You are on page 1of 4

Search

Dave Fourie ‑ PMP Follow


Owner and Freelance Trainer at PMTA (Project
Management Training Africa)
9 articles

What is PERT and how can we use


it?
Published on March 9, 2015

How can PERT help us?


All projects depend on estimations. We have to estimate the time it will take to complete an
activity and we need to estimate the cost that will be incurred in executing an activity, phase
or project. Estimates are approximations or "best guesses" and is subject to the uncertainty
with which we are confronted when making these estimates. From this we can see that the
more uncertainty there is, the less accurate our guess is, and therefore the higher the risk is
that our time and cost estimates will not be realistic. Should we only rely on one estimated
figure, for instance "it will take 8 days to complete the activity", then we will not take the
uncertainty into consideration. In short, PERT is a technique that helps us to take this
uncertainty into account when compiling realistic estimates on our projects.

So what is PERT?
What is PERT (Program Evaluation and Review Technique) and how can we use it to help
us on projects? PERT is a three point activity estimating technique that considers estimation
uncertainty and risk by using three estimates to define an approximate probability for an
activity’s cost or duration. The three estimates used are:

Most likely (M) - The cost/duration of the activity, based on a realistic effort assessment
for the required work and any predicted expenses.

Optimistic(O) - The activity cost/duration based on an analysis of the best-case scenario


for the activity.
How can PERT help us at activity level?
At activity level PERT can help us to determine a more realistic estimate. Let us take the
following estimates for five project activities as an example:

Let us assume that we obtained the following three


estimates for Activity A. Optimistically we can complete the
activity in five (5) days. Pessimistically we estimate that it
can take us up to Fifteen (15) days, while most likely it will
take us only seven (7) days.

PERT calculates a weighted average as the PERT estimate by using the formula : Pert
Estimate = (Optimistic + (4 X Most Likely) + Pessimistic)/6. That means that we are
weighting the most likely estimate by a factor of four (4) and then determining the average
of the weighted most likely time, the best case scenario and the worst case scenario. In the
case of Activity A that will be (5 +(4 X 7) +15)/6. The pert estimate is therefore calculated
as 8 days. If we compare the PERT estimate of 8 days with the normal average of the three
estimates of 9 days (5 + 7 + 15 /3 = 9) we can see that the PERT estimated is weighted
towards the most likely estimate. We use a weighted average calculation because statistically
we find that the largest portion of a randomly occurring population of data will be found
close to the mean as can be seen from the following bell curve, also called a normal
distribution curve:

This bell curve shows us that if we divide the data into 6 equal portions, then by far the
majority of the instances will be found in the 2 portions next to and on both sides of the
middle line (mean) while the probability of the occurrence falling in either the optimistic or
pessimistic block is much lower. We divide the graph into 6 equal block by calculating the
standard deviation also called the sigma (identified by the sigma symbol “ϭ”). By using the
simple formula Sigma = (Pessimistic – Optimistic) / 6 we divide the graph in 6 equal blocks.
From this we can see that the PERT estimating formula using (Optimistic + (4 X Most
Likely) + Pessimistic)/6 is based on this natural distribution. This also gives us a tool with
68% of the data will be found in one standard deviation from the mean in other words
between the mean minus one standard deviation and the mean plus one standard
deviation. We can also say that there is a 68% probability that the activity will be
completed within one standard deviation from the mean.

We also see that 95% of the data will be found within two standard deviations or, put
another way, that we can say with 95% certainty that the activity will be completed
withing the two sigma range.

At three sigma there is a 99,7% probability.

Lets apply this to Activity A:

From the above bell curve we can thus predict that there is:

A 68% probability of completing the activity between 6.3 and 9.7 days.

A 95% probability of completing the activity between 4.6 and 11.3 days.

A 99.7% probability of completing the activity between 3.0 and 13.0 days.

The same formulas can be used to calculate the one, two and three sigma figures for all the
activities:
How can PERT help us at project level?
If we assume that all five the activities are on the critical path and that they will all be
done sequentially, then it is estimated that it will take 60.3 days to complete the project. But
we also saw from the PERT calculations on activity level that there is uncertainty regarding
the estimates for every activity. Therefore there is a probability that any activity can take
longer or shorter than the PERT estimate to be completed. Because we do not know which
activities will take shorter and which will take longer the only option is to accept that some
will take less time and some will take more time to be completed. This means that it will be
unrealistic to ad up all the sigma values and make them applicable to the critical path.
However, there is a more realistic way to calculate the uncertainty of how long it will take
to complete the entire project. We can calculate a more realistic standard deviation for the
critical path by using the formula "Project critical path Sigma = √(sum of all PERT
variances)". We need to determine the PERT variances for this formula by calculating
sigma square (sigma X sigma). Then we add all the PERT variances together and calculate
the square root of the sum. This calculation gives a more realistic standard deviation that
can be used to express the uncertainty applicable to the project due date. The following table
shows the individual values of the PERT variance for every PERT standard deviation:

The project standard deviation can be calculated by determining the square root of the sum
of the PERT variances. As per the above table the sum of the PERT variances is 41.8. The
square root of 41.8 is 6.5. Therefore one standard deviation for the project as a whole is 6.5
days. This value can now be used to calculate the values for one, two and three sigma for the
total project:

There is a 68% probability that the project will be completed between 53.8 and 66.8
days.

There is a 95% probability that the project will be completed between 47.3 and 73.3
days.

There is a 99.7% probability that the project will be completed between 40.8 and 79.8
days.

In practice these percentages can be used to indicate to the sponsor that, due to the
uncertainty regarding the estimates, there is a:

50% probability that the project will be completed within 60 days.

68% probability that the project will be completed within 67 days.

95% probability that the project will be completed within 73 days.

You might also like