Professional Documents
Culture Documents
PROJECT SPECIFICATION
PIPELINE WEIGHT COATING SPECIFICATION
TABLE OF CONTENTS
Page
1.0 SCOPE 3
2.0 CODES AND COMPANY SPECIFICATIONS............................................................................3
3.0 DEFINITIONS...............................................................................................................................3
4.0 GENERAL REQUIREMENTS......................................................................................................4
5.0 CONCRETE WEIGHT COATING................................................................................................4
6.0 GUARANTEE..............................................................................................................................11
Page 2 of 11
028120-SPL-004 Rev C
27-02-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
1.0 SCOPE
This Specification covers the material, application, inspection and testing of weight coating of line
pipe for onshore and offshore use.
3.0 DEFINITIONS
CONTRACTOR is the independent party awarded a contract by COMPANY for the supply of
material, application, inspection and testing of insulation and weight coating of linepipe for
onshore and offshore pipelines.
Manufacturer is the supplier of the raw materials for insulation and weight coating for the
CONTRACTOR.
Page 3 of 11
028120-SPL-004 Rev C
27-02-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Page 4 of 11
028120-SPL-004 Rev C
27-02-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
No. 16 40 - 70
No. 50 10 - 30
No. 100 2 - 10
The heavy aggregate shall be free of clay and injurious amounts of salt, alkali, deleterious
substances, and organic impurities that may affect the strength of the concrete. COMPANY
reserves the right to reject any aggregate not deemed acceptable by virtue of either source or
quality.
Reinforcing steel shall be made from best quality billet-steel, formed into welded galvanized
wire fabric type reinforcing. The wire fabric shall be minimum 14 gauge (.08"). The
chemical and physical properties of the billet-steel shall conform to ASTM A615 Gr. 40.
One layer of 1.5"x1.5"x17 gauge (.054") galvanized hexagonal wire netting shall be used.
Two layers of reinforcing steel shall be used for concrete thicknesses of 2" and above.
Water shall be clean and free from injurious amounts of oil, acid, alkali, salt, or organic
material and shall be of potable quality.
5.3 Mix Design
The concrete mix shall be designed to yield the specified density on the drawings immersed
in sea water and with maximum water absorption of 3%. CONTRACTOR shall design its
mixes using the components approved and shall determine the proportions which will give
the required densities and strength. All mix designs are to be agreed with the COMPANY
prior to commencement of the Work.
Full details shall be provided by CONTRACTOR with regard to :
(a) the proportion and weights of the respective materials used in the mix
(b) the water/cement ratio
(c) the gradings of the various aggregates with combined grading curves as necessary.
5.4 Application of Reinforcing Steel
Reinforcing steel may be applied by any method that will provide for the continuity of
reinforcing. When reinforcing is spooled on, a lap of approximately 1 inch shall result.
A minimum of one reinforcing wrap shall be used, and it shall be placed as close as possible
to the center of the concrete coating. If more than one layer of reinforcing is used, the layers
shall be evenly distributed throughout the concrete thickness. The reinforcing wire shall not
contact the pipe corrosion coating or be exposed on the external coating surface.
5.5 Application of Concrete Coating
No concrete shall be applied if the surrounding temperature at the curing station is outside
the parameters of the approved procedure.
If kraft paper has been placed on the joint to protect the corrosion coating, the paper shall be
completely removed before the joint is concrete coated.
The dry materials shall be mechanically batch mixed in a paddle mixer or equal with
sufficient water to make homogeneous grout. The concrete shall then be applied to the pipe
within 30 minutes after the water is first added to the mix and then only provided there has
been no additional water added to the mix to return the concrete to the original slump.
Each joint of pipe shall be coated in a continuous operation. If more than one application is
required to produce a coating of the specified thickness, then the time allowed between
successive applications shall not exceed 30 minutes. If the time between coats does exceed
Page 5 of 11
028120-SPL-004 Rev C
27-02-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
30 minutes all previous coatings shall be removed and the entire joint recoated at no expense
to COMPANY.
5.6 Coating Joints with Anodes
Anodes shall be installed at the specified location on a certain number of the pipe joints.
After proper curing of the anode attachment coating repairs, the concrete weight coating may
be applied.
5.7 Curing
During curing, the concrete coated pipe shall be stacked on sand ridges or on a flat earth
surface free of obstructions.
If the joints are placed on sand ridges they should be so placed as to eliminate any injurious
deflection in the pipe. The concrete may be cured by water spray or by application of a
curing membrane. The concrete coated pipe shall cure for not less than 4 days after
application of concrete, and shall not be handled or loaded out from the yard until so cured.
No deviation from this requirement shall be permitted.
Water curing shall commence no later than 6 hours after coating. It shall consist of keeping
the concrete continuously moist for the curing period by means of intermittent watering.
During this treatment, pipe joints shall be kept continuously moist by means of either manual
or mechanical watering.
Membrane curing shall be of the white pigmented compound or plastic membrane type. It
shall be applied by mechanical apparatus to the coated surface in quantity to provide
complete coverage in accordance with manufacturer's recommendations. The application of
this curing compound or sheet shall take place immediately after coating is completed and
preferably before the pipe is removed from the concrete coating apparatus. A slight spray of
water applied after concrete application and before applying the curing agent shall be
required for the curing compound method.
5.8 Cutbacks
The concrete shall be square cut or tapered back from 10 1/2” from the pipe end at a
minimum two-to-one slope, until the required thickness of coating is reached.
The uncoated portion of the pipe and the bevels and lands shall be kept clean and free from
concrete spatters, oil, grease, etc.
5.9 Concrete Inspection and Testing
5.9.1 General
All testing shall be at CONTRACTOR's expense. The testing methods to be used
are outlined below.
Pipe coating not meeting the requirements, as outlined herein, shall be rejected and
recoated by CONTRACTOR at no expense to COMPANY. Coatings shall be
rejected for the following reasons :
(a) improper placement of reinforcing steel
(b) unfinished coatings which have been allowed to remain unfinished for a
period of 1/2 hour or more
(c) concrete strength below the specified values
(d) concrete density outside the specified range
(e) individual coated joint weight outside the specified range, or joint
average below the specified coated pipe weight.
Page 6 of 11
028120-SPL-004 Rev C
27-02-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
5.9.2 Tolerances
The minimum compressive strength of the as placed concrete, as determined from
tests, shall not be less than 3,500 psi after 7 days and 4,650 psi after 28 days.
The density of concrete, as determined from tests, shall be no more than 5 pcf
above or 0 pcf below the specified density as given in the individual submarine
pipeline specifications.
In addition, the average weight per foot (negative buoyancy) of five successively
coated joints shall be greater than or equal to the required weight per foot.
The nominal weight coating thickness and approximate length of pipe to be coated
will be specified for each pipe O.D. in the individual pipeline specification. The
concrete coating thickness shall be concentric and uniform around the
circumference of the pipe, and shall not vary more than 1/4" along the length of a
coated pipe joint.
5.9.3 Compressive Strength
Compressive strength of each mix, as applied during the coating operation, shall be
determined from samples prepared at the jobsite in cylindrical molds obtained in
accordance with practices outlined in ASTM C31. A minimum of two (2) test
cylinders shall be taken in the morning, and two (2) in the afternoon for each day
of production. These cylinders shall be tested according to procedures obtained in
ASTM C39 to determine the 7 day and 28 day compressive strengths of the
concrete.
Six core samples shall be taken and tested from each day’s production. The cores
shall be taken as close to 7 days after impingement as possible, but not less than 4
days after impingement. The cores shall be taken from coated pipes representing
three equally spaced periods of that day’s production. For this purpose three pipes
shall be selected, marked, and joint numbers noted at the time of impingement. The
cores shall be taken and tested in accordance with ASTM C42 to determine the 7
and 28 day compressive strengths of the concrete. Repair of the coating where the
cores were taken shall be per the repair section of this Specification.
If the average compressive strength obtained for the 7 day test for the cylinder or
core falls below the minimum, CONTRACTOR has the option to recoat all the
pipes coated during the days production when the samples were taken or,
alternatively, wait for the results of the 28 days tests.
5.9.4 Dry Density and Water Absorption
From one pipe out of every fifty or at least two per 24 hour period, a piece of
concrete is to be removed and weighed. Repair of the coating where the section
was removed shall be as per this Specification. After 24 hours curing, this concrete
sample is to be weighed. The sample shall then be immersed in a tank of fresh
water for not less than 24 hours. The volume of the sample is to be determined
from the volume of water displaced. The concrete dry density shall then be
calculated using this weight and volume.
After saturation the sample is reweighed immediately on removal from the tank
after surface water has drained off.
For a given length or pipe, weight of sea water absorbed is given by :
Wabs1 = Vc (Wsat - Wcs) 64/62.4 Vs
Where :
Vc = Volume of concrete per ft of pipe length (theoretical)
Page 7 of 11
028120-SPL-004 Rev C
27-02-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Wd = ((Wc-WCB)/(L-CB)) + Wabs
Where W = API standard weight/foot of line pipe.
For every fifty pipe production period the value of Wabs to be used is that
determined from the absorption test for that same period.
The negative buoyancy/foot in seawater for each length of pipe is then determined
and defined by:
NB = Wd - B
The theoretical value of negative buoyancy shall be calculated using the same
above formula's using the theoritical values of DA, Wc, L, CB and Wabs, and
compared to the computed NB for each coated joint. The actual average negative
buoyancy of successive coated joints shall be within -0 +10% of the theoretical
value, and -0 +15% for individual pipes.
Should a number of pipe lengths in a fifty pipe production period not satisfy the
negative buoyancy requirements using the value of Wabs1 obtained in the test, then
the contractor can select three further pipes from the same fifty pipe period and
subject samples from each of these to a water absorption test; the average value of
Wabs1 for the four must be used for checking negative buoyancy requirements.
If CONTRACTOR wishes to use an alternative method for calculating negative
buoyancy then this must be submitted in writing to COMPANY or its
representative for approval.
5.9.7 Moisture Content Inspection
The moisture content of the aggregate being used shall be checked at least once per
shift or more frequently if it is shown to be necessary in order to maintain a
satisfactory control on the water/cement ratio of the concrete mix.
5.9.8 Wire Mesh Inspection
CONTRACTOR shall be prepared with an ohmmeter or a 12v. light bulb to test
concrete coated joints to ensure that there is no contact between the wire
reinforcement and the pipe.
On the center of the first pipe of each day's production a water jet shall be used to
clear away the freshly placed concrete down to the corrosion coating for an area 1"
wide and 9" long in the longitudinal direction. This exposed area shall be used to
confirm that the mesh is positioned and overlapped within the concrete as
specified.
If the wire is not positioned correctly the pipe shall be rejected and recoated. Each
pipe in succession shall be inspected in this manner until the position of the mesh is
accepted.
Repair to the inspection slots shall be per this specification.
5.9.9 Equipment Inspection
The calibration of the weigh-batcher and the water gauge shall be checked at least
once per week.
5.10 Permissible Repairs
All removal and replacement of concrete not meeting the specification shall be at
CONTRACTOR's expense.
Page 9 of 11
028120-SPL-004 Rev C
27-02-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
6.0 GUARANTEE
Material and/or equipment shall be guaranteed by CONTRACTOR to perform in accordance with
specification requirements and to be free of defects and poor workmanship including, but not
limited to, those caused by inadequate preparation for shipment, for a period of one (1) year after
material/equipment is placed in service, but not exceeding eighteen (18) months following delivery
to the contracted destination.
CONTRACTOR shall repair or replace all defective items during the guarantee period at no cost to
COMPANY.
CONTRATOR shall obtain a similar guarantee from Manufacturer to warrant the raw materials
provided.
Page 11 of 11
028120-SPL-004 Rev C
27-02-2003