Professional Documents
Culture Documents
net/publication/300792891
CITATIONS READS
0 6,935
3 authors, including:
Some of the authors of this publication are also working on these related projects:
Green Supply Chain Assessment to Operations Improvement for Can Packaging Industry View project
All content following this page was uploaded by Suksan Prombanpong on 16 June 2016.
1 Introduction
2 Methodology
The process flow of tablet production is divided into 4 stages i.e. mixing,
compression, coating and packing respectively as shown in Fig. 1. Tablet dosage
form is classified into 2 type i.e. plain tablet and coated tablet (coating process is
required). The assignment task starts from the compression process which the mixing
process is assumed constant and the mixing machine is in the same line as
compression process. Once the materials are well amalgamated, the tablet will be
form by the punching machine and they will be coated and subsequently transferred
for packing and arranged into the box or container. Note that each processing step
must follow GMP/PICs (Good Manufacturing Product / Pharmaceutical Inspection
Co-Operation Scheme).
In this paper, tablet manufacturing at the GPO which produces altogether 142
items, requirement between 36,000 to 897,500,000 tablets per year and on average
order of 30-40 items per month. A considerable procedure for heuristic algorithm is
shown in Fig. 3. We begin by collecting the master data about each product and each
process and develop a heuristic algorithm for the priority setting of product items.
Next, we calculate the latest start and latest finish by the backward scheduling.
Finally, a heuristic algorithm for the MPS is designed.
The purpose of the algorithm is to classify each product item to Make to Order
(MTO) or Make to Stock (MTS) and ordering the item based on the priority setting
scenario. The flow chart of the algorithm is depicted in Fig. 4.
Latest start date is calculated for each process of tablet production to ensure that the
latest finish of each step still comply the sale order due date. The delivery lead time of
all products is 3 days which is considered for this research. We set
Let define:
2.4 Heuristic algorithm for selecting the start date and finished date
The sequent items from the priority setting rule must to determine the start date and finished
date by the simplified algorithm. The start date of each process should start before the latest
start date and check its standard time with the available time. If the capacity is enough to
accommodate the finished date is the same day. If it is not enough, check again with the next
day until the sufficient available time is occurred. Repeat this algorithm for each step of all
product sequences as shown in Fig. 5.
Fig. 5. The algorithm to choose start and finished date
3 Results
No. Product code No. of lots No. Product code No. of lots
1 P001 3 18 P072 4
2 P002 10 19 P074 13
3 P003 32 20 P081 5
4 P004 70 21 P097 10
5 P005 8 22 P099 8
6 P006 10 23 P102 6
7 P024 8 24 P106 1
8 P037 8 25 P107 2
9 P042 13 26 P113 4
10 P043 2 27 P114 2
11 P049 15 28 P115 2
12 P050 20 29 P116 15
13 P054 9 30 P117 30
14 P055 5 31 P118 10
15 P059 18 32 P123 30
16 P060 8 33 P131 20
17 P071 33 Total - 434
We prioritize the 33 products (434 lots) to 175 sequences by priority setting rule
as shown in Table 2. After that, the synchronized master production schedule of
tableting, coating and packing can be created the related start date to finished date
scheduling in each process as shown in Table 3.
Table 3. The example of the master production schedule on June 2014 (to-be)
4 Discussion
The master production schedule (to-be) on June 2014 can linkage the plan of all
production units with all products delivered on time whereas the experience planning
method (as-is) can scheduling on time only 80.65% of 434 batches. Moreover, the
study reveals that the total available time from the master production scheduling is
decreased by 3,755.40 hour or 26.30% and the manufacturer can know beforehand in
the production process problem because of the synchronized plan.
5 Conclusion
This research paper shows an attempt to apply an industrial engineering technique in
pharmaceutical industry. It is shown that the simplified algorithm is one of the
potential and useful methods for problem solving.
Although master production scheduling (MPS) has been studied and used by both
academia and industries for quite a long time, the real complexity involved in making
a master plan when capacity is limited, when products have the flexibility of being
made at different production lines, and when performance goals are tight due to
specifications, quality, efficacy and safety, but also the economy, has not yet been
presented in the literature in a simple and practical way. Thus, the heuristic algorithm
is proposed to simplify this task and make it more efficient.
References