Professional Documents
Culture Documents
Activity ID Activity Name Original Planned Start Planned Finish 2020 2021
Duration ust September October November December January February March
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 01 08 15
145d 01-Sep-20 23-Jan-21
Drone Delivery
Delive Integration Project
Initiation 7d 01-Sep-20 07-Sep-20
A1000 Develop project charter 2d 01-Sep-20 02-Sep-20 Develop project charter
A1010 Develop project scope 3d 03-Sep-20 05-Sep-20 Develop project scope
A1020 Develop stakeholder register 3d 03-Sep-20 05-Sep-20 Develop stakeholder register
A1030 Approvals (Internal & External) 1d 06-Sep-20 06-Sep-20 Approvals (Internal & External)
A1040 Project kickoff: Contract Signatures 1d 07-Sep-20 07-Sep-20 Project kickoff: Contract Signatures
Planning 23d 08-Sep-20 30-Sep-20
A1050 Project Management 3d 08-Sep-20 10-Sep-20 Project Management
A1060 Plan Budget & Schedule 3d 08-Sep-20 10-Sep-20 Plan Budget & Schedule
A1070 Communication Management Plan 3d 08-Sep-20 10-Sep-20 Communication Management Plan
A1080 Risk Management Plan 3d 08-Sep-20 10-Sep-20 Risk Management Plan
A1090 App design 4d 11-Sep-20 14-Sep-20 App design
A1100 Coding 4d 15-Sep-20 18-Sep-20 Coding
A1110 Design approvals 2d 19-Sep-20 20-Sep-20 Design approvals
A1120 Drone design 4d 21-Sep-20 24-Sep-20 Drone design
A1130 Purchase Materials 2d 25-Sep-20 26-Sep-20 Purchase Materials
A1140 Manufacture Pilot Drone 4d 27-Sep-20 30-Sep-20 Manufacture Pilot Drone
Execution/Integration
Execution/In 30d 01-Oct-20 30-Oct-20
A1150 App development & testing 10d 01-Oct-20 10-Oct-20 App development & testing
A1160 Integration of WIlmont & Dronetech S 7d 11-Oct-20 17-Oct-20 Integration of WIlmont & Dronetech Systems
A1170 IT Support 7d 11-Oct-20 17-Oct-20 IT Support
A1180 software updates 4d 18-Oct-20 21-Oct-20 software updates
A1190 security updates 4d 18-Oct-20 21-Oct-20 security updates
A1200 Encrypt Data 2d 22-Oct-20 23-Oct-20 Encrypt Data
A1210 Drone Flight Test 2d 24-Oct-20 25-Oct-20 Drone Flight Test
A1220 Drone Maintenance/ Testing 5d 24-Oct-20 28-Oct-20 Drone Maintenance/ Testing
A1230 Delivery Drones to 4 Pharmacies 2d 29-Oct-20 30-Oct-20 Delivery Drones to 4 Pharmacies
Management & Control
Managemen 45d 31-Oct-20 14-Dec-20
A1240 Training 7d 31-Oct-20 06-Nov-20 Training
A1250 App Training 5d 07-Nov-20 11-Nov-20 App Training
A1260 Drone Training 5d 12-Nov-20 16-Nov-20 Drone Training
A1270 Troubleshoot Training 2d 17-Nov-20 18-Nov-20 Troubleshoot Training
A1280 Access Control 7d 19-Nov-20 25-Nov-20 Access Control
A1290 Access to Consumer Data 7d 26-Nov-20 02-Dec-20 Access to Consumer Data
A1300 User manual & design documents 7d 03-Dec-20 09-Dec-20 User manual & design documents
A1310 Warranty information 5d 10-Dec-20 14-Dec-20 Warranty information
Closeout 40d 15-Dec-20 23-Jan-21
A1320 Closing Reports 14d 15-Dec-20 28-Dec-20 Closing Reports
A1330 Safeguard and Store Data 10d 29-Dec-20 07-Jan-21 Safeguard and Store Data
A1340 Audit Performance 7d 08-Jan-21 14-Jan-21 Audit Performance
A1350 Monitor Progress 9d 15-Jan-21 23-Jan-21 Monitor Progress
Actual Work Critical Remaining Work Page 1 of 1 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation