You are on page 1of 2

Document No.

Updated Document Title


A-QAC-PRO-730-38944 MONITORING AND MEASURING EQUIPMENT CONTROL PROCEDURE
A-MTL-PRO-730-38931 pWPS FOR COLUMN PIPE TO COLUMN PIPE AND 10 INCH DIA. PIPE TO PIPE WELDING WITH GTAW + SMAW PROCESS
A-MTL-PRO-730-38932 pWPS FOR STAINLESS STEEL PIPING OF <2" WITH GTAW PROCESS
A-MTL-PRO-730-38933 pWPS FOR STAINLESS STEEL PIPING OF >2" WITH GTAW+SMAW PROCESS
A-MTL-PRO-730-38934 pWPS FOR STAINLESS STEEL TO CARBON STEEL MATERIAL WELDING WITH GTAW PROCESS
A-MTL-PRO-730-38935 pWPS FOR STAINLESS STEEL TO CARBON STEEL MATERIAL FILLET WELDING WITH SMAW PROCESS
A-MTL-PRO-730-38936 PQR FOR CROWN TO PETAL AND PETAL TO PETAL WELDING WITH SMAW PROCESS
A-MTL-PRO-730-38937 PQR FOR COLUMN PIPE TO COLUMN PIPE AND 10 INCH DIA. PIPE TO PIPE WELDING WITH GTAW + SMAW PROCESS
A-MTL-PRO-730-38938 PQR FOR STAINLESS STEEL PIPING OF <2" WITH GTAW PROCESS
A-MTL-PRO-730-38939 PQR FOR STAINLESS STEEL PIPING OF >2" WITH GTAW+SMAW PROCESS
A-MTL-PRO-730-38940 PQR FOR STAINLESS STEEL TO CARBON STEEL MATERIAL WELDING WITH GTAW PROCESS
A-MTL-PRO-730-38941 PQR FOR STAINLESS STEEL TO CARBON STEEL MATERIAL FILLET WELDING WITH SMAW PROCESS
A-MTL-PRO-730-38942 WPS FOR CROWN TO PETAL AND PETAL TO PETAL WELDING WITH SMAW PROCESS
A-MTL-PRO-730-38943 WPS FOR COLUMN TO BASE PLATE, CROSS BRACING AND NOZZLE ASSEMBLY WELDING WITH SMAW PROCESS
A-MTL-PRO-730-38944 WPS FOR COLUMN PIPE TO COLUMN PIPE AND 10 INCH DIA. PIPE TO PIPE WELDING WITH GTAW + SMAW PROCESS
A-MTL-PRO-730-38945 WPS FOR STAINLESS STEEL FILLET WELDS WITH SMAW PROCESS
A-MTL-PRO-730-38946 WPS FOR STAINLESS STEEL PIPING OF <2" WITH GTAW PROCESS
A-MTL-PRO-730-38947 WPS FOR STAINLESS STEEL PIPING OF >2" WITH GTAW+SMAW PROCESS
A-MTL-PRO-730-38948 WPS FOR STAINLESS STEEL TO CARBON STEEL MATERIAL WELDING WITH GTAW PROCESS
A-MTL-PRO-730-38949 WPS FOR STAINLESS STEEL TO CARBON STEEL MATERIAL FILLET WELDING WITH SMAW PROCESS
A-QAC-CER-730-38928 WELDER/ WELDING OPERATOR QUALIFICATIONS
A-CON-PRO-730-38930 PROCEDURE FOR ERECTION AND TESTING OF SITE ERECTED 3 CS STORAGE TANKS & SPHERES BY CONVENTIONAL
A-CMM-PRO-730-38926 METHOD
SITE (if applicable)
ACCEPTANCE TEST PROCEDURE
A-QAC-PRO-730-38945 MATERIAL IDENTIFICAITON AND TRACEABILITY PROCEDURE
A-QAC-PRO-730-38946 BASE LINE THICKNESS MEASUREMENT PROCEDURE
A-QAC-MAN-730-38928 CONSTRUCTION RECORD BOOK
A-CON-PRO-730-38931 SPHERE MATERIAL LIFTING PROCEDURE (includes lifting beam, frame, slings)
A-RHU-ORG-730-38926 CVS OF KEY PERSONNEL
A-RHU-ORG-730-38927 ALL INSURANCES (WORKMEN’S COMPENSATION, PLANT, CONSTRUCTION EQUIPMENT AND ALL RISKS
A-PLN-SCH-730-38928 INSURANCE,
L4 SCHEDULEMOTOR VEHICLE INSURANCE
WITH COMPLETE PLANNING INCLUDING THIRD PARTY
PACKAGE INCLUDING AND PASSENGER
RESOURCE LOADING LIABILITY, ETC.)
A-CON-PRO-730-38932 MS FOR ERECTION & WELDING OF SPHERICAL TANKS (730-TK-03 A/B & C)
A-CON-PRO-730-38933 MS FOR ERECTION & WELDING OF NOZZLES (730-TK-03 A/B & C)
A-CON-PRO-730-38934 MS FOR ERECTION & WELDING OF STAIRWAY ACCESS AND TOP PLATFORM
A-CON-PRO-730-38935 MS FOR ERECTION OF SCAFFOLDING ACCESS PLATFORM FOR BLASTING, PAINTING & INSULATION WORKS
A-CON-PRO-730-38936 MS FOR STRUCTURAL ERECTION OF SUPPORT COLUMN & DIAGONAL BRACINGS
A-CON-PRO-730-38937 MS FOR ERECTION OF INSULATION WORKS OF SPHERICAL TANKS (730-TK-03 A/B & C)
A-CON-PRO-730-38938 MS FOR BLASTING AND PAINTING OF SPHERICAL TANKS (730-TK-03 A/B & C)
A-CON-PRO-730-38939 MS FOR HYRDO PNEUMATIC TESTING OF SPHERICAL TANKS (730-TK-03 A/B & C)
A-CON-PRO-730-38940 MS FOR ERECTION OF SPHERICAL TANKS INTERNAL PIPING
A-CON-PRO-730-38941 MS FOR HYDROTEST OF INTERNAL PIPING CONNECTIONS & FIRE FIGHTING SYSTEM
A-CON-PRO-730-38942 MS FOR ERECTION AND WELDING OF SPHEROCAL TANKS FIRE & FIGHTING SYSTEM
A-PLN-PLN-730-38926 MANPOWER MOBILIZATION PLAN
A-QAC-PLN-730-38926 PROJECT QUALITY PLAN FOR SPHERE CONSTRUCTION
A-QAC-PRO-730-38926 PROCEDURE FOR CALIBRATION OF WELDING EQUIPMENTS
A-MTL-PRO-730-38931 PROCEDURE FOR WELDING CONSUMABLE CONTROL
A-MTL-PRO-730-38932 INSPECTION AND TEST PLAN FOR INSTALLATION AND TESTING OF SPHERES
A-MTL-PRO-730-38933 WELDING REPAIR PROCEDURE
A-MTL-PRO-730-38934 PICKLING AND PASSIVATION PROCEDURE
A-CST-PRO-730-38926 INVOICING AND PAYMENT PROCEDURE
A-PLN-SCH-730-38926 OVERALL SPHERE SCHEDULE - PDF
A-PLN-SCH-730-38927 OVERALL SPHERE SCHEDULE - EXCEL
A-MTL-PRO-730-38927 pWPS FOR CROWN TO PETAL AND PETAL TO PETAL WELDING WITH SMAW PROCESS
A-MTL-PRO-730-38928 MATERIAL CONTROL AND TRACEABILITY PROCEDURE
A-QAC-PRO-730-38928 WELDING CONTROL PROCEDURE
A-MTL-PRO-730-38929 WELD LOCATION PLAN
A-QAC-PRO-730-38930 HYDROSTATIC TESTING AND DRYING PROCEDURE OF SPHERES
A-QAC-PRO-730-38931 PROCEDURE FOR SPHERE CALIBRATION
A-QAC-CER-730-38926 NDE OPERATOR QUALIFICATIONS
A-CMM-PRO-730-38926 GALVANISING REPAIR PROCEDURE FOR STRUCTURAL STEEL COMPONENTS
A-MTL-PRO-730-38930 SURFACE PREPARATION AND PAINTING PROCEDURE
A-QAC-PRO-730-38937 PROCEDURE FOR RADIOGRAPHY TESTING (RT)
A-QAC-PRO-730-38938 PROCEDURE FOR MAGNETIC TESTING (MT)
A-QAC-PRO-730-38939 PROCEDURE FOR ULTRASONIC TESTING (UT) (if applicable)
A-QAC-PRO-730-38940 PROCEDURE FOR PENETRANT TESTING (PT)
A-QAC-PRO-730-38941 PROCEDURE FOR HARDNESS TESTING (HT)
A-QAC-PRO-730-38942 PROCEDURE FOR POSITIVE MATERIAL IDENTIFICATION (PMI)
A-QAC-CER-730-38927 MATERIAL,WELDING AND NDE TEST SUMMARY OF COMPLETE SPHERE
A-QAC-DOS-730-38927 ARH FINAL DOSSIER
A-LGT-PRO-730-38927 PRESERVATION PROCEDURE
A-CON-PRO-730-38929 CONSTRUCTION METHOD STATEMENT
A-PLN-MRE-730-38927 MONTHLY PROGRESS REPORT
A-HSE-PRO-730-38926 PLANT & EQUIPMENT SAFETY PROCEDURE
A-HSE-PRO-730-38928 GROUND DISTURBANCE PROCEDURE
A-HSE-PRO-730-38929 MANAGEMENT OF HSSE RECORDS
A-HSE-LST-730-38926 DRUM ROLLER PRE-USE INSPECTION CHECKLIST
A-HSE-LST-730-38927 EXCAVATOR PRE-USE INSPECTION CHECKLIST
A-HSE-LST-730-38928 FORKLIFT PRE-USE INSPECTION CHECKLIST
A-HSE-LST-730-38929 MANLIFT PRE-USE INSPECTION CHECKLIST
A-HSE-LST-730-38930 MOBILE CRANE PRE-USE INSPECTION CHECKLIST
A-HSE-LST-730-38931 SCISSOR LIFT PRE-USE INSPECTION CHECKLIST
A-HSE-LST-730-38932 SIDE BOOM PRE-USE INSPECTION CHECKLIST
A-HSE-LST-730-38933 SKID STEER LOADER PRE-USE INSPECTION CHECKLIST
A-HSE-LST-730-38934 WHEEL LOADER PRE-USE INSPECTION CHECKLIST
A-HSE-PLN-730-38926 HSSE MANAGEMENT PLAN
A-LGT-PRO-730-38929 LAND TRANSPORT MANAGEMENT PROCEDURE
A-HSE-PRO-730-38930 RISK ASSESSMENT PROCEDURE

You might also like