DURATION
WBS No. TASK DESCRIPTION START FINISH
(Days)
Site Works
Chalk Stone 1 box
Laminated Sack Blue 1 roll
Steel Works
Chemical Anchor Fischer 10 tubes
16mm∅x150mm Weldable bolt 56 set
Welding rod 6011 40 kg
Welding rod 6013 10 kg
Welding rod 7018 20 kg
Cutting disc 4'' 12 pcs
Extension wire 40m 1 pc
Grinder 1 pc
Fire Extinguisher 2 set For Safety Precautions
Water Drum 1 pc For Safety Precautions
Water Hose 5 meter For Safety Precautions
Temporary Water Meter 1 set For Safety Precautions
Level Hose 1/2'' 10 meter
H-Frame 1/4'' x 6m 3kg 12 pcs
6sets
Cross Brace 24 pcs
16mm DRB 6 pcs Exbrace for Framing
G.I pipe 1 1/2'' 30 pcs support for scaffold
Daiden Welding Machine 3 pcs delivered on site
Bosch Grinder 2 pcs delivered on site
Bosch Cut-off Machine 1 pc delivered on site
Sika Grout 212 2 bags
Oxygen tank 2 pcs
3''x6'' C-Channel 3 pcs For column extension
16mm thk MS plate 3 pcs For existing columns
TOTAL 17480
COLUMNS
MATERIALS Quantity Unit Unit price Amount
3"x6" C-Channel 18 pcs. 5680 102240
MS PLATE 250x250 14 pcs 734 10276
MS PLATE (Additional) 3 pcs 490 1470
TOTAL 113986
STEEL GIRT
MATERIALS Quantity Unit Unit price Amount
Angle Bar 75mm x 6mm x 6m 1 pc 2180 2180
GI pipes 1 1/2 x .45m 597 pcs. 52.8 31521.6
GI pipes 1 1/2 x 6m 44 pcs. 704 30976
TOTAL 64677.6
STEEL RAFTER
MATERIALS Quantity Unit Unit price Amount
GI pipes 1 1/2 x .35m 1197 pcs. 41.06 49148.82
GI pipes 1 1/2 x .6m 78 pcs. 704 54912
TOTAL 104060.8
PURLINS
MATERIALS Quantity Unit Unit price Amount
C-Purlins GI 2x4x2mm 152 pcs 1340 203680
TOTAL 203680
CLEATS
MATERIALS Quantity Unit Unit price Amount
Angle Bar 1 1/2 x 1 1/2 x 3/16 8 pcs 685 5480
TOTAL 5480
SAG RODS
MATERIALS Quantity Unit Unit price Amount
Plain Round Bar 10mm x 6m 33 pcs 185 6105
TOTAL 6105
CROSS BRACING
MATERIALS Quantity Unit Unit price Amount
Plain Round Bar 16mm x 6m 6 pcs 540 3240
Turnbuckle 16mm 6 pcs 180 1080
TOTAL 4320
TOTAL 6600
PRIMERING (Welded Joints)
MATERIALS Quantity Unit Unit price Amount
Primer Red Oxide 2 gal 408 816
Paint Brush #2 2 pcs 27 54
TOTAL 870
OTHER CONSUMABLES
MATERIALS Quantity Unit Unit price Amount
Oxygen Tank Refill 4 tank 450 1800
Chalk Stone 1 box 720 720
Welding Rod 6011 4 box 2580 10320
Welding Rod 6013 2 box 2200 4400
Laminated Sack 1 roll 3980 3980
Cutting Disc 50 pcs 55 2750
TOTAL 23970
ACCOMPLISHMENT REPORT AS OF: 13-Oct-21
ITEM SCOPE OF WORKS COST WEIGHT ACCOMPLISHED
1 ANCHORAGES 17480 3.17% 3.17%
2 COLUMNS 113986 20.68% 20.68%
3 STEEL GIRT 64677.6 11.73% 11.73%
4 STEEL RAFTER 104060.8 18.88% 15.97%
5 PURLINS 203680 36.95% 8.24%
6 CLEATS 5480 0.99% 0.25%
7 SAG RODS 6105 1.11% 0.00%
8 CROSS BRACING 4320 0.78% 0.00%
9 Fascia and End Flashing FRAMING 6600 1.20% 0.00%
10 PRIMERING (Welded Joints) 870 0.16% 0.14%
11 OTHER CONSUMABLES 23970 4.35% 4.35%