TECHNICAL BID EVALUATION

FOR CARBON STEEL WELDED


BANGGAI AMMONIA FITTINGS (3RD MTO) Doc no : BAP-00-36-EB-0034-R
PLANT PROJECT Project No : 15-1802
Rev. No.: 0 Page 2 / 9

REVISION CONTROL SHEET

REV. DATE DESCRIPTION


0 July 25, 2016 Issue for Purchase
TECHNICAL BID EVALUATION
FOR CARBON STEEL WELDED
BANGGAI AMMONIA FITTINGS (3RD MTO) Doc no : BAP-00-36-EB-0034-R
PLANT PROJECT Project No : 15-1802
Rev. No.: 0 Page 3 / 9

TABLE OF CONTENT

1. GENERAL………………………………………………………………………………… 4
2. TECHNICAL BID EVALUATION……………………………………………………….. 6
3. RECOMMENDATION…………………………………………………………………… 8

Attachment – 1: Technical Bid Evaluation for Carbon Steel Welded Fittings (3rd MTO)
TECHNICAL BID EVALUATION
FOR CARBON STEEL WELDED
BANGGAI AMMONIA FITTINGS (3RD MTO) Doc no : BAP-00-36-EB-0034-R
PLANT PROJECT Project No : 15-1802
Rev. No.: 0 Page 4 / 9

1. GENERAL
This Technical Bid Evaluation is based on Bid documents for Carbon Steel Welded Fittings
(3rd MTO) material with specification according and/or comply to document Purchasing
Specification for Fitting (Doc No.BAP-00-36-MR-0001-R).
This evaluation is for the bill of quantity below:

Bill of Quantity No. Title


BAP-00-36-BQ-0034-R Requisition for Carbon Steel Welded Fittings (3rd MTO)

Terms stated in this technical requisition are defined as follows,

Description Definition

Owner PT Panca Amara Utama (PAU)


Project BANGGAI AMMONIA PROJECT (BAP) Plant to be built at Owner's
premises in Banggai, Central Sulawesi Indonesia
Purchaser PT Rekayasa Industri (REKIND)
KBR Kellogg Brown & Root, LLC, process licensor for the ammonia unit
of the Project and engineering designer for the equipment specified
in this requisition
Vendor or A company who performs design and/or fabrication and/or supply of
Suppliers or the material and/or equipment and/or construction services for the
Seller Project under a supply or subcontract agreement with Purchaser
Sub-Vendor A company who supports Vendor for the Project
Inspector Any personnel(s) engaged by and acting on behalf of Purchaser to
conduct inspection of the material and/or equipment supplied by
Vendor and/or its Sub-Vendor for the Project.
Purchaser Inspector is not to be construed as Authorized Inspector
assigned for compliance with governmental rules or regulations.
TECHNICAL BID EVALUATION
FOR CARBON STEEL WELDED
BANGGAI AMMONIA FITTINGS (3RD MTO) Doc no : BAP-00-36-EB-0034-R
PLANT PROJECT Project No : 15-1802
Rev. No.: 0 Page 5 / 9

1.1 Vendor
The inquiry was issued to 6 vendors with the status below:

1. AMARSON VR
 RFQ was sent to vendor on July 1, 2016.
 Vendor quotation reference No.: ANNEXURE C-BAP-00-36-BQ-0034-R_0 CS
FITTING WELD, which was sent on July 12, 2016

2. MITRA GALPERTI
 RFQ was sent to vendor on July 1, 2016.
 Vendor quotation reference No.: OFFER 3rd MTO Fitting-R2 - BAP Project, which
was sent on July 25, 2016.

3. NEOTECH PIPES
 RFQ was sent to vendor on July 1, 2016.
 Vendor quotation reference No.: QUOTATION - 1094 BAP-00-36-BQ-0034-R_0 CS
FITTING WELD, which was sent on July 14, 2016.

4. RED ENERGY
 RFQ was sent to vendor on July 1, 2016.
 Vendor quotation reference No.: Z BAP-00-36-BQ-0034-R_0 CS FITTING WELD rev
01, which was sent on July 11, 2016.

5. TK CORP
 RFQ was sent to vendor on July 1, 2016.
 Vendor quotation reference No.: DSL160713AF - BAP-00-36-BQ-0034-R_0 CS
FITTING WELD, which was sent on July 13, 2016.

6. TOPSTEEL
 RFQ was sent to vendor on July 22, 2016.
 Vendor quotation reference No.: OFFER FIVE - BAP-00-36-BQ-0034-R_0 CS
FITTING WELD, which was sent on July 27, 2016.

1.2 Evaluating Criteria


The Technical Evaluation was based on the following considerations:
1. Compliance with specifications, code and standards and scope of supply
2. Scope of evaluation consist:
TECHNICAL BID EVALUATION
FOR CARBON STEEL WELDED
BANGGAI AMMONIA FITTINGS (3RD MTO) Doc no : BAP-00-36-EB-0034-R
PLANT PROJECT Project No : 15-1802
Rev. No.: 0 Page 6 / 9

- Material specification
- Type/Design of Fittings
- Wall thickness / Schedule
- End Connection
- Features
- AML (Approved Manufacture List)
- Inspection & Test Procedure
3. Design features and performance of materials (temperature & pressure range)
4. Proven experiences in comparable applications
5. Completeness of quotation and vendor response to request for supplementary information
6. Delivery time & schedule.

2. TECHNICAL BID TABULATION


Based on the Bidder’s proposals and their response to clarifications, Contractor has
evaluated and tabulated the technical bid evaluation result as per Attachment 1 and as
summarized below.

The priority for interpretation shall be in the following order:


1. Requisition document
2. Individual specification shown in the sub-requisition document
3. General specification
4. Standard drawing (if any)
5. Inspection & Test Procedure

In addition, Vendor shall submit their interpretation for the conflict/discrepancy to get the
clarification from Contractor in writing.

2.1 AMARSON VR
Result:
 Vendor quoted for all material Carbon Steel Welded Fittings (3rd MTO), and evaluation
have done for all items offered on vendor’s quotation document.
 The evaluation result shown as specified on the table of Technical Bid Evaluation for
Carbon Steel Welded Fittings (3rd MTO) in Attachment 1.
 According to the technical quotation review and evaluation, they were accepted and met
with the requirement for all offered items.
TECHNICAL BID EVALUATION
FOR CARBON STEEL WELDED
BANGGAI AMMONIA FITTINGS (3RD MTO) Doc no : BAP-00-36-EB-0034-R
PLANT PROJECT Project No : 15-1802
Rev. No.: 0 Page 7 / 9

2.2 MITRA GALPERTI


Result:
 Vendor quoted for all material Carbon Steel Welded Fittings (3rd MTO), and evaluation
have done for all items offered on vendor’s quotation document.
 The evaluation result shown as specified on the table of Technical Bid Evaluation for
Carbon Steel Welded Fittings (3rd MTO) in Attachment 1.
 According to the technical quotation review and evaluation, they were accepted and met
with the requirement for all offered items.

2.3 NEOTECH PIPES


Result:
 Vendor quoted for all material Carbon Steel Welded Fittings (3rd MTO), and evaluation
have done for all items offered on vendor’s quotation document.
 The evaluation result shown as specified on the table of Technical Bid Evaluation for
Carbon Steel Welded Fittings (3rd MTO) in Attachment 1.
 According to the technical quotation review and evaluation, they were accepted and met
with the requirement for all offered items, except for items no 31-34.

2.4 RED ENERGY


Result:
 Vendor quoted for all material Carbon Steel Welded Fittings (3rd MTO), and evaluation
have done for all items offered on vendor’s quotation document.
 The evaluation result shown as specified on the table of Technical Bid Evaluation for
Carbon Steel Welded Fittings (3rd MTO) in Attachment 1.
 According to the technical quotation review and evaluation, they were accepted and met
with the requirement only for all offered items.

2.5 TK CORPS
Result:
 Vendor quoted for all material Carbon Steel Welded Fittings (3rd MTO), and evaluation
have done for all items offered on vendor’s quotation document.
 The evaluation result shown as specified on the table of Technical Bid Evaluation for
Carbon Steel Welded Fittings (3rd MTO) in Attachment 1.
 According to the technical quotation review and evaluation, they were accepted and met
with the requirement only for all offered items.
TECHNICAL BID EVALUATION
FOR CARBON STEEL WELDED
BANGGAI AMMONIA FITTINGS (3RD MTO) Doc no : BAP-00-36-EB-0034-R
PLANT PROJECT Project No : 15-1802
Rev. No.: 0 Page 8 / 9

2.6 TOPSTEEL
Result:
 Vendor quoted for some material Carbon Steel Welded Fittings (3rd MTO), and evaluation
have done for all items offered on vendor’s quotation document.
 The evaluation result shown as specified on the table of Technical Bid Evaluation for
Carbon Steel Welded Fittings (3rd MTO) in Attachment 1.
 According to the technical quotation review and evaluation, they were accepted and met
with the requirement only for all quoted items.

3. RECOMMENDATION
Having meticulously reviewed and evaluated all Bidders proposals and response to
clarifications, CONTRACTOR concludes the following technically acceptable Bidders which
shown below

1) MITRA GALPERTI (Recommended)


2) TK CORP (Technically accepted, delivery time shall be reduced)
3) RED ENERGY (Technically accepted), (if the Brand approved by Client)
4) AMARSON VR (Technically accepted), (if the Brand approved by Client)
5) TOPSTEEL (Technically accepted for all quoted items), (if the Brand approved by Client)
6) NEOTECH PIPES (Technically accepted, except for items no.31-34), (if the Brand
approved by Client. However, for information, this vendor had bad performance in
previous order 2nd MTO fittings packages which caused by poor quality)
TECHNICAL BID EVALUATION
FOR CARBON STEEL WELDED
BANGGAI AMMONIA FITTINGS (3RD MTO) Doc no : BAP-00-36-EB-0034-R
PLANT PROJECT Project No : 15-1802
Rev. No.: 0 Page 9 / 9

Attachment – 1: Technical Bid Evaluation for Carbon Steel Welded Fittings (3rd MTO)
Page 1 of 2

ATTACHMENT 1 - TECHNICAL BID EVALUATION FOR CARBON STEEL WELDED FITTINGS - 3RD MTO

PROJECT NAME : BAP PROJECT Evaluation Marked :

LOCATION T/A = TECHNICALLY ACCEPTED REV 0


: BANGGAI, CENTRAL SULAWESI, INDONESIA

JOB NO. : 15-1802 N/Q = NO QOUTED Date 18/7/16

DOCUMENT NO. : BAP-00-36-EB-0034 CLAR. = CLARIFIED Prep TFK

PURCHASING SPEC : BAP-00-36-MR-0001 DBA = DEVIATE BUT ACCEPTED Check Ai


DOC. NO.
N/A = NOT ACCEPTED Apprv. SOH/SG
REQUISITION DOC. NO. : BAP-00-36-EB-0034

SIZE -L SIZE -S
NO CODE NO MATERIAL DESCRIPTION QTY ISBL QTY OSBL QTY UNIT AMARSON VR MITRA GALPERTI NEOTECH PIPES RED ENERGY TK CORP TOPSTEEL
(INCH) (INCH)

1 L6B10514 2"-XS 45 ELBOW, A234-WPB, WELD, BW, ASME B16.9 2 2 0 9 9 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

2 L6B10515 3"-STD 45 ELBOW, A234-WPB, WELD, BW, ASME B16.9 3 3 12 0 12 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

3 L6B10518 8"-STD 45 ELBOW, A234-WPB, WELD, BW, ASME B16.9 8 8 0 2 2 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

4 L6B10510 10"-STD 45 ELBOW, A234-WPB, WELD, BW, ASME B16.9 10 10 0 1 1 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

5 L6B10048 12"-SCH20 45 ELBOW, A234-WPB, WELD, BW, ASME B16.9 12 12 0 1 1 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

6 L6B10511 12"-STD 45 ELBOW, A234-WPB, WELD, BW, ASME B16.9 12 12 2 0 2 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

7 L6B10513 16"-STD 45 ELBOW, A234-WPB, WELD, BW, ASME B16.9 16 16 1 0 1 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

8 L6B10021 26"-STD 45 ELBOW, A234-WPB, WELD, BW, ASME B16.9 26 26 2 0 2 EA T/A T/A DBA 2 Seam T/A T/A Portion 1 T/A

9 L6A10529 2"-XS 90 ELBOW, A234-WPB, WELD, BW, ASME B16.9 2 2 52 0 52 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

10 L6A10531 4"-STD 90 ELBOW, A234-WPB, WELD, BW, ASME B16.9 4 4 8 40 48 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

11 L6A10068 8"-SCH20 90 ELBOW, A234-WPB, WELD, BW, ASME B16.9 8 8 0 5 5 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

12 L6A10525 10"-STD 90 ELBOW, A234-WPB, WELD, BW, ASME B16.9 10 10 0 2 2 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

13 L6A10527 14"-STD 90 ELBOW, A234-WPB, WELD, BW, ASME B16.9 14 14 0 10 10 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

14 L6A10528 16"-STD 90 ELBOW, A234-WPB, WELD, BW, ASME B16.9 16 16 0 1 1 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

15 L6A10057 20"-STD 90 ELBOW, A234-WPB, WELD, BW, ASME B16.9 20 20 10 6 16 EA T/A T/A T/A T/A DBA SMLS, Portion 1 T/A

16 L6A10058 24"-STD 90 ELBOW, A234-WPB, WELD, BW, ASME B16.9 24 24 15 0 15 EA T/A T/A DBA 2 Seam T/A DBA SMLS, Portion 1 T/A

17 L6A10023 30"-STD 90 ELBOW, A234-WPB, WELD, BW, ASME B16.9 30 30 0 1 1 EA T/A T/A DBA 2 Seam T/A T/A Portion 1 T/A

18 L6A10535 30"-STD 90 ELBOW, A234-WPB, WELD, BW, ASME B16.9, PWHT 30 30 2 0 2 EA T/A T/A DBA 2 Seam T/A T/A Portion 1 N/Q DECLINE

19 L6A20019 30"-STD 90 ELBOW, A420-WPL6, WELD, BW, ASME B16.9 30 30 0 4 4 EA T/A T/A DBA 2 Seam T/A T/A Portion 1 N/Q DECLINE

20 L6A20080 30"-17.48mm 90 ELBOW, A420-WPL6, WELD, BW, ASME B16.9, PWHT 30 30 2 0 2 EA T/A DBA 2-Seam DBA 2 Seam T/A T/A Portion 1 N/Q DECLINE

21 L6A10027 38"-STD 90 ELBOW, A234-WPB, WELD, BW, ASME B16.9 38 38 0 4 4 EA T/A T/A DBA 2 Seam T/A T/A Portion 1 N/Q DECLINE

22 L6A20028 48"-STD 90 ELBOW, A420-WPL6, WELD, BW, ASME B16.9 48 48 0 7 7 EA T/A T/A DBA 2 Seam T/A T/A Portion 1 N/Q DECLINE

23 L6E11366 3"-STD*2"-XS CON. REDUCER, A234-WPB, WELD, BW, ASME B16.9 3 2 5 0 5 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

24 L6E11368 4"-STD*2"-XS CON. REDUCER, A234-WPB, WELD, BW, ASME B16.9 4 2 0 2 2 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 DBA M/C down one end from Sch 80/XS

25 L6E11369 4"-STD*3"-STD CON. REDUCER, A234-WPB, WELD, BW, ASME B16.9 4 3 15 9 24 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

WELD / CONICAL TYPE (H : 609.6),


26 L6E10052 26"-STD*24"-STD CON. REDUCER, A234-WPB, WELD, BW, ASME B16.9 26 24 2 0 2 EA T/A DBA CONICAL TYPE DBA 2 Seam DBA CONICAL TYPE DBA N/Q DECLINE
Portion 2

27 L6F11923 8"-STD*4"-STD ECC. REDUCER, A234-WPB, WELD, BW, ASME B16.9 8 4 1 2 3 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

28 L6F11913 18"-STD*14"-STD ECC. REDUCER, A234-WPB, WELD, BW, ASME B16.9 18 14 0 1 1 EA DBA SMLS T/A T/A T/A DBA SMLS, Portion 1 T/A

29 L6F11914 20"-STD*12"-STD ECC. REDUCER, A234-WPB, WELD, BW, ASME B16.9 20 12 1 0 1 EA T/A T/A T/A T/A DBA SMLS, Portion 1 N/Q DECLINE

WELD / CONICAL TYPE (H : 609.6),


30 L6F10496 42"-XS*32"-STD ECC. REDUCER, A234-WPB, WELD, BW, ASME B16.9 42 32 0 2 2 EA T/A DBA CONICAL TYPE DBA 2 Seam DBA CONICAL TYPE DBA N/Q DECLINE
Portion 1

SML'S MOTHER + SML'S BRANCH


RUN: SMLS, BRANCH: SMLS,
31 L7610211 4"-STD*2"-XS LATERAL RED. TEE, A234-WPB, WELD, BW, MFR STD 4 2 2 0 2 EA T/A DBA T/A Single welding joint, No Reinf Pad T/A DBA PIPE WELDING JOINT (RPAD) N/Q DECLINE
JOINT: RT (REINF PAD)
WITH RT, Portion 2
SML'S MOTHER + SML'S BRANCH
RUN: SMLS, BRANCH: SMLS,
32 L7610212 4"-STD*3"-STD LATERAL RED. TEE, A234-WPB, WELD, BW, MFR STD 4 3 12 0 12 EA T/A DBA T/A Single welding joint, No Reinf Pad T/A DBA PIPE WELDING JOINT (RPAD) N/Q DECLINE
JOINT: RT (REINF PAD)
WITH RT, Portion 2
WELD MOTHER + WELD BRANCH
One longitudinal seam by Stubin RUN: WELDED, BRANCH: SMLS,
33 L7610213 30"-STD*20"-STD LATERAL RED. TEE, A234-WPB, WELD, BW, MFR STD 30 20 2 1 3 EA DBA DBA DBA Single welding joint, No Reinf Pad T/A DBA PIPE WELDING JOINT WITH RT, N/Q DECLINE
method with reinforcing pad + RT JOINT: RT (REINF PAD)
Portion 2
WELD MOTHER + WELD BRANCH
One longitudinal seam by Stubin RUN: WELDED, BRANCH: SMLS,
34 L7610214 30"-STD*24"-STD LATERAL RED. TEE, A234-WPB, WELD, BW, MFR STD 30 24 1 1 2 EA DBA DBA DBA Single welding joint, No Reinf Pad T/A DBA PIPE WELDING JOINT WITH RT, N/Q DECLINE
method with reinforcing pad + RT JOINT: RT (REINF PAD)
Portion 2

35 L6D11479 4"-STD*3"-STD RED. TEE, A234-WPB, WELD, BW, ASME B16.9 4 3 3 9 12 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A
Page 2 of 2

ATTACHMENT 1 - TECHNICAL BID EVALUATION FOR CARBON STEEL WELDED FITTINGS - 3RD MTO

PROJECT NAME : BAP PROJECT Evaluation Marked :

LOCATION T/A = TECHNICALLY ACCEPTED REV 0


: BANGGAI, CENTRAL SULAWESI, INDONESIA

JOB NO. : 15-1802 N/Q = NO QOUTED Date 18/7/16

DOCUMENT NO. : BAP-00-36-EB-0034 CLAR. = CLARIFIED Prep TFK

PURCHASING SPEC : BAP-00-36-MR-0001 DBA = DEVIATE BUT ACCEPTED Check Ai


DOC. NO.
N/A = NOT ACCEPTED Apprv. SOH/SG
REQUISITION DOC. NO. : BAP-00-36-EB-0034

SIZE -L SIZE -S
NO CODE NO MATERIAL DESCRIPTION QTY ISBL QTY OSBL QTY UNIT AMARSON VR MITRA GALPERTI NEOTECH PIPES RED ENERGY TK CORP TOPSTEEL
(INCH) (INCH)

36 L6D11482 6"-STD*4"-STD RED. TEE, A234-WPB, WELD, BW, ASME B16.9 6 4 1 1 2 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

37 L6D11484 8"-STD*6"-STD RED. TEE, A234-WPB, WELD, BW, ASME B16.9 8 6 1 0 1 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

38 L6D11468 12"-STD*10"-STD RED. TEE, A234-WPB, WELD, BW, ASME B16.9 12 10 0 1 1 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

39 L6C10441 2"*2"-XS TEE, A234-WPB, WELD, BW, ASME B16.9 2 2 4 6 10 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

40 L6C10442 3"*3"-STD TEE, A234-WPB, WELD, BW, ASME B16.9 3 3 0 1 1 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

41 L6C10443 4"*4"-STD TEE, A234-WPB, WELD, BW, ASME B16.9 4 4 0 8 8 EA DBA SMLS T/A T/A DBA SMLS DBA SMLS, Portion 1 T/A

TOTAL CARBON STEEL FITTING SMLS - 3rd MTO 156 137 293 EA

ITEM REQUIREMENT AMARSON VR MITRA GALPERTI NEOTECH PIPES RED ENERGY TK CORP TOPSTEEL

DELIVERY TERM FOB COUNTRY OF ORIGIN FOB INDIA FOB KOREA FOB INDIA FOB SINGAPORE EXW KOREA EXW SINGAPORE

Portion 1 : 60- 75 Days after PO


DELIVERY TIME Maximum at site End of October 2016 8 Weeks 60 Days After Po 3-4 Weeks 4-6 Weeks 2 Months ARO
Portion 2 : 90-135 Days after PO

AWAJI, BASSI LUIGI, BENKAN, CHERO, DEE, KEON SAE, MEGA, NIPPON JOINT, PETROL RACCORD, PHOCEENNE-GENOYER, SUMIKIN KIKOH, SK BEND, TECHNOFORGE, IML, VIAR, MEGA, LAME, JD, ULMA, HYSCO,
AWAJI, TK BEND, INTERFIT, SK BEND,
BRAND / MANUFACTURE / COUNTRY OF ORIGIN TECTUBI, TK BEND, TUBE PRODUCTS, IML, METALFAR, BOTHWELL, ASK, SBC BEND, VIAR, SCHULZ, BKL, BUHLMANN, CRANE, DAEKYUNG BEND, DELCORTE, DONGJIN, VR ASSOCIATES MEGA, AWAJI, TECHNOFORGE NEOTECH PIPES SEAH, HUSTEEL, KUMSOO, SK, TK, TCC, TK BEND
T BENKAN
ERNE, EZEFLOW, FORITEX, GAM RACCORDI, INTERFIT, ITM, KANZEN, TAYLOR FORGE, WFI SAMYOUNG, BKL, ASK

ACCEPTED WITH NOTE 2 ACCEPTED ACCEPTED WITH NOTE 2, 3 ACCEPTED WITH NOTE 2 ACCEPTED WITH NOTE 1 ACCEPTED WITH NOTE 2
RESULT
(FOR ALL ITEMS) (FOR ALL ITEMS) (EXCEPT FOR ITEMS NO.31-34) (FOR ALL ITEMS) (FOR ALL ITEMS) (FOR ALL QOUTED ITEM)

Note : 1. Delivery time shall be reduced to maximum 8 weeks for all items
2. If the Brand approved by Client
3. for information, this vendor is had bad performance in previous order 2nd MTO fittings packages which caused by poor quality