DOCUMENTS DRAWINGS_____DRAWINGS_____DRAWINGS_____DRAWINGS_____DRAWINGS_____DRAWINGS_____DRA DOCUMENT PLANNING LIST VERSION 3.0 (01.01.

20) - AJ
Client: Job No.: 66562 TODAY'S DATE: 08 November 2021
DRBC Doc. No.: 66562-LIST-001 PASSWORD: zinger
Project: Author: Rev. 00 (ಠ_ಠ)
Amyaz Rev. Date: 27-Nov-20
Dur. Remarks Filename (In job design file)
Document No. Type Doc. seq no. Rev. Title description Status Author Verified Start date Expected finish date
(Days)

66562-001 MEC DWG 001 0 P&ID 100 % COMPLETE ND Sun 15-Mar-20 Sun 15-Mar-20 66562-001 (P&ID)
66562-002 MEC DWG 002 0 ISOMETRIC - COMPRESSER AIR TO RECEIVER 1 & RECEIVER 2 TO RECEIVER
100 %1 COMPLETE TA Tue 17-Mar-20 Tue 17-Mar-20 66562-002 (ISOMETRIC - COMPRESSER AIR TO RECEIVER 1 & RECEIVER 2 TO RECEIVER 1)
66562-003 MEC DWG 003 0 ISOMETRIC - INSTRUMENTS ON AIR RECEIVERS 100 % COMPLETE TA Fri 27-Mar-20 Fri 27-Mar-20 66562-003 (ISOMETRIC - INSTRUMENTS ON AIR RECEIVERS)
66562-004 MEC DWG 004 0 ISOMETRIC - AIR FILTER DRAIN 100 % COMPLETE TA Tue 31-Mar-20 Tue 31-Mar-20 66562-004 (ISOMETRIC - AIR FILTER DRAIN)
66562-005 MEC DWG 005 0 ISOMETRIC - AIR FROM RECEIVER 1 TO THERMAL DRYERS 100 % COMPLETE TA Mon 30-Mar-20 Mon 30-Mar-20 66562-005 (ISOMETRIC - AIR FROM RECEIVER 1 TO THERMAL DRYERS)
66562-006 MEC DWG 006 0 ISOMETRIC - COMPRESSER AIR TO RECEIVER 2 & 3 100 % COMPLETE TA Mon 30-Mar-20 Mon 30-Mar-20 66562-006 (ISOMETRIC - COMPRESSER AIR TO RECEIVER 2 & 3)
66562-007 CIV DWG 007 0 GENERAL LAYOUT 50 % IN PROGRESS AL 31 Tue 15-Dec-20 Fri 15-Jan-21 66562-007 (GENERAL LAYOUT)
66562-008 CIV DWG 008 0 BOILER FOUNDATION LAYOUT - PLAN VIEW 100 % COMPLETE AL 3 Tue 15-Dec-20 Fri 18-Dec-20 66562-008 (BOILER FOUNDATION LAYOUT - PLAN VIEW)
66562-009 CIV DWG 009 0 BOILER FOUNDATION LAYOUT - SECTIONAL VIEWS 1 100 % COMPLETE AL 3 Tue 15-Dec-20 Fri 18-Dec-20 66562-009 (BOILER FOUNDATION LAYOUT - SECTIONAL VIEWS 1)
66562-010 CIV DWG 010 0 BOILER FOUNDATION LAYOUT - SECTIONAL VIEWS 2 0% PENDING AL 4 Fri 18-Dec-20 Tue 22-Dec-20 66562-010 (BOILER FOUNDATION LAYOUT - SECTIONAL VIEWS 2)
66562-011 CIV DWG 011 0 BOILER FOUNDATION LAYOUT - ANCHORAGE DETAILS 100 % COMPLETE AL 3 Tue 15-Dec-20 Fri 18-Dec-20 66562-011 (BOILER FOUNDATION LAYOUT - ANCHORAGE DETAILS)
66562-012 CIV DWG 012 0 COLUMN FOUNDATION DETAILS - BOILER 60 % IN PROGRESS TA 6 Tue 15-Dec-20 Mon 21-Dec-20 66562-012 (COLUMN FOUNDATION DETAILS - BOILER)
66562-013 CIV DWG 013 0 COLUMN FOUNDATION DETAILS - DEAERATOR 60 % IN PROGRESS TA 6 Tue 15-Dec-20 Mon 21-Dec-20 66562-013 (COLUMN FOUNDATION DETAILS - DEAERATOR)
66562-014 CIV DWG 014 0 COLUMN FOUNDATION DETAILS - ECONOMISER 60 % IN PROGRESS TA 6 Tue 15-Dec-20 Mon 21-Dec-20 66562-014 (COLUMN FOUNDATION DETAILS - ECONOMISER )
66562-015 CIV DWG 015 0 COLUMN FOUNDATION DETAILS - MECHANICAL DUST COLLECTOR 60 % IN PROGRESS TA 6 Tue 15-Dec-20 Mon 21-Dec-20 66562-015 (COLUMN FOUNDATION DETAILS - MECHANICAL DUST COLLECTOR)
66562-016 CIV DWG 016 0 COLUMN FOUNDATION DETAILS - PLATFORM 60 % IN PROGRESS TA 6 Tue 15-Dec-20 Mon 21-Dec-20 66562-016 (COLUMN FOUNDATION DETAILS - PLATFORM)
66562-017 CIV DWG 017 0 FOUNDATION DETAILS - FEEDWATER PUMPS 0% PENDING AL 0 Fri 18-Dec-20 Fri 18-Dec-20 66562-017 (FOUNDATION DETAILS - FEEDWATER PUMPS )
66562-018 CIV DWG 018 0 FOUNDATION DETAILS - PRIMARY FD FAN 0% PENDING AL 3 Fri 18-Dec-20 Mon 21-Dec-20 66562-018 (FOUNDATION DETAILS - PRIMARY FD FAN )
66562-019 CIV DWG 019 0 FOUNDATION DETAILS - SECONDARY FD FAN 100 % COMPLETE AL 0 Fri 18-Dec-20 Fri 18-Dec-20 66562-019 (FOUNDATION DETAILS - SECONDARY FD FAN )
66562-020 DWG 020 0 0% PENDING Thu 02-Apr-20 Thu 02-Apr-20 66562-020 ()

66562-LIST-001 LIST 001 0 0% PENDING 00-Jan-00 66562-LIST-001 ()

66562-LIST-001 LIST 001 0 0% PENDING Sat Sat 00-Jan-00 66562-LIST-001 ()


Project end date