KINGDOM OF SAUDI ARABIA POWER AND WATER UTILITY COMPANY FOR JUBAIL AND YANBU (MARAFIQ)

NEW PUMP STATION PS-56A AND FORCE-MAIN TO SWTP-9, JUBAIL


AL-JUBAIL, SAUDI ARABIA

NEW PUMP STATION PS-56A AND FORCE-MAIN TO SWTP-9, Contract No.: Date:
JUBAIL 7200039700 December 23, 2019
INSPECTION & TEST PLAN (ITP) ROTATING EQUIPMENT H = Mandatory HOLD Point: Representative of indicated party W = Witness Point: Representative of indicated party to be notified 24 hours in advance by Inspection
must be in attendance. 24 hour advance notification by Inspection Request. If Client not in attendance 2.0 hours beyond specified time, inspection & work may proceed.
INSTALLATION Request is required. Work shall not proceed without approval.
Inspection & Test Plan: RA = Review & Approval. Representative of indicated party to S = Surveillance: Unscheduled inspection or monitoring of work. No Inspection Request notification is
MACO-ITPM-039700-006 REV. No. 00 MECHANICAL review submitted documents, results of test, etc. required.

Activity Controlling
THIRD
Stage / Activity Procedure/Spec/ Reference Document Acceptance Criteria MACO MARAFIQ ILF-PMC QA/QC Inspection Checklist/Forms
No.: Drawing
PARTY

ROTATING EQUIPMENT INSTALLATION


1.0 Document review
1.1 Review and approval of Material (Pumps) DIVISION 33 – Utilities RA RA RA MAC-CIF-008/015, Third party lab test
Section -330593, Para. DIVISION 33 – Utilities Section -330593, certificate to be attached.
1.05 – 1.08 and Project Drawings and Vendor Manual Para. 1.05 – 1.08 and Project specification
specification and IFC and IFC Drawing
Drawing
2.0 Material Receiving
2.1 Equipment Verification and Visual Inspection of DIVISION 33 – Utilities H W W MAC-CIF-QC-015, Third party lab test
Pumps Section -330593, Par. certificate to be attached & test as per
1.09 & 2.0 and Project Material Packing lists project spec.
specification and IFC
Drawing
2.2 Equipment Handling, Storage & Preservation DIVISION 33 – Utilities H W W MAC-CIF-008, Third party lab test
Section -330593, Par. SECTIONS 01 65 00 and certificate to be attached & test as per
1.09 and Project 01 66 00 project spec/. MAC-CIF-025
specification and IFC
Drawing
2.3 Verification, Visual inspection and DIVISION 31 – Visual Inspection Project Specification & of RC Division 31 Visual Inspection
storage/Preservation of Electrical and Earthwork SECTION Section -312300 Par. 3.02
instrumentation components 312300 and project
specification
3.0 Installation
3.1 Concrete Foundation Installation DIVISION 31 – Survey Report, 3rd party RC DIVISION 31 – Section -312300 Par. MAC-CIF-010, 3rd party issued
Earthwork SECTION issued calibration cert. 1.07-A.3 - project specification and IFC calibration certificate.
312300 and project drawings, QCP&M.S.
specification and IFC
drawings
3.2 Verification of Equip Support Structure or Foundation DIVISION 31 – Survey Report and RC Division 31- Section -312300 Par. 3.03, H W W MAC-CIF-010 / 001
(Pre-Installation) Earthwork SECTION Compaction Test Report 3.04 & 3.05 / Meet Drawing/ Method
312300 and project statement / 3rd party test report,
specification and IFC QCP/M.S. Project specs.
drawings
3.3 Mounting Plate ( Base plate and Soleplate) H W W
Installation and Leveling

3.4 Grouting of Machinery Support

Page 1 of 2
KINGDOM OF SAUDI ARABIA POWER AND WATER UTILITY COMPANY FOR JUBAIL AND YANBU (MARAFIQ)
NEW PUMP STATION PS-56A AND FORCE-MAIN TO SWTP-9, JUBAIL
AL-JUBAIL, SAUDI ARABIA

NEW PUMP STATION PS-56A AND FORCE-MAIN TO SWTP-9, Contract No.: Date:
JUBAIL 7200039700 December 23, 2019
INSPECTION & TEST PLAN (ITP) ROTATING EQUIPMENT H = Mandatory HOLD Point: Representative of indicated party W = Witness Point: Representative of indicated party to be notified 24 hours in advance by Inspection
must be in attendance. 24 hour advance notification by Inspection Request. If Client not in attendance 2.0 hours beyond specified time, inspection & work may proceed.
INSTALLATION Request is required. Work shall not proceed without approval.
Inspection & Test Plan: RA = Review & Approval. Representative of indicated party to S = Surveillance: Unscheduled inspection or monitoring of work. No Inspection Request notification is
MACO-ITPM-039700-006 REV. No. 00 MECHANICAL review submitted documents, results of test, etc. required.

Activity Controlling
THIRD
Stage / Activity Procedure/Spec/ Reference Document Acceptance Criteria MACO MARAFIQ ILF-PMC QA/QC Inspection Checklist/Forms
No.: Drawing
PARTY

3.5 Inspection of Auxiliary Piping Installation H W W

3.6 Pump Suction & Discharge Piping Connection H W W

3.7 Flange Joint, gasket verification and bolt tightening H W W

3.8 Electric Motor (Driver) Installation

3.9 Skid Mounted Aux. Electrical System installation

3.10 Skid Mounted Aux. Instrumentation Systems


installation
4.0 Pre-commissioning
4.1 Final Pump/Driver Shaft/Coupling Alignment H W W

4.2 Instrumentation and Electrical Pre- Commissioning


prior MCC

4.3 Final Insp/walkthrough (by Contractor) H W W

4.4 Final Inspection for mechanical completion H


acceptance

H = Mandatory HOLD Point: Representative of indicated party W = Witness Point: Representative of indicated party to be notified 24 hours in advance by Inspection
INSPECTION & TEST PLAN (ITP) EXCAVATION & BACKFILL must be in attendance. 24 hour advance notification by Inspection Request. If Client not in attendance 2.0 hours beyond specified time, inspection & work may proceed.
Request is required. Work shall not proceed without approval.
Prepared by: Reviewed by: Approved by:
Name Tamer Bardesi Amado P. Togle
Signature
Designation MACO Civil QC MACO QA/QC Mgr. MARAFIQ/ILF

Page 2 of 2