Professional Documents
Culture Documents
PRELIMINARY
NOT FOR PERMIT,
CONSTRUCTION OR
FINAL RELEASE
Ronald Pasadyn, P.E.
TX. LICENSE NO. 48327
EDG, INC. F-2480
EDG Project and Phase Task Code Sequence Revision Internal Use Only
DOCUMENT
CONTROL NO. 3348370 20400 10019 PPLG03
Vietnam Block B Gas Project EDG Engineering
FEED Contract No. 09-028agr
[VNM-IPGN-PPL-SPC-EDG-0000-00019-00]
(CES COM-SU-4042-F) (December 2009)
[Single-Layer Fusion-Bonded Epoxy for External Pipeline Coating]
Scope
1. This Project Addendum Specification (PA) defines additional requirements for the Vietnam
Block B Gas Project.
2. The requirements in this PA are modifications to the requirements in CES document [COM-SU-
4042-F].The type of modification shall be defined and indicated in subsequent text as follows:
(ADD) - Indicates the following statement(s) is/are added to the CES referenced text.
(DELETE) - Indicates the following statement(s) is/are deleted from the CES referenced text.
(REPLACE WITH) - Indicates the following statement(s) is/are revision(s) to the CES
referenced text.
3. In case of conflict, requirements in this PA take precedence, but in no case will a less stringent
requirement be used unless clearly stated in this PA that the requirement specifically replaces the
more stringent requirement.
1.0 SCOPE
[Add Para] In all cases the coating applicator shall inform the Purchaser of any deviations
from the requirements of this specification which are considered to be necessary in order to
comply with National and/or local regulations.
2.2 Industry Standards
National Association of Corrosion Engineers (NACE)
[Add] NACE RP0287 Field Measurement of Surface Profile of Abrasive Blast Cleaned
Steel Surfaces Using a Replica Tape
American Society for Testing and Materials
[Add] ASTM G14 Standard Test Method for Impact Resistance of Pipeline Coatings
(Falling Weight Test)
6.2 Storage of Powder Coating
[Add] 4. The relative humidity of the storage area shall be less than 50%. If storage room
temperature is lower than the application area, coatings should be acclimatised in unopened
containers prior to use.
6.3 Batch Information
1. [Add] f. The material type and product designation.
[Add] g. Manufacturing standards and specifications.
7.0 Application
7.2.3 Abrasive Cleaning
4. (b) Testex Press-O-Film [Replace With]Testex replica tape and micrometer in accordance
with NACE RP 0287.
13-Dec-2010 Page 3 of 5
Vietnam Block B Gas Project EDG Engineering
FEED Contract No. 09-028agr
[VNM-IPGN-PPL-SPC-EDG-0000-00019-00]
(CES COM-SU-4042-F) (December 2009)
[Single-Layer Fusion-Bonded Epoxy for External Pipeline Coating]
7.2.4 Inspection and Repair
[Add to End] 3. The Applicator shall be responsible for replacing any pipe joints with
unacceptable wall thickness following grinding operations, at Applicator’s own expense.
7.4 Heating
[Add to End] 4. Any Tempilstik marks shall be wire brushed from the pipe surface before
application of the coating.
7.5 Coating Application
5a. 25 percent [Replace With] 20 percent
7.6 Application of Repair Products
1. [Add] Pinholes (defects less than 1mm in diameter) shall need no more surface
preparation of the repair area.
7.7 Cutbacks
2. [Replace With] The length of the cutback shall be between 150mm and 200mm, measured
from the exterior shoulder of the bevel at the end of the pipe. The coating cutback shall be
further reviewed and approved by Purchaser during the pre-production meeting.
7.8 Pipe Marking
2. [Add to End] Coating thickness, pipe wall thickness, joint number
3. [Add] Applicator shall ensure traceability of all incoming and outgoing pipes by use of
pipe tally sheets referencing pipe joint numbers provided by the pipe mill, which Company
will supply with the bare pipe. Applicator shall not generate any new or duplicate pipe joint
numbers.
8.6.2 Thickness
[Add to Note] Other equivalent calibration standards may be accepted by Company. The
gauge shall have a range adequate for Company required coating thickness, which is
typically between 350 to 500 microns, unless otherwise stated in Company Purchase Order.
13-Dec-2010 Page 4 of 5
Vietnam Block B Gas Project EDG Engineering
FEED Contract No. 09-028agr
[VNM-IPGN-PPL-SPC-EDG-0000-00019-00]
(CES COM-SU-4042-F) (December 2009)
[Single-Layer Fusion-Bonded Epoxy for External Pipeline Coating]
8.8 Interpretation of Inspection Results
6. [Replace With] In the event that Company deems that the test results are inadequate, the
Company reserves the right to conduct any or all the tests required through an independent
laboratory or agency, at the Applicator’s cost.
9.0 Handling and Storage Procedures
9. [Add] If bevel protectors and/or end caps are provided by Company, they shall be
removed for coating and re-installed by Applicator prior to shipment of the coated pipe
joints. Any bevel protectors and/or end caps that are lost shall be replaced by Applicator at
his own expense.
10. [Add] The maximum stacking height of coated pipe on storage berms and during
transportation shall be determined by Applicator for each pipe diameter and wall thickness.
However the height of the pipes shall not exceed six (6) tiers, unless a lower limit is
determined by Applicator.
10.0 [Add] Documentation
Prior to the commencement of work, the Applicator shall submit the following details and
documentation for Company review and approval.
1. Applicator’s personnel and their qualifications.
2. Pipe receiving, initial inspection and defect reporting procedure.
3. Details of raw materials, together with quality control and Manufacturer’s data,
including test certificates, methods and standards used.
4. Environmental procedures and provisions for raw material storage.
5. Steel surface preparation procedure including pre-heating, steel defect removal,
cleanliness, profile, methods of measurement and consumables used.
6. Pipe heating, temperature and control.
7. Application of materials including application equipment, procedure and temperatures
used.
8. Quality Plan, Inspection and Testing Plan (ITP), recording and reporting formats and
current calibration certificates for equipment used.
9. Detailed methods for detecting, reporting, rejecting and repair of defects including
method used to strip defective coatings, based on nature and magnitude of defects and
repairs.
10. Pipe handling, stockpiling, load out and transportation procedures; including coated pipe
stacking procedures and limitations (e.g. maximum height).
11. The above documents shall be compiled along with pre-qualification/production reports
and inspection records together with instruments calibration certificates as part of
Manufacturing Record Book (MRB) and submitted to Purchaser after completion of the
coating works.
13-Dec-2010 Page 5 of 5
COM-SU-4042-F
CONTENTS
1.0 SCOPE
This specification covers the minimum material, application, and handling requirements for single
layer fusion bonded epoxy (FBE) powders used for external pipeline coating on steel pipes.
2.0 REFERENCES
1. The following documents are referenced herein and are considered part of this specification.
2. The most recently published industry standards shall be used unless otherwise specified.
3. Any discrepancies or conflicts among these documents and the technical requirements in this
specification shall be called to the attention of the Purchaser for resolution.
4. Coating application and inspection shall conform to the following industry standards, as well
as this specification.
3.0 SAFETY
1. Coatings and procedures used during the process shall comply with national, federal, state, and
local codes and regulations.
2. Personnel involved at the job site shall be trained in the safe operation of equipment before
work commences.
3. The coating manufacturer’s recommended precautions regarding toxicity and safe handling of
coating materials shall be followed.
Acceptance
Test Test method Notes
Criteria
Film thickness Within
manufacturer’s
stated range on the
product data sheet
Thermal Within CSA Z245.20 (12.7) Tg midpoint required
characteristics manufacturer’s
stated range on the
product data sheet
Cathodic 6.5 mm maximum CSA Z245.20 (12.8) 24 hours /
disbondment 65°C [149°F] –3.5v
Cathodic 8.5 mm maximum CSA Z245.20 (12.8) 28 days /
disbondment 20°C [68°F] / –1.5v
Cathodic 20 mm maximum CSA Z245.20 (12.8) 28 days /
disbondment 65°C [149°F] / –1.5v
This test is only for
powders with Tg
above 110°C [230°F]
Cathodic 20 mm maximum CSA Z245.20 (12.8) 28 days /
disbondment 95°C [203°F] / –1.5v
This test is only for
powders with Tg at or
below 110°C [230°F]
Porosity (interface Rating 1—4 CSA Z245. 20 (12.10)
and cross-section)
Acceptance
Test Test method Notes
Criteria
Flexibility 2.0° PPD, no CSA Z245. 20 (12.11) Tested at –30°C
cracking (for [–22°F]
powders with Tg
above 110°C
[230°F])
3.0° PPD, no
cracking (for
powders with Tg at
or below 110°C
[230°F])
Impact resistance 1.5J, no holidays CSA Z245.20 (12.12) Impact resistance
Cathodic No cracking CSA Z245.20 (12.13) 1.5° strained coating
disbondment of using Calomel for powders with Tg
strained coating Reference electrode above 110°C [230°F]
2.5° strained coating
for powders with Tg
at or below 110°C
[230°F]
Adhesion of the Rating 1–3 CSA Z245.20 (12.14) Run both 24 hour and
coating (hot water 28 day tests
soak)
6. Applicator’s quality control plan shall pay particular attention to the control of coating
suppliers and shall ensure that the requirements of this specification are satisfied.
7. Applicator’s quality control plan and associated procedures may be subject to audits by
Purchaser during production.
8. Applicator’s quality control shall be monitored by Purchaser-assigned third-party inspectors
who will witness the inspection, testing, and associated work required by this specification.
9. Applicator shall, in their tender, submit the manufacturers’ product data sheets of the FBE
powder and the repair products selected for acceptance.
10. Once approved, the FBE powder shall not be substituted by the Applicator without prior
written authorization of the Purchaser.
11. The acceptance decision shall not, in any case, be considered as a guarantee from the
Purchaser with respect to the coating material and repair products but at most shall be
considered an authorization for use.
5.2 Documentation
Applicator shall obtain from the Supplier and submit to the Purchaser the following:
1. The product data sheet certificate that the FBE powder shall meet the required coating
characteristics as set forth in this specification.
2. One production test certificate for the FBE powder material.
3. FBE powder application data including substrate temperature.
4. Repair product application conditions and repair procedures.
5. Packaging and storage requirements of FBE powder and repair product.
6.0 MATERIALS
6.1 Pipe
Pipe shall be supplied without varnish or mill lacquers. If the pipe has varnish or mill lacquer it
must be removed by burning, followed by blasting to remove the soot.
6.4 Segregation
1. Coating powder shall be segregated by batch numbers during shipment, storage, and handling.
2. Batches shall be used consecutively during coating application and shall not be mixed except
when necessary to keep the coating process continuous.
3. No powder stored beyond the manufacturer’s recommended shelf life shall be used for coating
pipe.
4. Coatings shall not be stored beyond their shelf life.
7.0 APPLICATION
7.1 General
1. The fusion bonded epoxy coating shall be applied in accordance with this specification.
2. Applicator shall develop an application procedure and submit it to the Purchaser for
acceptance.
a. Applicator shall have a copy of these procedures at the site where the coating is being
applied.
b. Any deviation from the coating manufacturer’s application procedures shall be submitted
to the Purchaser representative for acceptance
3. Applicator shall stop the coating process at any time conditions exist that are outside those
specified in the approved application procedure.
4. Purchaser’s representative may reject any product or procedure not proven by the Applicator
to be in compliance with this specification.
7.4 Heating
1. Before coating, the pipe shall be heated so that when it reaches the coating application area its
temperature is within the application temperature range recommended by the coating
manufacturer.
a. The temperature shall not exceed 260°C (500°F).
b. Oxidation (bluing) of the steel shall not be acceptable.
c. At the discretion of the Purchaser’s representative, pipe which has been blued and/or
heated above 260°C (500°F) shall be rejected as scrap, or the pipe shall be subjected to
mechanical testing to confirm properties of the steel.
d. Replacement or testing of blued and overheated pipe shall be at the Applicator’s expense.
2. Furnace atmosphere shall be such that the clean pipe surfaces are not contaminated.
3. Temperature of the pipe shall be monitored continuously and recorded by means of
thermometers and/or optical pyrometers.
4. For accurate control of pipe temperature, the pipe shall be continuously checked with an
optical pyrometer. “Tempilstik®” heat-indicating crayons or other suitable devices are also
acceptable, provided that the size of such marks shall be less than 3.2 mm (1/8 inch) wide and
less than 51 mm (2 inches) long.
5. The use of recycled powder shall be permitted, provided that it has not been contaminated, has
not been heat affected, and is continuously recovered from the powder hood and reprocessed
through magnetic separators and shaker screens no coarser than 80 mesh.
a. It shall be uniformly mixed with new virgin powder up to a maximum proportion of
25 percent recycled material.
b. Under no circumstances shall reclaimed powder (powder not continuously recycled from
the powder hood) be used.
6. Dry air shall be circulated continuously through fluidized beds while the plant is not operating.
Prior to coating application, only virgin powder may be added to make up the initial full load,
and dry air must be run through the fluidized bed for at least two hours prior to plant start-up.
7. Manufacturer’s recommendations for full curing shall be followed.
a. The curing reaction of the coating must be completed prior to any forced cooling.
b. Forced cooling of the pipe to facilitate inspection and repair may be conducted after the
coating has completely cured.
8. The cured coating shall be of uniform color and gloss, and shall be free of blisters, pinholes,
fish eyes, sags or runs, or any other irregularities.
9. Any coating that, in the Purchaser representative’s judgment, has not been applied in
conformance with these specifications or exhibits poor workmanship practices shall be
rejected.
7.7 Cutbacks
1. Finished coating shall have a cutback at each end of the pipe.
2. Length of the cutback shall be 7.6 cm (2 inches) or greater, measured from the exterior
shoulder of the bevel at the end of the pipe.
3. Cutback areas shall be free of coating material.
8.0 INSPECTION
8.1 General
1. Purchaser’s inspector shall have free access to all areas of the plants where the coating
materials are produced and where they are applied.
2. An office and all necessary means for the complete fulfillment of the inspector’s work shall be
made available by the manufacturer as well as by Supplier.
3. Applicator shall notify the Purchaser’s representative not less than fifteen days in advance of
the start of each production run and shall provide Purchaser with a detailed time schedule to
permit witnessing of all processing and testing phases.
4. The Applicator shall provide copies of the documents listed in Section 5.2 to the Purchaser’s
inspector.
5. Coating inspection shall be carried out by Supplier in the presence of the inspector. It shall
include the following operations:
a. Inspection of the FBE powder delivery.
b. Inspection of the FBE powder quality.
c. Inspection of the various application parameters of the FBE coating.
d. Systematic inspection of pipe coating or test samples taken from pipe end.
e. Systematic inspection of each coated pipe.
6. The Purchaser’s representative shall be the final authority on the acceptability of surface
preparation and coating application.
7. The Purchaser’s representative shall have access to each part of the process and shall have the
right and opportunity to witness any of the quality control tests and/or to perform such tests on
a random sampling basis.
8. Purchaser’s representative shall be the final authority on the acceptability of surface
preparation and coating application.
9. Purchaser’s representative shall have the right to reject coated pipe pending alterations or
corrections to the process to correct all faults found in the work that result in failure of the
work to conform to these specifications.
4. A complete report of the testing shall be submitted to the Owner’s coating specialist
for acceptance prior to continuing with FBE application procedure qualification.
4. Specification Requirements: The inspection of the dust degree of each pipe shall be
considered as acceptable when the proportion of adhesive surface-magnified
40 times–showing dust particles is less than 15 percent.
5. Failing the above: Investigate the source of the dust, correct, and test again.
3. Failing the above: Manufacturing process shall be adjusted until conformity with
specified requirements is obtained. Pipes already coated with unaccepted travel speed
shall be segregated and tests performed to determine if they are within the coating
material’s required characteristics. Should they fail testing the coating shall be
removed, the pipe reblasted then the coating reapplied.
8.6.1 Appearance
1. Method: Visual.
2. Inspection: 100 percent of the pipe coated surface.
3. Specification requirements: The inspection of each pipe shall be considered as
acceptable when the appearance is in uniform and consistent.
4. Failing the above: Inspector shall be entitled to decide on any further action.
8.6.2 Thickness
1. Material: Magnetic or electromagnetic type measuring instruments as described in
CSA Z245.20 section 7.3.2.7.1.1.
2. Method: Specific to the instrument used, which shall be suitably calibrated.
3. Inspection: Four thickness readings made on each pipe at equal intervals including
one over the weld seam when appropriate.
4. Specification requirements: The inspection of each pipe shall be considered as
acceptable if the thickness readings are within the range: specified thickness minus
10 percent or plus 20 percent.
5. If more than 2 percent of the pipes are found with any coating thickness reading out of
the above-mentioned range, the Applicator’s process shall be modified until
conformity with the specified requirements is obtained.
a. Only 2 percent of pipes will be accepted per shift with coating thickness between
specified thickness and specified thickness minus 10 percent.
b. All pipes with thickness below specified thickness minus 10 percent shall be
rejected and recoated.
Note Location and frequency for proving compliance with the specification
requirements for thickness of the coating shall be agreed between Supplier and
the Purchaser’s representative. Thickness measurement method shall comply with
SSPC-PA2.
8.6.3 Cutback
1. Material: Rule or template.
2. Method: Specific to the material used.
3. Inspection: At both ends of each coated pipe.
4. Specification requirements: The inspection of each pipe shall be considered as
acceptable when the cutback length is in conformity with the requirement of
Section 7.7.
5. Failing the above: Inspector shall alone be entitled to decide any further action.
8.7 Systematic Inspection of Pipe Coating or Test Samples Taken at Pipe Ends
1. The inspection shall be performed upon completion of coating application on pipes cooled
down to ambient temperature, which shall be less than 60°C (per OSHA 140°F) and more than
5°C (41°F) in order to check the following characteristics:
a. Thermal characteristics
b. Cathodic disbondment (24 hr)
c. Interface contamination
d. Porosity
e. Flexibility
f. Impact resistance
g. Adhesion of the coating (hot water soak test)
2. These characteristics shall meet the criteria specified in Sections 8.7.1–8.7.8 below.
8.7.5 Flexibility
1. Standard: CSA Z245.20 (12.11).
2. Test frequency: Two tests among the coated pipes. If one test does not satisfy the
requirements, two other tests shall be made; none of them shall be defective.
3. Specification requirements: No cracking.
4. Test at an angle of deflection of 2.5 per pipe diameter length.
8.10 Repairs
See Section 7.6 for more information.