You are on page 1of 3

BURJ AL ARAB

LOCATION

● United Arab Emirates – Dubai


● Private Island (280 m Offshore)

ABOUT

● Building Name: Burj-Al-Arab Hotel.


● Other/Former Names: Arab Sail.
● Chief Architect: The primary architect who designed the building Tom Wright of Atkins. •
● Chief Contractor: WS Atkins Partners Overseas.
● Construction Contractor: Murray & Roberts.
● Construction : 1993 – 1999. • Floors : 60.
● Floor Area : 111,500 m2 (1,200,000 sq ft

FACTS

● At 321 meters (1,053 feet) it is the third tallest hotel in the world (not including
buildings with mixed use); however, 39% of its total height is made up of non-occupiable
space.
● Burj Al Arab stands on an artificial island 280 meters (920 feet) from Jumeirah beach
and is connected to the mainland by a private curving bridge
● In 1993, architect Tom Wright of WS Atkins took on the challenge of creating this
groundbreaking superstructure.
● Construction began in 1994 and involved 3000 companies and contractors; 250
designers from the UK, USA and Dubai; and 3500 workmen on site at any given time. It
took two years to reclaim the island in the shore waters of the Arabian Gulf, and a further
three years to erect the magnificent landmark. Burj Al Arab’s doors officially opened on 1
December 1999.
● An incredible 70,000 cubic meters (2,472,026 cubic feet) of concrete and more than
9,000 tonnes (9.920 US tons) of steel were employed in the construction of the tower.
● Approximately 1,790 square meters (19,270 square feet) of 24-carat gold leaf was
used to embellish the interior.
● It will take you 1080 steps to reach the 27th floor of the hotel
● The building is supported by 250 columns that go 45 meters under the sea and is held in
place by the friction of the sand.
● Wind speed of 45 meters per second, under the recommendations of Dubai Municipality,
was adopted for the design
● To reinforce the structure from any potential swaying, two tuned mass dampers,
weighing about 2 tonnes each, limit vibrations in the tubular steel mast that projects 60 m
above the building.
● Island rises 7 and a half meters above the waves. Island protected by concrete
honeycomb shaped solid blocks designed to reduce the impact of waves.

THE CHALLENGE

● It was very challenging to design foundations to Support the mega structure-270


miles off coast, 320 mtr in height on man-made island (6mts from Arabian Sea)
resistant to earthquake (falling under range of major fault line) and wind that
blows 90 miles per hour

Load Analysis

● Total dead load : 2850,000,000 lbs


● Total live load : 86,160,000 lbs
● Total load on foundation : 150,000 lbs/SF
● Maximum horizontal wind load : 2,366,000 lbs

Load Tracing

● The structure transfers the vertical loading through the large spine. This is the
most direct way for the vertical loads to reach the ground.
● Secondly, the vertical loads transfer through the curved edge

TESTS AND RESULTS

● Initial core test-Drilling was done 180 mts down and no solid rock was formed but
the architect was defiant about the design and construction.
● Then, reinforced concrete foundation piles deep into sand with concept of skin
–friction were designed
● It is supported on 250 numbers of 1.5 meter diameter columns that drilled deep
into the sea
● Each column is a steel reinforced concrete foundation pile with 45 meters in
length.
● Piles -20 percent longer than planned were executed with a combined length of
six and a half miles-35 times as long as a tiring hotel to support.
● Foundations have the capacity to resist failure due to Liquefaction which is
caused during earthquakes.

You might also like