ANNEXURE - I

Pending works List for completion of workdone under Adilabad Division Dtd: 29.09.2021
Department MEIL
Estimate
S.N M.B M.B Recorded but items Balance items
o Name of the Work No.s Present Work Status d Cost in Recorded pending by agency to be rocorded
Lakhs Remarks Remarks Target Date
1 2 3 4 5 6 7 8 10 9

70% work done(upto brick work), remaining work recorded from last 25 days no work at Contrators problem for Work order
1 PMC Building- Ichoda 1 49.60 upto till As per Estimate
held up (MEIL) today work site pending
26.10.2021
recorded
2 PMC Building - Adilabad 1 Skeleton work completed, Balance work pending 300.00 upto till As per Estimate from last 20 days no work at Contrators problem for GST deduction
due to Sub contractor today work site
26.10.2021
3 Flow Meters 16 Not yet supplied & work not started 115.00 work not started 10.10.2021
4 Construction of Watchmen Quarters 1 Plumbing,Electrical,Water Supply & Tiles work 18.50 Yes Septic tank, sanitation & Furniture Work in Progress, Furniture works MB
at Babuldhole Sump pending pumpsets,& Furniture Plumbing works works work in Progress recording pending 15.10.2021
Construction of Watchmen Quarters Plumbing,Electrical,Water Supply & Tiles work Septic tank, sanitation & Furniture Work in Progress, Furniture works MB
5 at Bhutai K Sump 1 pending pumpsets,& Furniture 18.50 Yes Plumbing works works recording pending
work in Progress 15.10.2021
Construction of Watchmen Quarters Plumbing,Electrical,Water Supply & Tiles work Septic tank, sanitation & Furniture Work in Progress, Furniture works MB
6 at Damanguda Sump 1 pending pumpsets,& Furniture 18.50 Yes Plumbing works works recording pending
work in Progress 15.10.2021
Construction of Watchmen Quarters Plumbing,Electrical,Water Supply & Tiles work Septic tank, sanitation & Furniture Work in Progress, Furniture works MB
7 1 18.50 Yes
at Karatwada Sump pending pumpsets,& Furniture Plumbing works works recording pending
work in Progress 15.10.2021
Construction of Watchmen Quarters Plumbing,Electrical,Water Supply & Tiles work Septic tank, sanitation & Furniture Work in Progress, Furniture works MB
8 at Suryanagar Sump 1 pending pumpsets,& Furniture 18.50 Yes Plumbing works works recording pending
work in Progress 15.10.2021
Construction of Watchmen Quarters Plumbing,Electrical,Water Supply & Tiles work Septic tank, sanitation & Furniture Work in Progress, Furniture works MB
9 1 18.50 Yes
at Mandabaguda Sump pending pumpsets,& Furniture Plumbing works works work in Progress recording pending 15.10.2021
Construction of Watchmen Quarters Plumbing,Electrical,Water Supply & Tiles work Septic tank, sanitation & Furniture Work in Progress, Furniture works MB
10 at Gudam Sump 1 pending pumpsets,& Furniture 18.50 Yes Plumbing works works recording pending
work in Progress 15.10.2021

11 Construction of Watchmen Quarters 1 Plumbing,Electrical,Water Supply & Tiles work 18.50 Yes Septic tank, sanitation & Furniture Work in Progress, Furniture works MB
at Arepally GLBR pending pumpsets,& Furniture Plumbing works works recording pending
work in Progress 15.10.2021

12 Construction of Watchmen Quarters 1 Septic tank, Furniture & Pumpsets 17.00 Yes Septic tank, sanitation & Furniture Electrical works not completed Spectic tank (required material &
at Dahegaon Sump Electrical works pending works in full shape contrator),Furniture to be indent 15.10.2021
Construction of Watchmen Quarters Septic tank, sanitation & Furniture Electrical works not completed Spectic tank (required material &
13 1 Septic tank, Furniture & Pumpsets 17.00 Yes
at Ratnapur Sump Electrical works pending works in full shape contrator),Furniture to be indent 15.10.2021
Septic tank, sanitation &
14 Construction of Watchmen Quarters 1 Septic tank, Furniture & Pumpsets 17.00 Yes Electrical , Painting works Furniture Electrical works not completed Spectic tank (required material &
at Sunkidi GLBR pending works in full shape contrator),Furniture to be indent 15.10.2021

15 Construction of Watchmen Quarters 1 Septic tank, Furniture & Pumpsets 17.00 Yes Septic tank, sanitation & Furniture Electrical works not completed Spectic tank (required material &
at Addagutta Sump Electrical works pending works in full shape contrator),Furniture to be indent 15.10.2021
Construction of Watchmen Quarters Septic tank, sanitation & Furniture Electrical works not completed Spectic tank (required material &
16 at Jandaguda Sump 1 Septic tank, Furniture & Pumpsets 18.00 Yes Electrical works pending works contrator),Furniture to be indent
in full shape 15.10.2021

17 Construction of Watchmen Quarters 1 Septic tank, Furniture & Pumpsets 17.00 Yes Septic tank, sanitation & Furniture Electrical works not completed Spectic tank (required material &
at Daheguda Sump Electrical works pending works in full shape contrator),Furniture to be indent 15.10.2021
18 Construction of Watchmen Quarters 1 Furniture & Pumpsets 17.00 Recorded As Furniture Furniture to be indent
at Adilabad BPT per site works 15.10.2021
75/10 HDPE pipe to be procured for Janguguda
19 Pipeline- HDPE 3.50Km 24.00 pipe required
and Barampur Temple 20.10.2021
20 Pipeline- HDPE 9.50Km HDPE Pipe to be procured for 2 BHK & Schools pipe required
20.10.2021
21 Pipeline- GI 2Km GI Pipe to be procured for 2 BHK & Schools pipe required 20.10.2021
22 Valves 15 200, 300, 800 BFV's, 450NRV and Air valves for valves to be indent
above pipeline to be procured 15.09.2021
23 Air valve Cages 35 To be executed contrater required 15.10.2021

24 Route Indicators 500 To be executed for the pipeline Half of part completed remainig Contractor required
pending 20.10.2021
Estimate
S.N M.B M.B Recorded but items Balance items
Name of the Work No.s Present Work Status d Cost in
o Lakhs Recorded pending by agency to be rocorded
Remarks Remarks Target Date
1 2 3 4 5 6 7 8 10 9
25 New Pumpsets-Ichoda 3 Not yet supplied (15HP, 10HP & 7.5HP) 12.00 7.5HP pumpset Erected 20.10.2021
Brick work, plastering and
26 Pump house 3X4- Adilabad 2 Brick work pending 20.00 Yes painting and all finishing works contrater not respond
20.10.2021
27 Pump house 6X4- Adilabad 1 Rolling shutter pending Yes Rolling Shutter to be fix work order required 20.10.2021
Complusory
28 Pump Rooms 2 x 3m - Ichoda 10 Not Yet started 25.00 work order required
required 20.10.2021
29 Pannel Board Room - Adilabad 1 Brick work pending 6.00 Yes Brick work,plastering contractor required or material required
20.10.2021
30 Compound walls at Sakriyanayak Than 1 Not started 10.00 work order required 20.10.2021
Compound walll at Govindpur Jn 1 Not started 10.00 work order required 20.10.2021
Compound walls at Devijiguda
31 (Pendalwada Sump) 1 RR masonary completed- Balance to be done Recorded as contractor not respond
15.10.2021
per site
Compound walls at Toyaguda Sump 1 RR masonary completed- Balance to be done contractor not respond 15.10.2021
32 Development works at Bhutai Thanda 1 Not Started 15.00 work order required 15.10.2021
Development works at Dhabadi Jn 1 Not Started 11.00 work order required 15.10.2021
Development works at Upperpally 1 Not Started 10.00 work order required
Sump 15.10.2021
Development works at Chintakarra 1 Not Started 19.00 work order required
Sump 15.10.2021
Development works at Damanguda
1 Not Started 15.50 work order required 15.10.2021
Sump
Development works at Mathura Thand 1 Not Started 11.50 work order required 15.10.2021
Development works at Mandabaguda 1 Not Started 10.00 work order required
Sump 15.10.2021
Development works at Gudem Sump 1 Not Started 10.00 work order required 15.10.2021
C/o 2500KL Sump at Sunkidi,
33 Compound Wall Watchman Quarter 1 Not started 420.00 Land not final
and Pumpsets
Technical aspects:
1 AS Built drawings 2 Technical expert required As on this day no Person is 10.10.2021
2 Survey and LS, CS 2 To be provided from MEIL Agency arranged 10.10.2021
3 Technical staff regarding WD 2 To be provided from MEIL Agency Only one Person arranged 10.10.2021
O&M Issues
No valves and other materials at site from MEIL
1 Valves 80&100
Agency
No Pipeline and other materials at site from MEIL
2 Pipeline 75&90
Agency
3 Staff 7 Not engaged for the scattered habs
1. Filter Bed - 600mm Dia
2. Police Colony - 800mm Dia
3. Battisavergaon - 600mm Dia Under repair since last 6
4 Butterfly Valves 6 months in resulting BPT
4. Ekuta bhatti - 600mm Dia Overflow during night hours
5. BPT to ULB - 800mm Dia
6. BPT Inlet - 600mm Dia