Professional Documents
Culture Documents
PSS®E Training 1
DISCLAIMER
The material and the information contained
herein is prepared by Panacean Energy Solution
Pvt. Ltd., Mumbai solely for the purpose of
providing comprehensive training to MSETCL
Personnel. Information provided in this
document must not be reproduced, published,
re-sold or otherwise distributed in any medium
without prior permission of Panacean Energy
Solution Pvt. Ltd.
PSS®E Training 2
CONTENT
Introduction to Fault Analysis
Brief Introduction of Fault Analysis
Objective of Fault Analysis
PSS®E Training 4
Introduction to Fault Analysis
Power flow : Evaluate normal operating conditions
Fault Analysis: Evaluate abnormal operating conditions
In an electric power system, a fault is any abnormal electric current.
For example, a short circuit is a fault in which current bypasses the
normal load.
A fault in a circuit is any failure that interferes with the normal
system operation.
Lighting strokes cause most faults on high voltage transmission lines
producing a very high transient that greatly exceeds the rated
voltage of the line.
This voltage usually causes flashover between the phases and/or
the ground creating an arc.
PSS®E Training 5
Introduction Continue…
PSS®E Training 6
Importance of Fault Analysis Study
Electric systems occasionally experience short circuits.
This results in abnormally high currents.
Overcurrent protective devices should isolate faults at a given
location safely, with minimal damage
The fault analysis of a power system is required in order to provide
information for the selection of switchgear, setting of relays and
stability of system operation
If one, or two, or all three phases break or if insulators break due to
fatigue or inclement weather, this fault is called a permanent fault
since it will remain after a quick power removing.
Knowing the magnitude of the fault current is important when
selecting protection equipment (type, size, etc..)
PSS®E Training 7
Importance Continue…
There are three periods of time:
Sub-transient period: first cycle or so after the fault – AC
current is very large and falls rapidly;
Transient period: current falls at a slower rate;
Steady-state period: current reaches its steady value.
PSS®E Training 8
Types of Faults
PSS®E Training 9
Types of Faults Continue…
There are two main types of faults
Symmetric faults: System remains balanced; these faults are relatively
rare, but are the easiest to analyze.
Un-symmetric faults: System is no longer balanced; very common, but
more difficult to analyze
The most common type of fault on a three phase system by far is the
single line-to-ground (SLG), followed by the line-to-line faults (LL),
double line-to-ground (DLG) faults, and balanced three phase faults.
PSS®E Training 10
Fault Analysis results used for:
Specifying rating for circuit breakers and fuses
Protective replay settings
Specifying the impedance of transformers and generators
PSS®E Training 11
Fault MVA Calculations
In a power system, the maximum fault current (or fault MVA)
that can flow into a zero impedance fault is necessary to be
known for switch gear solution. This can either be the
balanced three phase value or the value at an asymmetrical
condition. The Fault Level defines the value for the
symmetrical condition. The fault level is usually expressed in
MVA (or corresponding per-unit value), with the maximum
fault current value being converted using the nominal voltage
rating.
PSS®E Training 12
Fault Level Calculation Continue…
The per unit value of the Fault Level may thus be written as
3 . 𝑁𝑜𝑟𝑚𝑖𝑛𝑎𝑙 𝑉𝑜𝑙𝑡𝑎𝑔𝑒. 𝐼𝑆𝐶 3 𝐼𝑠𝑐 𝑉𝑁𝑜𝑚𝑖𝑛𝑎𝑙.𝑃𝑢
𝐹𝑎𝑢𝑙𝑡 𝐿𝑒𝑣𝑒𝑙 = = = 𝐼𝑠𝑐.𝑝𝑢 =
3 . 𝑁𝑜𝑟𝑚𝑖𝑛𝑎𝑙 𝑉𝑜𝑙𝑡𝑎𝑔𝑒 . 𝐼𝑏𝑎𝑠𝑒 3 𝐼𝑏𝑎𝑠𝑒 𝑍𝑝𝑢
PSS®E Training 13
Example:
Given Data: Pre-fault Voltage = 11KV/11KV=1.0p.u
PSS®E Training 14
Positive Sequence
1 pu
~ X(+ve)=0.15
Xth(+ve) =0.15
Negative Sequence
X(+ve)=0.12
Xth(-ve) =0.12
PSS®E Training 15
Zero Sequence
X(+ve)=0.08
3Xn=0.15
Xth(Zero) =0.23
PSS®E Training 16
3𝑉
Fault Current 𝐼𝑓 = 3𝐼𝑅 = 𝑋 𝑡ℎ +𝑣𝑒 +𝑋 𝑡ℎ −𝑣𝑒 +𝑋 𝑡ℎ 𝑍𝑒𝑟𝑜
3∗1
=
0.15+0.12+0.23
= 6 𝑝𝑢 𝑎𝑡 −900
3
𝐼𝑓 = 6 𝐾𝐴 = 9.4𝐾𝐴
3∗11
𝐵𝑎𝑠𝑒 𝑀𝑉𝐴
Fault MVA =
𝑋 𝑡ℎ +𝑣𝑒 +𝑋 𝑡ℎ −𝑣𝑒 +𝑋 𝑡ℎ 𝑍𝑒𝑟𝑜
30
=
0.15 + 0.12 + 0.23
= 60 𝑀𝑉𝐴
PSS®E Training 17
Interconnection Of Sequence Network
PSS®E Training 18
PSS®E Training 19
FAULT CURRENT FORMULAE
PSS®E Training 20
PSS®E Training 21
Depends on type of fault
Three phase fault.
Only Positive Sequence Data. Negative, Zero sequence Network not
excited.
SLG fault
Positive, Negative, Zero sequence Data.
Typical fault study
SLG ( 70%)
Fault current can range in utility systems from a few percent to
possibly 125% of the three phase fault value.
Three phase (5%)
In industrial systems line to ground fault current of more than three
phase value is rare.
LL (15%)
fault currents are approximately 87% of three-phase fault
current
LLG (10%)
PSS®E Training 22
Processing Activities to Perform Fault
Analysis in PSS®E
Read Sequence Data (Activity RESQ)
File>Open…
Read sequence data file (*.seq file) for fault analysis. The requirement
of working case should be Positive sequence network where sequence
data is to be read must be resent in the working case.
Other way to append the .SEQ file is directly typing on command line
input as RESQ and it will asks you to enter the file name of .SEQ, enter
the name and press ENTER. It will display the activities entered. But, in
general the first approach is the best approach to perform.
PSS®E Training 23
Processing Activities Continue…
The Sequence Data File output activity RWSQ writes the sequence
data contained in the working case in the form of a Sequence Data
File. That is, when directed to a file, the data records written by
activity RWSQ are in a format suitable for input to activity RESQ.
Activity RWSQ is accessible from the Sequence Data tab of the Save
Network Data dialog as shown below.
PSS®E Training 24
Processing Activities Continue…
PSS®E Training 25
Data format in the Sequence Data File
(*.seq file)
POSITIVE SEQ. MACHINE IMPEDANCE DATA, it will update in
machine tab
PSS®E Training 26
Data Format Continue…
Bus R-ZERO
ID X-ZERO (PU)
Number (PU)
G-NEG
Bus Number B-NEG (PU)
(PU)
PSS®E Training 27
Data Format Continue…
Mutual Mutual
From To Bus From To
ID ID Impeda Impeda BIJ1 BIJ2 BKL1 BKL2
Bus 1 1 Bus 2 Bus 2
nce nce
PSS®E Training 28
Data Format Continue…
G- G- R- X-
FROM TO Impedan CONNEC
ID RESIST REACT ZERO ZERO
BUS BUS ce Table T CODE
(PU) (PU) (PU) (PU)
BUS
NUMBER
PSS®E Training 29
Data Format Continue…
The Example .SEQ file
0, 33 / PSS(R)E-33.2 THU, APR 25 2013 19:34
1,'1 ', 2.50000E-03, 2.50000E-01, 3.00000E-01, 1.80000E+00, 2.50000E-03, 2.50000E-01, 1.25000E-03, 1.25000E-01,1, 0.00000E+00, 0.00000E+00
2,'1 ', 2.50000E-03, 2.50000E-01, 3.00000E-01, 1.80000E+00, 2.50000E-03, 2.50000E-01, 1.25000E-03, 1.25000E-01,1, 0.00000E+00, 0.00000E+00
3,'1 ', 2.50000E-03, 2.50000E-01, 3.00000E-01, 1.80000E+00, 2.50000E-03, 2.50000E-01, 1.25000E-03, 1.25000E-01,1, 0.00000E+00, 0.00000E+00
4,'1 ', 2.50000E-03, 2.50000E-01, 3.00000E-01, 1.80000E+00, 2.50000E-03, 2.50000E-01, 1.25000E-03, 1.25000E-01,1, 0.00000E+00, 0.00000E+00
0 / END OF MACHINE IMPEDANCE DATA, BEGIN LOAD DATA
0 / END OF LOAD DATA, BEGIN ZERO SEQ. NON-TRANSFORMER BRANCH DATA
5, 6,'1 ', 7.37500E-3, 8.25000E-2, 0.02625, 0.00000E+0, 0.00000E+0, 0.00000E+0, 0.00000E+0, 0.00000E+0,0
6, 7,'1 ', 2.95000E-3, 3.30000E-2, 0.01050, 0.00000E+0, 0.00000E+0, 0.00000E+0, 0.00000E+0, 0.00000E+0,0
7, 8,'1 ', 3.24500E-2, 3.63000E-1, 0.11550, 0.00000E+0, 0.00000E+0, 0.00000E+0, 0.00000E+0, 0.00000E+0,0
7, 8,'2 ', 3.24500E-2, 3.63000E-1, 0.11550, 0.00000E+0, 0.00000E+0, 0.00000E+0, 0.00000E+0, 0.00000E+0,0
8, 9,'1 ', 3.24500E-2, 3.63000E-1, 0.11550, 0.00000E+0, 0.00000E+0, 0.00000E+0, 0.00000E+0, 0.00000E+0,0
8, 9,'2 ', 3.24500E-2, 3.63000E-1, 0.11550, 0.00000E+0, 0.00000E+0, 0.00000E+0, 0.00000E+0, 0.00000E+0,0
9, 10,'1 ', 2.95000E-3, 3.30000E-2, 0.01050, 0.00000E+0, 0.00000E+0, 0.00000E+0, 0.00000E+0, 0.00000E+0,0
10, 11,'1 ', 7.37500E-3, 8.25000E-2, 0.02625, 0.00000E+0, 0.00000E+0, 0.00000E+0, 0.00000E+0, 0.00000E+0,0
0 / END OF ZERO SEQ. NON-TRANSFORMER BRANCH DATA, BEGIN ZERO SEQ. MUTUAL DATA
0 / END OF ZERO SEQ. MUTUAL DATA, BEGIN ZERO SEQ. TRANSFORMER DATA
1, 5, 0,'1 ',1,1, 4, 0.00000E+0, 0.00000E+0, 0.00000E+0, 1.66000E-2, 0.00000E+0, 0.00000E+0, 0.00000E+0, 1.66000E-2, 0.00000E+0, 0.00000E+0
2, 6, 0,'1 ',1,1, 4, 0.00000E+0, 0.00000E+0, 0.00000E+0, 1.66000E-2, 0.00000E+0, 0.00000E+0, 0.00000E+0, 1.66000E-2, 0.00000E+0, 0.00000E+0
3, 11, 0,'1 ',1,1, 4, 0.00000E+0, 0.00000E+0, 0.00000E+0, 1.66000E-2, 0.00000E+0, 0.00000E+0, 0.00000E+0, 1.66000E-2, 0.00000E+0, 0.00000E+0
4, 10, 0,'1 ',1,1, 4, 0.00000E+0, 0.00000E+0, 0.00000E+0, 1.66000E-2, 0.00000E+0, 0.00000E+0, 0.00000E+0, 1.66000E-2, 0.00000E+0, 0.00000E+0
0 / END OF ZERO SEQ. TRANSFORMER DATA, BEGIN ZERO SEQ. SWITCHED SHUNT DATA
0 / END OF ZERO SEQ. SWITCHED SHUNT DATA, BEGIN ZERO SEQ. FIXED SHUNT DATA
0 / END OF ZERO SEQ. FIXED SHUNT DATA, BEGIN INDUCTION MACHINE DATA
0 / END OF INDUCTION MACHINE DATA
PSS®E Training 30
Processing Activities Continue…
Setup Network for Unbalance Solution
(Activity SEQD)
Fault > Setup network for unbalanced solution (SEQD)…
PSS®E Training 31
Processing Activities Continue…
If sequence data has not been read into the working case
by running activity RESQ, an appropriate error message is
printed and activity SEQD ends.
PSS®E Training 32
Processing Activities Continue…
Solve Network with unbalances (Activity
SCMU)
Fault > Solve and report network with unbalances (SCMU/SCOP)…
PSS®E Training 34
Processing Activities Continue…
Unbalance network tabular output
(Activity SCOP)
Fault > Unbalanced network tabular output (SCOP)…
PSS®E Training 35
Processing Activities Continue…
PSS®E Training 36
Processing Activities Continue…
Calculating Automatic Sequence Fault
(Activity ASCC)
Fault > Automatic sequence fault calculation (ASCC)…
PSS®E Training 37
Processing Activities Continue…
If a 1 is entered for the first data item (1 FOR L - G), both a three
phase fault and a phase A to ground fault are applied at each fault
location. Otherwise, only three phase faults are applied.
If a 1 is entered for the second data item (1 FOR LINE OUT), the
applied fault calculations are repeated at each home bus ‘n’
additional times: once with each of its ‘n’ connected branches
placed out-of-service.
If a 1 is entered for the third data item (1 FOR LINE END), the applied
fault calculations are repeated for each home bus at least ‘n’
additional times: once (twice for any three-winding transformer that
has all its windings in-service) with each of its ‘n’ connected
branches opened at the far end, with the fault located at the line
end position.
If a response of one is entered for the final data item (1 FOR FLAT
CONDITIONS), classical fault analysis conditions are assumed for the
network in the working case.
PSS®E Training 38
Processing Activities Continue…
If the flat conditions option is not enabled, the level of network
modeling and the bus boundary conditions used by activity ASCC as
the pre-fault network condition are as specified in the working case
at the time activity ASCC is run.
PSS®E Training 39
Processing Activities Continue…
At the time of it ask ENTER FILENAME in the process, you can press
ENTER key without entering file name.
Activity ASCC is can run without suffix or with suffix, it is user define.
Click [ … ] to open the selection window for a Fault Control Data file
(*.fcd). A Relay Output Data file (*.rel) and a Short Circuit Output file
(*.sc) may be specified to save the model data. Click [Go] to perform
the activity
PSS®E Training 40
Processing Activities Continue…
SQLI is used to list data from the working case for selected buses or
all buses. It will contain all data including sequence parameters for
bus, branch, and generator etc. data.
PSS®E Training 41
Processing Activities Continue…
List Data
PSS®E Training 42
Processing Activities Continue…
The separate pole circuit breaker activity SPCB calculates the positive
sequence pi-equivalent corresponding to a single transmission line
unbalance. This equivalent may subsequently be used in dynamic
simulations to model the branch unbalance.
Prior to entering activity SPCB, the PSSE working case and the SEQD
temporary file must be set up in the form required by activity SPCB.
The procedure is as follows:
• Solve the working case in the pre-unbalance condition.
• Place the transmission line that is to be subjected to the
unbalance, out-of-service by running activity CHNG.
• Ensure that the fault analysis modeling option setting is
placed in the normal three phase mode.
• Apply activity SEQD.
• Then apply activity SPCB.
PSS®E Training 43
Processing Activities Continue…
PSS®E Training 45
Procedure to Perform Fault Analysis
Step 1. Upload .SAV or .RAW file, and perform load flow.
Step 2. Upload .SEQ file
Step 3. Perform SEQD activity; it will set the data for unbalance study.
Step 4. Perform the SCMU activity; activity SCMU allows the user to
apply one or more faults; SCMU has option to select the above
step in the SCMU window, so that above step can be eliminated.
MiscChange Program Setting (OPTN)
Step 5. After performing the SCMU activity the output will display on
the window which contains, thevenin’s sequence impedances at
faulted bus, voltages in PU and branch currents which are
connected to the faulted bus in PU, sum of contribution of the
these branch currents and shunt + load currents and fault current
in PU and positive sequence admittance. The values are in
rectangular format with Real and Imaginary.
PSS®E Training 46
Procedure Continue…
Step 9. One can change remove the shunt while performing the fault
analysis; it is done by the activity SQCH.
Step 10. FLAT,CL is the activity can be used when data for LF not
available completely, This will sets voltage to 1 PU and angles to
zero and loads to zero and transformer zero sequence
impedance to zero.
PSS®E Training 47
Results
PSS®E Training 48
Activity SCOP for display output
SCOP activity 1 of 5
PSS®E Training 49
SCOP activity 2 of 5
PSS®E Training 50
SCOP activity 3 of 5
PSS®E Training 51
SCOP activity 4 of 5
PSS®E Training 52
SCOP activity 5 of 5
PSS®E Training 53
Miscellaneous
Important Points
If the fault analysis is to be based on full power flow detail, the
working case should be solved by SCMU before SEQD is run. The
results calculated by SCMU for instant t+ will show both fault
current and load current that continues to flow in unfaulted parts of
the system.
PSS®E Training 54
Important Continue…
PSS®E Training 55
Important Continue…
The impedances specified for all unbalances may range from zero to
infinity; judicious choice of impedances and unbalances allows
SCMU to handle a wide variety of fault, unbalanced load, and other
abnormal system conditions.
PSS®E Training 56
Important Continue…
PSS®E Training 57
Important Continue…
PSS®E Training 58
Rules must be observed in applying unbalances
For L-L fault, ZG=999+j*999
Three phase fault --> L-G + L-L-G
L-G (or) L-L-G unbalance may be placed in transmission line. SCMU
automatically assign a dummy bus, number 99999, to the fault
location.
The line or branch, where a line-end or in line unbalance will be
applied, must be in service in the power flow case before SEQD is
run.
The single-phase and double-phase closed unbalances place new
unbalanced branches in parallel with those already present in the
power flow case in the working file. Setting up a case with one or
two phases of a system component opened (or closed) requires
that component be out-of-service in the power flow case before
execution of SEQD.
PSS®E Training 59
Rules Continue..
PSS®E Training 60
PSS®E Training 61