welding with rear S C wall and
connections to LTSH coils.

After erection completion of all steam cooled walls align the following headers.

S H side wall outlet header.

S H front wall inlet header.

S H rear wall inlet header.

Check the verticality of S C wall.

Check the width and depth of second pass.

Check the end gap of LTSH/Eco coils with S C wall.

Complete the erection, alignment and welding of extended side waterwall inlet
header with the extended waterwall panels.

Complete the erection and welding of waterwall supply tubes with rear
waterwall and extended side inlet header.

Complete the erection, alignment and welding of S H extended S C W inlet


header and S H extended side S C W tubes.

Complete the erection alignment and welding of links between S H front wall
inlet header and S H extended S C W inlet header.

Bharat Heavy Electricals Limited


ERECTION O F W A T E R W A L L A N D
SH S T E A M C O O L E D W A L L

TUBE SIZE :<r>51 X 5- 6


NO, OF RIBS: 8

Bharat Heavy Electricals Limited


BOILER ERECTION O F WATERWALL A N D
Erection SH S T E A M C O O L E D WALL

F I G : 2. SEAL B O X DETAILS

SCALLOPED BAR WELDING DETAIL

FIG. 2Y FIG 2Z
b) OPENING FOR POURING
/ REFRACTORY ^

CUT THE SCALLOPED BAR

1. CUT THE SCALLOPED BAR (ONLY TOP SCALLOPED BAR OF SEAL BOX)
AS SHOWN IN FIG. IX.
2. WELD I T E M ® . BOTTOM SCALLOPED BAR AND SEAL BOX WITH
PRESSURE PARTS BEFORE THE HYDRAULIC TEST (REFER THE FIG. tY)
3. ITEM 0 WAS TO BE WELDED TO ITEM (g) AFTER POURING CASTABLE
REFRACTORY INSIOE THE SEAL BOX (REFER FIG. 1 2 )

Bharat Heavy Electricals Limited


ERECTION O F W A T E R W A L L AND
SH S T E A M C O O L E D W A L L
BOILER ERECTION O F W A T E R W A L L A N D
Erection SH S T E A M C O O L E D W A L L

PANEL ERECTION ATTACHMENT

PANEL

F I G . .j .SUGGESTED PANEL HANDLING METHOD

Bharat Heavy Electricals Limited


ERECTION O F W A T E R W A L L AND
SH S T E A M C O O L E D WALL

FIG. 5,v. FURNACE ALIGNMENT WITH RESPECT TO

BOILER / F U R N A C E AXIS

Bharat Heavy Electricals Limited


BOILER ERECTION O F W A T E R W A L L A N D
Erection SH S T E A M C O O L E D W A L L

FIG. 5B FURNACE WIDTH/DEPTH/DIAGONAL TOLERANCE

TUBE SPACING *
TUBE DIA + 18 MAX.

1.5 M1N

FIG. 5 C . ALIGNMENTS WELDING OF PANEL EDGE BARS

Bharat Heavy Electricals Limited


ERECTION OF WATERWALL AND
SH STEAM COOLED WALL

EW ( H D R )

G A P
® - ® = © = ® = RET WEEN

BOTTOM OF RH

( R E A R ) «. R E A R

ARCH TUBES

L'iL .£"> A R R A N G E M E N T O F Ji E A R _ A R C H _ T I J D B A NO

R E M ••'Al E R COIL'.;

Bharat Heavy Electricals Limited


ERECTION O F W A T E R W A L L A N D
SH S T E A M C O O L E D W A L L

FIG. 6A. RISER TUBE ALIGNMENT

FIG. 6B. RISFR T U B E A L I G N M E N T

Bharat Heavy Electricals Limited


ERECTION O F W A T E R W A L L A N D
SH S T E A M C O O L E D W A L L

BRIEF DETAILS ABOUT WATERWALLS

TOTAL WEIGHT O F W A T E R W A L L P A N E L S : 553 MT

TOTAL N O S . O F P A N E L S 164 N O S

M A X WEIGHT O F SINGLE P A N E L 5.3 MT

MAX. L E N G T H O F SINGLE P A N E L : 24000 M M

MAX. WIDTH O F P A N E L 1715 M M

NO. O F T U B E S FORMING F U R N A C E 1062 N O S .

TYPE OF TUBES : RIFLED

TYPE OF PANELS FUSION W E L D E D

SIZE O F T U B E S : DIA 5 1 X 5 . 6 M M

PITCH O F T H E A D J A C E N T T U B E S 63.5 M M

MATERIAL O F T H E T U B E S : SA210GR.A&GR. C

MAX. NO O F T U B E S IN E A C H P A N E L : 28 N O S

FURNACE DEPTH : 15797 M M

F U R N A C E WIDTH : 19177 M M

Bharat Heavy Electricals Limited


DOWNCOMER
PIPES ERECTION

Bharat Heavy Eiectricals Limited


DOWNCOMER PIPES ERECTION

- Check the downcomer stub centerline with respect to reference axis.

- Check the downcomer stub-to-stub distance.


Note : These checks can be made before drum erection also.

- There are six downcomer pipes connecting boiler drum at top and bottom ring
header at bottom.

- Down comer pipe straight pipe pieces are preassembled on pre-assembly bed
on the ground.

- After pre-assembly these pieces are transported to furnace cavity and erected
below the drum with the help of winches.

- Preassembled top pieces are welded with drum stubs and second pieces are
fixed to the top piece with the help of erection attachment as shown in the Fig.
No.1

- After welding the second piece, further straight pieces are erected and welded
up to suction manifold following the same procedure.

- Suction manifold is received in three pieces. All three pieces are erected
individually and assembled with temporary supports at elevation approximately
27 metres.

- Suction manifold is aligned parallel to front water wall and it is in line with drum
longitudinal axis, Refer Fig. 2.

- After completion of welding of suction manifold, all six downcomer pipes are
fitted to the suction manifold top stubs and welded.

Bharat Heavy Electricals Limited 57


DOWNCOMER PIPES ERECTION

- Three Nos. suction spools are fitted and welded to the bottom stubs of
suction manifold.

- Three Nos. motor operated suction valves are fitted to the bottom of suction
spool with stem horizontal and temporarily supported.

- After locating the hand wheel properly, valves are welded with the suction
spool.

- One more suction spool is welded below the suction valve.

- C C pump volute without Impeller is fitted to the bottom of suction spool and
supported temporarily.

- Bottom flange of the volute is carefully aligned and leveled before welding
with the suction spool.

- After ensuring uniform level of bottom flange of C C pump volute, suction


spools are welded with top portion of volute.

- Precautions are taken to avoid any distortion during welding of volute with
suction spool.

- Two Nos. manual operated discharge valves are erected on discharge side
of the volute and welded.

- After completion of erection and welding, the following jobs are required to
be completed.

- Radiography of joints

Radiographic plug welding

Stress relieving

- Cutting and trimming of erection attachment. Blanking of C C pump volute for


Hydro test.

- After completion of Hydro test, C C pump volute blanks are removed and C C
pumps are erected. (Refer C C pump erection procedure).

Bharat Heavy Electricals Limited


DOWNCOMER PIPES ERECTION

VIEW-A

FIG. 1. ERECTION ATTACHMENT FOR DOWNCOMER PIPES

Bharat Heavy Electricals Limited


ERECTION
OF
CONTROLLED CIRCULATION
PUMP

Bharat Heavy Electricals Limited


ERECTION OF CONTROLLED CIRCULATION PUMP

Brief details of CC pump and motor

Type single suction - Double discharge.

2
Design pressure 208.5 K g s / c m

Design Temperature 366°C

2
Hydro Test pressure 312.8 kgf/cm

2
Suction pressure 195.6 Kgf/cm

Quantity pumped 48453 Litre/min.

Wt. Of pump case 3425 Kgs.

Motor

Type Wet stator - squirrel cage - Induction

Out put 354 KW

Motor case design Temperature 343°C

2
Motor case design pressure 208.5 Kgf/cm

Full load speed 1450 R P M

Full load current 84 Amps

Wt. of motor complete 7443 Kgs.

Bharat Heavy Electricals Limited


ERECTION OF CONTROLLED CIRCULATION PUMP

Special features of pump motor

1. Assembled underneath the pump.

2. Glandless

3. Impeller is mounted on the extended shaft of motor. No separate coupling is


required.

4. Bearings and motor windings are directly cooled by same boiler water.

5. Volute/pump casing is directly welded to the piping.

1.0 ERECTION OF CC PUMPS

Controlled circulation 500 M W Boiler is provided with three Nos. circulating pumps
of each of 50% capacity. The Boiler water-circulating pump comprises a single
stage centrifugal pump driven by a wet stator induction motor as shown in Fig. No.1
The motor suspended beneath the pump casing is filled with water at full system
pressure, Whilst no seal exists between the pump and motor, a baffle plus base
clearance between the stator and motor casing neck, restrict solids and hot water
entering the motor. The rotor shaft is supported by water lubricated, tilting pad
radial and thrust bearing mounted on the end of the stator shell.

Each pump has a center inlet and two tangential discharges. Each discharges of
the pump is provided with the elbow down stop check valve in the discharge lines.
The discharge lines are connected to the front bottom ring header.

Bharat Heavy Electricals Limited


ERECTION O F C O N T R O L L E D CIRCULATION PUMP

1.1 CC PUMP C A S E INSTALLATION

- Pump case/volute flange and branch and covers are


removed and cleaned.

- Suction manifold and suction valves three Nos. with spool pieces are
perfectly leveled.

- All three volutes are transported to furnace cavity and slings are attached
to erection eyebolts provided on the casing.

- Typical volute is shown in Fig. No.2.

- Volute is raised to the position with the help of electric winch.

- Temporary supports are provided to hold volute at its elevation.

- After alignment of volute with suction spool. It may be tack welded.


Horizontality of bottom flange is rechecked to keep it within % degree or -
Vz degree.

- Suction spool with volute is welded following the applicable procedure in


welding manual.

- Radiography and stress relieving are to be completed after completion of


welding.

- Radiographic hole is plugged.

Bharat Heavy Electricals Limited £j>


BOILER
ERECTION OF CONTROLLED CIRCULATION PUMP
Erection

PUMP C A S E .

DISCHARGE
...DISCHARGE

• MAIN STUD

EXCHANGER CONNECTION
DTE : HEAT EXCHANGER OMITTED
FOR CLARITY

•STATOR WINDINGS

ROTOR

MOTOR CASE - . A
• STATOR !.AM">!AItO 'S

COVERENO
BEARING HOUSING I COVER-END JOURNAL BEARING
i (TILTING PAOI

THRUST DISC
AND AUXILIARY IMPELLER

REVERSE THRUST BEARING

HEAT EXCHANGER CONNECTION

FILTER
GASKET

FILL AND DRAIN


CONNECTION
TERMINAL -
SOX

MOTOR COVER

FIGTr1;C.mn'UTINfl H'Mf

Bharat Heavy Electricals Limited


BOILER
ERECTION OF CONTROLLED CIRCULATION PUMP
Erection

m-llfVM? CASK INSTALLATION

Bharat Heavy Electricals Limited


ERECTION OF CONTROLLED CIRCULATION PUMP

SYSTEM PIPEWORK

PUMP CASE

"'4

INSULATION

SYSTEM PIPEWORK

E Q U A L A L L ROUND f L A N G E
T H R O U G H O U T LIFT

LONG LIFT HOIST


IMP
••SE
V

SHACKLE

R E M O V A B L E LIFTING LUGS
(Ref. Oniyl
HEAT E X C H A N G E R
KEEP C O O L E R
OPERATIONAL
WHEN INSTALL-NO '."OTOR ASSEMBLY
THE MOTOR
ON A HOT BOILER

LOW PRESSURE
SYSTEM

F L E X I B L E HOSE

T E R M I N A L BOX

T E R M I N A L BOX C A B L E
ENTRY G L A N O .
(CUSTOMER SUPPLY

LOOP SUPPLY C A B L E S AT
L E A S T 600mm TO A L L O W
ALLOW AT LEAST 600mm F R O M ANY FOR CIRCULATOR EXPANSION
O B S T A C L E FOR THE MOTOR TO SINK A N D C O N T R A C T I O N WITH
WHEN THE BOILER SYSTEM IS H E A T E C BOILER PIPEWORK
AND THE SYSTEM EXPANDS.
KEEP A R i A BENEATH MOTOR C L E A R
OF A N C I L L A R Y EQUIPMENT TO PERMIT
SUBSEQUENT MOTOR R E M O V A L .
MINIMUM DISTANCE REQUIRED
IS9V4.4mm. -L

F»q-3: MOTOR fNSTfM l,ATION

Bharat Heavy Electricals Limited


WELD UP INTER
CONNECTING
PIPEWORK (3 WELOSI

NOTE:
ENSURE THAT INTER CONNECTING
PIPEWORK ASSEMBLY IS M A R K E D
WITH. AND MATCHES THE UNIT
SERIAL NUMBER

[ASSEMBLE IN NUMERICAL SEQUENCE j

Fl r—*f
r y A T
EXCHANGER INSTALLATION

Bharat Heavy Electricals Limited


BOILER ERECTION OF CONTROLLED CIRCULATION PUMP
Erection

- Dummy and covers are fixed to the bottom flange and nuts are tightened
to the required torque value indicated by the pump manufacturer.

- After completion of Hydro test, dummy covers are removed and volute is
thoroughly cleaned.

1.2 CC PUMP MOTOR INSTALLATION

- Motor Installation is shown in Fig. No.3.

- When installing circulators the following conditions must be observed.

1. System pipe work should be adequately supported to accept the weight


of the circulator.

2. When mounted, the pump should accommodate movement in the pipe


without imposing excessive loads on the casing and branches.

3. Sufficient clearance should be allowed beneath the motor to permit


lowering of the motor from the pump case for maintenance. If removable
floors are fitted after the motor is installed, ensure that the terminal boxes
or low pressure cooling water supply lines will not foul them when the
boiler is on load and the circulator moves downwards due to thermal
expansion.

4. Ensure the main system is free from solids before


mounting the circulators. Hose down internally, the pump case, the
valves and adjacent piping, to ensure the removal of all loose debris.

Bharat Heavy Electricals Limited


BOILER
ERECTION OF CONTROLLED CIRCULATION PUMP
Erection

- Motor assembly is transported to furnace cavity and kept in a vertical


position, on the motor cover stand, and in the correct orientation to the
pump.

- Inspection cover at the top of the transit canister is removed and drain
plug is removed to drain off the inhibitor.

- Transit canister is removed from the motor case.

- Lifting shackles and slings are attached to the lifting lugs.

- Using long lift power hoists, motor is lifted to the position until the motor
impeller is about to enter the pump case. In this condition motor load is
transferred to chain type hoist.

- Distance between the pump case and motor flanges are measured at
four 90 degree points on the flange periphery. If necessary motor is
adjusted to make the distances equal all around.

- Care is to be taken to see that the studs are centered in the motor flange
holes.

- With the chain hoists working in Unison motor is raised


until an increase in the effort required on the hoist indicates that the
gasket is in contact with the pump case face. At this stage, the gap
between the flange faces should be equal all round the flange.

- The stud threads are coated with high temperature anti-seize compound
and nuts are installed by hand.

- Nuts are tightened with hydraulic stud tensioning unit following the
procedure given by the manufacturers.

- Lifting tackles are removed.


Bharat Heavy Electricals Limited ~ 9
BOILER
Erection ERECTION OF CONTROLLED CIRCULATION PUMP

1.3 Installation of Heat exchanger

- Heat exchanger is loosely mounted on the motor case


brackets with the heat exchanger weight being taken by the lifting
tackles.

- Heat exchanger is aligned parallel to the motor as shown in the Fig. No. 4
by adjusting the screws on the bracket, on completion of adjustment,
adjusting screws are locked with locknuts and lifting tackles is removed.

- Interconnecting pipe work of Heat exchanger is completed.

- Thermocouples, pressure gauges and temperature alarm switches are


installed.

- Power supply cable is connected to the motor terminals.

- Thus the erection of C C pumps is completed.

Bharat Heavy Electricals Limited


Bharat Heavy Electricals Limited
ERECTION OF COILS

Pre erection checks

Check the width and length of the coils, flexible connections availability and
welding as per drawing.

Check for damages like sling marks, deep cut and dent etc.

Check the weld end connections such as edge preparation and ID and
compare with header/stub weld end connections

Clean the edge preparation and apply weldable primer.

Check for any permanent bow (if bow is observed, inform manufacturing unit
for corrective action before taking it up for erection).

Remove the end caps and carry out sponge test and then fix all the end caps.
The end caps are to be removed only at the time of final fit up.

Complete Boiler Inspector's ground Inspection of Coils.

Pre-Assembly of End Bars

Erection of coils (Platen SH, RH and Divisional panels)

The suspension arrangement to be pre assembled and positioned as explained in


the first pass roof erection.

Fabricate an anti deformation frame as shown in Fig. 1A, (Temporary binder if any
are to be removed)

And also fabricate a lifting device as shown in Fig : TB.

Fix the lifting and guide pulleys according to site condition.

Bharat Heavy Electricals Limited


ERECTION OF COILS

ASSEMBLIES O F COIL SUSPENSIONS-CROWN PLATES+END B A R S FOR


SH.AND RH COILS

FIG.1 TYPICAL ASSY

AREA NO OF ASSY X P-PITCH OF L IN mm


COILS

PLATEN SH.COILS ORG.OIMN.


SUSPENSION ROW FIVE + 762mm 2650
'F' AND 'G' 2 TO 3mm

SH.REAR VERTICAL DRG.OIMN.


SPACED COILS six 305mm 2058
+
ROW 'R' AND 'S' 2 TO 3mm
RH REAR COILS ORG.DIMN.
FIVE + 190.5mm 3085
ROW ' L ' 8 'M' 2 TO 3mm

RH FRONT COILS DRG.DIMN.


EIGHT 381mm 2459
ROW 'H' ANO 'S 2 TO 3mm

Bharat Heavy Electricals Limited


ERECTION OF COILS

L 60X 60X5 PIN 1 250 [3 ISMC 150

3 FLOATING PULLEY

ERW PIPE

R.H . COIL PlATgN OIVISION


PANEL
DETAIL " A

FIG. 1A. ANTl DEFORMATION FRAME FOR R H . AND SH.COILS

Bharat Heavy Electricals Limited


ERECTION OF COILS

500

© a
SO

100
12 TO 16 MM THICK
300 THICKNESS OF PLATE JUST I ESS THAN 9

®- 7 © S
20 100
2HJ
6P \
PLATE THICKNESS * OR > 8 MM
TH - 20 MM 0-

Q.32MM (£) AS PER REQD


© 6P
<i 1

32 MM d

©
_LP_

FIG. 1 B . FABRICATION DETAILS OF LIFTING DEVICE

Bharat Heavy Electricals Limited


ERECTION OF COILS

PRE ASSEMBLY AND ERECTION OF END BAR ASSEMBLIES

Crown plates and End bars can be pre assembled over the pre-assembly bed on
the ground crown plates are placed between two end bars and welded with end
bars maintaining the gap and dimensions as per the drawing For facilitating coil
erection, gap between crown plates may be kept 3 to 5 mm more than the
dimension given in the drawing Typical end bar and crown plate assembly is shown
in the fig, 1. These are around 25 such assemblies supporting superheater and
Reheater coils. These assemblies erected from the furnace cavity with the help of
electrical winches. After reaching its elevation, these assemblies can be
suspended, on the permanent supports. All these assemblies are erected before
the erection of roof panels.

This arrangement should be in such a way that it can be shifted at top to lift each
coil.

The coils are to be lifted as shown in Fig. 2.

The coil load is to be transferred to crown plate by providing a temporary rest bar
as shown in Fig : 3A & 3B.

Note : Complete assembly to be ground assembled.

The coils are to be welded with header stubs.

Complete the erection and welding of steam-cooled spacers.

Bharat Heavy Electricals Limited


ERECTION OF COILS

DIP TROLY

FIG • 2 .COIL ERECTION USING LIFTING DEVICE

Bharat Heavy Electricals Limited


BOILER
ERECTION OF COILS
Erection

FIGI3A. CROWN PLATE ASSEMBLY COIL SUSPENSION


ARRANGEMENT

Bharat Heavy Electricals Limited


BOILER
ERECTION OF COILS
Erection

TEMPORARY ERECTED POSITION

FIG; 3-8- STO. SUPPORT LUG

Bharat Heavy Electricals Limited


ERECTION OF COILS

The coil load is to be transferred to Hi-crown/end bar by welding Hi-crown with coil
seal band after checking verticality and spacing.

Note : For checking verticality the following are to be carried out:

1. Usage of Sky climber/ platform for platen S H & Reheater (front).

2. Reheater (Rear) coils verticality is to be checked by keeping a platform


below furnace after completion of Rear Arch Front tubes erection.

Check and record the bottom clearance after erection completion of arch portion.

Erection of LTSH and Eco Coils

LTSH Lower and upper bank shall be pre-assembled on the preassembly bed and
check overall dimensions.

Sponge test is to be carried out for the Eco coils.

Erect all S H hanger tubes with permanent support.

Prepare a floating pulley system for the erection of L T S H and Eco coils as shown in
Fig. 4.

Lift the pre-assembled L T S H coils after sponge test and weld with S H hanger
tubes.

Note. : The cassette baffle plates for LTSH and Eco can be pre
assembled and then the coils can be erected.

Bharat Heavy Electricals Limited


ERECTION OF COILS

ROPE PULLER TO L O C A T E
PULLEY

32 MM ROPE
; TIED TO STRUCTURE
! OM BOTH END
THROUGH SIDE
WALLS

DETAIL - A

FIG: k , FLOATING PULLEY S Y S T E M FOR LTSH AND EC0N0M1SER


COILS

Bharat Heavy Electricals Limited


ERECTION OF COILS

Weld the LTSH bottom terminal tube with the header stubs (Header is already
welded with rear steam cooled wall) through the connecting tubes.

Erect the Economiser outlet header and support with hanger tubes after checking
the header alignment.

Lift the upper Eco coils using the floating pulley system.

Weld the upper Eco coil terminal tube connection with the header stubs.

Erect the Eco upper and lower bank connecting suspension arrangement.

Lift the lower Eco coils and suspend with the support plate already erected, with
upper coil.

Weld the terminal tube connection between upper and lower coils.

Erect the Eco inlet header with its supports and align.

Complete the welding of inlet header stub with the Eco lower terminal tubes.

The baffle plate arresting arrangement is to be completed as per drawing.

Complete the erection and welding of Eco outlet header to drum links including
permanent support.

Complete the erection, alignment and welding of

DESH links between LTSH outlet header and Divisional panel


Inlet Header including permanent supports (orientation of Stubs to be
checked).

Links between Divisional panel Header and platen S H Header.


Bharat Heavy Electricals Limited ^
ERECTION OF COILS

Important aspects of coil erection and alignment are shown in the Fig. 5A to 5L &
5N, 5R.

ERECTION OF DIVISIONAL PANELS

Divisional panels are transported to furnace cavity and lifted to the position using
erection lugs and rigging arrangement from ceiling structures. After lifting to its final
elevation, panels are temporarily supported with wire rope from ceiling structure.
These temporary supports can be removed only after the welding completion of
loose tubes with divisional panel header. Temporary rope supports are removed
and loaded on permanent supports. A typical panel arrangement is shown in Fig.
5Q & 5 R.

Bharat Heavy Electricals Limited


ERECTION OF COILS

Bharat Heavy Electricals Limited


ERECTION OF COILS

Bharat Heavy Electricals Limited


ERECTION OF COILS

Bharat Heavy Electricals Limited


ERECTION OF COILS

Bharat Heavy Electricals Limited


ERECTION OF COILS

Bharat Heavy Electricals Limited


ERECTION OF COILS

Bharat Heavy Electricals Limited


ERECTION OF COILS

Bharat Heavy Electricals Limited


ERECTION OF COILS

FIG. 5Ll. HI - CROWN SUPPORTS

Bharat Heavy Electricals Limited


ERECTION OF COILS

Bharat Heavy Electricals Limited


BOILER
ERECTION OF COILS
Erection

MECHANICAL SPACER BAR

FIG. 5 N

Bharat Heavy Electricals Limited


ERECTION OF COILS

FIG. 5P. VIBRATION S N U B B E R S

DETAIL-A

Bharat Heavy Electricals Limited


500 MW ARRGT OF DIVISION PANEL L E T T E

FIG: 5Q

Bharat Heavy Electricals Limited


Bharat Heavy Electricals Limited
Bharat Heavy Electricals Limited
ERECTION OF BUCKSTAY

Units with wrap around buckstay system require that the Buckstays are
preassembled and raised to their respective elevations hung prior to erection of
furnace walls. Stirrup plates are pre-assembled with top and bottom angle as
shown in Fig No. 1.

Pre-assembled stirrup and angle assemblies are inserted over the furnace
side flange of the buckstays beam.

After positioning the stirrup assemblies at pre-determined locations, key


buckstays are positioned with web vertical and welded with the stirrup plates.

These preassembled buckstays are temporarily supported before erection of


waterwalls either on wire ropes or on brackets welded to columns.

Method: I

Wire rope of one inch diameter three nos. are hung as close to waterwall
location from ceiling structure.

Three holes are drilled on the main buckstay beam as shown in the Fig.
No.2A.

Top level buckstay is first erected with the help of separate rigging
arrangement.

Before lifting, the wire ropes which are hung from ceiling structure are inserted
through the holes in the buckstay beam.

These buckstays are raised to the location through these wire ropes.

Bharat Heavy Electricals Limited


ERECTION OF BUCKSTAY

Bharat Heavy Electricals Limited


ERECTION OF BUCKSTAY

Bharat Heavy Electricals Limited


BOILER
ERECTION OF BUCKSTAY
Erection

- Buckstay is temporarily fixed to the wire rope at the elevation shown in the
drawing. With the help of T-rod and clamps as shown in the Fig No.2 B.

- With horizontal leg of the Tee under the buckstay and the vertical leg above, all
the clamps are installed using the buckstay as platform.

- The clamp nuts are tightened properly with the help of mechanical wrench.

- Following the above procedure, buckstays at different elevations are hung from
the same wire rope at the locations shown in the drawing.

- After erection of waterwalls, buckstays starting from top elevation is pushed


towards waterwall and welded with scalloped plates after final alignment.

Method: II

- Temporary Brackets are welded to the columns inside the


furnace at the predetermined buckstay elevations.

- Preassembled buckstays are rigged through ceiling structure and erected over
the brackets as shown in the Fig no. 2 C .

- After erection of waterwall panels and alignment, these buckstays are supported
with chain blocks and moved towards waterwall panels.

- After positioning the buckstay at correct location, scalloped plates are welded
with waterwall and key buckstays on both top and bottom side of key buckstay
flanges.

Bharat Heavy Electricals Limited


ERECTION OF BUCKSTAY

CHANNEL

t OF BUCKSTAY BEAM
AND CHANNEL

SPACER PLATE
I—RA (TYP )

80LTLESS STIRRUP

WELD BETWEEN CHANNEL AND


STIRRUP
CHANNEL
BUCKSTAY BEAM

SECTION-AA

RA - ARRESTOR PLATES TO BE WELDED TO THE BUCKSTAY BEAM FLANGE.


ONLY FOR THOSE STIRRUPS COMING AT THE ORIGIN OF EXPANSION.

FIG.2 PRE ASSEMBLY OF BUCKSTAY


(80 LTLESS STIRRUPS)

Bharat Heavy Electricals Limited


ERECTION OF BUCKSTAY
ERECTION OF BUCKSTAY

BUSKSTAY SUPPORT METHOD

WELD STOP

A SUGGESTED METHOD FOR SUPPORTING


BUCKSTAYS FROM CABLE.

THIS A L L O W S A L L W O R K TO B E
DONE FROM ON T O P O F T H E B U C K S T A Y

S K E T C H N O . B.

Bharat Heavy Electricals Limited /©2-


ERECTION OF BUCKSTAY

FINAL ELEVATION

TEMPORARY SUPPORTING OF BUCKSTAYS

SKETCH. C.

Bharat Heavy Electricals Limited


ERECTION OF BUCKSTAY

The Figs: 3A & 3B give the details of:

- Origin of expansion in first and second pass:

- Fixed connection between buckstay and walls.

- Indicate the direction of relative movement of wall with respect to buckstay


beam.

Pre-assembly of Buckstay (Refer : Fig 1)

- Assemble the key channel with stirrups (the number of


stirrups and its locations to be maintained as per contract drawing).

- Align the buckstay beam with stirrups. (Ensure that the stirrup is in full contact
with the buckstay beam flange).

- Weld the top and bottom angle with the stirrup. (Ensure the bottom stirrup angle
is in full bearing with the toe of the buckstay beam flange).

- Lock the assembly at the ends and in between, to avoid the buckstay beam
slipping from its location.

- Lift the buckstay and place it over the temporary support provided on the main
column at the appropriate level (where the buckstay is to be fixed with wall
panels) as shown in Fig : 2 C .

- Mark the centerline of the buckstay on the wall panels. (Refer Fig. 4).

Bharat Heavy Electricals Limited


ERECTION OF BUCKSTAY

CL-CENTRE LINE O F
BUCK STAY

S-SCALLOPED PLATES

FIG.4.BUCKSTAY C / l MARKING

Bharat Heavy Electricals Limited


ERECTION OF BUCKSTAY

- Check and ensure the completion of panel to panel welding and closing of all
voids in the buckstay region.

- Weld the bottom side scalloped plates/ pad on wall panels after leveling
them.

- Fix the buckstay assembly (already preassembled) over the scalloped


plate/pad.

- Ensure that the key channel is in full contact with all tubes of the wall panels.

- Fix the top scalloped plate/pad on wall panel, and complete the welding.

- Weld the scalloped plate/pad with key channel both at top and bottom.

- Complete the corner link connection (the corner link should be inclined
outwards with respect to wall. This is to accommodate the expansion of wall.
The buckstay does not expand).

- Complete the erection of vertical buckstay including support hangers and


links.

Note : There shall be no rigid connection (welding)


between vertical and horizontal buckstays.

- Complete the erection of leveler channels with


guide. (The leveler channel shall be rigidly connected at one end and guided
at the other end).

Bharat Heavy Electricals Limited


- Complete the erection of furnace guide. Keep 3mm clearance for the
guides to move down without any obstruction for boiler expansion. (These
guides are to be erected after floating the furnace).

The important aspects of buckstay erection details are given in the Fig's : 5A
to 5T.

Bharat Heavy Electricals Limited


ERECTION OF BUCKSTAY

POURABLE
INSULATION

BUCKSTAY BEAM

FILLER PADS

W E L D S I Z E S TO BE AS PER C O N T R A C T DRC. NO. OF S T I R R U P S AND STIRRUP


SPACING TO B E AS PER C O N T R A C T O R O .
C H A N N E L CAVITY S H A L L BE F I L L E D WITH P O U R A B L E INSULATION
A S PER CONTRACT ORG.

FIG . 5A

POINT OF FIXED CONNECTION


B E T W E E N WALL AND BUCKSTAY
BEAM

BUCKSTAY BEAM

THE WALL ONLY EXPANDS ANO T H E B U C K S T A Y DOSE NOT EXPAND


IN T H E AS E R E C T E D CONDITION THE C O R N E R LINKS SHOULD B E
INCLINED OUTWAROS WITH R E S P E C T TO T H E WALL.

FIG. 5B

Bharat Heavy Electricals Limited


ERECTION OF BUCKSTAY

Bharat Heavy Electricals Limited


ERECTION OF BUCKSTAY

LOAD T R A N S F E R E D TO T H E PERPENDICULAR
WALL THRO' CORNER CONNECTION

LOAO T R A N S F E R E D TO THE PERPENDICULAR


WALL T H R O ' W I N D BOX PARTITION P L A T E

ALL HORIZONTAL BUCKSTAYS SHOULD HAVE CONNECTIONS AT THE


CORNERS FOR LOAD TRANSFER.

FIG. 5E

Bharat Heavy Electricals Limited


ERECTION OF BUCKSTAY

Bharat Heavy Electricals Limited


ERECTION OF BUCKSTAY

Bharat Heavy Electricals Limited


ERECTION OF BUCKSTAY

A - OFFSET TO ACCOMMODATE FURNACE D O W N WARD EXPANSION.

B - OFFSET TO ACCOMMODATE FURNACE REAR EXPANSION.

PRESCRIBED OFFSETS AS I N D I C A T E D IN THE CONTRACT ORG.


SHOULD BE MAINTAINED AT T H E TIME OF ERECTION.

FIG. 5 K

Bharat Heavy Electricals Limited


BOILER
Erection ERECTION OF BUCKSTAY

BACK PASS HORZ.

BUCKSTAY BEAM

SECTION - XX

VIEW . Y

A - O F F S E T TO A C C O M M O D A T E VERTICAL MOVEMENT OF H O R Z . BEAMS


AS PER THE CONTRACT DRG.

S - B E A M S TO T R A N S F E R LOADS TO V E R T I C A L BUCKSTAY BEAM.


THERE SHALL BE NO RIGID C O N N E C T I O N BETWEEN VERTICAL
AND HORIZONTAL BUCKSTAYS.

FIG. 5L

Bharat Heavy Electricals Limited


ERECTION OF BUCKSTAY

Bharat Heavy Electricals Limited


ERECTION OF BUCKSTAY

Bharat Heavy Electricals Limited


ERECTION OF BUCKSTAY

KEEP 3mm CLEARANCE FOR T H E GUIDES TO M O V E


OOWN WITHOUT ANY O B S T R U C T I O N FOR BOILER EXPANSION

FIG. 5S

DO NOT S U P P O R T A N Y LOADS FROM B U C K S T A Y GUIDES WITHOUT


CONCURRENCE FROM DESIGN DEPARTMENT
FIG.5T

Bharat Heavy Electricals Limited


VOIDS THAT ARE TO BE
CLOSED IN PRESSURE PARTS

Bharat Heavy Electricals Limited


BOILER
Erection VOIDS THAT ARE TO BE CLOSED IN PRESSURE PARTS

Fig : 1 shows few important locations for voids filling.

1. Around penetration for pendant surfaces and the radiant roof/SH screen
tubes/second pass roof tubes.

2. Between loose front waterwall tubes above front upper panel and below radiant
roof.

3. Gap between radiant roof tubes at the junction of front waterwall.

4. Extreme rear arch tubes and side waterwalls/ extended side waterwalls.

5. Extreme S H screen tubes and S H extended steam cooled wall.

6. Gaps between tubes / nipples in the steam cooled rear, side and front wall and
the respective headers.

7. Extreme tubes of front rear hopper panel and side waterwall lower panel.

Other important locations of voids fillings

- Side waterwall / extended side waterwall and the extreme tubes of radiant roof.

- Extended side steam cooled wall and the extreme tubes of S H screen tubes.

Bharat Heavy Electricals Limited


Bharat Heavy Electricals Limited
BOILER
VOIDS THAT ARE TO BE CLOSED IN PRESSURE PARTS
Erection

Steam cooled sidewall and the extreme tubes of second pass roof.

Between tubes in upper corner transition tubes.

Between tubes in lower corner transition tubes.

Gap between tubes/ nipples of side waterwall lower header at the ash
hopper throat region.

Voids due to lifting slots in fusion / fin welded panels.

Voids due to erection slots in fusion / fin welded panels.

Fusion / fin welded panel fin splits at the panel tube-to-tube butt joint
location.

- Voids are to be closed suitably to retain refractory in position.

Bharat Heavy Electricals Limited


RECOMMENDED HYDROSTATIC
TEST PROCEDURE

Bharat Heavy Electricals Limited


RECOMMENDED HYDROSTATIC TEST PROCEDURE

This is general procedure given as a guide line. Approved procedure for the contract to
be followed for each boiler.

General

After installation of all pressure parts, the Unit is subjected to required Hydrostatic
Pressure test.

The Unit shall be hydro tested for confirmation to IBR code requirements in two areas:

A) Primary circuitory, Drum, Economiser, waterwalls, super Heater and connected


drain and vent lines.

B) Reheater coils, cold and Hot Reheat piping up to isolators.

Limits of Hydro Test

A) Main Boiler with water circulation system (from feed check valve inlet to
Economiser, Drum, Waterwalls) and super Heater system from Drum to M S stop
valve (Ref. Fig. 1)

B) Reheaters inlet header to Outlet header (up to isolating devices installed on C R H


and H R H piping) Ref. Fig.2 Generally hydrostatic test for reheater system is done
at a later date but before taking up its steam blowing activity.

Test Pressure

1) Primary circuitory system One and half times drum


including Economiser, waterwall >• design pressure.
and super heat system

Bharat Heavy Electricals Limited / i.)


RECOMMENDED HYDROSTATIC TEST PROCEDURE

Bharat Heavy Electricals Limited


BOILER
RECOMMENDED HYDROSTATIC TEST PROCEDURE
Erection

FIG. 2. HYP. TEST LIMIT REHEATER SYSTEM

Bharat Heavy Electricals Limited


RECOMMENDED HYDROSTATIC TEST PROCEDURE

2) Reheater system - One and half times Reheater


design pressure or at minimum
of 70 kg/sq.cm.

Completion of pressure part system for Hydro test

1) All pressure parts like Economisers, waterwalls and super Heaters


including drains and vents are erected.

2) All necessary H P welds completed, NDT completed and stress relieved.

3) Completion of F Q P checks and logging of erection alignment readings.

4) All radiographs and stress reliving charts of Pr. Parts system accepted
and signed by Boiler Inspector.

5) All necessary valves including drain and vent valves are installed.

6) All safety valves with shop installed hydrostatic plug are installed.

7) All manhole doors like drum and bottom ring headers are closed with the
Bolting arrangement.

8) Isolating valves are provided to all the other branching system like Soot
Blowers system tapping, Aux. steam tapping, spray connections,
Pressure Gauges etc.

9) All buckstays on waterwalls and second pass are completed along with
corners connections.

10) All fin welding of waterwalls, roof tubes and second pass panels are
completed.

Bharat Heavy Electricals Limited


RECOMMENDED HYDROSTATIC TEST PROCEDURE

11) All attachment welding including skin casing, Insulation attachment,


buckstay attachment.

12) All Pr. Part system supports are completed.

13) Radiographic plugs are welded and Instrument tapping are closed.

14) C C pump impeller and motor assembly is not installed as this assembly
is not to be subjected to hydro test pressure. C C pump volute is blanked
with suitable blanks. These blanks are bolted to the volute with the
suitable gasket. Tightening of the bolts are done as per the procedure
given by pump supplier.

15) Fine fittings including drains, vents and instrument tapping are
completed.

It is preferable to do the hydro test at the one stroke at the stipulated hydro test
pressure indicated in the pressure part arrangement drawing. If it is not possible
to accomplish this, the hydro test may be conducted twice, once for drainable
portion and another full hydro test including non-drainable portion.

Preparation for Hydro Test (Drainable Portion)

1) For drainable portion Hydrotest, D E S H links connecting Divisional Panel


headers are blanked and spacer tubes from S H bottom header are also
blanked.

2) All debris are removed manually from all pressure parts including Headers and
Drum .

3) All vents necessary to prevent air entrapment during filling operation such as
superheater link vents, eco, link vents, Drum vents etc, are kept open.

Bharat Heavy Electricals Limited


RECOMMENDED HYDROSTATIC TEST PROCEDURE

4) Filling pump of 40-50 Ips flow rate with 100 metre head is connected to
permanent filling line through bottom waterwall drain header.

5) Pressuring pumps preferably 3 pumps with the following details are connected
to the bottom drain header. Through one inch tapping point.

a) 0 - 250 Kg/Sq. cm 24 Ipm

b) 0 - 400 Kg/Sq.cm 161pm

c) 0 - 600 Kg/Sq.cm 121pm

All three pumps outlets are connected to common pressuring line with independent
isolation valves. In case only two pumps are available 0 - 250 Kg/Sq.cm and 0 - 600
Kg/sq. cm may be used.

6) At least three calibrated pressure gauges are fixed at the following locations.

Drum Level
Operating floor level
Near pressurizing pumps

The indicator of the pressure gauges selected should have at least 6" dial
graduated for a range of double the intended maximum test pressure, but in no
case the range be less than 1!4 times that pressure. The pressure gauges are
to be calibrated as per Q A manual.

For typical "Test pressure gauge range" refer table I.

Bharat Heavy Electricals Limited


RECOMMENDED HYDROSTATIC TEST PROCEDURE

7) When valves are in T A N D O M (DOUBLE V A L V E S ) both valves must be closed


during the hydro test.

8) Joint inspection protocol prior to hydro test of Boiler for the completion of the
works is to be made and duly filled up (Ref. F Q P ) .

Bharat Heavy Electricals Limited


RECOMMENDED HYDROSTATIC TEST PROCEDURE

TABLE -1

TYPICAL HYDRO TEST PRESSURE AND TEST PRESSURE GAUGE RANGE

BOILER HYDRO TEST TEST P R E S S U R E REMARKS


PRESSURE GAUGE RANGE
2
2
K g / C m (G) K g / C m (G)

1. 500 M W 306 0-600 Water walls, S H


and E C O System

2. 500 M W 79 0-200 Re-heater system

AIR TESTING OF PRESSURE PARTS

2
500 M W - Recommended Air pressure - 2 k g / C m (G) Pr., after regulator

2
Range of Pressure Gauge 0 - 4 Kg/ C m

Bharat Heavy Electricals Limited


BOILER
Erection RECOMMENDED HYDROSTATIC TEST PROCEDURE

Water Quality

- It is the responsibility of the customer to provide properly treated


water, as specified below at ambient temperature but in no case less than 20 deg.
C.

Note

The temperature limitation for hydrostatic testing is 20 deg. C. The important point is
that the hydrostatic pressure should not be applied when the water temperature is less
than this limit.

The easiest way to achieve and maintain proper hydrostatic temperature in cold
weather is with an external steam supply. The full water is heated with a direct contact
heater and the temperature is maintained by using the steam coil air heater. For a new
project where no steam is available, it is advised to consider electric heaters or fuel
fired space heaters.

During testing, the temperature of water should in no case exceed 50 deg. C

- It is recommended to use demineralised or condensate quality water


of specified purity for both drainable and non-drainable portions.

For quality of Treated water, Refer T a b l e - 2 .

Bharat Heavy Electricals Limited -fiy


BOILER
RECOMMENDED HYDROSTATIC TEST PROCEDURE
Erection

The treated Demineralised (DM) water shall include 10-ppm ammonia and 200-ppm
hydrazine. This treated water will have a pH value of approximately 10.

In case only water walls economiser are to be hydro tested, filtered water clear, free
from suspended and colloidal impurities with a restriction of the total dissolved solid
contents to 100 ppm can be used. It should be free from chlorine, free from colour and
pH valves varies between 8.8 to 9.

Note

Demineralised or condensate quality water is defined as containing no more than 1


ppm identifiable solids and essentially a zero concentration (or lowest detectable
level) of organic materials.

After chemical cleaning, steam blowing and lay up of the units, if situation warrants to
do hydraulic testing of the pressure parts usage of treated D M water or treated
condensate is only recommended. For quality of treated DM water Refer Table -2.

Bharat Heavy Electricals Limited )30


BOILER
RECOMMENDED HYDROSTATIC TEST PROCEDURE
Erection

Table-2

Quality of Water

Demineralised water (Specification)

1. pH at 25 deg. C 7*0.2

2. Electrical Conductivity at 25 deg C Less than 0.2


Michromho/cm

3. Total Hardness (Ca+Mg) P P M C a C o 3


Nil

4. Total Silica Less than 0.02

5. Si0 PPM
2
Less than 0.02 is
preferable

6. Chloride P P M as N a d Nil

7. Sodium P P M as Na Less than 0.003

8. Organic Matter Mgm Should be free (in any


K Mn0 /Litre
4
case it should not
exceed 0.2 P P M on an
average)

General Appearance Clear, Free from odour,


colour and haziness.
No glittering to
tyndal effect.

Bharat Heavy Electricals Limited


RECOMMENDED HYDROSTATIC TEST PROCEDURE

2. Quality of treated DM water or treated condensate :

The DM water or Condensate treated with 10-ppm ammonia and 200-ppm hydrazine
to have a pH value of approximately 10.

Air Testing the pressure parts

- Before filling the boiler with water an air tightness test is to be performed to
detect leakages due to valve left in open position, X-ray plug forgotten, any cuts
or gouges etc. not observed by visual inspection. This will reduce the DM water
consumption, as well as time.

- The air should be filtered and free from oil and dust prior to entering the unit.

- The boiler is to be pressurized not more than 2 kg/sq.cm (G), taking safety
aspects into consideration.

- Before admitting air, close the drum manhole, handhole stubs, isolating valves
in drain lines, branching lines and vent lines including the vent valves in S H link,
eco link and drum link, Drain and Test Valves in official pressure gauge etc.

- After completing the air tightness testing keep the vents open.

Bharat Heavy Electricals Limited )%M~


BOILER
Erection

FILLING THE SYSTEM

Filling pumps is used to fill the system. Details of Typical filling pump is given below.

PUMP DETAILS

Total Head 10 Metres

Rate of flow 33.3 L P S

Speed 2960 R P M

Rating 90 KW

MOTOR DETAILS

Motor Rating 90 KW

Speed 2960 R P M

Amps 160 A

Voltage 415 V

Filling pump suction line is connected to the DM water tank and delivery line is
connected to the Boiler filling line. Filling line is connected to the Boiler drain Header,
Recirculation line is connected from the delivery line to the tank.

- Suction valve is kept open and delivery valve is closed. Pump is started and correct
direction of rotation is checked. Air vent valve is kept open during start up.

- Recirculation valve is kept open fully.

- Delivery valve is gradually opened and recirculation valve is closed for filling the
boiler.

- Filling line pressure is monitored through the pressure gauge on the delivery line.

- The boiler water circulation system is filled through filling lines connected to the
boiler drain headers and Economiser Filling Line.

- A s the water raises up to drum manholes, the later shall be tightly closed and filling
shall be completed once the water flows fully in air vents, which are closed
subsequently.

Bharat Heavy Electricals Limited


BOILER
Erection RECOMMENDED HYDROSTATIC TEST PROCEDURE

- In no case water entry into superheater should be permitted through the drum. This
is to prevent carry over of suspended impurities into the superheater.

- Superheater is filled through the S H drain header with treated DM water of quality
as indicated in Table-2, until all the elements are filled and the water overflows
through the vent valves.

- Vent valves are closed and opened several times to allow the entrapped air to be
vented out.

- Filling pump is stopped and delivery valve is closed pressurizing the system.

- Pressure is raised by means of Hydro Test pumps.

- Pressuring pump details, Types is shown below.


2 2
Pressure rating 0 - 400 kg/cm 0 - 600 kg / c m
Discharge capacity 16LPM 12LPM
Motor 25 H P 40 HP

Accessories with pump - Spring loaded safety valve, non return valve, Isolating valve
and pressure gauge.

- Hydro Test Pump suction is connected to the mini DM water tank which received
water from main D M water tank.

- Hydro Test pump delivery is connected to the drain header with 25 to 38mm
seamless pipe.

- All the joints of temporary lines are to be welded with H P welders.

- Temporary lines are adequately supported.

- Suction valve is kept open. Pressurising pump is started and delivery valve is
opened immediately.

2
- Pressure is increased at the rate of not more than 10 K G / C M per minute up to
2
approximately 80% of the test pressure and by 1-2 K g / C m (g) per minute beyond
that value.
Bharat Heavy Electricals Limited
BOILER
Erection RECOMMENDED HYDROSTATIC TEST PROCEDURE

- At this stage, all the safety valves with hydro test plugs installed are gagged.

2
- Pressure is recorded at every 10 K g / C m rise with time. Time V s Pressure graph
can be plotted.

- Raise the pressure to the hydrostatic test pressure. The pressure shall be under
proper control at all times. The pump operator and the responsible person watching
the official test gauge must have radio-telephonic contact. Once the test pressure is
reached the responsible person watching the test gauge shall give orders to stop
the test pumps immediately and to cut off the electric connections.

- The test pressure is held for about half an hour. During the holding time the test
gauge pressure reading shall not drop noticeably.

Hydrostatic Testing

- The hydraulic test pressure reading will be taken from the


official pressure gauge located at the highest point in the presence of the Inspector.

- After the hydraulic test pressure has been noted and agreed to by the Inspector,
the hydraulic test pressure is then reduced to not less than the maximum allowable
working pr. And the whole pressure parts check will be carried out.

- If leaks are found, it will be necessary to release the pressure and drain these
portions. Make the repairs and refill the unit as mentioned above and repeat
hydrostatic test.

- Details of the leaks noticed during Hydraulic Tests are to be furnished as given
below for better understanding :

a) Exact location of leak(s) component circuit, elevation, materials etc.

b) Description of leak(s) such as straight tube elbow, shop or field weld, torchcut,
where a lug was removed, and attachment weld etc.

Bharat Heavy Electricals Limited /35*


BOILER
Erection RECOMMENDED HYDROSTATIC TEST PROCEDURE

c) Magnitude of leaks - sweeping /sweating, leaks, burn through, longtituditional


crack.

De-pressurisation of the Pressure Parts.

The pressure parts shall be depressurized at a depressurization rate of 1


2
kg/cm per minute.

While releasing the pressure, the vents should be opened when the system
pressure reaches 1 kg/sq,cm to prevent creation of vacuum in the system.

Note : Remove the gags at less than 80% design set pressure.

Inspection of the Boiler Pressure Parts after Testing.

After completion of the Hydraulic test, the inspector shall carefully examine the
boiler inside and outside and satisfy himself that it has satisfactorily withstood
the test.

To enable the inside inspection of the boiler, the interior has to be equipped
with suitable scaffolding for inspecting the elements, walls, tubes and welds.

Proceedings to Prevent Accidents and Endangering of Persons during


Pressure Test.

Due to the fact that during the pressure test the boiler and boiler house area
are under an increased risk of danger, special safety precautions have to be
taken to prevent accidents. These arrangements are made by the erection and
commissioning services according to the instructions of the site
managements.

During the period of raising, holding and releasing the test pressure, the entry
to the boiler house is prohibited for all persons not participating in the pressure
test. Works at the pressure parts or in the direct neighborhood^ are not
permitted.

Bharat Heavy Electricals Limited , R


BOILER
Erection RECOMMENDED HYDROSTATIC TEST PROCEDURE

Hydrostatic Test Report

After completion of the hydrostatic test a written report as per the IBR format
shall be issued and signed by the Inspection Authority.

Preservation of Boiler after Hydrostatic Test.

- There is generally some time delay between hydrostatic test and further initial
boiling out and chemical cleaning of the unit. Hence, the unit should be kept
under preservation for protecting the internal surface from oxidation.

- Fill the unit with hydrazine and Ammonia treated DM water containing 300-
ppm hydrazine and 10ppm Ammonia with a pH value of 10.0 to 10.5 till it
overflows at vents.

- The unit should be kept under nitrogen cover with a pressure of 0.5 kg/sq.cm.
In the absence of nitrogen capping facility the unit should be pressurized with
the aid of a fill pump to 5 kg/sq.cm. pressure.

- Samples can be collected periodically say once a week or fortnight, depending


on the pressure holding worthiness of the system, tested for pH and hydrazine
content.

- In case the sample water does not meet the criteria for lay up water, the
conditioning system shall be operated as to restore the required composition.

- No welding shall be carried out on pressure parts when the system is under
preservation or the system is filled with water.

- If there is a chance of freezing, the water in the drainable circuits can be


displaced by nitrogen and the unit can be laid up under nitrogen pressure.
Temporary heating equipment should be provided to keep the non-drainable
superheater/ reheater elements above freezing temperature.

- The reheater should be laid up under nitrogen pressure with the reheater
isolating devices closed or with the blank flanges.

Bharat Heavy Electricals Limited /39 17


RECOMMENDED HYDROSTATIC TEST PROCEDURE

After completion of Hydrotest of:

- Drainable portion of pressure parts, clearance may be given for Insulation.

- Blanks are removed from D E S H links, Final S H elements and S H divisional


panels completed. S H Links are completed.

- After completion of non-drainable portion of pressure parts, Full Hydro test is


completed just before lightup.

- After completion of Full Hydrotest, Boiler is registered with Boiler Inspectorate.

- Boiler waterwall, Superheater and Economiser are hydrostatically tested as a


unit. The Reheater is normally hydro tested separately at the recommended
pressure. If the unit is not provided with Isolators, these inlets should be
isolated by means of blank flanges.

Bharat Heavy Electricals Limited


RECOMMENDED HYDROSTATIC TEST PROCEDURE

TABLE - 3

WATER VOLUME (TYPICAL)

SYSTEM 500 MW VOLUME CUM

1. CIRCULATION S Y S T E M 170

2. D R U M (FULL) 60

3. FP.nNnMI.9FR 150

4. SUPERHEATER 130

5. REHEATER 105

TOTAL 615 C U M

Bharat Heavy Electricals Limited

You might also like