0 ratings0% found this document useful (0 votes) 1K views12 pagesTC 36
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here.
Available Formats
Download as PDF or read online on Scribd
MADHYA PRADESH WATER RESOURCES DEPARTMENT
Design Series Technical Circular No.36
3-9-93
(Issue Vide Memo No.229 /BODHI/R & C/TC/11/93, Dt.*9%..
Guidelines for design_of_stop_dams_on_continuous._pervious
foundations.
1
General
Stop dams are barriers constructed across nalla and
yivulets to store water to certain depth confined
well within the top of river bank level.
In general, stop dams are to be constructed across
streams having hard impervious strata at or near
their bed level. However, these dams may
exceptionally be required to be constructed on
rivers having permeable foundations. In which
context, a stop dam can be defined as a_ low,
barrage/weir and should in principle be designed
based on the design criteria being applied for
design of barrages/weir.
Following guidelines are therefore being issued for
design of stop dams across streams having continuous
pervious foundations.
These guidelines shall be referred to as a
complementary to the guidelines issued Vide
Technical Circular No.30 Vide BODHI's memo No.215/
Bodhi/ R&C/ TC/ 11/ 88 Dated 29.04.91.
2. Data_required for_design.
Data required for design of such stop dams are listed
below:~ :
2.1 Catchment area_(M)-
catchment area upto the stop dam site may be worked
out from Topo sheets of scale ratio 1:50,000 issued
by the G.S.I. However, for catchment area less than
2.5 sq.km actual catchment. area survey should be
carried out.
2.2 Hydraulic gradiont_(8)s. J
Hydraulic gradient or average water surface slope,
considering the nalla reach 0.5 km. u/s and 0.5 km
a/s of the proposed stop dam site should be worked
out for the water surface of the main stream flowing
through unobstructed river cross section.
DRAFT2.WPS Page-1
ne neaheaenremlamn inertia
\GO2.3 Observed Mighest Flood Level. (H.E.L.)
W.F.L. may be confirmed from local inquiry or if
possible by actual observations
2.4 Observed. Maximum Flood:
The maximum flood, on the © isis of discharge data
available for as many years as possible should be
calculated.
2.5 Cross Section:
cross section of nalla at proposed stop dam site may
be plotted on a convenient scale after carrying out
proper survey.
2.6 Information about foundat Lon:
Type and extent of strata available at construction
site may be confirmed by excavating, trial pits at
the dam site. The depth of a trial pit should be
equal to H or 1.5 m which ever is more. Where “H!
represents height of stop dam above stream bed
level.
2.7 Yalues of constants_and_coefficients:
a) Manning's 'n!
b) Dickens Coefficient 'c!
c) Lacey's Silt factor 'f!
a) A constant 'Cy," depending upen fineness of
material.
Degign procedure:
3.1 The maximum flovd to be taken as designed. flood
should be based on the observed fleod of as many
years as possibic. The value should #iso be checked
using frequency snalysis in which past xecord of
the floods for as many years as available is used
and with stat:stical approach, flowd of 50 year
return period ‘; computed. 50 year return period
flood indicates a value of the flcoi which occurs
atleast once in 50 years.
oF bage-23.2 The following Formula may also be used for working
nut max. flood in casey.) above is not possible.
a) Dicken!s..formula:
= (m3/4 in cumec
where,
Q = Max.flood discharge in cumee for 3 hour spate.
M catchment area of the stream upto stop dam site in
sq.km.
© = Dicken's coefficient. It's value in M.K system
varies from 11 to 25. Higher value be adopted for
steep and small catchment areas and for dams of
greater hazard potential.
b) Prolonged _£lood:.
Apart from spate of high intensity and short
duration (as above in case of Dicken's formula),
maximum flood discharge for prolowse! floot which
will depend on the type and slope of the catchment,
may also be worked out bascd on following va‘ues:
i) For catchment area upto 500 sq.km. Run olf duc
to rainfall of 1.50 cm per hour for 24 hour:
ii)For catchment area above 500 sq.km; Run off due
to rainfall of 0.75 cm per hour. for 24 hours be
adopted. :
c} Using Manning's equation max. velocity may be found
out corresponding to the maximum flood discharge. At
the observed M.W.L. the area may be calculated. The
discharge will be = A x V. Manning's equation he
written as below:
v= ayn x (s)}/? (R)2/?
where
Vo Velocity of Clow in virgin stream in m/s.
$ » Water surface slope
R- aA/P
1 ~ Wetted perimeter of nalla in m
A= Area of nalla section corresponding to M.W.L. in
sq.m. :
n= Rugocity constant or Manning s constant. (For
rivers in bad order and regime. the value may be
adopted as 0.03)
3.3 Adopt the highest value of flood as worked out from
above 3.1 or 2.2 and co-relate it with the revised
M.W.L., if required, by trial and error method,
satisfying the Manning's equation.
DRAFT2.WPS Page-33.4 Fix up the top level of stop dam. It should,
however, not be more than 2 m from the deepest river
bed level. Lay out of the stop dam should be such
that the piers and openings as provided should give
max. opening area.
3.5 Find out afflux under two conditions of flow:
i) (At the maximum flood discharge.
ii) At the discharge when the virgin nalla flow
level is at proposed top elevation of stop dam.
+ v2 + + a2 +
Afflux= | -- 40.015 | | --- -a1
+ 2g + + a2 +
Where,
V= Velocity of flow through the virgin section
in m/s
A = Unobstructed area of cross section of nalla
in sq.m.
a = Reduced area of Nalla Cross section on
account of obstruction due to construction in
Sq.m.
9 = Acceleration due to gravity. In M.K.S. = 9.81
n/s/s.
Afflux-The difference of water elevation at any
point upstream of obstruction before and
after its construction. Maximum afflux
occurs just upstream of obstruction.
3.6
Where
discharge per metre length of nalla.
Max. discharge in cumec.
p = Wetted perimeter in m.
R = llydraulic mean radius in m.
(ii) Add 20% for concentration of flood
qd = design discharge = 1.20 x q
3.7 Eind out the scour depth below H.F.L.
Ds = 1.374 ( qd2/£)1/3
Where,
bs = Depth of scour in m, measured from the Il.F.L.
qd = Design discharge in cumec per m run of the nalla
bed.
£ = Lacey's silt factor = 1.76 fie
mr = Average particle size in mm. (In absence of any
value this may be taken as 0.80.)
DRAFT2.uPS Page-43.8 Length of floor: MI
Length of floor shall be:
0
(4) Ls -----
0.12
or (41) Le cp xn :
where,
Ho= Maximum hydraulic head under any working
condition.
SL = A constant which may be taken as 7 to 12. (For
fine sand the value may be taken as 12. The
value may be reduced for silty sand.)
Larger floor length worked out by (4) & (ii) above
may be adopted.
3-9 Thickness of floor
Floor thickness may be worked out from the formula
H
t= 1.20 ~--------
(re-1)
Where,
t Floor thickness in'm
H Gan iTum hydraulic Head acting over floor of stop
dam in m. under any working condition.
Fe = Density of concrete in T/m3 which generally
adopted as 2.4,
The thickness of the floor may be gradually reducea
Fo 0.5 m. at the downstream end of the floow,
3-10 Repth of cut_offs:.
Measuring from HFL, provide depth of U/s & D/s_cut
offs as 1.2 Ds and 1.5 Ds respectively. Where,~Ds!
denotes depth of scour. However, the depth of cutoff
quail not be less than 2 m from the river bod level.
Minimum thickness at the bottom of cut oft should be
0-50 m and should be well connected with tloo
DRAFT2.WPS Page-53.11 Length of Loose apron:
it has to be provided beyond the downstream end of
the floor.
Length of loose apron (La) with 35 cm. average size
fhe TOOK fragments / boulders,should be greater of
the following:
(1) Equal to the depth of scour in m
(41) Equal to the total width of clear opening in the
stop dam in m.
3-12 Bank protection:
Bank protection against erosion is generally
unavoidable for both up stream and dow2 strean
portions. This increases the cost of stop dam
Substantially and sometimes may be too costly and
Proposal has to be dropped. Routinization of
protection is not possible and decision may vary
from site to site depending upon the hydraulic
gradient and depth of flow, shape and depth of bank
and type of soil. It is advised to provide the down
stream bank protection up to the full léngth of
bank. The protection may be made of conerets blocks
Gr fs rock fragments both flexible. The average
Gimension of which should not be less than o/s °s on
ane gizections laid over the trimmed nalla’ pane”
hue Proposal of constructing the wing walls can acy
be considered. The height of such Protection should
ee etary above the top of dam or twice the marsnac
afflux under condition 3.5(ii) above.
3-13 Bank connections:
The structure of the stop dam should be keyed in to
the banks minimum two and half times the maximum
head of water above foundation level in case of soil
Sroutetthered rock. In case of sandy soil, keying
fhould be minimum three and half tines’ the naximum
head of water above foundation.
2-14 2% typical design along with drawing of stop dam on
Permeable foundation is enclosed.
DRAFT2. WPS. Page-63.15 This technical circular is mainly intended to
introduce the field officers to a _ sct design
procedure to fulfill the present day needs wherever
required. Nothing herein need be taken as dogmatic
and the implementing officers are absolutely free
without making any reference to the higher up, to
make such changes as the site conditions may warrant
and to improve upon the design if they find that
such changes will improve safety and quality of
work along with achieving economy on the basis of
their past engineering experiences.
b— *
A
wee 693 Wer ape
TS.P. PALT WAL) K. AMBAJ! ))"
Chief Engineer ngineer-in-Cnief
BODHI, Bhopal (M.P.) Water Resources Department
Bhopal (M.P.)A_TYPICAL_DESIGN..OF..STOR_DAM ON PERYIOUS FOUNDATION
STEP-1 DETERMINATION OF DESIGN FLOOD
(i) As per clause 3.2 of 1.C. using Dicken's
formula
Qg = cH 3/4
Q = 19.4 (89.427)9/4
= 564.16 cumec sees
(ii) As per clause 3.2(b) (i) of T.C.
89.427x1000x1000
Qe meee cece n beeen ten nenn=
100 60x60
= 372.61 cumec
(iil) as per clause 3.2(C) using — Manning's
equation at observed HFL i.e. 101.00 m (in
present case)
1
Q = Ax v= aAx-- x 82/2 x (R)2/?
n
since s = .0018 and R = 3.08 (as worked out)
1
=188.50 x --x (0.0018) 2/2 x(3.08)?/3
0.03
=564.16 cumec tetris c
value larger among A and B above should be
approximately equal to the value C, In case it
aiffers considerably change the HFL to match the
discharge value by trial and error.
STEP-2 DETERMINATION OF AFFLUX,
(i) AT THE MAXIMUM FLOOD DISCHARGE.
(All openings closed)
1
vow nex s2/2xR?/3
n
= 2.9937 m/sec.
Say 3 m/sec.
+ + (188.50)?
40.015 | }--—
2x9.81 + +(188.50-20)?
Page-1(ii) At the discharge, when the flow in virgin nalla is
at the’ devel of proposed stop-dam-crest and atl
gates open.
1
R2/3g1/2 (flow in virgin nalla at the
n level of proposed stop dam-
crest)
(1.5)2/3 (0, 0018) 1/2
0.03
= 1.85 m/sec.
+
(1.85)?
won---= 40.015
2x9.82,
Afflux
toe nee +
{
}
+
= - 0.9945 m
Say lm beeen ee AZ
(iii) Afflux when the gates are closed for the discharge
under condition when the flow in virgin nalla is at
the level of proposed stop-dam-crest.
Under this condition the stop dam may be assumed
to behave as broad crested weir.
Q = 1.85 x 20 = 37 cumec.
2 =cxLx H/2
1.6 x 12 x H9/2 = 37
Ho = 1.548 m
Say 1.60 m bee ee ee eA
Compare Al, A2 and A3 and adopt maximum value as
afflux.
Page-2Ser
DRVERMINATION OF CUP-OFF DEP
Flood Discharge per metre =q =
61.219 - 2 x 3.08
= 10.246 Cumec/m
Design flood discharge per metré
qd
= 1.20 x 10.246
= 12.30 cumec/m
Ds = ‘Scour depth
Where f = 1.76 x(0.8) 1/2= 1.574
Ds = 6.29 m
Say 6.50 m
(i) u/s cut off = 1.2 x Ds
= 1.2 x 6.50 = 7.8m
Elevation of bottom of u/s cut off
= 101 - 7.8 = 93.20 m
Check: .
{This level should be < (The minimum nalla bed level~ 2 m)
i.e. 94,50 - 2.0 = 92.50 m
Thus the bottom of u/s cut off is provided at BL 92.50 m
(ii) d/s cut off = 1.5 x Ds
1.5 x6.5 = 9.75 m
Elevation = 101.0 - 9.75
= 91.25 m
check:
This level should be < (The nalla bed level - 2 m)
ise. 94.50 -2.0 = 92.50 m
provide a/s cut off bottom at EL 91.25 m. ) »
Page-3STEP-4
STEP-5
STEP-6
DEVERMINATLON OF FLOOR LENGTIL
Find out the maximum operative head as follows:
(4) Top level, of stop dam - lowest ‘a/s nalla’ bed
level = 2.0 m
(ii) Maximum afflux as worked out under STEP-2=1.60m
Maximum Operating Head H = 2m
H
(i) Length of floor L =-----
0.11
2
= cn-- = 18,18 m
O.11 al
(ii) Length of floor L = cy,x H
=12x2= 24m
Provide length of floor larger of (i) and (ii)
above.
Thus length of floor provided= 24 m
DETERMINATION OF FLOOR THICKNESS
"
=
4"
©
a
Maximum Operating Head
a
Thickness of floor
= 1.75 0
The floor thickness may be gradually reduced to 0.50
m as shown in the drawing.
LENGTH OF LOOSE APRON
(4) Scour depth = 6.5m"
(i4i)Potal Length of opening = 4 x 1.5 = 6m
Provide length of loose apron larger of (i) and (ii)
above.
Thus length provided = 6.50 m
~--###--~
Page-4FIN