You are on page 1of 1

DMCI PROJECT DEVELOPERS, INC. FORM NO.

:
PLUMBING AND SANITARY SYSTEM QC-MEPF-015A-DU
(PRIOR TO TOG/QMD/UNIT OWNER ACCEPTANCE)
Project : Ref. No. :
Building : Time of Request :
Unit/Level : Date of Request :
Location :
Subcontractor :

Functionality Test for Plumbing Fixture


A. LDK Description YES NO N/A Remarks
1. Kitchen sink Single Filled to overflow. Faucet's handle must not rotate as you
with Side Drain Board turn the faucet to avoid connection in the future. Check Specification Drain Time
if there is a drain cap.
47 - 60 sec.
Check piping if acceptable. Inlet pipe is lower than outlet pipe. Baffle plate must be not
2. Grease Trap
perforated. Check if grease trap has cover with locks.
3. Flexible hose Must be "Fanski Brand". Must be fixed properly. Check if there are leak at joits.
4. Balcony drain 1 Pour 2 pails of water (16L/pail)
5. Balcony drain 2 Pour 2 pails of water (16L/pail)
6. FCU/ACU Stubout 1 Pour 1 bottle of water (1.5L/btl) using funnel with clear hose (1/4"-3/8" dia)
7. Washing Machine Drain Remove cap, use funnel suitable for drain pipe's size and pour 2 pails of water (16L/pail).
Return the cap properly.
8. Others
B. Toilet and Bath 1
Specification Drain Time
1. Watercloset Flush with 5 set of 14-cut length of toilet tissue paper (double-ply).
7 - 15 sec.
2. Flexible hose Must be "Fanski Brand". Must be fixed properly. Check if there are leak at joints.
Check if pop-up drain is working. Filled to overflow. Faucet's handle must not rotate as Specification Drain Time
3. Lavatory
you turn the faucet to avoid loose connection in the future 47 - 60 sec.
4. Flexible hose Must be "Fanski Brand". Must be fixed properly. Check if there are leak at joits.
5. Shower head Check functionality of shower Valve, Faucet and Shower head. All shower head holes
6. Shower faucet should have continuous flow of water
7. Shower drain Pour 2 pails of water (16L/pail)
8. Floor drain Pour 2 pails of water (16L/pail)
9. Washing Machine Drain Remove cap, use funnel suitable for drain pipe's size and pour 2 pails of water (16L/pail).
Return the cap properly.
Check hand holes if P-traps above (Shower Drain, Floor Drain and Washing Machine
10. P-Traps Above Ceiling Drain) are accessible. Double check if debris inside P-traps were removed. P-trap caps
must be properly returned.
a. Flow Test of Pour 2 pails of water each for Shower drain, Floor Drain, Floor Clean-out and Washing
T&B Above Machine drain above the unit you are dressing.
Ensure that the gully trap is free from any solid waste, and free from excess application of
11. Gully trap waterproofing. Check inside the gully trap if the baffle is inserted properly. Rubber seal in
the baffle must be attached and fitted properly.
Pour 2 pails of water (16L/pail).
a. Flow Test of T&B above
b. Accessories Install complete accessories: odor trap, gasket, strainer, floor drain

12. Others
C. Toilet and Bath 2
Check hand holes if P-traps above (Shower Drain, Floor Drain and Washing Machine
10. P-Traps Above Ceiling Drain) are accessible. Double check if debris inside P-traps were removed. P-trap caps
must be properly returned.
a. Flow Test of Pour 2 pails of water each for Shower drain, Floor Drain, Floor Clean-out and Washing
T&B Above Machine drain above the unit you are dressing.
Ensure that the gully trap is free from any solid waste, and free from excess application of
11. Gully Ttrap waterproofing. Check inside the gully trap if the baffle is inserted properly. Rubber seal in
the baffle must be attached and fitted properly.
Pour 2 pails of water (16L/pail)
a. Flow Test of T&B above
b. Accessories Install complete accessories: odor trap, gasket, strainer, floor drain

12. Others
D. Bedroom 1
1. Balcony drain 1 Pour 2 pails of water (16L/pail)
2. Balcony drain 2 Pour 2 pails of water (16L/pail)
3. FCU/ACU Stubout 1 Pour 1 bottle of water (1.5L/btl) using funnel with clear hose (1/4"-3/8" dia)
4. FCU/ACU Stubout 2 Pour 1 bottle of water (1.5L/btl) using funnel with clear hose (1/4"-3/8" dia)
5. Others
E. Bedroom 2
1. Balcony drain 1 Pour 2 pails of water (16L/pail)
2. Balcony drain 2 Pour 2 pails of water (16L/pail)
3. FCU/ACU Stubout 1 Pour 1 bottle of water (1.5L/btl) using funnel with clear hose (1/4"-3/8" dia)
4. FCU/ACU Stubout 2 Pour 1 bottle of water (1.5L/btl) using funnel with clear hose (1/4"-3/8" dia)
5. Others
Serial No.: Check if water meter is functioning correctly. Check all
F. Water Meter Initial Reading : joints/connections if there are traces of leaks. Check if
the water meter cover is intact.
G. Gate Valve Check if gate valve is passing. Open the faucet & close the gate valve, if water is still
flowing the gate valve is defective.

Observations and Comments:

Conducted by: Witnessed and Attested by: Noted by:

ALPA Representative DMCI - TOG DMCI MEPF T&C

DMCI MEPF Coordinator DMCI - QMD

NOTE: Signature Over Printed Name is Required