REPAIR OF EXPOSED 30" PIPELINE AT RCB-TNF 565 & 563

CONTRACT No. 4600009769

WELDING CONTROL PROCEDURE

2 15 Feb 2015 HP Issued for Approval PS / BN AM / WS


1 14 Dec 2014 HP Issued for Approval PS / BN AM / WS
0 6 Nov 2014 HP Issued for Comment PS / BN AM / WS
CHECK APPR CTR CPY
REV DATE BY DESCRIPTION
APPROVAL APPR. APPR.

TOTAL OR PARTIAL REPRODUCTION AND / OR UTILIZATION OF THIS DOCUMENT


ARE FORBIDDEN WITHOUT PRIOR WRITTEN AUTHORIZATION ON THE OWNER
TOTAL E&P INDONESIE
REPAIR OF EXPOSED 30" PIPELINE
AT RCB-TNF 565 & 563

PT. ONASIS INDONESIA

Doc No: CLASS REVISION STATUS


9769-22-TNF-PWK-3-009-P 1 2 B
WELDING CONTROL PROCEDURE
9769-22-TNF-PWK-3-009-P
REV.2 REPAIR OF EXPOSED 30" PIPELINE
AT RCB - TNF 565 & 563 PAGE
Status : B 1 of 10
CONTRACT No. 4600009769

REVISION LIST
Revision Status Revision Status Revision Status
Page Page Page
0 1 2 3 4 5 6 0 1 2 3 4 5 6 0 1 2 3 4 5 6
0 X 42 84
1 X 43 85
2 X 44 86
3 X 45 87
4 X 46 88
5 X 47 89
6 X 48 90
7 X 49 91
8 X 50 92
9 X 51 93
10 X 52 94
11 53 95
12 54 96
13 55 97
14 56 98
15 57 99
16 58 100
17 59 101
18 60 102
19 61 103
20 62 104
21 63 105
22 64 106
23 65 107
24 66 108
25 67 109
26 68 110
27 69 111
28 70 112
29 71 113
30 72 114
31 73 115
32 74 116
33 75 117
34 76 118
35 77 119
36 78 120
37 79 121
38 80 122
39 81 123
40 82 124
41 83 125
WELDING CONTROL PROCEDURE
9769-22-TNF-PWK-3-009-P
REV.2 REPAIR OF EXPOSED 30" PIPELINE
AT RCB - TNF 565 & 563 PAGE
Status : B 2 of 10
CONTRACT No. 4600009769

CONTENTS
C1. TITLE PROCEDURE ....................................................................................................... 0
C2. REVISION LIST ............................................................................................................... 1
C3. CONTENTS ..................................................................................................................... 2
1. PURPOSE ................................................................................................................ 3
2. DEFINITIONS ............................................................................................................ 3
3. SCOPE ...................................................................................................................... 3
4. RESPONSIBILITIES .................................................................................................. 4
5 EQUIPMENT & TOOL ............................................................................................... 5
6. IMPLEMENTATION ................................................................................................... 6
6.1 WELDING PROCEDURE .................................................................................... 6
6.2 WELDER QUALIFICATION ................................................................................ 6
6.3 PRODUCTION WELDING ................................................................................... 7
6.4 WELDING INSPECTION ..................................................................................... 8
6.5 WELD REPAIR .................................................................................................... 9
7. EXAMINATION & TEST ............................................................................................ 10
8. RECORDS................................................................................................................. 10
9. REFERENCES .......................................................................................................... 10
WELDING CONTROL PROCEDURE
9769-22-TNF-PWK-3-009-P
REV.2 REPAIR OF EXPOSED 30" PIPELINE
AT RCB - TNF 565 & 563 PAGE
Status : B 3 of 10
CONTRACT No. 4600009769

1 PURPOSE
The Purpose of this Welding Control Procedure is to describe the Project
Requirement for control of welding procedure specifications, procedure qualification
testing, welder performance testing and welding control during production welding.

2 DEFINITIONS
PWPS : Preliminary Welding Procedure Specification
WPS : Welding Procedure Specification
PQR : Procedure Qualification Record
WPQ : Welder Performance Qualification
Design Code:
AWS D1.1, 2010 Edition Structural Welding Code Steel
ASME V Non destructive Examination
ITP (Inspection and Test Plan)
Document Number : 9769-22-TNF-PWK-3-009-P

3 SCOPE
This Welding Control Procedure is applicable to perform any welding operations on
structural steel and include welding procedure specification, welder and welding
procedure qualification testing and maintenance of all welder, production and
traceability records. Production welding of structural steel, inspection, testing and
welder data will be recorded of Repair of Exposed 30" Pipeline at RCB - TNF 565 &
563 .
WELDING CONTROL PROCEDURE
9769-22-TNF-PWK-3-009-P
REV.2 REPAIR OF EXPOSED 30" PIPELINE
AT RCB - TNF 565 & 563 PAGE
Status : B 4 of 10
CONTRACT No. 4600009769

4. RESPONSIBILITIES
4.1 Contractor
Contractor shall mean any person or company for the performance of any part of the
work.

4.2 Contractor responsible for implementing the contractors quality assurance /


quality control program that include 100% inspection of the work. Contractor QC
Personnel shall require to be approved by company (TEPI). Contractor (Onasis)
Inspection & Test Plan shall require to be submitted to TEPI for review and approval
before any work can commence. These ITP’s must be submitted by contractor to
Company for Review / comments before the specific construction discipline activities
begin. The Contractor will submit a request for inspection no later than 24 hours
before inspection of the activities its to take place.

4.3 Contractor (Onasis) shall follow All Requirement for Approved Welding Control
Procedure. Detail proposed Welding Procedure Specification shall be issued for
approval.

4.4 QA/QC and NDT personnel are required to be approved by TEPI before they
can commence working on the Project Repair Of Exposed 30" Pipeline At RCB -
TNF 565 & 563.

4.5 Contractor (Onasis) is to understand the engineering, procurement,


construction, commissioning, and overall project management, as well as the
rendering of assistance to start up, all in accordance with the terms and condition of
the contract.

4.6 Company (TEPI) Site QA/QC Department is responsible for the review and
acceptance of all required submittals of welder and welding data. Further, all
WELDING CONTROL PROCEDURE
9769-22-TNF-PWK-3-009-P
REV.2 REPAIR OF EXPOSED 30" PIPELINE
AT RCB - TNF 565 & 563 PAGE
Status : B 5 of 10
CONTRACT No. 4600009769

welding work and related documentation will be monitored and / or audited by


company (TEPI), authorities, and contractor quality control and quality assurance
personnel. Contractor (Onasis) will monitor and record welding data, the
performance of welders, weld repairs, welder qualification, in report of visual
inspection .

4.7 Contractor (Onasis) QC personnel approved by Company (TEPI) shall perform


full time surveillance of the work in progress, and shall issue request for inspection
to Company (TEPI) in accordance with the Witness and Hold points specified by
Company (TEPI) in the Approved Inspection and Test Plan.

4.8 Company (TEPI) will monitor the Quality Control / inspection of the work
performed by Contractor (Onasis). The QA/QC personnel will determine if the
inspection are being performed in a competent and satisfactory manner and that the
relevant documentation is being prepared and signed concurrent with the work and
is being maintained in retrievable.

5. EQUIPMENT & TOOL


 GTAW welding machine set (Complete with Automatic Gun).
 SMAW welding machine set
 Pencil grinder (Tungsten Carbide Mat erial)
 Grinder Machine
 Grinding Disk
 Steel Brush
 Hand Brush
 Baking Electrode
 Tang Ampere
 Inf ra Red Temperature Thermometer
 Free Chloride and Zinc Marke r
WELDING CONTROL PROCEDURE
9769-22-TNF-PWK-3-009-P
REV.2 REPAIR OF EXPOSED 30" PIPELINE
AT RCB - TNF 565 & 563 PAGE
Status : B 6 of 10
CONTRACT No. 4600009769

6. IMPLEMENTATION

6.1 Welding Procedures


6.1.1 Contractor (Onasis) require to follow all requirement for approved Welding
Procedure Specification.

6.1.2 . Contractor (Onasis) shall submit welding procedure specification and


supporting Welding procedure qualification record (PQR’s) for Company Approval.

6.1.3 Contractor (Onasis) must ensure WPS/PQR adequately covers all material
types grades and thickness ranges within scope of work.

6.1.4 Contractor (Onasis) shall ensure that all welding procedure shall be numbered
in a sequential and consistent manner employed by the contractor. WPS & PQR’s
shall be assigned individual document numbers for electronic data tracking.

6.2 Welder Qualification.

6.2.1 Contractor (Onasis) shall be responsible for satisfactory qualification of


welders to qualified welding procedure specifications approved by Company (TEPI)
and MIGAS

6.2.2 All welders shall be assigned unique identification numbers by Contractor


(Onasis). Welder identification symbol shall show the following information as a
minimum on the welder qualification record.
a) welder name
b) badge number
c) welding process
WELDING CONTROL PROCEDURE
9769-22-TNF-PWK-3-009-P
REV.2 REPAIR OF EXPOSED 30" PIPELINE
AT RCB - TNF 565 & 563 PAGE
Status : B 7 of 10
CONTRACT No. 4600009769

d) WPS number Qualified


e) positions qualified.
f) material type grade and thickness
g) contractor name / contract number
h) company QC Coordinator signature.

6.2.3 Contractor (Onasis) shall maintain an up to date register of qualified welders


detailing limits of each welder’s qualification and will formally submit this update
welder register to company (TEPI).

6.2.4 Company (TEPI) approval of all welders is required prior to commencing


production welding.

6.2.5 Contractor (Onasis) weld foreman shall keep copies of approved welding
procedure specification available for reference as needed.

6.2.6 Contractor (Onasis) shall follow the welding consumable control procedure for
handling, storage, conditioning issue, usage, return of unused rods/electrodes and
traceability. It is imperative that a welder has only the correct welding
rods/electrodes in his possession for the weld joint being welded.

6.3 Production Welding


Contractor (Onasis) welders are responsible for their work. He must assure that
his equipment is kept in good working order with no breaks in the welding cableor
leaks in the gas hoses. Upon being assigned a joint to weld, he must ascertain the
types of material to be joined and have it confirmed with his supervisor. He must
verify that he has the correct welding consumable for the joint to be welded as
specified by the welding supervisor. The welder shall be satisfied that the joint is
properly fit-up before welding the root pass. He should notify the welding inspector
WELDING CONTROL PROCEDURE
9769-22-TNF-PWK-3-009-P
REV.2 REPAIR OF EXPOSED 30" PIPELINE
AT RCB - TNF 565 & 563 PAGE
Status : B 8 of 10
CONTRACT No. 4600009769

or supervisor if there is any reason that would prevent him from making an
acceptable weld. The welding foremen shall verify that each fit-up is acceptable.
The welder is responsible for welding within of his qualification test and the
applicable WPS, including: correct electrode type and size, keeping electrodes in
heated quivers, amperage, polarity, technique, position, material thickness. A copy
of the approved WPS shall be displayed at all prominent locations of the welding
activities.

6.4 Fit-up / pre & post – welding inspection


All weld joint will be inspected and documented by the Contractor (Onasis) .
welding inspector at the fit-up stage ad prior to welding of the root pass. All welds
joints joints are to be 100% visually inspected by company (TEPI) and Contractor
(Onasis) QC Inspector. This is process examination shall include the following:
a) welder qualified
b) joint preparation, root face, bevel angle, dimensional checking prior to welding etc
c) fit-up , root gap, joint clearance and internal alignment (for piping)
e) filler metal
f) interpass condition at cleaning.
g) appearance of finished joint
h) welder stamp
i) weld joint number
j) NDT performed i.e UT and MPI
k) dimensional check.
The root pass shall be welded immediately after visual inspection of the fit-up is
approved by the Welding Inspector (company or contractor). The company (TEPI)
and Contractor (Onasis) inspector shall verify that the welders are qualified.
WELDING CONTROL PROCEDURE
9769-22-TNF-PWK-3-009-P
REV.2 REPAIR OF EXPOSED 30" PIPELINE
AT RCB - TNF 565 & 563 PAGE
Status : B 9 of 10
CONTRACT No. 4600009769

6.5 Weld Repairs

6.5.1 Weld Repair Methodology


All weld repairs shall be performed in accordance with a qualified and
approved repair WPS. The number repairs at the same location on a specific weld
shall be limited to one unless otherwise approved by company (i.e re-repairs are not
allowed unless agreed upon parties). Repair welding shall always be carried with a
minimum of two passes (hot pass technique). If gouging is required, preheating shall
be applied. After excavation of defect areas, viaual examination and MPI shall be
applied for confirmation of removal of the defect (s). in all cases at least 25 mm of
sound metal beyond each defect as determined by visual inspection and/or NDT
shall be removed. The minimum distance between separate weld repairs shall be
100mm. in event the distance between various excavation is less than 100 mm, the
repairs shall be made continuously. All repair shall be subject to 100% visual
inspection and NDT.
Prior to any repair welding, the condition of the weld preparation / excavation
requires to be absolutely free of any rust or debris. Carbonized surfaces shall be
cleaned by burring too (fraise) to bright metal.
Notes:
1) For defects identified as cracks, the cause of cracking shall be determined and
evaluated.
2) Remedial action shall be proposed to company and will be subject to approval.
3) Removal of linear indications is only to be done by gouging and / or burring tool
(fraise) and not by grinding as defect might propagate.
4) Repair of cracks shall not be carried out prior to this approval.

6.5.2 Company (TEPI) QC Welding inspector shall determine when welds do not
meet the acceptance criteria and must be repaired or replaced. Welds rejected for
surface imperfection detect by visual inspection can be rectified, except for any
WELDING CONTROL PROCEDURE
9769-22-TNF-PWK-3-009-P
REV.2 REPAIR OF EXPOSED 30" PIPELINE
AT RCB - TNF 565 & 563 PAGE
Status : B 10 of 10
CONTRACT No. 4600009769

surface cracks. All surface crack defect shall be reported to company (TEPI). No
repairs on cracked welds shall be performed without the cause being determined
and evaluated . weld repairs resulting from NDT methods such as UT, PT, MT. all
crack defects identified by UT, PT, MT NDT Methods shall be reported to company
(TEPI). “All weld repairs shall be documented on the inspection and test reports”.

7. EXAMINATION & TESTS


The company (TEPI) and Contractor (Onasis) Inspectors will be responsible for
completing the welding information on a daily basis. The result of all inspections and
tests shall be maintained by Contractor (Onasis) in the Onasis Quality Control System
and shall be easily retrievable and traceable. Contractor (Onasis) Records shall include
the welding date, weld joint number, base metal, welder stamp, and NDT report shall be
in detail. Welding traceability shall be maintained by recording the assigned weld joint
number and welder stamp on the contractor (Onasis) specific welding map drawing, in
order to maintain the welding and welder traceability records. Personnel performing
NDE examination shall be qualified.

8.0 RECORDS
8.1 All Copies of records shall be submitted to company (TEPI) on daily basis and
original of these records shall be retained by the subcontractor during the term
of their construction and shall be subject to review / audit by company (TEPI).
8.2 Company (TEPI) QA/QC Department shall be responsible for retention of
Contractor formally records.

9.0 REFERENCES
9.1 GS EP STR 201 Rev.11
9.2 GS EP STR 301 Rev.12
9.3 AWS D1.1, 2010 Edition
9.4 Approved Applicable Drawing.
ATTACHMENT 1
APPROVED DRAWING
1) GENERAL LAYOUT
2) TYPICAL CROSS SECTION
3) TYPICAL DETAIL EARTH RETAINING STRUCTURE
4) STANDARD DETAIL FOR STRUCTURAL STEEL WORKS
. ,. = .: .'- = . -. =i:
. -. . : - .
1 ;'7 =i:: , ;:::' 2i i ''-< ,
=
i ! i. .i ;
" := =.= .: : :i=i=
t::::
,Z 1 ,i;=-i
.? ; :::1j
F ;i i- t4 =-! == - :i;:1 :-
=: E5 - :;ll= ;: s i=;;:-
t+E::R
r /-:ii, i i3 ; :jiei ;; j ;i:t:;
o *
z
E:- =
i.4=?=!-a-2!64'=.-:a:[:gJ1-
< a -i<, !: I
? ; i!;9 :+ t :316: q=
z 3 : i:i; i: , r.i 1=_ : ,i::ii
i:
:;---: '.'- ?
E
ts 9 9o - i i'.i2.::
. { -i:; :i-, E:lE! : lZiztl':,
(9
-.==a:.2 D
\ 2,2i.1 a:i.,i::.i==E!: Eilii;=i
izi., ;i; :'i;,El!1.;,i ;i: s;:;?e"i:
E= 1- i {',r e-=f i : F; ;5.:;i ; -=: qs"'; F
o i!.;a r:' :', l* x: t: ! -l:5::<. - ::
: : <r :: i: ; ..; :
t= E l- >a
= -: -:
-_ e=
ta < !; ;: i
lr-l
i.-
i=
i
5E
I= Uo =F 6s =?it
- Ea=; Li< <-sL<r
aO a l{ :9 Y5;9*.r *L =i
. -'.4 a<
6oic
=z *!a <0 i-^r -.r;i<*;
d91if;- q: iN
=:-E i^ <s;: iE -1:
its ir <oil><e ! oI ;
; E .E=E< iE Y i; o q3=<ad o
- 1=
l]U: 2
g+rE
P >;!.t c=
;; g 6!s:
=SsE EE -, iI{si: z9
i 9 P- e -,* :;a;=;=6
E Ex'ga EEx
o<io 4
s !3f E se{e 1,fr
,=3;E! ia9 iB !o u!!<4+!o lt=
"q:=d;;
zZEtr-id 5 :!Ei
Y-.n :a s{r99BeE z
6
:;:nAo;^i
EJE;:eo;!!: ;-E!Ef ;i B=rS:6<<<6n
i>:
; j! l9 EEi!Es
.\..f
a-'.
6'
ix sb
R '.-,
s<-
N e.l c0
ui E
O
o-
a> )t Lr.l
L]J
o- s 9(J co
4 zooa<O Ltl
() oa *
UJ U] LIJ
L! < r.l.J L t
= ::e
.-)
F
q I
q=i O-! Lr.l
d
qrP =
Q_ o-
o- cL
OL)
Ia!
== -o
: z
b i\r o J
N CL
ui (,
o_ - <l z
t!
zod t
_L
L
--J LL
LJI O LJJ
< Lr.l =
Ll..l
F ql
a coN
J<
LIJ
LU ^
::
alL
s
co
tr
(-)
I!
co
LU IU
)x
==
Ll,l lLl
=-
a
'-.
: : :i- ::
-- -:=..: -: - a l
=-:f : ..- ' :t= <
= -:.-- - = :F>--
r-: : =:-:<
i|
:J :: n't .i .E:=: J: { !?ga:
tE < Y _rr
P
i= i= r5ir;
=: i: : :95=>
o
F
o : E , (E ;E E.i ;ae-':
i4z:!-
:ti;e
6:
zY .! 9E+::E.
lue!5-
;< ; f [>i:+-
:: +
z
IJJ
2 ; s 1i63 >C s: ::!i9
ili^292 : =>;:65
; 3E:aEs
:
: 3:
=ry
EN
(9
I i <35* <c z oo<*< =9
;z .tr -lu."]<il.-
9 =ie:F :E t +:{Es9
I
k : 3
# ffEP" -* :. ii={6: E9: <;
= i= -_ a!rii 0 g
- ;
: g P- i, aI{r cr :
rt =i5:;
?;te: Ets
i:Eqi tsi
=e -' ":{-*e! , 6B
i< c
= =
rD ; 390> e=@<5E
ir P;19H, Ht = +;&;;*25 =2
:!sf,::ix 593=*r6i h:
6^i:lEEE C
eEEa.$Eig
EY-E edEretEX e9
i=<!9=ft' :;Q di:=:.3i3; 9{rgSasE
Ei4IEi---;:B
:
;
6F;!ttued-u;i se i 5 I ie H":*# c's i= B *
E E
i :!- ]? -'e:i:5
<><U<J t.
StX
E?i!gE;!;:==6"." ^
;<;
.;dn+
:'..
: :'.
&
tP
c0
d
O O
Lr.t
@
L]J
Lr.l
z (
ltl
I
u.l
I
d E
d @
f,
o-
t
() F
(-) l
o_
=
F
Lr.l
@<
d
N F
Lll
u,.l ^ N..j f(
I
a P o-- c)
dl
d
ry E- uJ
uJ
O
9 EU
Lr,.l
F
o D
u.t
+= =
S
Z)
ro
d.
O
UJ
--l
co @
t
O
lJl
E,
IJ.J
I
=
',: ,
::::: . =-'- :
, : :'- :l :
.. =:.j --:>::< I - :_ _L _-
: rlY: ':
r::A;:si:I:,i=lii:==
<ac> , r::- =

-
a^ <: ':
- ) =
4
t =i -7 <i4
(J
-.2 YO<
6z
4g
i-
+!
;j
.': ;<9< ?:^--=
9ii,i,z1;t
>- o
i:6i.lt
: := 3^
' ^:
i>
Q; :
-> u d , ><rk = -=I
Eo-
=;u <B>i3P*ti=
=="^z:r
i-, -: du!c z11l\" "a;?= f Ei eI
, :i,. !s<^-
> 6E>5>= i^.-;lr =i 2 41o?1
D 4dz\a
:,
JO
r>;Afr(-)
ur -24.;
rD
r3
u;
i aY ;eiAal Sk JalEb=-;
> az=:i-
a =:,=3i
;"-;i
iti=-<
<=
v 414 4,4'l l) =;iiA;_,3?ag!::€
9=0i5u6;= !{=[i;E=!=]!ii=
z9
,!-,oq> -<7 z= ^-;\-;rr
ir3::=:
6:r
]==?Ba
-;-1o ;e", o2
X 5 F 9 ; o o ; . ^ ! d z b : : \ > ! .^-d o 6 < !. :i >
=;iEQ?t*3 i,=ri::=::=;=o=!=l-=,'
-Jrit;=!r;
= = = =
. =
r!r;J(J-
itdiiv*. ==!=i.19ai-a=!-221
. ;r>a.<;<a o<;<o<<lt< @u o
.
.E
Er Hf EE
;E E
Et :T E E?
dL;E!
EE i5
e1
E
l!
j
e9 i
ts Ei E9
EE
l: EE F:
EE
I
HEI
E
.l
.t
g Tbl
:l
E, F:
q zl
ol_
t )lr
E
!, Oli oli
dt: cal=
otd ! olE
ti
.,
. :,,: . i :i'
-
_: .- i',== i'.;' <=q i=;
' - i' a'Z> :i=.
::=: +
:= =:> =?:- =
,) = ; .==- i
+ =i=. ::5
= t= :; '. --.= ==:-
=>;; =
- -i:. =6:a=
_
E ,' = :i==
- 7=1< =;=-1 ?=
<E-ie_
ga;
=[>],-= za
< 4 := : a1:a-. =YiQ ==ia;
-!! _.;= <;
==1= 4 ,;4 e;
L- Z i :;1s =-ii;i.i
qi=<r446-
Z = >4 E;E<1t
= =6=aq
==11t I 4=E==qC=
- -or?
- 5 s--==+ tr5ai- =;;- 4Fu<fax=
.--r=
=--J:
a= =
1 =;?-==
acl-=!
r=::i
arl;a s= ==+=2==\-=rr:
o
a -"1 E aod.-
4=iir=rts;EE=E+
=-;a:-,:i
i==.=E:=_E .-a_1vc EE==i+;<<=;>Ji
-e=-r>ooqo-:=o=;:l
2
<=a5<,..=6;o<a< b
..;
t'-T-
\./] A, 6)
:l
,ll l7't
'FlL- I
(,
l't.
o
o
5:
u; Lll
zz
E
o
\r
B 9
!-----L-----J
i---'t--
_5
d
e
sj czzzE)-
a=-= {
E C,
z
2 e3: c c
AI 9 r'3lr n :
5l
sl
i: I f
6
5' il
!i:;
=; a
frl
.z
-e
B ol =E
-.-:
E a:= 59 i:
:al ' r.;1. .
-! i: '- -=
-j.::.r == i'
l'..
-=< :=:-! 7 -:+ t::r i .-:
=-i ,..i u -z:
!jip9 -=:{ - !z= iEIsS
a==; 31
.E=e = ;=6 z
<- r=1=
-Yr.
<.:; z2 ===
-=;
o2?'r+cF >=F <t
3=,'-> z= ;+=ie=fs
-:>3=L =22
=!!_ 5a{;€r== ?Y
s5=3=-
SEstr rr*=zF.'= .Za aier<f+<:<
9<d=)'?qq
-'*; 9a==i<)4= ,; ai
+d? -Para==!=
\z=a)
s-;-i=E= = =;io
-22261--13h
g+<+&a=+i= :i:;;;f=!-
:,-i-.-3-*'6
=;;-> ?Y>9-*->=-*! +-<<>d>;i
-i-9
*
d
E
E
t
o E
o
^o
:<
s
<Ei 3
o: a;
"6-
:
:
'. . . ,:=. : -= :- = :'
-==: = .::
r j---
=;a= i -== -:: ;
: -==- f
l) 4 = 6 =',=Z
= = -j-==
-.=: o=E 2ii^=
5 a #--q i>=i; !zz ;=azi E6
F y)
= - <=<z S3:: :!24==
al =
> = : =E=:
>==> =*sE i,j.E z<
===HE
-^ae'-
< -e =
Q =
:.==
; E=6H ==:=
=,2 -
d. =.o: -=-:
;ts'l6_cE:2=
-
==f 5=
=
===f - -
IJJ
z < i .:>S =6d
-s* E=
(, i z ==29a=?
-ti<"1 9 B=26 ==E;=f==
- Eao->-=E a9:Y : + z ! o
=
r.z e 1>
=
=
; !. ;E=x== !==E !
a-6 <;=->--
z4> a add:a
;.i!r+ =35?6==*6=
+i'j6o:q.q=+=;
:==!,
ii=-;
:l- H .aa2-99!-E+H
==>_=5Y+F=
=s==EE66E3EE=5F
iEiEiS ==a=EaE===:i
=:&-iU;
+ ;si
a
/\
g=
OA
i:
e
.x
!
o
1z
o3 ;'
o{ a:
..r.,
a
': 'i Z:
a
1 - - "= - "= o1
:i
; -. g: ! :: ,j:
, ::Ei : i=q,: ;;; =.,
i : i3 Er=I
. r - i:2>
! i:: . {l;
=: :; q;3
"_2:-" :=
;
; =
. i l;ii := :i'_=: ',? a'.i42".
o
F
zo ;z I - :E"I ; FEir: 7E ; itq:. :* 63 ;
; r iEEi,3 s ::iip ii ? 6'-:!5
&
z ::E J Eai;: EN <g :
l9
(, oo 6 d X 2 ,Z:Ez] a 92i;t ,z ' -E s2-
i : riat;5 E it:a: :i E :ii:;i i 1>
z d
3 I
L 2 >iI"-)i: 2e
E 99..
;a:;
I
: [ :eis:i. 1 :r{;; ij' :=.';:
a:;._j A7;
:1<;i:ie
=""41^. a.1
,Etr

I
= i-;2E:!i9;
q-6i':-;> -,; z!-"".;!;a
; -i;- q-= !F3:i;=^6
-;:; i . -
;;-lia1;a?--- .aZi^\=\3
:=;:iEl|;:;$i:ir::::.;j:EEi ;
j,";.e ll*[q;t] lF;l:i;;;i:::=:,
-t n di i ; J - oi I "i
<E
z9
* aG
F: ;f
#H
tu
* tr
,,1
i{ $
d"
fl
a
e
=)
l
:!
=
R
s
I
E'
q
\
-
ta
t
t
tu
=\
!.
lq
+ ,'lr ii
-l ro
=
: -. .:: . =..
a
r = r- -. -., . .. a:
!.6 j -*-*
i ; -, i.'-l,t .>< -<e6:
-..E o-
':
:5 s= 5 :p:E
_r#:c 9.:i;6 !a li
a Z
-; r n:8+= {: 9= 3
= * iiii4E : 9.:=o <6 Eoa<d o sE := l
(5 i{;6?3 tr- aii
d. 't 2 2<i364e - o2 I asBs{i ) =
3
3 ^>q^rl,-
?.? nJs<:,
; E 9-
=i=23 - Ett>:ft
I I ,., tr!l*a<1
q
s
:2:-<=
adEe-
o l
o<
- t sEXlrEH g 2;;3.::;4 !5
i 9u;g*E*g
s"6=5;;!:;E 3:-=>+3:3*
zzraL-a6Y!i
!-;^;=$Bi;=
EE-'E;-:rrI!: fiYe-.ieie= :::
rd-uo9-E-- i!! 3
2
fl
1/
e
!a

N
*+--
x
tro-
L!e
= =
d e
l - >L
d
-
I
F z
o-
zo
t
u-
&-
.r9
L6
F
s
t
!i =
qr
"*
..
--lj :
:
1 : !- -r
-' r :-i i
r =. -r - =.:::: :. ?-=-'
-:, =-
I i ; '=:;
n | 2 -'==
:- ,,:i-d :: ?
t
- i::9:
a 2_:6 ;= - :-,2..
- : 5E;" ' ;:a-c. 2. F ;-;.-?
: = \=
z\-J I < - ..ra i< ; _-=:i; 1
L i ,lj.,1; >a ).lBii :.5
4 -" ;7"oa"<
;^ :.s aoi{..
=:i:ii a E:
(,
uJ *)
E. " I ij;-:
=Y_i
2 '-';ix22 z 9ii""t
; e3-6* 'z o l":Y'R
qi i69 4,
z Q t ,'. a2'-i r !<:Ei ' f:?139
: {+={6.
:: 3 ? ,x:.1i : i-xz_ =: ,4 ;5a'1:
" - 7 ;A"=iti , i1)= =1 :.' a;"ta;
'6;J(9
; E =i:.iri-!
;,..-?=R;e*:
i+iEB-E*
z-i'...ar42 1Z<Zr2z.Z
UE
=e
c-'.i="-;>rf ; i!;;-+-a i=Li\..42
du";;*rS
a:--a' )".t= z>r,"-=\, ;!it--d.=
;,i5:;ia:>Ei1!aii.:!!
== j!:Beir;
-1. -, -?t! i!:i93
6:;33<:
6Z --<'',>oodi;E=- irdi:i
-_ r
-=t -
- 1- 2- > 6<<>
5
6<
;2.- ai3? "a - "
":<I;9...'?9b:;iEY
- i a < - - . -- :
i\ F
I ;f
{
."1 d
4/
-,1
= =
d s
!
q
E I
i f-
l
o
=
o
I I J
(D
t
o
I.JJ
J
!o
t!
t
=
e ul
;] 0-
N- =
J
E Lo
I
a +1
E
t-
i a.
9o
e
> Lrl
o
.:
I : :- .=-- -, : I :- . 1 '. - ,-) ='
a <1
.i= >=.ls zi;ir)tr - - <
-: <>_cz : :/+* - -i <: -= z
IJJ
F
E
i,^2 :s=
I -
2?9e 2:::.s,! 1 ; Ai = = - l
::t
j= i>
v" o
i:-
i' '=91
j:y :z =:"
I7 Zt;
E:< 3i:_::oE: :;>1=;;Q Z ;ii
6l!. ;* iiIi q:
i: j;=
;3 Ed
HE
14ts
a <' -;n o_; 1-=Y :5>:,-ei:'-
=r-==az,-= i1= 7 i=^z,z o 6P
E ;F=i:= i';e;=qH =q'==)== = "'i;V*
d:,-,o 1>
=:?kjq -==:,=aP*
z l);i;i ,z====2=
o -, ; ; A ; :- < ; ; ; : I ; ; IziEi
!
= ==a iE r-,a{eR
iz-_=.2- ?V
(9 9-'
= a-EUb E
6E65q:?,i\=Z=+==[;'i=!!isf
=_:5;i;?:R!i{z=2!?21r, ]a ?=-i=. .=31i,{
;:r=ila ; ; i I : E i a ? 1i12lc-za==2? q j ! E s i :
i.:'
o I = -o-o. <
-=:. j = 5 < 7 <: <- 5 r
z
--i=?.-Yl - = i - I;=ci;
F-
. " S7r>oa <] 6: <2i i E: ; : ?zI <
-.: . -= d
=i?i
<<<a<<; = <7<-o<7<o<<r5
.l:oisui-":
._
E
F.
CE
l!
:E
. :E
!s
I
q E
E .! 3l
f !l ?:l
+l
f;l t^l
9; -\2
'-\tol:
H?
a;
NH
1 x.t
3ii oti (.)d
7: :. -: -a' =:: -' l :. -: I :l: =
: i, : :t -i. r. .i---i !
-i
:,
: i 6 - - ir >Z :-
i : ;--:, r=:-
=-.-' - ;1 i:
5 ,-r€ :;:
i
-- -: :1 . =-1 4 a , il i :-- r!
F < _:; =foz -o1<i;?. "
: "k ;;1 z 4t f
<B
: ]o? <7 1d:? <<'o-=7r :i:+ << i\ 21,
1;- &> -"- :> -> e=4::1=9 o -
9d- a >B i; o;
2==,-=2
< --<2>: 5:5
a<a-+u,! €E=g:i.Z z,=:l != 6<= 6 <=9Y=
a?9:
EN
:i!
:1L z -:2 > t=-=-./6+
:!=
=>== e au=<t_=<_ ;:i <t
L]J
-: z= -a -1J9.' .=<"99?Y? <-^
<.,; n;=
\
':if
=o1ts- r. ;::
! e,i
=:ta:;
(, <=<c",r: ^a
:ris=:;:<-eH;=E;=.
- ;r d=' Aa o-=--O-
!]s?
r=-
uu!
=
:
u
<
=2-zz
<--:<i
6=X!-N
s
6 q=:F=! i 5c+ +; + 3 r:-t:r orJ.h
u<;z-
6"-=J
a_.!d6=r-
r
i:
EE r:_r:i
r!!
=:ia;.>i "L ": oX > 3< 4 z - a "-7\
a a=
-j=>_-A -,)= J=_+<-2.- = =
=.aa=izD 9;rEtsrHr:rsd z
j= r!<uL--
r2_--<=:^i )!n
-'-;;o='; : J:'==;- -<-
=i;;
qlZT< ==J>-,.--^-..1
Ei!
r-o
!.=n-:<;<n<-(,u
--'-7 -9: =:t= r--z
<a<E<<;-' ;B>o.]<;ailo<;< :.r
.::
-I
"i = ',: ;
'=- 1
\
--l
rl
z
o o
J
F o
LL
uJ o
a N
o
a o
a Y
o
t
()
B
I
=
=
5 ::
=
a
-
a-1
=
=
_r=: -
=:::_
- G
: i
= r-z=
=i-.: ===;
=!e,1
::= =<"-a
,= a !;-- i=eG
lrJ ii:
F = - ==: <==z
o
= - ;: t'+aj >L!N-
n1E sE>l= s9 :;: z B;:
= z-J !oa=d
e ; H=-E z50H -=- r:i
o<=
=e6-G+
Ei<-=l^i
<t :a:
i; j
= E Eg.PiiiE -6I=
*<<= l:-
=;-
."^<>:6=
i55=1i; i !!
= i==+>=
=e;E=+ 5-ie
=
E E=:,-=i ih"=a
=*t=======
UE
=2
= !. r.=q==i42= s=
= =in-1== ===
:j= :-a:i =9trY;tt>a=
1 =.;--:r =:= !:l
=:==+96!B=EgEE -B= !:.
-i ; + ;6 !
-r-
\"/l !/ fl
+
[ f-
E
6)
I e)) )l/ 7 z
'[ a
\-, [ O:
a;
o
b:
T--
t I
a1
_)-- z
t- 6
i! E:
!::::_-:__:-,-
/i a
i_
E
o - .,,+-
'v/
la'
<i
5
I ad

z:^3:3
=;SFE!
*6b:\ {
2
2
a
h "
3:- =i3
c
BI i.: E
e
;t
9
ar
? H]; )
Z z--5: -:i
EI 2
6 frls Zi
TI
:t a ; l.;==
5Lr Z
-a i E
...:
z: i' E
za
i; -
--.' i.:
. : . . ,i; i,t: : ,=. .- r,: 5
: : ) z +== - --?1
i Z;Z-" .::
:i .'. : ^-7.
-:Z;
i= .-
; ie ==' i
"--
= ==?- a i33rA
j =a := !4= )-c=:a
E=: =;a/^ ? =Z==14
93.
i-6=e_
---"=:
?==:s
z z> ; 5??+ ==i> V !<6 Z<= =l
Hd
5;. j=i> 3E;
aEiI =1;?
dL- >: x{ >:o; an B
=
=
I= = = -ilf 6E 3
I
aI35 ?Z;?&: =-- <::"{"
< { :=-= zaai >a 6=A
E i =+;:--_ i;
z =
E = i=a3l+:14?i_i
i =
(9 E > >o::*". ,ia:=-'= ==Y;.1rii=
= i; Zi: J i-.i==: rai..zz_J=;
=:= =a:e;a
= Z ,=)---1. >a^=zi-
--.- -96=++-A-
io5 g;-=-=: =A
2z; =;==;: 2-.d4i;=
===1-._i-r^
=6J:o< ==^>?a ^i7Za
3=? ;= 7 ac*==;=
-i!-l: q:i ::;*:-=-zB
=Ei=iEzz:4.-+=
-.i=
=i
- -.:
s
<-
I
d
a
o
o
E :
e
.
o
oi J
F
aE 1-
,i
g:
.'
:.' : .: :=: -: a. :-.= : -!, .:l
.
=
:..
<;<: === - -,= -
"-. 2a=
= = a + .=== :=-= --= 4
i;-:r - :=: ;
::= =Ld
==:[
g==: =
E =s::o<
i 5ir =--i=E
= ts
= e-oe=
=!=- 6>o
= -= =1 =4a- --=!2 =
€a= +seH=
==:-;
=
I= =_: ; l+,=i= z.-=,a=E=3
==:E:e = =q= s9-+r
--:1 '::
:a .B
= ;:r=< ==:=.i
i ^Z'. <-{-3=
=== "-+=ier
222
<;
>
= =
E;EEiX
= <==9a* <
iA?1-=a*il: >;= =-ii=a;
e
:
=E;: ia
= ; frio><=
:: - <-=
:-=;1- a J jri;2;=-=:
=-j-=='
= - 1=aErG 12+='.t= -: 3Ee6€t+4= EE F
i=:;:i=rEEV a;i1= z I
24. 6::e=
= * d < q c = * a !!
=aq>eax;;u> 9:> c !;=-=_ = -% _,o
i =
e<<=-> = =
o -
:E:5:S
=: 65=?e5=5===3<dU -i
-i6i;+
3
I \ a-
il--]
It
r'a
i
__:=-r__-_:
;
=::
. TE-
: -.}
r ;2ie-
:;:
.::cE::-'=
g -=aEq.*
E
F: d 5=3^- :
E
;; '=
3.-E
= =3
a;:E-:;
5
*?E tr 1:E
lz -
Ll
'i- L
r'E s
;s ! <:
i! .= +! tr z :::
a\ at
sE
:
REPAIR OF EXPOSED 30" PIPELINE AT RCB-TNF 565 & 563
CONTRACT No. 4600009769

INSPECTION AND TEST PLAN

1 14/12/14 Issued for Approval HP PS/BN WS/AM

0 07/11/14 Issued for Comments HP PS/BN WS/AM

REV DATE DESCRIPTION PREP’D CHK’D APPR’D COMP’Y


STATUS CODE : A = Issued for Comments, B = Issued for Approval, C = Approved, X= Cancelled
Info= For Information
© This document is copyright.
No part may be reproduced or used without the written permission of the Owner

REPAIR OF EXPOSED 30" PIPELINE


AT RCB-TNF 565 & 563

PWK-A/OI-QC-ITP/001/2014 REV. STATUS


1 B
1

REVISIONS ATTTACH
STATUS
PAGE MENT PAGE
0 1 2 3 4 5 6 A B C X I
1 X 1 X
2 X 2 X
3 X 3 X
1 of 3 X
2 of 3 X
3 of 3 X

REPAIR OF EXPOSED 30" PIPELINE AT RCB-TNF 565 & 563


2

TABLE OF CONTENT

PAGE

I. COVER...................................................................................................................i

II. TABULATION OF REVISION PAGE....................................................................1

III. TABLE OF CONTENT...........................................................................................2

IV. INSPECTION AND TEST PLAN ( ATTACHMENT )

REPAIR OF EXPOSED 30" PIPELINE AT RCB-TNF 565 & 563


INSPECTION AND TEST PLAN
REPAIR OF EXPOSED 30" PIPELINE AT RCB-TNF 565 & 563
DOCUMENT NO : PWK-A/OI-QC-ITP/001/2014 DATE : December 14, 2014

CONTRACT NO : 4600009769 REVISION : 1

DISTRIBUTION : TOTAL E & P INDONESIE PAGE : 1 of 3

INSPECTION
NO DESCRIPTION VERIFICATION DOCUMENT REFERENCES ACCEPTANCE CRITERIA REMARKS
PT. OI TOTAL EP

1 PRE-INSPECTION MEETING - COMPANY SPECIFICATION MOM H H

2 DOCUMENT SUBMIT, REVIEW AND APPROVAL

2.1 PROJECT QUALITY PLAN TWC PT OI Quality Manual - H R

2.2 PROCEDURE FOR MATERIAL CONTROL Procedure for Material Control GS-EP-STR 201 Rev 11 ASME Sect. II Part A H R
OI-SOP-PR-7503 GS-EP-STR-301 Rev 12 GS-EP-STR 201 Rev 11
GS-EP-STR-301 Rev 12

2.3 RECEIVING, STORAGE, & HANDLING OF WELDING ELECTRODE PROCEDURE Receiving, Storage, Handling of- GS-EP-STR 201 Rev 11 ASME Sect. II Part C H W/R
Welding Electrode Procedure- ASME II Part C GS-EP-STR 201 Rev 11
TWC-A/OI-QC-EL/2013 Electrode Manufacture- Electrode Manufacture-
Recommendation Recommendation

2.4 WPS/PQR APPROVAL WELDING BOOK Welding Book for Structure GS-EP-STR 201 Rev 11 AWS D1.1 H W/R
TWC-A/OI-QC-WPS/001/2013 GS-EP-STR-301 Rev 12 GS-EP-STR 201 Rev 11
AWS D1.1 GS-EP-STR-301 Rev 12

2.5 WELDER QUALIFICATION / PERFORMANCE Welder Qualification Certificate Welding Book for Structure AWS D1.1 H W/R
Welder Qualification List GS-EP-STR 201 Rev 11 Welding Book for Structure
TWC-A/OI-QC-CERT/001/2013 GS-EP-STR-301 Rev 12 GS-EP-STR 201 Rev 11
AWS D1.1 GS-EP-STR-301 Rev 12

2.6 PAINTING PROCEDURE Painting Procedure GS-COR 350 Rev. 10 GS-COR 350 Rev. 10 H W/R
TWC-A/OI-QC-P/2013 GS-COR 352 Rev. 10 GS-COR 352 Rev. 10
GS-COR 450 Rev. 08 GS-COR 450 Rev. 08

2.7 NDT PROCEDURE NDT PROCEDURE GS-EP-STR 201 Rev 11 GS-EP-STR 201 Rev 11 H R
TWC-A/OI-QC-NDT-STR/2013 GS-EP-STR-301 Rev 12 GS-EP-STR-301 Rev 12
AWS D1.1 AWS D1.1

2.8 STRUCTURE DRAWING AFC Structure Drawing GS EP STR 100 Rev.12 AFC STRUCTURE DRAWING H R
Certificate List for Structure GS EP STR 201 Rev.11 GS EP STR 100 Rev.12
GS EP STR 301 Rev.12 GS-EP-STR 201 Rev 11
Company Data Sheet GS-EP-STR-301 Rev 12

2.9 WELDING MAP & NDT PLAN Welding Map & NDT Plan Welding Book for Structure AWS D1.1 H R
TWC-A/OI-QC-WPS/001/2013 WELDING BOOK FOR-
NDT Procedure STRUCTURE
TWC-A/OI-QC-P/2013 GS-EP-STR 201 Rev 11
GS-EP-STR 201 Rev 11 GS-EP-STR-301 Rev 12
GS-EP-STR-301 Rev 12 TWC-A/OI-QC-P/2013
AWS D1.1

3 MATERIALS

3.1 MATERIALS RECEIVING

3.1.1 MILL TEST CERTIFICATE & PURCHASE ORDER CERTIFICATES GS EP STR 201 Rev.11 ASME Sect. II Part A H R
Mill Certificate OI-SOP-PR-7503 GS-EP-STR 201 Rev 11
EN 10204

3.1.2 VISUAL INSPECTION MVR REPORT/CERTIFICATE - ASME Sect. II Part A H W/R


GS-EP-STR-201 Rev 11
EN 10204
INSPECTION AND TEST PLAN
REPAIR OF EXPOSED 30" PIPELINE AT RCB-TNF 565 & 563
DOCUMENT NO : PWK-A/OI-QC-ITP/001/2014 DATE : December 14, 2014

CONTRACT NO : 4600009769 REVISION : 1

DISTRIBUTION : TOTAL E & P INDONESIE PAGE : 2 of 3

INSPECTION
NO DESCRIPTION VERIFICATION DOCUMENT REFERENCES ACCEPTANCE CRITERIA REMARKS
PT. OI TOTAL EP

3.1.3 DIMENSIONAL & QUANTITY CHECK MVR REPORT/CERTIFICATE


- COMPANY SPECIFICATION ASME Sect.
MOMII Part A H W/R
H
GS-EP-STR-201 Rev 11
EN 10204

3.1.4 HEAT NO. TRACEABILITY MVR REPORT/CERTIFICATE OI-SOP-PR-7503 GS-EP-STR-201 Rev 11 H W/R
EN 10204
Code Related to Material Specification

3.2 WELDING CONSUMABLES

3.2.1 REVIEW BATCH CERTIFICATES MVR REPORT/CERTIFICATE TWC-A/OI-QC-EL/2013 AWS D1.1 H R


GS-EP-STR 201 Rev 11
GS-EP-STR-301 Rev 12

3.2.2 ELECTRODE & DRYING WELDING ELECTRODE OVEN- TWC-A/OI-QC-EL/2013 GS-EP-STR 201 Rev 11 H R
CONTROL REGISTER GS-EP-STR-301 Rev 12
Electrode Manufacturer-
Recommendation

4 FABRICATION

4.1 LAY OUT & CUTTING


4.1.1 CHECK TRANSFER OF HEAT NUMBERS & IDENTIFY Cut Profile Inspection Report Heat Number Transferred Shall- W/H M/R
be Same with Original Material
AFC Structure Drawing
Fabrication & Installation Procedure
GS EP STR 301 Rev.12

4.1.2 CHECK DIMENSIONS, MARKING, & CUTTING PROFILE Cut Profile Inspection Report AFC Structure Drawing AFC STRUCTURE DRAWING W/H M/R
Fabrication & Installation Procedure
GS EP STR 301 Rev.12

4.2 FIT-UP

4.2.1 PRE-WELDING DIMENSIONAL CHECK - AFC STRUCTURE DRAWING H M


GS-EP-STR-301 Rev 12

4.2.2 INSPECT WELD FIT-UP (ANGLE, GAP, HI-LO, PREPARATION) FIT-UP INSPECTION REPORT Welding Book for Structure GS EP STR 301 Rev 12 H M/R
Applicable WPS & PQR Welding Book for Structure
Applicable WPS & PQR

4.3 WELDING
4.3.1 CHECK CONFORMANCE WITH WPS VISUAL INSPECTION REPORT WPS/PQR Applicable WPS & PQR GS-EP-STR-301 Rev 12 H M/R
4.3.2 CHECK WELDER PERFORMANCE WRR RECORD WELDER LIST AND CERTIFICATE AWS D1.1 H M/R
4.3.3 VISUAL INSPECTION VISUAL INSPECTION REPORT Welding Map Applicable WPS & PQR H R

4.4 POST WELD DIMENSION CHECK


4.5.1 CHECK FINAL VISUAL INSPECTION AND STRAIGHTNESS Dimensional Inspection Report Approved Structure Drawing GS-EP-STR-301 Rev 12 H W
Fabrication & Installation Procedure Approved Structured Drawing
GS EP STR 301 Rev.12
INSPECTION AND TEST PLAN
REPAIR OF EXPOSED 30" PIPELINE AT RCB-TNF 565 & 563
DOCUMENT NO : PWK-A/OI-QC-ITP/001/2014 DATE : December 14, 2014

CONTRACT NO : 4600009769 REVISION : 1

DISTRIBUTION : TOTAL E & P INDONESIE PAGE : 3 of 3

INSPECTION
NO DESCRIPTION VERIFICATION DOCUMENT REFERENCES ACCEPTANCE CRITERIA REMARKS
PT. OI TOTAL EP

5 TESTING - COMPANY SPECIFICATION MOM H H

5.1 NDT
5.1.1 RADIOGRAPHIC Radiographic Test Report TWC-A/OI-QC-NDT-STR/2013 GS-EP-STR-301 Rev 12 H R
Film Radiographic Review NDT PLAN AWS D1.1

5.1.2 UT/MPI/DPT UT/MPI/DPT TES REPORT TWC-A/OI-QC-NDT-STR/2013 GS-EP-STR-301 Rev 12 H W


NDT PLAN AWS D1.1

5.1.3 CHECK NDT COVERAGE AND COMPLETENESS NDT CLEARANCE REPORT NDT PLAN DRAWING, WELDING MAP & NDT PLAN H R

5.1.4 CHECK WELD REPAIR COMPLETE NDT REPORT WPS/PQR GS-EP-STR-301 Rev 12 H R
Applicable WPS & PQR Applicable WPS & PQR

6 INSTALLATION

6..1 FIT-UP - - -

6.1.1 CHECK DIMENSION LOCALLY AND GLOBALLY FIT-UP INSPECTION REPORT - AFC STRUCTURE DRAWING H W

6.1.2 INSPECT WELD FIT-UP (ANGLE, GAP, HI-LO, PREPARATION) FIT-UP INSPECTION REPORT WPS/PQR GS-EP-STR 301 Rev 12 H M

6.2 WELDING

6.2.1 CHECK CONFORMANCE WITH WPS VISUAL INSPECTION REPORT WPS/PQR H M

6.2.2 CHECK TEMP. OF PREHEATING CONFORM TO WPS VISUAL INSPECTION REPORT WPS/PQR H M

6.2.3 CHECK WELDER PERFORMANCE REPAIR RATE REPORT WELDER LIST WPS/PQR H M
& WELDER CERTIFICATE AWS D1.1

6.3 VISUAL AND DIMENSIONAL

6.3.1 CHECK FINAL VISUAL INSPECTION & STRAIGHTNESS Dimensional Inspection Report - AFC STRUCTURAL DRAWING H W/R
GS-EP-STR 301 Rev.12

7 REPORT AND RECORD

7.1 INSPECTION RELEASED CERTIFICATES (IRC) IRC - - - H

7.2 COMPLETE OF DOCUMENT : CERTIFICATE, REPORT, AND RECORD DOSSIER - CONTRACT H R

7.3 HAND OVER DOSSIER & FINAL DOCUMENTATION DOSSIER - CONTRACT H R


STATUS: I = Information, H = Hold Point, W = Witness , SW = Spot Witness , V = Verification , R = Review Document, QC = Quality Control, E = Engineering, A = Approved, M = Monitoring
OI = PT. ONASIS INDONESIA, INT/QLY = ENG/QAC/OPS TOTAL E&P Indonesie, CST/OPS = ENG/CST/OPS TOTAL E&P Indonesie, P = Provide, MN = Material Man

" Information " I Documents pertaining to the relevant task or stage must be transmitted to the verifying party, solely for the purpose of information
" Review " R Documents pertaining to the relevant spesific task or stage must be transmitted to the verifying party for review, before pursuing the execution process
" Monitoring " M The verifying party attends the execution of the task, either continually or occasionally, as suitable for him/her
" Witmess Point " W The verifying party must be notified in advance (to be defined beforehead) of the execution of the relevant task or move on to the relevant stage. The absence of a verifying authority does not suspend the continuation of the execution process
" Hold Point " H The verifying party must be notified in advance (defined beforehand) of the execution of the task or move onto the stage. The execution process is suspended (at a hold point) in the event of absence of the verifying authority
ATTACHMENT 3
WELDING PROCEDURE SPECIFICATION
LIST OF WPS & PQR ( AWS D1.1 )
WPS PQR Range Qualification
NO. Base Material Thick. Dia. Welding Filler Metal Preheat Thick. Dia. Remarks
Code & Spec. WPS No. Procedure Joint Type Pos Pos
Mat'l Spec. (P/S No.) & (Group No.) (mm) (inch) Process F no. AWS Class. (oC) (mm) (inch)
9
1 AWS D1.1 OI/WPS-55/AWS/08 T1 : 9 E 7018 H4R 27 ºC T1: 3.18 - 12.7 OD ≥ 24" 1F & TOTAL & MIGAS
Main WPS A516 Gr.70 Group II To Group II Plate SMAW 2F 4
GS STR 301 OI/PQR-55/AWS/08 Multi pass
T2 : 12 ( LINCOLN ) (Ambient) T2: 6 - 18 or PLATE 2F APPROVED
Single pass T1

Min. 6 mm Min Leg size for single Pass, 5 mm


Min. 5 mm
Min Leg size for Multi Pass, 12 mm
0 (+2,-0)
T2 12

Min. 4-2 mm

T1
9
2 AWS D1.1 OI/WPS-56/AWS/08 T1 : 9 E 7018 H4R 31 ºC T1: 3.18 - 12.7 OD ≥ 24" 3F TOTAL & MIGAS
Main WPS A516 Gr.70 Group II To Group II Plate SMAW 3F 4
GS STR 301 OI/PQR-56/AWS/08 T1
Multi pass
T2 : 12 ( LINCOLN ) (Ambient) T2: 6 - 18 or PLATE APPROVED
Single pass

Min Leg size for single Pass, 10 mm


Min. 13 mm
Min. 10 mm Min Leg size for Multi Pass, 13 mm
0 (+2,-0)
T2 12

Min. 0,7L

T1 T2
60° (+10°, -0)
3 AWS D1.1 OI/WPS-58/AWS/08 GTAW 6& ER 70S-6 27 ºC OD ≥ 24" TOTAL & MIGAS
Main WPS S 355 Group II To Group II 19.05 Pipe 24" 6G 9.5 - 28.55 ALL
GS STR 301 OI/PQR-58/AWS/08 SMAW 4 E 7018 H4R (Ambient) or PLATE APPROVED

SMAW ( LINCOLN )
T
GTAW

1.5-2mm.
3.0 - 5.0 mm

T2T2 T1T1
T2
T1 T1
T2 T1
LIST OF WPS & PQR ( AWS D1.1 )
WPS PQR Range Qualification
NO. Base Material Thick. Dia. Welding Filler Metal Preheat Thick. Dia. Remarks
Code & Spec. WPS No. Procedure Joint Type Pos Pos
Mat'l Spec. (P/S No.) & (Group No.) (mm) (inch) Process F no. AWS Class. (oC) (mm) (inch)
T2T2 T1T1
T2
T1 T1
T2 T1
60° (+10°, -0)
4 AWS D1.1 OI/WPS - 69/AWS/10 GTAW 6& ER 70S-6 32 ºC TOTAL & MIGAS
Main WPS API 5L-X52 Group II To Group II 19.05 Pipe 16" 6G 9.5 - 28.5 12" ≤OD< 24" ALL
GS STR 301 OI/PQR - 69/AWS/10 SMAW 4 E 7018 H4R (Ambient) APPROVED

T
( LINCOLN )
SMAW

GTAW

3.0 - 5.0 mm 1. mm.

5 AWS D1.1 OI/WPS-72/AWS/12 45° (+10°, -0) E 7018 H4R 32 ºC OD ≥ 24" 1G and TOTAL & MIGAS
Main WPS A516 Gr.70 Group II To Group II 12 Plate SMAW 2G 4 6 - 18
GS STR 301 OI/PQR-72/AWS/12 ( LINCOLN ) (Ambient) or PLATE 2G APPROVED

Back Chipping 3.0 - 5.0 mm 2. mm. max

6 AWS D1.1 OI/WPS-75/AWS/13 45° (+10°, -0º) T1 : 12.7 E 7016-1 & 33 ºC


Main WPS API 5L-X52 Group II To Group II Pipe 16" SMAW TKY 4 6.35 - 19.05 12"≤OD<24" ALL
GS STR 301 OI/PQR-75/AWS/13 T2 : 15 E 7018 H4R (Ambient)
To A516-70
PLATE

OI/PQR-75A/AWS/13 ( LINCOLN )
2 mm max.

3-5mm

PIPE T1

T2
LIST OF WPS & PQR ( AWS D1.1 )
WPS PQR Range Qualification
NO. Base Material Thick. Dia. Welding Filler Metal Preheat Thick. Dia. Remarks
Code & Spec. WPS No. Procedure Joint Type Pos Pos
Mat'l Spec. (P/S No.) & (Group No.) (mm) (inch) Process F no. AWS Class. (oC) (mm) (inch)

7 AWS D1.1 OI/PQR-75A/AWS/13 E 7016-1 & 33 ºC


Main WPS 12 37°, -0,5º S 355 KL+20 Group II To Group II 19.1 Pipe 20" SMAW 6GR 4 6.35 - 19.05 12"≤OD<24" ALL
GS STR 301 E 7018 H4R (Ambient)
To
150 ( LINCOLN )
S 355 KL+20
1.5 - 2 mm
T

5mm Min
3-5mm

8 AWS D1.1 OI/WPS-76/AWS/13 E 7016-1 & 33 ºC OD ≥ 24"


Main WPS T2 A516 Gr.70 Group II To Group II 15 Plate SMAW TKY 4 7.5 - 22.5 ALL
GS STR 301 OI/PQR-76/AWS/13 E 7018 H4R (Ambient) or PLATE
3-5mm
( LINCOLN )
45° (+10°, -0º)
2 mm max.

T1

9 AWS D1.1 OI/WPS-77/AWS/15 E 7018 H4R 33 ºC OD ≥ 24"


Main WPS S355 Group II To Group II 16 Plate SMAW 4G 4 8 - 24 4G
GS STR 301 OI/PQR-77/AWS/15 ( LINCOLN ) (Ambient) or PLATE
back weld

approved with comment


==================
ECP/QSE/OPS - DW
ATTACHMENT 4
WELDER LIST
LIST OF WELDER CERTIFICATE FOR STRUCTURAL ( AWS D1.1 )

Welder Qualification Test RANGE QUALIFICATION

Base Metal Electrode


WELDER NAME and
No. Migas Certificate Validity Date REMARKS
STAMP NO. Nom Dia Thickness

Dia (Inch)

Thk.(mm)
Process Position Position
Group Group (mm) (mm)
Spec. AWS No.
No. No.

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


1 RUSTAM (W-06) 6034/10.12/DMT/2014 August 17, 2017 API 5L Gr B 8" 12.70 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


2 SUGENG P (W-07) 6161/10.12/DMT/2012 August 11, 2015 API 5L Gr B 10" 15.90 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


3 ISRAJUDIN ( W-18 ) 4004/10.12/DMTS/2014 May 18, 2017 API 5L Gr B 8" 12.70 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited

GTAW ER 70S-6 F6 Min. = 5 mm


ALL / UP except
4005/10.12/DMTS/2014 May 18, 2017 API 5L Gr B 8" 12.70 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited
4 ABDUL RAUF ( W-19 )
E 7016-1 Min. = 5 mm
POS. 6GR
2011/10.12/DMTS/2014 March 11, 2017 SMAW API 5L Gr B 10" 14.05 I F4 6GR/UP ALL / UP 100 MIN
Ø10"
E 7018 H4R Max. = Unlimited

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


5 TONY KRISBIYONO (W-21) 6240/10.12/DMT/2013 June 12, 2016 API 5L Gr B 6" 14.27 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


4006/10.12/DMTS/2014 May 18, 2017 API 5L Gr B 8" 12.70 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited
ENDANG SUHENDRA
6
( W-30 ) E 7016-1 Min. = 5 mm
POS. 6GR
2013/10.12/DMTS/2014 March 11, 2017 SMAW API 5L GR B 10" 14.05 I F4 6GR/UP ALL / UP 100 MIN
Ø10"
E 7018 H4R Max. = Unlimited

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


4008/10.12/DMTS/2014 May 18, 2017 API 5L Gr B 8" 12.70 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited

E 7016-1 Min. = 5 mm POS. 6GR


7 PRAYITNO ( W-31 ) 2016/10.12/DMTS/2014 March 11, 2017 SMAW API 5L Gr B 10" 14.05 I F4 6GR/UP ALL / UP 100 MIN
Ø10"
E 7018 H4R Max. = Unlimited

E 7016-1 20 MIN Min. = 3 mm POS. 6GR


2031/10.12/DMTS/2014 March 11, 2017 SMAW API 5L-Gr.B 3" 5.49 I F4 6GR/UP ALL / UP
100 MAX Max.= 20 mm Ø3"
E 7018 H4R

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


8 SUNYOTO ( W-32 ) 4009/10.12/DMTS/2014 May 18, 2017 API 5L Gr B 8" 12.70 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited

E 7016-1 Min. = 5 mm POS. 6GR


9 SYAHRANI (W-33) 2020/10.12/DMTS/2014 March 11, 2017 SMAW API 5L Gr B 10" 14.05 I F4 6GR/UP ALL / UP 100 MIN
Ø10"
E 7018 H4R Max. = Unlimited

E 7016-1 Min. = 5 mm POS. 6GR


2017/10.12/DMTS/2014 March 11, 2017 SMAW API 5L-Gr.B 10" 14.05 I F4 6GR/UP ALL / UP 100 MIN
Ø10"
E 7018 H4R Max. = Unlimited
10 SYARIFUDIN ( W-35 )
E 7016-1 20 MIN Min. = 3 mm POS. 6GR
2032/10.12/DMTS/2014 March 11, 2017 SMAW API 5L-Gr.B 3" 5.49 I F4 6GR/UP ALL / UP
100 MAX Max.= 20 mm Ø3"
E 7018 H4R
LIST OF WELDER CERTIFICATE FOR STRUCTURAL ( AWS D1.1 )

Welder Qualification Test RANGE QUALIFICATION

Base Metal Electrode


WELDER NAME and
No. Migas Certificate Validity Date REMARKS
STAMP NO. Nom Dia Thickness

Dia (Inch)

Thk.(mm)
Process Position Position
Group Group (mm) (mm)
Spec. AWS No.
No. No.

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


6162/10.12/DMT/2012 August 11, 2015 API 5L Gr B 10" 15.90 I 6G/UP 100 Min.
TYK
JAWAHIRUL ABROR SMAW E 7018 H4R F4 Max. = Unlimited
11
(W-38)
E 7016-1 Min. = 5 mm POS. 6GR
2014/10.12/DMTS/2014 March 11, 2017 SMAW API 5L Gr B 10" 14.05 I F4 6GR/UP ALL / UP 100 MIN
Ø10"
E 7018 H4R Max. = Unlimited

ER 70S-6 F6 ALL / UP except Min. = 5 mm


12 YUSRIANTO (W-40) 6160/10.12/DMT/2012 August 11, 2015 SMAW API 5L Gr B 10" 15.90 I 6G/UP 100 Min.
TYK
E 7018 H4R F4 Max. = Unlimited

E 7016-1 Min. = 5 mm POS. 6GR


13 SUPIANSYAH (W-41) 2019/10.12/DMTS/2014 March 11, 2017 SMAW API 5L Gr B 10" 14.05 I F4 6GR/UP ALL / UP 100 MIN
Ø10"
E 7018 H4R Max. = Unlimited

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


14 SUPRIADI ( W-49 ) 2022/10.12/DMTS/2014 March 11, 2017 S 355 8" 12.70 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


6242/10.12/DMT/2013 June 12, 2016 API 5L Gr B 6" 14.27 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited

E 7016-1 Min. = 5 mm POS. 6GR


15 GABRIEL MANEK (W-54) 2015/10.12/DMTS/2014 March 11, 2017 SMAW API 5L Gr B 10" 14.05 I F4 6GR/UP ALL / UP 100 MIN
Ø10"
E 7018 H4R Max. = Unlimited

E 7016-1 20 MIN Min. = 3 mm POS. 6GR


2030/10.12/DMTS/2014 March 11, 2017 SMAW API 5L-Gr.B 3" 5.49 I F4 6GR/UP ALL / UP
100 MAX Max.= 20 mm Ø3"
E 7018 H4R

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


16 ZAINUDDIN HS (W-55) 6243/10.12/DMT/2013 June 12, 2016 API 5L-Gr.B 6" 14.27 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


6241/10.12/DMT/2013 June 12, 2016 API 5L-Gr.B 6" 14.27 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited
17 RUDIANSYAH ( W-56 )
E 7016-1 Min. = 5 mm POS. 6GR
2012/10.12/DMTS/2014 March 11, 2017 SMAW API 5L-Gr.B 10" 14.05 I F4 6GR/UP ALL / UP 100 MIN
Ø10"
E 7018 H4R Max. = Unlimited

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


18 ALIM BAHRI ( W-57 ) 2021/10.12/DMTS/2014 March 11, 2017 S 355 8" 12.70 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


19 ALI USMAN (W-58) 6244/10.12/DMT/2013 June 12, 2016 API 5L-Gr.B 6" 14.27 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


20 BAHARUDDIN (W-59) 6244/10.12/DMT/2013 June 12, 2016 API 5L-Gr.B 6" 14.27 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


21 HAMSAR (W-60) 6248/10.12/DMT/2013 June 12, 2016 API 5L Gr B 6" 14.27 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited
LIST OF WELDER CERTIFICATE FOR STRUCTURAL ( AWS D1.1 )

Welder Qualification Test RANGE QUALIFICATION

Base Metal Electrode


WELDER NAME and
No. Migas Certificate Validity Date REMARKS
STAMP NO. Nom Dia Thickness

Dia (Inch)

Thk.(mm)
Process Position Position
Group Group (mm) (mm)
Spec. AWS No.
No. No.

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


22 ZAM ZAM S (W-61) 6255/10.12/DMT/2013 June 12, 2016 API 5L-Gr.B 6" 14.27 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


23 HIDAYAT (W-62) 6245/10.12/DMT/2013 June 12, 2016 API 5L-Gr.B 6" 14.27 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


24 JIMI CANDRA (W-63) 6250/10.12/DMT/2013 June 12, 2016 API 5L-Gr.B 6" 14.27 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


25 SABRAN (W-64) 6246/10.12/DMT/2013 June 12, 2016 API 5L-Gr.B 6" 14.27 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


26 MULKAN (65) 6247/10.12/DMT/2013 June 12, 2016 API 5L-Gr.B 6" 14.27 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


27 ANDI AMRI (W-66) 4013/10.12/DMTS/2014 May 18, 2017 API 5L Gr B 8" 12.70 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited

GTAW ER 70S-6 F6 ALL / UP except Min. = 5 mm


28 ERWANSYAH (W-67) 4010/10.12/DMTS/2014 May 18, 2017 API 5L Gr B 8" 12.70 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited

GTAW ER 70S-6 F6 Min. = 5 mm


ALL / UP except
29 WAHID (W-68) 4011/10.12/DMTS/2014 May 18, 2017 API 5L Gr B 8" 12.70 I 6G/UP 100 Min.
TYK
SMAW E 7018 H4R F4 Max. = Unlimited

GTAW ER 70S-6 F6 Min. = 5 mm


M YUNUS ALL / UP except
30 6035/10.12/DMTS/2014 August 17, 2017 API 5L Gr B 8" 12.70 I 6G/UP 100 Min.
(W-69) TYK
SMAW E 7018 H4R F4 Max. = Unlimited
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL HEPUBLIK INDONESIA
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI
KUALIFIKASI JURU LAS
Nomor:4004 110.12IDMTS/201 4

Direktur Teknik dan Lingkungan Migas selaku Kepala lnspeksi menyatakan bahwa:

Nama :ISRAJUDDIN
Nomor Registrasi : T5-4505141112376.001
Tempat dan tanggal lahir : Bima, 01 Nopember 1976
Alamat . Jl. lr Soekarno, RT 15 Ma Jawa - Kutai Kartanegara
Perusahaan : PT. ONASIS INDONESIA
Telah dikualifikasi sebagaijuru las sesuai dengan .
Nomor WPS : OIANPS-53/AWS/08 xa
J

Nomor PQR : O|/PQR-53iAWS/08


Standar : AWS D1.1 -2010
Dengan data sebagai berikut :

Penqujian LapanEan Batasan Kualifikasi


Proses Pengelasan GTAW & SMAW GTAW & SMAW
Sifat Listrik DCSP & DCRP DCSP & DCRP
Posisi / Arah Pengelasan 6G / Naik SesuaiTabel4.l0 / Naik
Material Dasar:
- Disain sambungan Single "V" Groove Semua desain sambungan
- Diameter inch (mm) 8" (219.1 mm) Minimurn 100 mm
- Tebal (mm) 12.7 mm Minimum 5 mm
- Spesifikasi Material Uji API 5L Gr B Sesuai Tabel 3.1
Bahan Pengisi ER 70S-6 & E 7018 H4R FNo4,A5.18&FNo4,A5.1
Serbuk Pelindung Anron 99.99% Argon 99,99o/o
Backing Gas
Jenis Pemeriksaan :

- Visual X
- Radiography X
- Destructive
-MPI/PT/LIT
- Dan lain-lain

Kualifikasi Juru Las ini hanya berlaku pada perusahaan tersebut diatas sampai dengan
tanggal 18 Mei 2017. Bila dalam waktu tiga bulan secara terus menerus tidak bekerja
sesuai kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

Diuji Oleh: 2[1{


Inspektur Migas

1].}:]/:':"P'v
'NrP
196709f 2 199603 1001 198703 2001
Sert jl.AWS
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL REPUBLIK INDONESIA
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI
KUALIFIKASI JURU LAS
Nomor: 4ms 11O.12/DMTS/2014

Direktur Teknik dan Lingkungan Migas selaku Kepala lnspeksi menyatakan bahwa:

Nama : ABDUL RAUF


Nomor Registrasi : TS-2305141412483 OO1
Tempat dan tanggal lahir : Handil A, 31 Desember 1983
Alamat : Jl. Handil A, RT 06, Anggana - Kutai Kartanegara
Perusahaan : PT. ONASIS INDONESIA
Telah dikualifikasi sebagaijuru las sesuai dengan :
Nomor WPS : OIAI/PS-53/AWS/08
Nomor PQR . ot/PQR-53/AWS/08
Standar : AWS D1.1 - 2010 . a)*'
Dengan data sebagai berikut
:
'i1u e t
Penquiian Lapanqan Batasan Kualifikasi
Proses Pengelasan GTAW & SMAW GTAW & SMAW
Sifat Listrik DCSP & DCRP DCSP & DCRP
Posisi / Arah Pengelasan 6G / Nalk SesuaiTabel 4.10 / Naik
Material Dasar:
- Disain sambungan Single "V" Groove Semua desain sambunqan
- Diameter inch (mm) 8" (219,1 rnm) Minimum 100 mm
- Tebal (mm) 12,7 mm Minimum 5 mm
- Spesifikasi Material Uji API 5L Gr B Sesuai Tabel 3.1
Bahan Pengisi ER 705-6 & E 7018 H4R FNo4,A5.18&FNo4,A5.1
Serbuk Pelindung Aroon 99.99o/o Aroon 99.99o/o
Backing Gas
Jenis Pemeriksaan :

- Visual X
- Radiography X
- Destructive
.MPI/PT/UT
- Dan lain-lain

Kualifikasi Juru Las ini hanya berlaku pada perusahaan tersebut diatas sampai dengan
tanggal 18 Mei 2017. Bila dalam waktu tiga bulan secara terus menerus tidak bekerja
sesuai kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

Diuji Oleh: 0 JUN 701{


r Migas

rl. -Lr_rr r vqvslr.v


NIP 19670912 199603 1001 1987 [. ,oo,
..1
Sert.jl.AWS

,ll
KEMENTEBIAN ENERGI DAN SUMBER DAYA MINERAL REPUBLIK INDONESIA
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI
KUALIFIKASI JURU LAS
Nomor: 4006 I1O.12|DMTS/201 4

Direktur Teknik dan Lingkungan Migas selaku Kepala lnspeksi menyatakan bahwa.

Nama : ENDANG SLIHENDRA


Nomor Registrasi : TS-2705141221981.001
Tempat dan tanggal lahir : Muara Jawa, 12 Juli 1981
Alamat . Jl. Cempaka, RT 38 Rw Makmur Palaran-Samarinda
Perusahaan : PT. ONASIS INDONESIA
Telah dikualifikasi sebagaijuru las sesuai dengan
Nomor WPS : OIAI/PS-53iAWS/08 6*:*
Nomor PQR : OI/PQR-53/AWS/08
Standar : AWS D1,1 - 2010 {@rrn
Dengan data sebagai berikut : 9; s
Penquiian, Lapanqan Batasan Kualff[kasi
Proses Pengelasan GTAW & SMAW GTAW & SMAW
Sifat Listrik DCSP & DCRP DCSP & DCRP
Posisi / Arah Pengelasan 6G / Naik SesuaiTabel4.l0 / Naik
Material Dasar:
- Disain sambungan Sinole'V" Groove Semua desain sambungan
- Diameter inch (mm) 8" (219.1 mm) Minimum 100 mm
- Tebal(mm) 12,7 mm Minimum 5 mm
- Spesifikasi Material Uji API 5L GT B Sesuai Tabel 3.1
Bahan Pengisi ER 705-6 & E 7018 H4R F No 4, A 5.'18 & F No 4, A 5.1
Serbuk Pelindung Aroon 99,997o Aroon 99.99%
Backing Gas
Jenis Pemeriksaan :

- Visual X
- Radiography X
- Destructive
-MPI/PT/UT
- Dan lain-lain

Kualiflkasi Juru Las ini hanya berlaku pada perusahaan tersebut Oiaias sampai dengan
tanggal 18 Mei 2017. Bila dalam waktu tiga bulan secara terus menerus tidak bekerja
sesuai kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

Diuji Oleh: i'*Sl;n,, l]lfi run ?or{


lnspektur Migas .ftqsubi{i!. Standardisasi Migas
' 't\
" ":i
4\O llj
v
"v/
Subagio
NtP 19670912 199603 1001
Sert.jl.AWS
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL REPUBLIK INDONESIA
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI
KUALIFIKASI JURU LAS
Nomor: 4ooB l10.12IDMTS/2014

Direktur Teknik dan Lingkungan Migas selaku Kepala lnspeksi menyatakan bahwa:

Nama :PRAYITNO
Nomor Registrasi : TS-350514t291879 001
Tempat dan tanggal lahir : Kebumen, 19 Juni 1979
Alamat : Jl. MT Haryono Gg Selancar 7, RT 82 - Bontang
Perusahaan

Nomor WPS
Nomor PQR
: PT. ONASIS INDONESIA
Telah dikualifikasi sebagaijuru las sesuai dengan
otAf/PS-53/AWS/08
OI/PQR.s3/AWS/OB
.
ft
Standar . AWS D1.1 - 2010 &""'*"**
qu.$'l* * j
Dengan data sebagai berikut :

Pengujian Lapangan Batasan Kualifikasi


Proses Pengelasan GTAW & SMAW GTAW & SMAW
Sifat Listrik DCSP & DCRP DCSP & DCRP
Posisi / Arah Pengelasan 6G / Naik SesuaiTabel 4.10 / Naik
Material Dasar.
- Disain sambungan Sinole "V" Groove Semua desain sambungan
- Diameter inch (mm) 8" (219,1 mm) Minimum 100 mm
- Tebal (mm) 12.7 mm Minimum 5 mm
- Spesifikasi Material Uji API 5L Gr B Sesuai Tabel 3.1
Bahan Pengisi ER 705-6 & E 7018 H4R FNo4,A5.1B&FNo4,A5.1
Serbuk Pelindung Aroon 99.99% Arqon 99,99%
Backing Gas
Jenis Pemeriksaan :

- Visual X
- Radiography X
- Destructive
-MPI/PT/LIT
- Dan lain-lain

Kualifikasi Juru Las ini hanya berlaku pada perusahaan tersebut diatas sampai dengan
tanggal 18 Mei 2017. Bila dalam waktu tiga bulan secara terus menerus tidak bekerja
sesuai kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

Jakarta: llE $ juN 2011


Diuji Oleh: Mengetahui
lnsnl ftur Migas . Xas-Ub-di! Standardisasi Migas

Subagio an
NtP 19670912 199603 1001 198703 2001
Sert.ll.AWS
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL REPUBLIK INDONESIA
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI
KUALIFIK,ASI JURU LAS
Nomor: 4ooe l1O.12|DMTS/2014

Direktur Teknik dan Lingkungan Migas selaku Kepala lnspeksi menyatakan bahwa:

SUNYOTO
Registrasi
Nomor : TS-51 4514t121469.001
Tempat dan tanggal lahir : Kebumen, 02 Pebruari 1969
Alamat . Jl
M Hatta Handil 7, RT 13 Muara Jawa-Kutai Kartanegard
Perusahaan PT. ONASIS INDONESIA
:

Telah dikualifikasi sebagaijuru las sesuai dengan :

Nomor WPS : OIANPS-53/AWS/08


Nomor PQR or/PQ R-53/AWS/08
Standar : AWS D1.1 - 2010
Dengan data sebagai berikut :

Pengujian Lapangan Batasan Kualifikasi


Proses Pengelasan GTAW & SMAW GTAW & SMAW
Sifat Listrik DCSP & DCRP DCSP & DCRP
Posisi / Arah Pengelasan 6G / Naik Sesuai Tabel 4.10 / Naik
Material Dasar:
- Disain sambungan Sinole "V" Groove Semua desain sambungaq
- Diameter inch (mm) 8" (219,1 mm) Minimum 100 mm
- Tebal (mm) 12,7 mm Minimum 5 mm
- Spesifikasi Material Uji API 5L Gr B Sesuai Tabel 3.1
Bahan Pengisi ER 705-6 & E 7018 H4R FNo4,A5.18&FNo4,A5.1
Serbuk Pelindung Aroon 99.99o/o Argon 99,99%
Backing Gas
Jenis Pemeriksaan :

- Visual X
- Radiography X
- Destructive
.MPI/PT/LIT
- Dan lain-lain

Kualifikasi Juru Las ini hanya berlaku pada perusahaan tersebut diatas sampai dengan
tanggal 18 Mei 2017. Bila dalam waktu tiga bulan secara terus menerus tidak bekerja
sesuai kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

Diuji Oleh: Ll $ )ull 2r]1{


lnspektur Migas Migas

d;;trt
X.

2 199603 1001
Sert.jl.AWS
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL HEPUBLIK INDONESIA
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI
KUALIFIKASI JURU LAS
Nomor: 6246 nA.12lDMT 12013

Direktur Teknik dan Lingkungan Migas selaku Kepala lnspeksi menyatakan bahwa:

Nama SABRAN
Nomor Registrasi 330616/201 582.001
Tempat dan tanggal lahir Samarinda, 10 Maret 1982
Alamat Handil D RT.005 Anggana - Kutai Kartanegara
Perusahaan PT ONASIS INDONESIA
Telah dikualifikasi sebagaijuru las sesuai dengan:

Nomor WPS OI^/1/PS-53/AWS/08


Nomor PQR : O|/PQR-S3/A]Y,5l08
Standar : AWS D1.12010
Dengan data sebagai berikut

Proses pengelasan GTAW & SMA


sifat Listrik DCSP & DCRP SF & DCRP
Posisi/Arah pengelasan $esuai:table 4.10 / Naik
Material Dasar:
- Disain sambungan Sesuaidisain sambu
- Diameter inch (mm) Minimum 100 mm
- Tebal (mm) Minimum 5,0 mm
- Spesifikasi Material Uji API 5L GT B uaitable 3.1
Bahan pengisi ER 7OS€ & E 7018 H4R F No.6, SDF 5.18 & F No. 4, SFA 5.1
Serbuk pelindung
Backing Gas
Jenis Pemeriksaan .

- Visual
- Radiography
- Destructive
- MPI IPT I UT
- Dan lain-lain

Kualifikasi Juru Las ini hanya berlaku pada perusahaan tersebut diatas sampai dengan
tanggal 12 Juni 2016. Bila dalam waktu tiga bulan secara terus menbrus tidak bekerja sesuai
kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

Diuji oleh: Jakarta: 1l Y t, i(t1i


lnspelrtur Migas/ Verifikasi L .UL iurr
Pelaksana lnspeksi Tambang Migas

W--
Banaruvoto, ST
NrP 19770316 200502 1001
SertJL.aws.b
KEMENTERIAN ENERGI DAN SUMBER DAYA M!NERAL REPUBLIK INDONESIA
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI
KUALIFIKASI JURU LAS
Nomor: 6247110.121DMTl2013

DirekturTeknik dan Lingkungan Migas selaku Kepala lnspeksi menyatakan bahwa:

Nama : MULKAN
Registrasi : 370616/372385.001
Nomor
lahir : Handil D, 27 November 1985
Tempat dan tanggal
Alamat : Handil D RT.001 Anggana - Kutai Kartanegara
Perusahaan : PT ONASIS INDONESIA
Telah dikualifikasi sebagaijuru las sesuai dengan :
Nomor WPS
Nomor PQR
OI^//PS-53/AWS/08
ot/PQR-53/AWS/08
/#rLis
Standar
Dengan data sebagai berikut
AWS D1.1 2010

Penquiian Iapanqan
:$ry
Batasan"lfrfdiftlt€si
Proses pengelasan GTAW.& SMAW GTAW & SMAW
Sifat Listrik DCSP & DCRP DCSP & DCRP
Posisi/Arah pen gelasan 6G / Naik Sesuai table 4.10 / Naik
Material Dasar:
- Disain sambungan Single "V" Gtpove SesUai disain sambunqan
- Diameter inch (mm) 6', Minimum 100 mm
- Tebal (mm) 14,27 mm ,, Minimum 5,0 mm

- Spesifikasi Material Uji API 5L GT B Sesuaitable 3.1


Bahan pengisi ER 7OS€ & E 7018 H4R F No. 6, SDF 5.18 & F No. 4, SFA 5.1
Selbuk pelindung Aroon 99.99% Argon 99,99%
Backing Gas
Jenis Pemeriksaan :
- Visual X
- Radiography X
- Destructive
-MPI/PT/UT
- Dan lain-lain

Kualifikasi Juru Las ini hanya berlaku pada perusahaan tersebut diatas sampai dengan
tanggal 12 Juni 2016. Bila dalam waktu tiga bulan secara terus menerus tidak bekerja sesuai
kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

Diuii oleh: Jakarta: ,1 I lr, ,1,\)/l

lnspektur Migas/
l4 )',:'L l'J;i
Pelaksana lnspeksi Tambang Migas Standardisasi Migas

b'*"0-
Bananroto, ST
NtP 1s770316 200502 1001 198703'1002
Sert.JL.aure.b
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL REPUBLIK INDONESIA
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI
KUALIFIKASI JURU LAS
Nomor: 4oL3 11O.12/DMTS/2014

Direktur Teknik dan Lingkungan Migas selaku Kepala lnspeksi menyatakan bahwa.

Nama : ANDI AMRI


Nomor Registrasi TS-230514t151970.4O1
Tempat dan tanggal lahir : Bone, 05 Juli 1970
Alamat . Jl. BPP Handil ll RT 06 Samboja - Kutai Kartanegara
Perusahaan : PT- ONASIS INDONESIA
Telah dikualifikasi sebagaijuru las sesuai dengan :
Nomor WPS : OIANPS-53/AWS/08 3't
Nomor PQR o r/P Q R-53/AWS/08 .',
,u. t,
q:;" 1

Standar . AWS D1.1 - 2010


Dengan data sebagai berikut * M IU,I
Penquiian Lapangan Batasan Kualifikasi
Proses Pengelasan GTAW & SMAW GTAW & SMAW
Sifat Listrik DCSP & DCRP DCSP & DCRP
Posisi / Arah Pengelasan 6G / Naik SesuaiTabel4.l0 / Naik
Material Dasar:
- Disain sambungan Single "V" Groove Semua desain sambungan
- Diameter inch (mm) 8" (219,1 mm) Minimum'100 mm
- Tebal (mm) 12,7 mm Minimum 5 mm
- Spesifikasi Material Uji API 5L Gr B Sesuai Tabel 3.1
Bahan Pengisi ER 70S-6 & E 7018 H4R FNo4,A5.1B&FNo4,A5.1
Serbuk Pelindung Arson 99,99% Arqon 99,99o/o
Backing Gas
Jenis Pemeriksaan :

- Visual X
- Radiography X
- Destructive
-MPI/PT/UT
- Dan lain-lain

Kualifikasi Juru Las ini hanya berlaku pada perusahaan tersebut diatas sampai dengan
tanggal '18 Mei 2017. Bila dalam waktu tiga bulan secara terus menerus tidak bekerja
sesuai kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

Diuji Oleh: 3* JUN lnrn

i(
/ar{ Sunagio
P {9670912 199603 1001
Sert.jl.AWS
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL REPUBLIK INDONESIA
DIHEKTORAT JENDERAL MINYAK DAN GAS BUMI
KUALIFIKASI JURU LAS
Nomor: 4010 /10.1 2/DMTS/2014

Direktur Teknik dan Lingkungan Migas selaku Kepala lnspeksi menyatakan bahwa:

Nama : ERWANSYAH
Nomor Registrasi : T5-4605141142078.001
Tempat dan tanggal lahir : Pendingin, M Agustus
'1978
Alamat Jl. Pudak Baru, RT 10, Pendingin Sangasanga-Kutai
Perusahaan : PT. ONASIS INDONESIA
Telah dikualiflkasi sebagaijuru las sesuai dengan
Nomor WPS : OIANPS-53/AWS/08
Nomor PQR : O|/PQR-53/AWS/08
Standar : AWS D1.1 - 2010
Dengan data sebagai berikut
Penquiian Lapangan Batasan Kualifikasi
Proses Pengelasan GTAW & SMAW GTAW & SMAW
Sifat Listrik DCSP & DCRP DCSP & DCRP
Posisi / Arah Pengelasan 6G / Naik Sesuai Tabel 4.10 / Naik
Material Dasar:
- Disain sambungan Sinole "V" Groove Semua desain sambungan
- Diameter inch (mm) 8" (219,1 mm) Minimum 100 mm
- Tebal (mm) 12,7 mm Minimum 5 mm
- Spesifikasi Material Uji API 5L Gr B Sesuai Tabel 3.1
Bahan Pengisi ER 70S-6 & E 7018 H4R FNo4,A5,1B&FNo4,A5.1
Serbuk Pelindung Arqon 99,99% Argon 99,99%
Backing Gas
Jenis Pemeriksaan :

- Visual X
- Radiography X
- Destructive
-MPI/PT/UT
- Dan lain-lain

Kualifikasi Juru Las ini hanya berlaku pada perr-rsahaan tersebut diatas sampai dengan
tanggal 18 Mei 2017. Bila dalam waktu tiga bulan secara terus menerus tidak bekerja
sesuai kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

Jakarta: 11 0 JUN l8lt


Mengetahui
tur Migas rKas$bdit. Standardisasi Migas
y''t.r r':,,."*.,
i !:;l:
l'* \ ::f t
1, \ dr';i
\lt E Subagio
NIP 1'9670912 199603 1001 198703 2001
Sert.jl.AWS
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL HEPUBLIK INDONESIA
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI
KUALIFIKASI JURU LAS
Nomor: 4011 /1 0.1 2/DMTS/2014

Direktur Teknik dan Lingkungan Migas selaku Kepala lnspeksi menyatakan bahwa:

Nama : WA H !D
Nomor Registrasi : TS490514/111685.001
Tempat dan tanggal lahir : Pendingin, 01 April 1985
Alamat : Jl. Setia Bakti, RT 08, Pendingin Sangasanga-Kutai
Perusahaan PT. ONASIS INDONESIA
Ap'-? '
Telah dikualifikasi sebagaijuru las sesuai dengan :
{*"/-.
Nomor WPS : OlAlr/PS-53/AWS/08 j
' I',r31,'
Nomor PQR : OI/PQR-53/AWS/08 t ,.\'.y'!*'
t--*
Standar : AWS D1.1 - 2010 \',

Dengan data sebagai berikut


Penguiian Lapangan Batasan Kualifikasi
Proses Pengelasan GTAW & SMAW GTAW & SMAW
Sifat Listrik DCSP & DCRP DCSP & DCRP
Posisi / Arah Pengelasan 6G / Naik SesuaiTabel 4.10 / Naik
Material Dasar:
- Disain sambungan Sinole "V" Groove Semua desain sambungan
- Diameter inch (mm) 8" (219,1 mm) Minimum 100 mm
- Tebal (mm) 12,7 mm Minimum 5 mm
- Spesifikasi Material Uji API 5L Gr B Sesuai Tabel 3.1
Bahan Pengisi ER 705.6 & E 7O1B H4R FNo4,A5.1B&FNo4,A5.1
Serbuk Pelindung Argon 99,99% Arson 99,997o
Backing Gas
Jenis Pemeriksaan :

- Visual X
- Radiography X
- Destructive
.MPI/PT/UT
- Dan lain-lain

Las ini hanya berlaku pada perusahaan tersebut diatas sampai dengan
Kr-ralifikasi Jurr-l
tanggal 18 Mei 2017. Bila dalam waktu tiga bulan secara terus menerus tidak bekerja
sesuai kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

Diuji Oleh:
J-akarta:
. 1-1 0 JUN 1!ll

Nrp 1-9670912 199603 1001


Sert.jl.AWS
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL REPUBLIK INDONESIA

DIREKTORAT JENDERAL MINYAK DAN GAS BUMI

KUALIFIKASI JURU LAS

Nemer: 2011 /10.121DMTS/2014

Direktur Teknik dan Lingkungan Migas selaku Kepala Inspeksi menyatakan bahwa:

Nama : ABDUL RAUF


Nemer Registrasi : TS-160314/412483.001
Tempat dan tanggallahir : Handil A, 31 Desember 1983
Alamat : Handil A, Kel. Handil Terusan, Kalimantan Timur
Perusahaan : PT. ONASIS INDONESIA
Telah dikualifikasi sebaqai juru las sesuai dengan :
Nemer WPS OIIWPS-74A1AWS/13
Nemer PQR : OI/PQR-74A1AWS/13
Standar : AWS D1.1
Dengan data sebagai berikut
Pen an asi
Proses Pengelasan SMAW
Sifat Listrik DCRP
Posisi/Arah Pengelasan 6GR
Material Dasar :
- Disain Sambungan Sin Ie Bevel Sesuai disain sambun an
- Diameter inch (mm) 10" 273.05 mm Minimum 100 mm
- Tebal (mm) 15.06 mm ke 21.06 mm Minimum5mm
- Spesifikasi Material Uji API5LGr. B Sesuai Table 3.1
Bahan Pengisi E 7016-1 & E 7018-H4R F No 4, SFA 5.1 & F No 4, SFA 5.1
Serbuk Pelindung
Backing Gas
Jenis Pemeriksaan :
- Visual x
- Radiography x
- Destructive
- MPII PT I UT
- Dan lain-lain

Ku~lifikasiJuru Las ini hanya berlaku pada perusahaan tersebut diatas sampai dengan
tanggal 11 Maret 2017. Bila dalam waktu tiga bulan secara terus menerus tidak bekerja
sesuai kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

1 0 APR 2014
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL REPUBLIK INDONESIA

DIREKTORAT JENDERAL MINYAK DAN GAS BUMI

KUALIFIKASI JURU LAS


Nomor: 2012 /10.121DMTS/2014

Direktur Teknik dan Lingkungan Migas selaku Kepala Inspeksi menyatakan bahwa:

Nama : RUDIANSYAH
Nomor Registrasi : TS-300314/121678.001
Tempat dan tanggallahir : Pundak Baru, 05 Agustus 1976
Alamat : JI. Pundak baru, Kel. Pendingin, Kalimantan Timur
Perusahaan : PT. ONASIS INDONESIA
Telah dikualifikasi sebagai juru las sesuai dengan :
Nomor WPS oIIWPS-74A1AWS/13
Nomor PQR : OI/PQR-74A1AWS/13
Standar : AWS 01.1
Dengan data sebagai berikut
Pen Batasa
Proses Pengelasan SMAW SMAW
Sifat Listrik DCRP DCRP
Posisi/Arah Pengelasan 6GR Sesuai Table 4.10 / Naik
Material Dasar :
- Disain Sambungan Sin Ie Bevel Sesuai disain sambun an
- Diameter inch (mm) 10" (273.05 mm Minimum 100 mm
- Tebal (mm) 15.06 mm ke21.06 mm Minimum 5 mm
- Spesifikasi Material Uji API5LGr. B Sesuai Table 3.1
Bahan Pengisi E 7016-1 & E 7018-H4R F No 4, SFA 5.1 & F No 4, SFA 5.1
Serbuk Pelindung
Backing Gas
Jenis Pemeriksaan :
- Visual x
- Radiography x
- Destructive
- MPI / PT / UT
- Dan lain-lain

Kualifikasi Juru Las ini hanya berlaku pada perusahaan tersebut diatas sampai dengan
tanggal 11 Maret 2017. Bila dalam waktu tiga bulan secara terus menerus tidak bekerja
sesuai kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

1 0 APR 2014
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL REPUBLIK INDONESIA
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI
KUALIFIKASI JURU LAS
Nomor: 2013 /10.121DMTS/2014

Direktur Teknik dan Lingkungan Migas selaku Kepala Inspeksi menyatakan bahwa:

Nama : ENDANG SUHENDRA


Nomor Registrasi : TS-200314/242181.001
Tempat dan tanggallahir : Muara Jawa, 12 Juli 1981
Alamat : JI. Cempaka, Kel. Rawa Makmur, Kalimantan Timur
Perusahaan : PT. ONASIS INDONESIA
Telah dikualifikasi sebagai juru las sesuai dengan :
Nomor WPS OIIWPS-74AJAWS/13
Nomor PQR : OI/PQR-74AJAWS/13
Standar : AWS D1.1
Dengan data sebagai berikut
Pen asi
Proses Pengelasan SMAW
Sifat Listrik DCRP
Posisi/Arah Pengelasan 6GR
Material Dasar :
- Disain Sambungan Sin Ie Bevel Sesuai disain sambungan
- Diameter inch (mm) 10" 273.05 mm Minimum 100 mm
- Tebal (mm) 15.06 mm ke 21.06 mm Minimum5mm
- Spesifikasi Material Uji API5LGr. B Sesuai Table 3.1
Bahan Pengisi E 7016-1 & E 7018-H4R F No 4, SFA 5.1 & F No 4, SFA 5.1
Serbuk Pelindung
Backing Gas
Jenis Pemeriksaan :
- Visual x
- Radiography x
- Destructive
- MPII PT I UT
- Dan lain-lain

Kualifikasi Juru Las ini hanya berlaku pada perusahaan tersebut diatas sampai dengan
tanggal 11 Maret 2017. Bila dalam waktu tiga bulan secara terus menerus tidak bekerja
sesuai kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

10 J~ PR 2014

~ *
'8~aFW'OtO, ST.
NIP 19770316 200502 1001
Sert.jl.AWS
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL REPUBLIK INDONESIA
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI
KUALlFIKASI JURU LAS
Nomor: 2014 /10.121DMTS/2014

Direktur Teknik dan Lingkungan Migas selaku Kepala Inspeksi menyatakan bahwa:

Nama : JAWAHIRUL ABROR


Nomor Registrasi : TS-450314/321877.001
Tempat dan tanggallahir : Bojonegara, 22 Juni 1977
Alamat : JI. P. Antasari, Kel. Bukuan, Kalimantan Timur
Perusahaan : PT. ONASIS INDONESIA
Telah dikualifikasi sebagai juru las sesuai dengan :
Nomor WPS OIIWPS-74A1AWS/13
Nomor PQR : OI/PQR-74A1AWS/13
Standar : AWS 01.1
Dengan data sebagai berikut
r--~- __- - - - - - " " - ­ ---If""""BIlil"-~~------.
Pen
Proses Pengelasan SMAW
Sifat Listrik DCRP

Posisi/Arah Pengelasan 6GR

Material Dasar :
- Disain Sambungan Sin Ie Bevel Sesuai disain sambun an
- Diameter inch (mm) 10" (273.05 mm Minimum 100 mm
- Tebal (mm) 15.06 mm ke 21.06 mm Minimum5mm
- Spesifikasi Material Uji API5LGr. B Sesuai Table 3.1
Bahan Pengisi E 7016-1 & E 7018-H4R F No 4, SFA 5.1 & F No 4, SFA 5.1
Serbuk Pelindung
Backing Gas
Jenis Pemeriksaan :
- Visual x
- Radiography x
- Destructive
- MPII PT I UT
- Dan lain-lain

Kualifikasi Juru Las ini hanya berlaku pada perusahaan tersebut diatas sampai dengan
tanggal 11 Maret 2017. Bila dalam waktu tiga bulan secara terus menerus tidak bekerja
sesuai kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

1 0 APR 2014
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL REPUBLIK INDONESIA

DIREKTORAT JENDERAL MINYAK DAN GAS BUMI

KUALIFIKASI JURU LAS

Nomor: 2015/10.121DMTS/2014

Direktur Teknik dan Lingkungan Migas selaku Kepala Inspeksi menyatakan bahwa:

Nama : GABRIEL MANIK


Nomor Registrasi : TS-200314/162478.001
Tempat dan tanggallahir : Habibola, 06 Desember 1978
Alamat : Handil 5, Kec. Muara jawa, Kalimantan Timur
Perusahaan : PT. ONASIS INDONESIA
Telah dikualifikasi sebagai juru las sesuai dengan :
Nomor WPS OIIWPS-74AJAWS/13
Nomor PQR : OI/PQR-74AJAWS/13
Standar : AWS 01.1
Dengan data sebagai berikut
r--~=---""":":"'"---:~----.,..----=::---~~~",,""~--,
Pen
Proses Pengelasan SMAW
Sifat Listrik DCRP
Posisi/Arah Pengelasan 6GR
Material Dasar :
- Disain Sambungan Sin Ie Bevel Sesuai disain sambun an
- Diameter inch (mm) 10" (273.05 mm Minimum 100 mm
- Tebal (mm) 15.06 mm ke 21.06 mm Minimum 5 mm
- Spesifikasi Material Uji API5LGr. B Sesuai Table 3.1
Bahan Pengisi E 7016-1 & E 7018-H4R F No 4, SFA 5.1 & F No 4, SFA 5.1
Serbuk Pelindung
Backing Gas
Jenis Pemeriksaan :
- Visual x
- Radiography x
- Destructive
- MPII PT I UT
- Dan lain-lain

Kualifikasi Juru Las ini hanya berlaku pada perusahaan tersebut diatas sampai dengan
tanggal 11 Maret 2017. Bila dalam waktu tiga bulan secara terus menerus tidak bekerja
sesuai kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

1 0 AP R 2014

~~If(H'~tI6ardian \
~lUl-11t1i~325 198703 1002
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL REPUBLIK INDONESIA
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI
KUALIFIKASI JURU LAS
Nomor: 2016 /10.121DMTS/2014

Direktur Teknik dan Lingkungan Migas selaku Kepala Inspeksi menyatakan bahwa:

Nama : PRAYITNO
Nomor Registrasi : TS-280314/292079.001
Tempat dan tanggal lahir : Kebumen, 19 Juni 1979
Alamat : JI. MT. Haryono, Gg. Selancar 7, Kalimantan Timur
Perusahaan : PT. ONASIS INDONESIA
Telah dikualifikasi sebagai juru las sesuai dengan :
Nomor WPS OIMJPS-74A1AWS/13
Nomor PQR : OI/PQR-74A1AWS/13
Standar : AWS 01.1
Dengan data sebagai berikut
Pen Batasan asi
Proses Pengelasan SMAW SMAW
Sifat Listrik DCRP DCRP
Posisi/Arah Pengelasan 6GR Sesuai Table 4.10 I Naik
Material Dasar :
- Disain Sambungan Sin Ie Bevel $esuai disain sambun an
- Diameter inch (mm) 10" 273.05 mm Minimum 100 mm
- Tebal (mm) 15.06 mm ke 21.06 mm Minimum5mm
- Spesifikasi Material Uji API5LGr. B Sesuai Table 3.1
Bahan Pengisi E 7016-1 & E 7018-H4R F No 4, SFA 5.1 & F No 4, SFA 5.1
Serbuk Pelindung
Backing Gas
Jenis Pemeriksaan :
- Visual x
- Radiography x
- Destructive
- MPII PT I UT
- Dan lain-lain

Kualifikasi Juru Las ini hanya berlaku pada perusahaan tersebut diatas sampai dengan
tanggal 11 Maret 2017. Bila dalam waktu tiga bulan secara terus menerus tidak bekerja
sesuai kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

*
~"A1t)1bto,
ST.
NI 197703162005021001
Sert.jI.AWS
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL REPUBLIK INDONESIA
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI
KUALlFIKASI JURU LAS
Nomor: 2017 /10.121DMTS/2014

Direktur Teknik dan Lingkungan Migas selaku Kepala Inspeksi menyatakan bahwa:

Nama : SYARIFUDIN
Nomor Registrasi : TS-300314/121678.001
Tempat dan tanggallahir : Serang, 02 April 1978
Alamat : JI. Pudak Baru, Kel. Pendingin, Kalimantan Timur
Perusahaan : PT. ONASIS INDONESIA
Telah dikualifikasi sebagai juru las sesuai dengan :
Nomor WPS OIIWPS-74AJAWS/13
Nomor PQR : OIlPQR-74AJAWS/13
Standar : AWS 01.1
Dengan data sebagai berikut
Pen Batasan si
Proses Pengelasan SMAW SMAW
Sifat Listrik DCRP DCRP
Posisi/Arah Pengelasan 6GR Sesuai Table 4.10 I Naik
Material Dasar :
- Disain Sambungan Sin Ie Bevel Sesuai disain sambun an
- Diameter inch (mm) 10" 273.05 mm Minimum 100 mm
- Tebal (mm) 15.06 mm ke 21.06 mm Minimum 5mm
- Spesifikasi Material Uji API5LGr. B Sesuai Table 3.1
Bahan Pengisi E 7016-1 & E 7018-H4R F No 4, SFA 5.1 & F No4, SFA 5.1
Serbuk Pelindung
Backing Gas
Jenis Pemeriksaan :
- Visual x
- Radiography x
- Destructive
- MPII PT I UT
- Dan lain-lain

Kualifikasi Juru Las ini hanya berlaku pada perusahaan terse but diatas sampai dengan
tanggal 11 Maret 2017. Bila dalam waktu tiga bulan secara terus menerus tidak bekerja
sesuai kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

1 0 APR 20M
KEMENTERIAN ENERGI DAN SUMBER DAYAMINERALREPUBLIK INDONESIA

DIREKTORAT JENDERAL MINYAK DAN GAS BUMI

KUALIFIKASI JURU LAS


Nomor: 2019 /10.121DMTS/2014

Direktur Teknik dan Lingkungan Migas selaku Kepala Inspeksi menyatakan bahwa:

Nama : SUPIANSYAH
Nomor Registrasi : TS-460314/182186.001
Tempat dan tanggallahir : Handil A, 8 September 1986
Alamat : Handil A, Kel. S. Mariam, Kalimantan Timur
Perusahaan : PT. ONASIS INDONESIA
Telah dikualifikasi sebagai juru las sesuai dengan :
Nomor WPS OIIWPS-74A1AWS/13
Nomor PQR : OIlPQR-74A1AWS/13
Standar : AWS D1.1
Dengandatasebagaiberik~u~t~~~~~~~~~~~~~~~~~~~~~~
Pen angan
Proses Pengelasan SMAW
Sifat Listrik DCRP
Posisi/Arah Pengelasan 6GR
Material Dasar :
- Disain Sambungan Sin Ie Bevel Sesuai disain sambun an
- Diameter inch (mrn) 10" (273.05 mm) Minimum 100 mm
- Tebal (mm) 15.06 mm ke 21.06 mm Minimum 5 mm
- Spesifikasi Material Uji API 5LGr. B Sesuai Table 3.1
Bahan Pengisi E 7016-1 & E 7018-H4R F No 4, SFA 5.1 & F No 4, SFA 5.1
Serbuk Pelindung
Backing Gas
Jenis Pemeriksaan :
- Visual x
- Radiography x
- Destructive
- MPII PT I UT
- Dan lain-lain

Kualifikasi Juru Las ini hanya berlaku pada perusahaan tersebut diatas sampai dengan
tanggal 11 Maret 2017. Bila dalam waktu tiga bulan secara terus menerus tidak bekerja
sesuai kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

1 0 APR 2014

~) .
:s: .C"l
~/j;.
~~tfMt~Bardian
~lJP1JdMl325 198703 1002
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL REPUBLIK INDONESIA

DIREKTORAT JENDERAL MINYAK DAN GAS BUMI

KUALlFIKASI JURU LAS

Nomor: 2020 /10.121DMTS/2014

Direktur Teknik dan Lingkungan Migas selaku Kepala Inspeksi menyatakan bahwa:

Nama : SYAHRANI
Nomor Registrasi : TS-310314/192182.001
Tempat dan tanggal lahir : Muara Jawa, 09 September 1982
Alamat : JI. Pudak Baru, Kel. Pendingin, Kalimantan Timur
Perusahaan : PT. ONASIS INDONESIA
Telah dikualifikasi sebagai juru las sesuai dengan :
Nomor WPS OIIWPS-74A1AWS/13
Nomor PQR : OI/PQR-74A1AWS/13
Standar : AWS 01.1
Dengan data sebagai berikut
Pen Batasa
Proses Penqelasan SMAW SMAW
Sifat Listrik DCRP DCRP
Posisi/Arah Pengelasan 6GR Sesuai Table 4.10 I Naik
Material Dasar :
- Disain Sambungan Sin Ie Bevel Sesuai disain sambun an
- Diameter inch (mm) 10" 273.05 mm Minimum 100 mm
- Tebal (mm) 15.06 mm ke 21.06 mm Minimum5mm
- Spesifikasi Material Uji API5LGr. B Sesuai Table 3.1
Bahan Pengisi E 7016-1 & E 7018-H4R F No 4, SFA 5.1 & F No 4, SFA 5.1
Serbuk Pelindung
Backing Gas
Jenis Pemeriksaan :
- Visual x
- Radiography x
- Destructive
- MPII PT I UT
- Dan lain-lain

Kualifikasi Juru Las ini hanya berlaku pada perusahaan tersebut diatassampai dengan
tanggal 11 Maret 2017. Bila dalam waktu tiga bulan secara terus menerus tidak bekerja
sesuai kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

1 0 APR 2014

~,JtiIj(djij9Jj/6ardian\
~~~10325 198703 1002
KEMENTERIAN ENERGI DAN SUMBER DAVA MINERAL REPUBLIK INDONESIA
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI
KUALlFIKASI JURU LAS

Nomor: 2030/10.121DMTS/2014

Direktur Teknik dan Lingkungan Migas selaku Kepala Inspeksi menyatakan bahwa:

Nama : GABRIEL MANIK


Nomor Registrasi : TS-200314/162478.001
Tempat dan tanggallahir : Habibola, 06 Desember 1978
Alamat : Handil 5, Kec. Muara jawa, Kalimantan Timur
Perusahaan : PT. ONASIS INDONESIA
Telah dikualifikasi sebagai juru las sesuai dengan :
NomorWPS OIIWPS-74A1AWS/13
Nomor PQR : OllPQR-74A1AWS/13
Standar : AWS 01.1
Dengan data sebagai berikut
Pen
Proses Pengelasan SMAW
Sifat Listrik DCRP
PosisilArah Pengelasan 6GR
Material Dasar :
- Disain Sambungan Sesuai disain sambun an
- Diameter inch (mm) Maksimum 100 mm
- Tebal (mm) Minimum3mm
- Spesifikasi Material Uji Sesuai Table 3.1
Bahan Pengisi F No 4, SFA 5.1 & F No 4, SFA 5.1
Serbuk Pelindung
Backing Gas
Jenis Pemeriksaan :
- Visual x
- Radiography x
- Destructive
- MPII PT I UT
- Dan lain-lain

Kualifikasi Juru Las ini hanya berlaku pada perusahaan tersebut diatas sampai dengan
tanggal 11 Maret 2017. Bila dalam waktu tiga bulan secara terus menerus tidak bekerja
sesuai kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.
KEMENTERIAN ENERGI DAN SUMBER DAVA MINERAL REPUBLIK INDONESIA

DIREKTORAT JENDERAL MINYAK DAN GAS BUMI

KUALIFIKASI JURU LAS


Nomor: 2031 /10.121DMTS/2014

Direktur Teknik dan Lingkungan Migas selaku Kepala Inspeksi menyatakan bahwa:

Nama : PRAVITNO
Nomor Registrasi : TS-280314/292079.001
Tempat dan tanggallahir : Kebumen, 19 Juni 1979
Alamat : JI. MT. Haryono, Gg. Selancar 7, Kalimantan Timur
Perusahaan : PT. ONASIS INDONESIA
Telah dikualifikasi sebagai juru las sesuai dengan :
Nomor WPS OIIWPS-74A1AWS/13
Nomor PQR : OI/PQR-74A1AWS/13
Standar : AWS 01.1
Dengan data sebagai berikut
Pen Batas*
Proses Pengelasan SMAW SMAW
Sifat Listrik DCRP DCRP
Posisi/Arah Pengelasan 6GR Sesuai Table 4.10 I Naik
Material Dasar :
- Disain Sambungan Sesuai disain sambungan
- Diameter inch (mm) Maksimum 100 mm
- Tebal (mm) Minimum3mm
- Spesifikasi Material Uji Sesuai Table 3.1
Bahan Pengisi F No 4, SFA 5.1 & F No 4, SFA 5.1
Serbuk Pelindung
Backing Gas
Jenis Pemeriksaan :
- Visual x
- Radiography x
- Destructive
- MPII PT I UT
- Dan lain-lain

Kualifikasi Juru Las ini hanya berlaku pada perusahaan terse but diatas sampai dengan
tanggal 11 Maret 2017. Bila dalam waktu tiga bulan secara terus menerus tidak bekerja
sesuai kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

1 0 APR 2014

~~~=~
f(j
Bannan \
80325 19870B 1002
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL REPUBLIK INDONESIA

DIREKTORAT JENDERAL MINYAK DAN GAS BUMI

KUALIFIKASI JURU LAS

Nomor: 2032 /10.121DMTS/2014

Direktur Teknik dan Lingkungan Migas selaku Kepala Inspeksi menyatakan bahwa:

Nama : SYARIFUDIN
Nomor Registrasi : TS-300314/121678.001
Tempat dan tanggal lahir : Serang, 02 April 1978
Alamat : JI. Pudak Baru, Kel. Pendingin, Kalimantan Timur
Perusahaan : PT. ONASIS INDONESIA
Telah dikualifikasi sebaqai juru las sesuai dengan :
Nomor WPS OIIWPS-74A1AWS/13
Nomor PQR : OIlPQR-74A1AWS/13
Standar : AWS 01.1
Dengan data sebagai berikut
Pen Batasa
Proses Pengelasan SMAW SMAW
Sifat Listrik DCRP DCRP
Posisi/Arah Pengelasan 6GR Sesuai Table 4.10 I Naik
Material Dasar :
- Disain Sambungan Sesuai disain sambun an
- Diameter inch (mm) Maksimum 100 mm
- Tebal (mm) Minimum3mm
- Spesifikasi Material Uji Sesuai Table 3.1
Bahan Pengisi F No 4, SFA 5.1 & F No 4, SFA 5.1
Serbuk Pelindung
Backing Gas
Jenis Pemeriksaan :
- Visual x
- Radiography x
- Destructive
- MPII PT I UT
- Dan lain-lain

Kualifikasi Juru Las ini hanya berlaku pada perusahaan tersebut diatas sampai dengan
tanggal 11 Maret 2017. Bila dalam waktu tiga bulan secara terus rnenerus tidak bekerja
sesuai kualifikasinya maka Kualifikasi Juru Las ini dianggap tidak berlaku lagi.

Diuji Oleh: 1 0 APR 2014


In tur Migas/
~~~i\\a Inspeksi Tambang Migas

Banarwoto, ST. ~~~~aardian I

NIP 197703162005021001 ,.;;-N~um325 198703 1002

Sert.jI.AWS
ATTACHMENT 5
WELDING MAP & NDT PLAN
OE "l
:t
i
I
{ s
9i I
E s {
=r: = :
I 5 E
a
; .\
3
E E > EI
di:a;: i;38
a6 \+
I E ;339:1.; ;-=69;:r 6 A - 4 ; 6
xi;: 3;1 4 3 6 I I 8
-1-1a t' 1 : ; - j c e
o
a =
t s
?l
I
a i J{i F- g l'd H, i'
-l tr "' e
1&
f e :.: x 9.:1 it
I o
.
5',- ;--- b b b b
i*
c" i*c" rta" s*s" F*
I
l9 d' 'E)
; =
!)
s"'g g"E E"'E g"g
t
:l
I sd
g,e E,c. E",E" s"'E" 6
3
EI
1 { {
cl
9- 9d - 9d 9-
z PF5 ,n.
PE5 Er,. E5 355 6:S
J
- o
E'- j'E5 B: =s
..i- ga Ed
o- I o
F EI
d
zo I
o
06
o. ^^-t I 9
iE
E
= FE
zo le
E
a
(,
o
t6
J
uJ

6 214
6 eoR
$;isE EEi
3 E sR
e
= o :.;
ii :..] 'i
=
tr Etrtr o
r' gl i;- :;
;,= 5; EE :- ;; Eg :-s :$
I!FIE:i
i'9- >>>ini
EtsE3,
3 :t-*{tt
}3t92>
39: =B
Oo
IE 3
li ;,
i!_
t,
Be_
=3 e
gs
=9 :: ts
,e P-
aY
tg- r6 :; i3* E= E8 E;
IEL :3 __2
1
:raii
I ri !
i
I| $e
2e *:s :s! ssI
3
I E EE
I
ls g i o b o i, E F H g^h
q ?8ec E^e
? o
Ig E; A sE !.,'il Pi e c = r:E ,I--e
t8I + e:
E
g a= -
lE$iiE = ?2 isE a..E 8Pp E,", E,"F E a q
6GOo6a60oo
K- K. :inX :i4R {< ai
i-
*r
-l 1 :
ci
i:;:
r=E .
t
!z - 3a
E! E g* !";
. : .] : .
. 't-a= : ..- r::-l 0
= a4:a =
;ji: ;= E=: a=...j
= : :-ts :!;=-
=:=: =-==
zr--= ;
.: :::E
;!=j -Er,:-== ===
==a=
l=-
= :-=je
-aja!:
. E+ a
a r.--==:--E : -::
;" r_ ;--i:
'-"'- a - -'-':a
- ir.
';t: r ..:='-.-
=, -^
:_!t . : ! !
P
@.
<-<>
!,, !
€)
s a ,-.
i;*./ ar t
E
\
9
(
:B
,{
P

-,]
@
Z
a
t .....".,.
t
n@
=
P'
7
@
IFI i.
E
:-!
)-.,
-E*
I
2
E
:
'",1
?
dG)
: :: :::j:
--:
==::: :!]j..
i .-'
=.:]-;-::n:
i -=:= Er.'::: 95 9 :
= ?!==
a ==ii
!= i :E1! ==3P
i!:: .-. +P: :: -:
: : =i: = i9
1 = :;1: E-=! i.:.
'': ,g rE -: :
!!.. Ea 4
zY: 3!
Ez'.:i:; -
:: .
=i===,i =d+=
. D2 i
: ::: .:_
:=:r_ii::6:.:-E .
- .; ::
o! ]':
/a\ \G,J
\g
e
q7
)
, J,
l-: "
.
!
a
:: l:::- : :
_.=..
.,4-,, -:-a=.-::' .
!!,t - <
=
1
;:5
= = i i=i- a>az
z
'=:- -a
.;3= < it;=
=5lc= E1
z
=;5 -:e>s;
"=1-=
:= * <
- i=1i-
-ia> qa:i=q : iN
= i : =:== -r:i:=
:6aF.- -z-==- :a-_o+
=Elp-6 -1
a=d ==1==-
a
<t
:= = =6;==-
=-!i:: =<;;=:
'--_4^,J
--<-Jq .,==6!J
=+!
--=
:s=-:=:g=i4
=E:
=6q=aa
.u<a+
=
? a ,=io><5
-di:; =2
, 3::: F; e-l===4
=q===-
>u-s-==
;3E94=A+a=
i;oo=at 6== 6
=
=oo
a--:
a:< -
-'==:>
*.^.-2
9-"-i='
i>Yu-
ca-_]l-E:r
q!
I € 'J9 9 f --=
==
ia:_3;:33E.3-:===:E1 =-r+E<<=ts=
.a==a
+ r' j
J6\ . /'a'
/;-\a) = \ts1
P e
I
=
TA
o(1
fr-i+ L rl-i
i {-
I\ l-
u=
=;
a.
il
Il-T
i
1----=E i
t-\
I P
>s
e
t
o
o
l'
I

^3
- =*
L!= 4e
--
G -l
:l:. 1
I

;
E

{
+E
::* I E
-l
| .9
.$ $ E : E : : ;
s
3 Hl
9:l
;; I
F : ct s
- E
T > EI
!r ES
I E
'6

frGTT {*GG
iSBS rE S
;li: i.';:
-3
F
;
:
P
:
P
I
g\ F o
D
;
l'tg
I
g
.l gdH s :.dH
t
I i i
6l = =
nl n P\E
)&
g
{
A
4 '= I:l
* :-i '
T:" li
i :-F :
:
I d
FE 9
d
-= I
t
B
B
_g_
z
J
o-
T -9 I
9
F
o
z ! I
ca
o- 9 I
E !
tsE
zo
EI
o 6
.=
!
o sl RERi I
I"1<* i : ; : E i
J 6
-t
gl
l,lJ
el B o I* -\
= e <aa
!!. -!y E9 g B
tr Etrf = ii- il :{ ;E ig ?! !t
;; e: ;;' :' ;;- :' -i !t
-i
-i
:
s<{
=;3 ;*;:i
s-ahFfi
E rar
alB
rf33x.
3:Ei3
ajo6'6o-
a
;;
z E.
: _*,
EL]
SJ
nll tr : 9 s ees :e! ss$
3
E Bi
44 ,I ! RP g"e
o e"e h"e ! :q 3 i.+ ;=^g
EESg:
<6
g o= Eig s'E q E E"i '"R
J="E
;si iFt E
3,"3 :,"3 ieE 3ea' ;':! i A i
:E'; 5i!iLro5o,!
lsol
l:=€
o

ffit!nrrl
Jr:
-
E ! E g: f"o
.:- ...
_a
a=..= =
:!.=
:: -=> <L.:t !
!
== I
5=q
>=: :== ;t=i.:O
F =;=i
+=
=e =
= >!?6=- :s
>>: oa 5= =5i
g=; f [=,.:=
i
=5 2 =
La tl
=< =l.j+-l= ->ia
--= 6_
-!!
ie --i;=
;;-
d.
uJ 9E< a-, =+ 33i 5=l?=: - -
<;
lE .d I
z
LIJ
(, =qq =^4=a->>
E= g=+====:az=tr: '-ul
* IE
e-i= '.2\2A=iar= e9
I
=2 = I
::;e::-i=
5> E-=-E==E 4i=3aqe54EtE
gEij=6<<=5>:- F
=E:k*is
.in;
/;\
rz€/
a
^2
.t vl----
,--
!
a") c-:
"5 t-
l
g
P: t- s
(9
o
=
zLrl
z
o
\--7 FF
L:=::=:)
t/
e -t-_-__-___l I
4 \") e
*H E :rH
g'
( i f=-!
(s
:
n'<a)
a +tY)
11
B
t-=
t;
--z
i-6:i
5
o =;g i
z G. f,-
irr
I
* L=;a
al ii i-;I
EI
-I; 6 o- : EE,
;;5'
i
ln El=
a =9
-.:/3r Pld
al+ k
t- E
Er
EI:
-A
a
-_, .= I.ii.: :i::= :i ,. '.1: i
'---
=
.
I i :: _:li= >: i- 1
-_ I - =i=+
:
--
.=>
;,_.1 ::
5:_ ;E
:I i. )+=?
=-;=
=-;i a=42
=j+i 4 '2= :n
;=
F 2- -:ii _ 6E
?a]] ;=
= : ;iPg ;1== ? ;;B <: z=
-= = a6?:
< = \. jX-= 4g; !>
"a HE
EN
6[
6. 9 :e ^=4a =;=!=1
/tr6:>e
9?
.;1;
| i^+= ?=i -s_ 6 <:
z = - -= :--:>
i )6=;- 2a =- - -t :6:
l31Ei;
;=
.;
(, -
-:a=
= =
ii=-== ===
4:= 4=
= t*= =;:=!i
=i=il9 =i:!;= a?3=r=
==EIi; -r==1=
3-=
= ====+<
i-====E==-E
j :: 5i=:=:
=Zi=1
I
== -i, ;== - = 3 o-; - = =.
G 1i < i-
= =i
--r /S
l- e
: :
o
aili-, -
a
!
E
t E
e
o
4
O
I
!
e 1
l:
)l <t
?!
----L i! k
L: = i-i
"a-\
I :t..
I=:::'-
..]:
: : i-:i:
-
-<: :==
=_, =
=
>
= =-=i
=:ra= =a= =;= i>
i,i .-, a i ;=<; -+:;
i^ > 2 : ?E== =
= -= = =-E!
= q?P=
' + E g < ts < 5 >.-
.- - q5>= iE?=; = EN B
==
s;=2;"== =d=
q= 1>
= B
> aal2 s<:-
E = a E #;-- - -
e
E
= ;= ;Jo2<E
=:?-t? .=€aa<h =:;- p4=E==;==
y=i --!=;i;;
>e
UE
=
z= ;-eB3EE oz
z .= <!-i':== -!.=9r=i-{=
=====:=:z:i,- "i
z
4==
= 4==*U?v =9-EY54(!5===
!.-a€-'99=-'=-H
=:.i=4=;;-=
5=i=;=ee!. ,+-:E!a-+==3sts<<=;>-: :
-i6i;+ d
3
t------_
v
fr; <.
i OH
:-3"
oa
tO
nc.
^"e O
=<
!'A
i <g -
/ - o=
[? E=
i:
A,
ATTACHMENT 6
DAILY VISUAL INSPECTION
DAILY VISUAL INSPECTION

JOB TITLE :
CLIENT :
CONTRACT No. :
ITEM No. :
DRAWING No. :

MATERIAL USED
WELD FIT UP WELDING WELDER
Identification REMARKS
NO. TYPE SIZE SCH/THK (mm)/RATING STAMP
Heat No / Mirc DATE GAP DATE VIS

Reported By, Reviewed By, Reviewed By, Note :

Sign : Sign : Sign :

Date : Date : Date :

WELDING INSPECTOR ECP / QSE / OPS ENG / CST / OPT


ATTACHMENT 7
WELDING LOG
WELDING LOG

Project :
Client :
Contract No. :
ITEM No. :
Drawing No. :

MATERIAL USE
WELDER PRE INTER
FIT UP

WELD PWHT
TYPE SIZE WPS NO. Vis Date HEAT PASS REMARKS
NO MATERIAL °C
SPECIFICATION NAME NO. °C °C
Ø (INCH) THK. (mm)

Reported by, Reported by, Note :

Sign : Sign :

Date : Date :

WELDING INSPECTOR ECP / QSE / OPS