MONITORING FINAL ALLIGMENT KSB PUMP

Final alignment
Alligment Pipe
<0.05mm
No. Tag No. Equipment area Outstanding Pump Outstanding Pipe TIM FINAL Remarks
OK Date OK Date

1 011200PU002 WETMILL AREA OK 28-Oct-21 OK 28-Oct-21 KSB


2 011200PU003 WETMILL AREA OK 26-Oct-21 OK 26-Oct-21 KSB
3 011200PU004 WETMILL AREA OK 29-Oct-21 OK 29-Oct-21 KSB
4 011403PU001 WETMILL AREA OK 8-Nov-21 OK 8-Nov-21 PUTRANATA
5 011403PU002 WETMILL AREA REPAIR 8-Nov-21 Motor butuh turun +/- 6,24 mm (actual sudah tanpa shim) REPAIR 8-Nov-21 Repair line
6 011502PU002 WETMILL AREA OK 3-Nov-21 OK 3-Nov-21 PUTRANATA
7 011200PU005 WETMILL AREA OK 29-Oct-21 Mech seal bocor OK 29-Oct-21 KSB
8 011305PU001 WETMILL AREA REPAIR 8-Nov-21 Geser pump atau enlarge hole base plate REPAIR 4-Nov-21 Need Support On Process
9 011404PU001 WETMILL AREA
10 011404PU002 WETMILL AREA REPAIR 8-Nov-21 Repair line discharge
11 011503PU001A WETMILL AREA OK 4-Nov-21 OK 4-Nov-21 CARGILL
12 011503PU001B WETMILL AREA REPAIR 8-Nov-21 Butuh geser horizontal +/- 2,44 mm REPAIR 8-Nov-21 Repair line
13 061101PU001A WETMILL AREA
14 061101PU001B WETMILL AREA
15 011930PU001 WETMILL AREA OK 8-Nov-21 OK 8-Nov-21 CARGILL
16 011403PU003 WETMILL AREA
17 011403PU004 WETMILL AREA
18 011403PU005 WETMILL AREA
19 011403PU006 WETMILL AREA
20 011402PU002 WETMILL AREA OK 4-Nov-21 OK 4-Nov-21 PUTRANATA
21 011601PU001 WETMILL AREA Mech seal bocor
22 011501PU001 WETMILL AREA
23 011502PU001 WETMILL AREA OK 3-Nov-21 OK 3-Nov-21 PUTRANATA
24 011603PU001 WETMILL AREA OK 26-Oct-21 OK 26-Oct-21 KSB
25 011602PU001 WETMILL AREA OK 26-Oct-21 OK 26-Oct-21 KSB
26 011301PU001 WETMILL AREA OK 6-Nov-21 OK 6-Nov-21 KSB
27 011401PU001 WETMILL AREA OK 6-Nov-21 OK 6-Nov-21 KSB
28 011402PU001 WETMILL AREA OK 8-Nov-21 OK 8-Nov-21 KSB
29 011601PU002 WETMILL AREA OK 8-Nov-21 OK 8-Nov-21 CARGILL
30 011602PU014 WETMILL AREA
31 011946PU001 WETMILL AREA
32 011602PU002 WETMILL AREA
33 011602PU003 WETMILL AREA
34 011602PU004 WETMILL AREA
35 011602PU005 WETMILL AREA
36 011602PU006 WETMILL AREA
37 011200PU001 STEEP AREA OK 4-Nov-21 Mech seal bocor OK 4-Nov-21 KSB
38 011202PU011 STEEP AREA OK 4-Nov-21 OK 4-Nov-21 CARGILL
39 011202PU001 STEEP AREA OK 4-Nov-21 OK 4-Nov-21 CARGILL
40 011202PU002 STEEP AREA OK 5-Nov-21 OK 5-Nov-21 KSB
41 011202PU003 STEEP AREA OK 4-Nov-21 OK 4-Nov-21 KSB
42 011202PU004 STEEP AREA OK 4-Nov-21 OK 4-Nov-21 KSB
43 011202PU005 STEEP AREA OK 4-Nov-21 OK 4-Nov-21 KSB
44 011202PU006 STEEP AREA OK 8-Nov-21 OK 8-Nov-21 KSB
45 011202PU007 STEEP AREA OK 28-Oct-21 OK 28-Oct-21 KSB
46 011202PU008 STEEP AREA OK 28-Oct-21 OK 28-Oct-21 KSB
47 011202PU009 STEEP AREA OK OK KSB
48 011602PU007 WETMILL AREA
49 011602PU008 WETMILL AREA
50 011602PU009 WETMILL AREA
51 011602PU010 WETMILL AREA
52 011602PU011 WETMILL AREA
53 011602PU012 WETMILL AREA
54 011602PU013 WETMILL AREA
55 011942PU001 CHEMICAL AREA OK OK KSB
56 011942PU003 CHEMICAL AREA OK 28-Oct-21 OK 28-Oct-21 KSB
57 011941PU002 CHEMICAL AREA OK 27-Oct-21 OK 27-Oct-21 KSB
58 011942PU002 CHEMICAL AREA OK OK KSB
59 011941PU001 CHEMICAL AREA No Need Alignment
60 011941PU003 CHEMICAL AREA OK OK KSB
61 011942PU004 CHEMICAL AREA OK OK KSB
62 901302PU003 CSL EVAPORATOR
63 011702PU013 CSL EVAPORATOR
64 901302PU002 CSL EVAPORATOR
65 011702PU011 CSL EVAPORATOR
66 011702PU010 CSL EVAPORATOR
67 011202PU010 STEEP AREA OK OK KSB
68 011202PU012 STEEP AREA OK 5-Nov-21 OK 5-Nov-21 PUTRANATA
69 011204PU001 STEEP AREA REPAIR 6-Nov-21 Cut reweld, repair, realligemnt pipe
70 011202PU013 STEEP AREA OK 29-Oct-21 OK 29-Oct-21 KSB
71 921201PU002A WTP AREA OK OK CARGILL
72 921201PU002B WTP AREA OK OK KSB
73 961101PU001 COOLING TOWER AREA OK 6-Nov-21 OK 6-Nov-21 KSB
74 961101PU002 COOLING TOWER AREA OK 6-Nov-21 OK 6-Nov-21 KSB
75 961101PU003 COOLING TOWER AREA OK 4-Nov-21 OK 4-Nov-21 KSB
76 011704PU003 CO-PRODUCT DRYER OK 6-Nov-21 OK 6-Nov-21 CARGILL
77 011102PU001 CORN INTAKE AREA OK OK KSB
78 011102PU002 CORN INTAKE AREA OK OK KSB
79 901302PU001 STARCH DRYER AREA
80 081101PU001 STARCH DRYER AREA
81 081101PU003 STARCH DRYER AREA
82 081101PU007 STARCH DRYER AREA
83 081101PU008 STARCH DRYER AREA OK 6-Nov-21 OK 6-Nov-21 CARGILL
84 081101PU004 STARCH DRYER AREA
85 081101PU005 STARCH DRYER AREA
86 081101PU006 STARCH DRYER AREA
87 921200PU004 UTILITY AREA OK OK KSB
88 961103PU001A UTILITY BUILDING 1
89 961103PU001B UTILITY BUILDING 1
90 921201PU005 WIPRO OK OK KSB
TOTAL PROGRESS FINALL ALLIGMENT ACC 47 47

REMAINING PUMP 43
REPAIR PUMP ALIGNMENT 3
REPAIR PIPING ALLIGMENT 5
TOTAL PROGRESS FINAL ALIGNMENT KSB PUMP 52%
Update: 08 November 2021

CARGILL 9%
KSB 37%
PUTRANATA 6%