PETROFAC INTERNATIONAL (UAE) LLC.

SUB CONTRACTOR DOCUMENT TRANSMITTAL

TO:
CERI DATE: 13/Nov/2021 JOB. JI-2045
TUNIS
CHARQUIA PROJECT: JI-2045-Ain Tsila Development
Z. I
www.CERITUNISIE.com
Tunisia

Attn:

TRANSMITTAL NO.TR-PIUL-CERI-0036

TRANSMITTING OF : MONITORING AND MEASURING EQUIPMENT CONTROL PROCEDURE ETC...

SL
NO DOCUMENT NO. REV. DOCUMENT TITLE CODE
.
0
1 A-QAC-PLN-000-30000 PROJECT QUALITY PLAN

0 MATERIAL CONTROL AND TRACEABILITY


2 A-QAC-PRO-000-30000
PROCEDURE

0 MONITORING AND MEASURING EQUIPMENT


3 A-QAC-PRO-000-30001
CONTROL PROCEDURE

0
4 A-QAC-PRO-000-30003 RECEIVING INSPECTION PROCEDURE

0
5 A-QAC-PRO-000-30004 QUALITY RECORD CONTROL PROCEDURE

QUALIFICATION AND CERTIFICATION OF


0
6 A-QAC-PRO-000-30005 MEASURING AND MONITORING PERSONNEL AT
THE AIN TSILA SITE

0 WELDING PROCEDURE QUALIFICATION


7 A-QAC-PRO-000-30006
PROCEDURE

0
8 A-QAC-PRO-000-30007 WELDER QUALIFICATION PROCEDURE

0
9 A-QAC-PRO-000-30008 QUALITY AUDIT PROCEDURE

0
10 A-QAC-PRO-000-30009 NONCONFORMING ITEM CONTROL PROCEDURE

0 CORRECTIVE AND PREVENTIVE ACTION


11 A-QAC-PRO-000-30010
PROCEDURE

0 POSITIVE MATERIAL IDENTIFICATION (PMI)


12 A-QAC-PRO-000-30011
PROCEDURE
1
13 A-QAC-PRO-000-30012 QUALITY REQUIREMENT FOR SUBCONTRACTORS

0
14 A-QAC-PRO-000-30013 INSPECTION AND TEST CONTROL PROCEDURE

LEGEND FOR CODE


1 - Accepted without comments
2 - Accepted with comments.
3 - Not Accepted. Revise and resubmit.
4 - For Information.
5 - Void-Cancelled / Superseded.

REMARKS

ISSUE REASON: IFU

Transmitted By

Chawki Bou Khalil


Construction Director
Received by:
Please acknowledge receipt by signing and returning (Signature)
a copy of this transmittal to
Petrofac, PO Box. 23467, Sharjah, UAE.
Name:
Tel.: +971-6-5740999, Fax: +971-6-5740099
Date:
Attention : Document Controller ( JI-2045)