Sl.

No Description
Day 1 Day 2 Day 3

Checking of material
01
recevied on site and storage
Level Checking of the lift well construction
02
by dropping Plum

03 Erection of support brackets

Moving of material like rails and beams


04
into the lift well

05 Erection of Guide rails

06 Erection of ISMB + Gear loaction and leveling

07 Erection of landing frame

08 Installing the Controller panel

09 Painting of lift well

10 Laying of the electric wires

11 Fixing of Car Sling and Counter Weight Frame

12 Ropeing

13 Power Taken

14 Fixing of cabin and lift car top work

Fixing and aliging the counter weights in the frame


15
Installing OSG and PitWork

16 Installation of landing doors

17 Installation of Car doors

18 Final Checking
On Day 12 & 13, Machine Packing, Fixing of Buffer Block has to be done by Civil Contractors
PHASE 1

Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Day 11 Day 12 Day 13
e by Civil Contractors
Day 14 Day 15 Day 16 Day 17 Day 18 Day 19 Day 20 Day 21 Day 22
PHASE 2

Day 23 Day 24 Day 25 Day 26 Day 27 Day 28 Day 29 Day 30 Day 31


Day 32 Day 33 Day 34 Day 35