START
used from list of ITR (ITR/MC index) CONSTRUCTION REGARDING CONSTRUCTION REGARDING
WORK COMPLETION PUNCHLIST CLOSEOUT /
2. Make sure to get the following information & fill in (MIM INTERNAL INSPECTION) RECTIFICATION WORK
the ITR format correctly :
- ITR serial number
- System number
- Sub-system number
- Equipment tag number / ID
All above information should be provided by TS
No WORK WORK No
3. If there is no matching / suitable ITR format
available, modify existing MC format to be used as
COMPLETE? COMPLETE?
ITR format
Yes Yes
PREPARE
ITR Form Preparation
Yes
Not in the
No EXISTING ITR/MC
ITR list CHECK WITH ITR /
1 FORMAT CAN BE
MC INDEX
MODIFIED ?
OK, avail. in
ITR index
Supporting Document Check /
Yes
2 DOCUMENT ISSUE?
No
PREPARE RFI
2
1. Check applicable supporting documents for inspection latest approval
status from document controller (DCC)
- IFC revision numbers (Rev. 0, 1, ..) with official approval signature from
Customer
- Construction drawing (detailed internal MIM drawing) – marked IFC sent
at least 1 (one) day before inspection to each party. INSPECTION
ITR SIGN-OFF /
CLOSEOUT
Finish
FINISH