You are on page 1of 7

Ain Shams Engineering Journal xxx (xxxx) xxx

Contents lists available at ScienceDirect

Ain Shams Engineering Journal


journal homepage: www.sciencedirect.com

Civil Engineering

Using BIM as a lean management tool in construction processes – A case


study
Ahmed.M. Eldeep a,⇑, Moataz.A.M. Farag a, L.M. Abd El-hafez a,b
a
Faculty of Engineering, Minia University, Aswan Agricultural Road, Minia, Egypt
b
Faculty of Engineering, El-Nahda University, Kornish Al Nile, Bani Sweif, Egypt

a r t i c l e i n f o a b s t r a c t

Article history: One of the most important reasons that may result in poor performance in Architectural, Engineering, and
Received 22 February 2021 Construction (AEC) is to create a visualization of construction processes and poor exchanging of informa-
Revised 24 July 2021 tion between different work teams. Lean construction seeks to reduce and eliminate waste in the con-
Accepted 31 July 2021
struction processes, while BIM seeks to improve collaboration between project team members.
Available online xxxx
This paper investigates BIM as a lean tool in the construction processes with a case study by concen-
trating on understanding the interactions between the design and implementation processes. The
Keywords:
research demonstrates that BIM can detect errors, omissions, and clashes before construction, which
Wastes
Lean Construction
helped reduce waste and make the construction processes more linear. BIM helped to minimize the
BIM design time to nearly 50% and supports prefabrication and installation activities to save up to one and
Information Flow a half months during execution by removing the waiting time wastes through construction processes.
Alternatively, the BIM model can help reduce the number of change orders and RFI’s; About 11% of
increasing the total contract price and 25% of increasing the total contract time could be avoided by using
BIM as a lean construction process tool.
Ó 2021 THE AUTHORS. Published by Elsevier BV on behalf of Faculty of Engineering, Ain Shams Uni-
versity. This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/
by-nc-nd/4.0/).

1. Introduction a flow, and all unuseful activities are wastes. Lean construction
provides principles and tools that help companies identify and
One of the crucial causes of declining construction project per- remove wastes from processes, improve productivity, and provide
formance is engineering-based information exchange problems. value to customers [7–9]; optimum results could be obtained by
Traditionally, the construction method starts in execution after continuous removing more wastes [10]. A composed strategy
the designer has finished drawings, which results in several kinds incorporates lean construction principles and value management
of clashes being created [1]. Many wastes are created by taking dif- to enhance the four significant areas of a company: philosophy,
ferent decisions through design and construction; generating process, people/partner, and plant, which lead to encourage com-
waste through design is complex [2]. In cooperation, lean and panies to apply sustainable practices to their company [11].
BIM help in removing many of those wastes [3]. According to [12], Individuals and teams can enhance the pro-
The five fundamentals of lean theory can be summarised as fol- cesses and systems they work with by using a realistic collection
lows: (value, value stream, flow, pull, and perfection) [4–6]. The of theories, tenets, methods, and ways of thinking, which means
lean objective is to raise the value to the customer while removing they are lean.
wastes. Lean construction considers the construction processes as

2. Interaction between BIM and lean


⇑ Corresponding author.
E-mail address: ah7madmo@gmail.com (A.M. Eldeep).
According to [13–15], BIM is a process rather than a tool or soft-
Peer review under responsibility of Ain Shams University.
ware. BIM is defined as a modeling technology and associated set
of processes for producing, communicating, and analyzing building
models. An exciting feature of the BIM process is that it makes
administration more transparent [16]. Through a questionnaire
Production and hosting by Elsevier
study, [17] stated a significant relationship between BIM benefits

https://doi.org/10.1016/j.asej.2021.07.009
2090-4479/Ó 2021 THE AUTHORS. Published by Elsevier BV on behalf of Faculty of Engineering, Ain Shams University.
This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/).

Please cite this article as: Ahmed.M. Eldeep, Moataz.A.M. Farag and L.M. Abd El-hafez, Using BIM as a lean management tool in construction processes – A
case study, Ain Shams Engineering Journal, https://doi.org/10.1016/j.asej.2021.07.009
Ahmed.M. Eldeep, Moataz.A.M. Farag and L.M. Abd El-hafez Ain Shams Engineering Journal xxx (xxxx) xxx

and its implementation. Awareness of BIM benefits and its imple- Through a case study [28] highlighted that if BIM features are
mentation could significantly increase project productivity and not correctly implemented and managed, this will lead to an unsta-
performance. ble and challenging process. The availability of technical expertise
BIM technology would be efficient in managing projects at any will encourage BIM implementation in construction companies
stage during the project lifecycle if the construction processes have and will support the team with exceptional experiences to simul-
been linked to BIM concepts [18]. It was concluded that imple- taneous implementation.
menting BIM applications in project management could ultimately
enhance the project management process and encompass all man- 3. Research methodology
agement areas unevenly.
There is no direct relationship between lean and BIM, and the This study is based on a case study aim to demonstrate that BIM
integrated project delivery (IPD) approach could be achieved with- leads to leaner construction projects and to investigate using BIM
out BIM. However, by adopting the integration of BIM with lean, as a lean tool or, in other words, BIM improves lean values and
the complete potential improvement can be achieved [19,20]; it reduces waste in the construction processes. It was decided to
is recommended that BIM be necessary to achieve the required col- select a project that did not use BIM or Lean management tools
laboration for IPD effectively. The best work sequence between the through the design or construction phases. This choice was made
different participants could be planned simultaneously by imple- to understand better the inherent practical issues related to BIM
menting lean concepts and the BIM model, reducing the activity and Lean’s simultaneous application to investigate if we can use
duration to around half. BIM is considered one of the best BIM as a lean tool.
resources for empowering lean [21]. The Construction of Classes, Classrooms, and Laboratories for
BIM reduces wastes and ineffectiveness of creating a distinct set the College of Administrative Sciences and Computer at the
of detailed drawings and reduces litigation likelihood, thus University of Dammam in Saudi Arabia fit the criteria thus estab-
enhancing any company/project’s lean outcomes [15,22]. By inte- lished and used to get this research conclusion. This paper focused
grating BIM with the Last Planner System (LPS), the work packages on applying many lean and BIM interactions to a project and
will be filtered, and the flow’s consistency and value will be explore the possible benefits of this integration through a case
increased [23]. study. The design phase focused on 3D direct digital workflow,
In another research [24] highlighted that using 4D CAD model- as-built before construction/prefabrication, and collision detection,
ing helps plan a stable workflow and deliver standardized proce- while the execution phase focused on the direct fabrication from
dures to the team. They emphasize that BIM also helps in BIM and change orders. This was done based on exploring a real-
delivering materials just in the time they needed and increased life project that depicts BIM and Lean’s relationships to report
the design’s confidence by increased collaboration between the experiences explicitly and lessons learned. This paper is part of
project team. an extensive study that aims to develop an innovative approach
Fifty-six interconnection recognized as hypotheses of interac- for information flow process model to be used in BIM-Lean
tion amongst BIM and lean were presented by [3]. They strongly projects.
corroboration the assumption that BIM and lean have a substantial
interaction. They concluded a framework could consider the realis-
tic challenges that firms face when adopting lean and BIM. Because 4. Case study
of the large number of BIM-lean encounters, it appears that parallel
implementation can be done slightly. The successful approach is to Dammam University just completed the new Administrative
identify the desired interest, carefully get experience to plan and Sciences and Computer College, which had 48 classrooms, 8 labo-
execute BIM/lean accordingly, and move forward in gradual steps ratories, and offices with a total cost of 36 million SAR with a tra-
to leverage more positive connections between BIM and lean. ditional procurement method which was Design Bid Build. The
In the following paragraphs, attempts to explore more synergies project was completed as of November 2015, using only 2-
amongst BIM and lean construction: Dimensional drawings. The project was handled by the University’s
Based on a four-year case study, and to evaluate the impact of Department of the Projects and Construction Services, which the
what [25] called (CAVT) ’Computer Advanced Visualization Soft- first researcher had been working there at that time, and for this
ware,’ they applied a collection of lean basics as the conceptual project, he worked as PMC (Project Manager Consultant). The
framework. They concluded that using CAVT reduces waste, design stage took about four months, followed by the bidding pro-
improves flow, and adds value to the customer, demonstrating a cess (about two months), then the execution stage, which took
sturdy interaction between CAVT and lean construction. 22 months. For this project, no BIM management tools or lean
In a case study, [26] implement the Lean Project Delivery Sys- techniques had been used.
tem (LPDS) using 3D and 4D CAD. They provide a brief guideline To test the hypothesis, the researchers evolved the traditional
on applying the Virtual Building Technologies effectively during 2D CAD drawings for the university project to a full 3D integrated
the lean design phase of LPDS. In another attempt, [27] confirmed BIM model to enable effective use of a 3D model. A redesign for the
by the findings of a case study that Virtual Design and Construction project was done by using Revit and Naviswork software. The time
(VDC) improves the LPDS when implemented at the required spent modeling the project was approximately two months. (Fig. 1)
levels. shows a comparison between 2D CAD drawings and the 3D BIM
Ten detailed case studies have been provided by [15] on BIM model.
application; two concentrated on projects where prefabrication
has been widely used. They remark that close cooperation is 5. Results and discussion
required between the main contractor and subcontractor for
adopting lean during fabrication procurement of prefabricated 5.1. 3D direct digital workflow
components by subcontracted suppliers to confirm installation
with the necessary resources on site. Since BIM delivers a proper The university project followed the traditional information flow
design model, it provides a base for better preparation and (2D CAD). The design stage started with the preliminary design,
scheduling for subcontractors and ensures that staff, equipment, followed by an appraisal from the owner and a repetitions (re-
and materials reach in the required time. work) period. Once the owner reviews and accept the concept
2
Ahmed.M. Eldeep, Moataz.A.M. Farag and L.M. Abd El-hafez Ain Shams Engineering Journal xxx (xxxx) xxx

Fig. 1. Comparison between 2D CAD drawings and 3D BIM model.

design, the schematic design is started. A review and iterations on raising the actual dimensions from the site, which determines
period follow in a similar style for schematic design. Once the sche- the exact dimensions of the hollow core panels, after that, the
matic design ended, the design players moved to the subsequent design and shop drawings of the HCS submitted. Regarding to
detailed design stage after receiving the owner’s approval. the consultant’s approval for the design and the shop drawings,
By comparing the conventional 2D CAD method with the gener- the subcontractor started the hollow core panels’ prefabrication
ated BIM-based model, many wastes can be removed, and many process off-site. Then it was transported and installed on the site,
benefits can be gained from the new 3D model; and this process took three weeks (for a one-floor slab); see (Fig. 2).
Full design model: The detailed designs will straightforwardly It is easily noticeable that the three-week delay (for a one-floor
be derived from the completely corresponding 3D model, including slab) in designing and installing the hollow core panels is a waiting
all of the required details needed for shop drawing or site time waste as defined by lean. The generated BIM model can elim-
installation. inate and remove that kind of waste, as the model contains accu-
Improved visualization: 3D models were developed and saved rate information and dimensions about the building. A new
to 3D Revit with a physical model, which allows the owner and approach can be followed to eliminate this waste; After completing
contractors to access, view quickly, and visualize the project’s the structural design, an iterative process should be initiated
details with the possibility to use the appropriate information. between the design team and the subcontractor of the HCS. This
Waiting time waste: With the newly generated BIM model, the process will be built on sharing and exchange of information using
design team will not wait for each other to proceed. Therefore, the BIM model. The subcontractor will receive the model, extract
early and easy data will be shared through the model before data the quantities and dimensions of HCS, and make the design and
completion so that the multidisciplinary teams (Architecture, details of the HCS. After this, the design team will reintegrate the
Structural, and MEP Engineers) can concurrently develop designs. HCS detailed design with the original model and check for conflicts.
Regarding to the case study, BIM helped reduce the amount of time It will then be easy to synchronize during the execution phase
required for the design process to nearly 50% by reducing the wait- between poring the main beams that carry the hollow core panels
ing time waste in the traditional design process. and prefabricating the panels off-site to have the hollow core pan-
Reduce steps: By removing unnecessary steps in the conven- els ready while the bearing beams are casting on site. By using this
tional 2D CAD paper-based process, a greater consistency will be approach, the structural design will be finalized early with a time-
enabled. In addition, it also eliminated overhead time for drawing frame, as well as the detailed design of other trades and related
layout, printing, and delivery. Collaborative work using the BIM activities. The as-built model will be ready before beginning in exe-
model will enable opportunities to save more time, for instance, cution; thus, the design and shop drawings were combined.
clash detection and off-site prefabrication; this may help a lot in Using the digital BIM model will reduce the paper-based work-
avoiding many issues that could occur during implementation. flow; it will be easy to extract the shop drawings from the digital
Continuous information flow: The information will be up-to- model for approval decisions and access the as-built HCS model
date with a BIM-based design through the early exchange of infor- before construction. Effectively, tight subcontractor integration
mation between members. This allows adjustments, modifications, and several design review iterations will reduce any inconvenient
and development in the least possible time to the design. The clear HCS panels onsite during installation.
visualization of design will facilitate communication between dif- Using the BIM model and this well-planned process, the HCS
ferent players and allow a continuous flow of information. erection could be completed three weeks early (for a one-floor
With the new BIM model, the owner can participate early in the slab) during construction and without any modifications. The
design procedure, eliminating late decisions on the design by BIM model can help save up to one and half months for the univer-
extracting any design information from the model. This will save sity project using As-built before construction/prefabrication for
several wastes of rework in case of rejection. Also, continuously the HCS by removing the waiting time waste, leading to achieving
engagement the owner as the design developments will maximize lean. Likewise, this can be applied to install other elements in min-
the value throughout the project’s life cycle by early feedback from imum time, such as HVAC, electrical, and IT systems. Moreover, the
the owner. work environment changes will be reduced, and the people and
materials’ movement will be minimal. That will improve site safety
5.2. As-built before construction / direct fabrication from BIM and increase the team’s morale, and they will have greater confi-
dence and pride in their work.
The applied statical system in the university project was the For this project, the BIM model can involve many onsite activi-
Hollow Core Slab (HCS). The method of implementing HCS depends ties such as structural concrete, architectural elements (walls,

3
Ahmed.M. Eldeep, Moataz.A.M. Farag and L.M. Abd El-hafez Ain Shams Engineering Journal xxx (xxxx) xxx

Fig. 2. Installing the hollow-core slab (HCS) onsite.

doors, ceilings, etc.), mechanical, plumbing, and electrical. For conditioning ducts with those dimensions under the beam. The
example, there was a lack of skylight detailing in the 2D cad draw- mechanical design drawings did not contain details and installa-
ing, which does not specify many details needed to implement sky- tion, thus did not signify the entire depth of the elements precisely,
light onsite, especially the skylight’s pyramid shape, See (Fig. 3). which caused a collision between the concrete beams and the
With the newly generated BIM model, making all the details of ducts of conditioning.
the skylight pyramid’s shape and specifying all the required This case included a significant redesign of the entire condition-
dimensions and heights has become easy. ing ductwork to suit the concrete beams’ dimensions and depth. A
collateral waste was generated as the other trades needed to revise
their drawings to be tailored and integrated with the new air con-
5.3. Collision detection
ditioning duct arrangements. This issue arose due to the lack of
visualization and concurrence of the site’s existing layout and com-
Traditionally, the design consultants use overlaid drawings to
munication breakdown between the subcontractor and the general
spot clashes manually. Using this method leads to many clashes
contractor relating to the conditioning duct systems’ design. More-
between various elements during the implementation of projects
over, due to the owner not waiting for all project designs to be
that require much time and cost to solve those clashes. This tradi-
completed, the construction began without completing the HVAC
tional method does not enable the discovery of clashes early, espe-
designs. A subcontractor made the HVAC designs through the main
cially when using 2D CAD drawings.
contractor, which was incompatible with what was implemented
Several clashes were discovered during the execution of the
onsite, especially the concrete parts.
university project. For example, clashes between mechanical
This problem had been resolved by redesigning the HVAC sys-
works and ducts of conditioning with substantial parts of the
tem and changing the paths, sizes, and dimensions of ducts, and
skeleton and clashes between mechanical works and fire alarm
changing many concrete potholes. Ultimately, this issue resulted
and extinguishing work occurred. The project faced many clashes
in a three-week delay in completing the project and nearly cost
between different elements through execution, which varied
200,000 SAR to redesign and remove the wrong duct installation
between minor and significant clashes.
and change the duct opening locations.
The main clash faced during this project’s implementation was
(Fig. 4) shows a comparison between the problem that occurred
the inadequacy of central air-conditioning ducts’ sizes and dimen-
in the presence of a clash between the air-conditioning ducts and
sions due to the total depth of the beams of 1.0 m; it clashed with
concrete beams (improper installation for ducts), and how this
the main beams of the classrooms. Because of the suspended
problem could be easily avoided when creating a BIM model,
ceiling’s height restriction, it was not easy to move the air-

Fig. 3. Onsite installation of the skylight.

4
Ahmed.M. Eldeep, Moataz.A.M. Farag and L.M. Abd El-hafez Ain Shams Engineering Journal xxx (xxxx) xxx

Fig. 4. On-site wrong installation for air-conditioning ducts as it interfered with the concrete beam and how this clash could be avoided if using the BIM model.

which can save time and cost to solve this problem discovered dur- semi-integrated one. The BIM model will enhance information
ing project execution. The BIM model enhances the detection of transmission to the design team and provide an environment that
clashes and errors quickly and early in the project, enabling to allows them to interact and collaborate more effectively and make
achieve significant cost savings compared to the traditional design timely, integrated, and accurate decisions after eliminating many
process. design stage wastes.
Revit and Navisworks programs had been used to detect the col-
lisions and clashes for the university project. Many clashes and 5.4. Change orders
errors were recognized and fixed (over 100 clashes); represents
clashes between different elements and components of the project Change orders impact the project’s cost and schedule signifi-
like architecture elements, concrete structure, mechanical, electri- cantly, and therefore, the existing research will examine how
cal, and plumping. (Fig. 5) illustrate some of the detected clashes BIM affects change orders and change order management. A
between different elements in the 3d model. change order is usually the result of a change in the scope or time
In the AEC industry, design errors are common because multiple of a project initiated by the owner, unforeseen conditions requiring
and various participants like Architects, Civil, and MEP engineers change, or a design error/omission resulting in change. An owner-
do the building’s design work. Rework, and construction waste originated change at its core is a change in the project’s scope or
can result from these design errors. Design reviews and clash duration, which the owner asks. Change orders involving unfore-
detection are the BIM-based techniques to minimizing construc- seen conditions are usually the result of physical conditions that
tion and design waste by eliminating design errors detected in differ from what the initial contract agreed. Because of design
construction. errors/omissions, inadequate designs prevent the contractor from
The 3D model precisely presents the interconnection between completing their work result in a change order. Design reviews,
each element and enables teamwork between different trades. It coordination meetings, checklists, and 3D modeling are common
can be said that using the BIM model for the university project ways to avoid change orders.
can save at least three weeks and 200,000 SAR in the project result- Projects at Dammam University follow a strict deadline, and
ing from the design errors. Furthermore, the conventional design therefore they rarely allow time extensions for contracts. This
stage could be transformed from a flawed design process to a paper will determine each change order’s cause and allow for a

Fig. 5. Clashes between elements of different disciplines in the 3D model.

5
Ahmed.M. Eldeep, Moataz.A.M. Farag and L.M. Abd El-hafez Ain Shams Engineering Journal xxx (xxxx) xxx

Table 1
Numbers and types of change orders in the university project.

Change Order Type owner-initiated changes design errors/omissions unforeseen conditions


No. of change orders 12 5 3

more accurate picture of the influence BIM enforces on change affect the original contract price by 11% and the original contract
orders if BIM could have made an impact. To see what kind of time by 25%.
change BIM has the most impact on, classified for each change Approximately 17 from 20 change orders (more than 80%) that
order needed. Changes originated by the owner (owner-initiated), belong to owner-initiated changes and design errors/omissions
design errors/omissions, and unforeseen conditions are the three changes might be avoided using the BIM model. A 3D model’s ben-
main categories. efit could help visualize rooms, layouts, and equipment that could
After reviewing the change orders with the case study, it was prevent changes. The BIM model could be used when plans and
determined that there are 20 change orders and about 70 RFIs specifications do not fulfill university standards, reducing change
(Contractor Requests For Information) in the project (Table 1 orders and RFI’s.
reflects the numbers and types of university project change
orders).
From (Table 1) it has become apparent that owner-initiated 6. Conclusions
changes are the project’s most significant source of change. During
the project implementation, there had been many site visits from Building information modeling helps eliminate many wastes
the owner (especially from the university’s vice president). Those during the construction process, such as design errors/inappropri-
visits reflected many of the owner’s changes to be compatible with ate design, poor communication, and unexpected changes in
the project’s educational use. Many changes were made, such as designs during execution. BIM enables creating an accurate model,
places and number of computer laboratories, changes in the qual- rich in information and free of clashes, which helps to make the
ity of the finishes used, and changes in many classrooms by re- right decisions during different construction stages.
division to be distinct for faculty members. Approximately 12 This study shows that implementing lean using BIM in the
change orders were handled to fit the changes requested by the design works contributes significantly to project efficiency. BIM
owner. Furthermore, the effect of those changes was addressed helped reduce the time required for the design progression to
and calculated on the project’s schedule and budget. Consequently, nearly 50% by reducing the waiting time waste. The BIM model
the timetable was modified by adding additional periods and can help save up to one and half months for the university project
adopting all additional costs for those changes. through implementing the Hollow Core Slab (HCS) just in time by
The main reason for those changes made by the owner is that removing the waiting time waste and achieving lean principles. On
the owner did not have a complete visualization of the project at the other hand, design reviews, and clash detection are the BIM-
the project start. When the owner saw the two-dimensional draw- based technique to minimizing construction and design waste by
ings for the project at the early stage, he almost did not understand eliminating design errors detected in construction. It can be said
what those drawing reflects. During implementation and with rou- that through the BIM model, clash detection can save at least three
tine site visits, the picture becomes more apparent, leading the weeks and 200,000 SAR at the university project, which results
owner to make changes during implementation. Nevertheless, if from the design errors.
the owner saw a three-dimensional or four-dimensional model, Even though eliminating all change orders that can arise at any
he will clarify all his observations and opinions to be done during project will be almost impossible, it seems that BIM can reduce the
the design stage. cost and the time of change orders as a result of this study. The
The evolution of the model through stages will help the project most significant reduction in change order was discovered when
to save time and money. The majority of BIM software has a high BIM was implemented on the project. Approximately 17 from 20
degree of visualization capabilities in response to the owner’s change orders (more than 80%) that belong to owner-initiated
demands, which can prevent making late changes based on physi- changes and design errors/omissions changes might be avoided
cal sight. The model enables a walkthrough, which ensures that using the BIM model, making the project more linear.
owners clearly understand and acknowledge the design. The owner On the university project at Dammam University, using BIM as a
will not have to wait till the work begins to see his project physi- tool will help achieving lean principles by adding value to the
cally. Through visualization using 3d, and 4d in the early stages of owner and reducing waste. About 11% of increasing the total con-
the design, it will be easy to get early feedback and comments from tract price and a 25% increase in the original contract time could be
the owner about the design, which minimize changes later through avoided.
the construction phase.
On the other hand, five change orders were detected due to
Declaration of Competing Interest
design errors/omissions; as we mentioned earlier, the primary
design errors are the inadequate HVAC system design with other
The authors declare that they have no known competing finan-
disciplines. This change order resulted in a three-week delay in
cial interests or personal relationships that could have appeared
completing the project and cost nearly 200,000 SAR to redesign
to influence the work reported in this paper.
and remove what was installed from ducts and change the
openings.
The initial project cost was about 32 million SAR after the con- References
tract had been signed between the owner and the general contrac-
tor, ended with 36 million SAR due to the modifications made [1] Tommelein, I.D. and S. Gholami. Root causes of clashes in building information
according to the project’s change orders. The project’s initial dura- models. in Proc., 20th Annual Conf. of the Int. Group for Lean Construction,
Curran Associates, Red Hook, NY. 2012.
tion was 18 months, ended with 22 months after adding the exten- [2] Koskela L. Application Of The New Production Philosophy To Construction, Cife
sion of time due to change orders. It can be said that change orders Technical Report #72. CA: Stanford University; 1992.

6
Ahmed.M. Eldeep, Moataz.A.M. Farag and L.M. Abd El-hafez Ain Shams Engineering Journal xxx (xxxx) xxx

[3] Sacks R et al. The Interaction of Lean and Building Information Modeling in [20] Eckblad S et al. Integrated project delivery-a working definition. AIA California
Construction. J Constr Eng Manage 2010. doi: https://doi.org/10.1061/(ASCE) Council: Sacramento, CA; 2007. p. 25.
CO.1943-7862.0000203, 968-980. [21] Clemente J, Cachadinha N. <BIM-lean synergies in the management on MEP
[4] Womack, J.P., D.T. Jones, and D.J.N.Y.R.A. Roos, The machine that changed the works in public facilities of intensive use a case study.pdf>. 20th Annual
world: the story of lean production. 1991. 2003. Conference of the International Group of Lean Construction, 2013.
[5] Björnfot, A., An exploration of lean thinking for multi-storey timber housing [22] Sacks R, Radosavljevic M, Barak R. Requirements for building information
construction: contemporary Swedish practices and future opportunities. 2006, modeling based lean production management systems for construction.
Luleå tekniska universitet. Autom Constr 2010;19(5):641–55.
[6] Brookfield, E., et al. The architectural technologist’s role in linking lean design [23] Sacks R, Treckmann M, Rozenfeld O. Visualization of work flow to support lean
with lean construction. in Proceedings of 12th Annual Conference on Lean. construction. J Constr Eng Manage 2009;135(12):1307–15.
2004. Citeseer. [24] Sacks, R., et al., Analysis framework for the interaction between lean
[7] Alarcón, L., Lean construction. 1997: CRC Press. construction and building information modelling. 2009.
[8] Erol, H.H., Identifying the effects of Lean Construction principles on variability [25] Rischmoller L, Alarcón LF, Koskela L. Improving value generation in the design
of project duration. 2014. process of industrial projects using CAVT. J Manage Eng 2006;22(2):52–60.
[9] Musa, M.M., C. Pasquire, and A. Hurst, Where lean construction and value [26] Khanzode A, Fischer M, Reed D. Case study of the implementation of the lean
management meet. 2016. project delivery system (LPDS) using virtual building technologies on a large
[10] Plenert, G.J., Lean management principles for information technology. 2011: healthcare project. International Group on Lean Construction; 2005.
CRC Press. [27] Khanzode A et al. A guide to applying the principles of virtual design &
[11] Dante Silva*, B.V., Kevin Lawrence De Jesus, Lamberto Marcial Jr., Raphaela Lois construction (VDC) to the lean project delivery process. CIFE: Stanford
Ejera, Clara Vina Villa-Real, Jan Marvin Zarraga, Design Initiative University, Palo Alto, CA; 2006.
Implementation Framework: A Model Integrating Kolmogorov-Smirnov in [28] Gómez-Sánchez JM, Ponz-Tienda JL, Romero-Cortés JP. Lean and BIM
Sustainable Practices for Triple-Bottom-Line Principles in Construction Implementation in Colombia; Interactions and Lessons Learned, in Proc. In: 27th
Industry. Civil Eng Archit 8(4): 599–617, 2020, 2020. Annual Conference of the International Group for Lean Construction (IGLC). p.
[12] Mossman, A., What Is Lean Construction: Another Look - 2018, in 26th Annual 1117–28.
Conference of the International Group for Lean Construction. 2018. p. 1240–
1250.
[13] Hardin, B. and D. McCool, BIM and construction management: proven tools,
methods, and workflows. 2015: John Wiley & Sons. Ahmed Mohamed Eldeep has over 20 years of experi-
[14] Eastman, C., et al., BIM handbook: A guide to building information modeling ence in driving Civil projects management in Egypt &
for owners, managers, designers, engineers and contractors. 2011: John Wiley Saudi Arabia. His distinction of executing prestigious
& Sons. projects of large magnitude within the strict schedule,
[15] Eastman, C., et al., A Guide to Building Information Modeling for Owners, cost, and quality. He has a Master’s level education in
Managers, Architects, Engineers, Contractors, and Fabricators. 2008, John civil engineering (M.Sc.) from Asuit University, Egypt
Wiley and Sons, Hoboken, NJ. with certifications in project management (PMP, PMI-
[16] Kymmell, W., Building Information Modeling: Planning and Managing RMP, Six Sigma, and Scrum Fundamentals). He also
Construction Projects with 4D CAD and Simulations (McGraw-Hill Working as a lecturer at the Arab Academy for Science
Construction Series): Planning and Managing Construction Projects with 4D and Technology (AAST) to teach project management
CAD and Simulations. 2008: McGraw Hill Professional. subjects and supervisor of graduation projects for pro-
[17] Al-Ashmori YY et al. BIM benefits and its influence on the BIM implementation
ject management.
in Malaysia. Ain Shams Eng J 2020;11(4):1013–9.
[18] Shaqour EN. The role of implementing BIM applications in enhancing project
management knowledge areas in Egypt. Ain Shams Eng J 2021.
[19] Sacks R et al. Interaction of lean and building information modeling in
construction. J Constr Eng Manage 2010;136(9):968–80.

You might also like