2 Module Box unpacking Medium Risk Module Box may topple JCB speed should be less than 5 km.
cut injury Use of Job specific PPE(cut free Gloves)
Use Proper tool for unpacking,Do unpacking work
Module may damage Availblity of spare material
carefully by cutting straping without hurting module
3 Module erection & alignment Medium Risk Use of Job specific PPE(cut free Gloves,shoulder pad) Physical injuiry First aid availblity
cut injury Module should be handled by two person.
Module should be placed by two person by taking care of
Module tedlar sheet may damage
the sharp edges of MMS parts
If module placing and fixing height is more than 1.8
meters then appropriate stool/stand should be used.
5 Housekeeping Medium Risk Use of Job specific PPE(cut free Gloves) Physical injuiry First aid availblity
Physical injury injury ensure TBT of workers
Ensure the non availability of insects, Scorpion & Snake
Scorpion stings & snake bites Scorpion stings & snake bites Availblity of snake venum antidot
bites.
Ensure Good weather condition
Ensure Proper Illumination