TRANSMITTAL

Ain Tsila Development Project

TR-CERI-PIUL-0051 DATE: 21/11/2021

FROM TO
sdc.2045@petrofac.com
Mr dcc.aintsila@ceri.com.tn Mrs

Subcontractor: CERI Contractor Petrofac


Copy to
Gireesh Hegde, Edwin Gabriel, Baiju Salim, Subrahmanya Kolachina

Please find the following documents:

Item Qty Title / Designation REFERENCE Rev Remarks

MONITORING AND
B
1 1
MEASURING EQUIPMENT A-QAC-PRO-730-38944
CONTROL PROCEDURE

Ces documents sont transmis pour/Thesedocuments are transmitted for :

Review and approval

Ces documentssonttransmis par/These documentsaretransmittedby : E-mail


STATUS:
Support:
P : Hard Copy
E :E-Mail
CD : CD-Rom