Professional Documents
Culture Documents
The SMM directs that certain activities on which a contractor incurs money shall not be measured. The
contractor has to allow costs for carrying out these activities in the rates of the measured items.
The costs the contractor incurs on those activities not measured as per SMM are assumed to or “deemed”
as it were allowed for in the rates quoted. Claims for extra in regard to these items can’t succeed.
Examples;
Extra over
For speed or convenience of measurement, SMM directs that overall dimensions or quantity be given with
the general description. Within this general item there could be extra cost component not specifically
mentioned. SMM directs that such cost component be given as extra over.
Examples;
Day works
This a method of payment by the reimbursement to the contractor of the prime cost of all materials,
labour and plant used in carrying out work, with a percentage addition to the total cost of each of these
groups for overheads and profit.
Day works is a reliable formula in case of unsatisfactory data is available for carrying out measurement
e.g. pot holes or a repairing a structural crack.
Post contract, the consultant may instruct in writing that any additional or substituted work to be
executed on a day work basis. Therefore pre contract it is necessary to include a day work section for
materials, labour and plant in the bills of quantities.
A prime cost sum is allowed for materials, labour and plant and an allowance for profits and over heads
is made on each of these as below.
DAYWORK SECTION
General
Labour
A percentage of over heads and profit can be obtained from tenderers which renders the
tendering process competitive. It forms part of the tender sum.
In order to avoid negotiations with the contractor at a later date post contract.
Proprietary systems
For example a ceiling system or fire alarm system. An item may not be fully detailed but reference made
to the manufacturer’s catalogue in the BQs. Specify brand or equal and approved.
A system developed by the manufacturer and incudes patent rights. A manufacturer has patent rights
over the system.
Contingency sum
Sum allowed in the bills of quantities to meet costs of undefined work which cannot be foreseen pre
contract and which may not arise at all.
Serves to reduce the total cost of any extra or more expensive work than originally envisaged.