You are on page 1of 7

Customer's Affected

Time to Survive Calculations


Description Affected
ABN002 21,745,875 ABN002 = 5 weeks
ABX001 21,745,875 ABX001 = 36.125 + 52 = 88.125 units/week = 133 / 88.125 = 1.5 weeks
BBR474 14,985,784 BBR474 = 36.125 + 315 = 351.601 units/week = 97 / 351.601 = 0.3 weeks
BLY283 6,129,943 BLY283 = 8.625 + 127 = 135.41 units / week = 447 / 135.41 = 3.5 weeks
BNT172 22,084,936 BNT172 = 37.812 + 75 = 112.812 units / week = 888 / 112.812 = 8 weeks
FBT937 21,115,727 FBT937 = 20.312 + 5 = 25.312 units / week = 889 / 25.312 = 35 weeks
GHY456 22,084,936 GHY456 = 37.812 + 6 = 43.812 units / week = 477 / 43.812 = 11 weeks
JK1768 15,954,993 JK1768 = 29.187 + 6 = 35.187 units / week = 165 / 35.187 = 5 weeks
JK1984 6,129,943 JK1984 = 8.625 + 6 = 14.625 units / week = 334 / 14.625 = 23 weeks
JK1990 14,985,784 JK1990 = 18.625 + 101 = 119.815 units / week = 554 / 119.815 = 5 weeks
KJU879 15,615,932 KJU879 = 27.5 + 30 = 57.5 units / week = 1186 / 57.5 = 21 weeks
KTY476 14,985,784 KTY476 = 18.625 + 6 = 24.625 units / week = 781 / 24.625 = 32 weeks
MBR034 22,084,936 MBR034 = 37.812 + 45 = 82.812 units / week = 465 / 82.812 = 6 weeks
MNA923 630,148 MNA923 = 8.875 + 71.428 = 80.303 units / week = 342 / 80.303 = 4.5 weeks
NDH563 21,745,875 NDH563 = 36.125 + 6 = 42.125 units / week = 788 / 42.125 = 19 weeks
NMU839 15,615,932 NMU839 = 27.5 + 6 = 33.5 units / week = 664 / 33.5 = 20 weeks
PFR934 15,615,932 PFR934 = 27.5 + 83.333 = 110.833 units / week = 159 / 110.833 = 1.5 weeks
PRT847 22,084,936 PRT847 = 37.812 + 6 = 43.812 units / week = 807 / 43.812 = 18.5 weeks
RTV213 22,084,936 RTV213 = 37.812 + 89 = 127.037 units / week = 136 / 127.037 = 1 week
RVN493 22,084,936 RVN493 = 37.812 + 23 = 60.812 units / week = 780 / 60.812 = 13 weeks
TTN332 22,084,936 TTN332 = 37.812 + 12 = 49.812 units / week = 1666 / 49.812 = 33.5 weeks
TYN932 22,084,936 TYN932 = 37.812 + 24 = 61.812 units / week = 885 / 61.812 = 14.5 weeks
YRE374 6,760,091 YRE374 = 17.50 + 137 = 150.404 units / week = 972 / 150.404 = 6.5 weeks
YTH478 339,061 YTH478 = 1.687 + 72 = 73.11 units / week = 1299 / 73.11 =18 weeks
YTH789 15,615,932 YTH789 = 27.5 + 323 = 350.119 units / week = 1003 / 350.119 = 3 weeks
YTH934 6,129,943 YTH934 = 8.625 + 139 = 147.910 units / week = 1099 / 147.910 = 7.5 weeks
ZVY568 22,084,936 ZVY568 = 37.812 + 42 = 79.624 units / week = 646 / 79.624 = 8 weeks
ons

88.125 = 1.5 weeks


351.601 = 0.3 weeks
135.41 = 3.5 weeks
/ 112.812 = 8 weeks
5.312 = 35 weeks
43.812 = 11 weeks
5.187 = 5 weeks
625 = 23 weeks
/ 119.815 = 5 weeks
5 = 21 weeks
24.625 = 32 weeks
/ 82.812 = 6 weeks
42 / 80.303 = 4.5 weeks
42.125 = 19 weeks
= 20 weeks
9 / 110.833 = 1.5 weeks
3.812 = 18.5 weeks
/ 127.037 = 1 week
60.812 = 13 weeks
/ 49.812 = 33.5 weeks
61.812 = 14.5 weeks
/ 150.404 = 6.5 weeks
73.11 =18 weeks
/ 350.119 = 3 weeks
9 / 147.910 = 7.5 weeks
79.624 = 8 weeks
Components Customers Affected TTS in weeks Cost Systems Criticality
ABN002 21,745,875 5 56 2
ABX001 21,745,875 1.5 158 3
BBR474 14,985,784 0.3 125 3
BLY283 6,129,943 3.5 15 2
BNT172 22,084,936 8 99 1
FBT937 21,115,727 35 45 3
GHY456 22,084,936 11 3 1
JK1768 15,954,993 5 0.1 3
JK1984 6,129,943 23 0.2 1
JK1990 14,985,784 5 0.1 3
KJU879 15,615,932 21 44 2
KTY476 14,985,784 32 1 2
MBR034 22,084,936 6 0.1 1
MNA923 630,148 4.5 35 3
NDH563 21,745,875 19 85 2
NMU839 15,615,932 20 0.1 2
PFR934 15,615,932 1.5 17 2
PRT847 22,084,936 18.5 7 1
RTY213 22,084,936 1 10 2
RVN493 22,084,936 13 235 1
TTN332 22,084,936 33.5 12 1
TYN932 22,084,936 14.5 245 1
YRE374 6,760,091 6.5 44 3
YTH478 339,061 18 0.01 4
YTH789 15,615,932 3 0.01 4
YTH934 6,129,943 7.5 0.01 4
ZVY568 22,084,936 8 25 3
Components Customers Affected TTS in weeks Cost Systems Criticality
BNT172 22,084,936 8 99 1
MBR034 22,084,936 6 0.1 1
Replacement Rate per Week
75
45
Data for Critical Item: MBR 034

Carrying Cost = $ 0.20


Per Unit Cost = $ 0.10
Total Cost per Unit = $ 0.30
Average Revenue per User = $200
Total Revenue Lost = Revenue x Lost Sales (Customers Affected) = 200 x 22,084,936 = $ 4,416,987.200

By rising the inventory level

MBR034 = 37.812 + 45 = 82.812 units / week = 765 / 82.812 = 9 weeks

By carrying more inventory in stock (300 units), TTS will increase to approximate 9 weeks which will be h
36 = $ 4,416,987.200

9 weeks which will be helpful in

You might also like