FLOW CHART- INSTALLATION OF ESE LA ARRESTER

Start

Land grading and cleaning of area where LA arrester


foundation to be done

Marking as per approved coordinates

Excavate the LA Foundation as per approved drawing


measurments

Barbinding as per approved drawing

Install anchor bolt as per drawing

Inspection
NO

YES

Cast the LA foundation with Approved grade of concrete as

Visual Inspection of ESE Lighting NO Rework/Repair/Return to vendor


arresters recevied at site

YES

Shift the LA Arresters near location to be installed

Assemble the LA Arrester as per drawing

Erect the LA Arrester on to the foundation and tighten the


anchor bolts as per approved drawing

Connect the LA Arrester to earth flat to earth pits as per


approved drawing

Inspection

END