Professional Documents
Culture Documents
Presented to
The School of Mechanical and Manufacturing Engineering
Mapúa University
Submitted by:
May 2021
Table of Contents
CHAPTER 1: INTRODUCTION.........................................................................................5
1.1.1 Background of the Study...................................................................................5
1.1.2 Location of the Power Plant..............................................................................6
1.1.3 Load Curve of the Locality.................................................................................7
1.2 FUNDAMENTAL CONCEPT OF GEOTHERMAL POWER PLANT.......................8
1.2.1 Principles of Geothermal Power Plant..............................................................8
1.2.2 Types of Geothermal Power Plant....................................................................8
1.2.3 The Energy Source Cycle...............................................................................11
1.2.4 Advantages and Disadvantages of Geothermal Power Plant.........................12
CHAPTER 2: DESIGN, CALCULATION, AND COMPUTATION....................................15
2.1 SINGLE FLASH POWER PLANT CONFIGURATION..........................................15
2.2 THERMODYNAMIC CYCLE..................................................................................16
2.3 DESIGN AND SELECTION OF FLASH TANK......................................................19
2.4 DESIGN AND SELECTION OF STEAM TURBINE...............................................21
2.5 DESIGN AND SELECTION OF THE CONDENSER.............................................22
2.6 DESIGN AND SELECTION OF COOLING WATER PUMP..................................27
2.7 DESIGN AND SELECTION OF COOLING TOWER.............................................30
2.8 DETERMINING THE DESIGN CAPACITY............................................................34
CHAPTER 3: INSTALLATION AND COMMISSIONING.................................................34
3.1 STANDARDS.........................................................................................................34
3.1.1 American National Standards Institute (ANSI)................................................34
3.1.2 American Petroleum Institute (API).................................................................34
3.1.3 American Society of Mechanical Engineers (ASME)......................................35
3.1.4 American Society for Testing and Materials (ASTM.......................................35
3.1.5 Institute of Electrical and Electronics Engineers (IEEE).................................36
3.1.6 International Code Council (ICC)....................................................................37
3.1.7 International Organization for Standardization (ISO)......................................37
3.1.8 National Electrical Manufacturer’s Association (NEMA).................................37
3.1.9 National Fire Protection Association (NFPA)..................................................37
3.2 INSTALLATION......................................................................................................37
3.2.1 Requirement....................................................................................................37
3.2.2 Main Components...........................................................................................39
3.3 Procedure...............................................................................................................41
3.4 COMMISSIONING.................................................................................................46
3.4.1 General Requirements and Initial Startup.......................................................48
3.4.2 Operational Checkout......................................................................................54
3.4.3 Hydrostatic Testing..........................................................................................54
CHAPTER 4: OPERATION AND MAINTENANCE.........................................................55
4.1 OPERATION..........................................................................................................56
4.1.1 Steam System.................................................................................................56
4.1.2 Water Condensation System..........................................................................56
4.1.3 Turbogenerator and Auxiliary Equipment.......................................................57
4.1.4 Electric System for the Plant...........................................................................58
4.1.5 Communication...............................................................................................59
4.1.6 Supervision and Control..................................................................................59
4.1.7 Protection........................................................................................................60
4.1.8 Fire Safety System..........................................................................................62
4.1.9 Miscellaneous Systems: Air compressors, Service Water..............................64
4.1.10 Environmental Control...................................................................................64
4.1.11 Wastewater....................................................................................................65
4.2 MAINTENANCE.....................................................................................................65
4.3 MAINTENANCE SCHEDULE................................................................................66
4.3.1 Routine Maintenance......................................................................................66
4.3.2 Major Maintenance..........................................................................................70
4.3.3 Corrective Maintenance..................................................................................76
4.4 Optimum maintenance strategy.............................................................................77
CHAPTER 5: ENVIRONMENTAL CONCERNS, LAWS AND STUDIES........................78
5.1 LEGAL ENVIRONMENTAL FRAMEWORK..........................................................78
5.1.1 Environmental Impact Assessment.................................................................80
5.1.2 Environmental Compliance Certificate............................................................83
5.1.3 The role of laws, regulations, standards, codes, guidelines and best practices
..................................................................................................................................84
5.2 ENVIRONMENTAL AND SOCIAL IMPACT OF GEOTHERMAL POWER PLANTS
.....................................................................................................................................90
5.2.1 Environmental Impact......................................................................................90
5.2.1.1 Environmental Pollution................................................................................90
5.2.1.2 Terrain Changes...........................................................................................92
5.2.2 Social Impact...................................................................................................92
5.3 ENVIRONMENTAL MONITORING OF GEOTHERMAL POWER PLANTS.........93
REFENCES.....................................................................................................................94
CHAPTER 1: INTRODUCTION
Since its inception, electricity has become one of humanity’s fundamental needs.
The demand for electricity continues to increase globally and is projected to continually
increase further [ CITATION Int19 \l 13321 ]. As such, power generation also becomes
fuels. The installed capacity for the country in 2019 was 15,124 MW, more than 70% of
consequences. The Philippines imports fossil fuels which have led to inflexibility, high
and unstable power costs, and trade deficits [ CITATION Ahm20 \l 13321 ]. In addition
to this, fossil fuels have been linked as primary contributors to environmental crisis
This necessitates the need for alternative means of power generation. The
surrounding the Pacific Ocean which has significant prospects for geothermal energy.
Philippine energy mix. In fact, the Philippines is the second largest geothermal energy
One location in the Philippines that has been identified of having a geothermal
using power generated from fossil fuels, hydroelectric and wind energy (NEA, 2020).
In this paper, a design of a single flash geothermal power plant is proposed. The
power plant is intended to cater for the 30MW base load power demand in Oriental
Mindoro.
The proposed location of the power plant is at Brgy. Montelago, Naujan, Oriental
Mindoro. It is located on along the east coast of the Mindoro Island as shown in Figure 1
has been determined that this location can be developed for electricity generation
The load curve for the areas serviced by ORMECO released by the National
Electrification Administration (NEA) in 2020 and is shown in Figure 2. The base load for
the area on 2018 was determined to be 29.75 MW with a peak demand of 52.1 MW
(NEA, 2020). The proposed power plant is designed to cater only for the base load
demand.
Figure 2. Load curve for the areas serviced by ORMECO (NEA, 2020).
5.8% of the demand while industrial establishments account for 0.1% (NEA, 2020).
isotopes in the crust and mantle. This heat energy is called geothermal energy, and it
can be extracted for human use such as in electric power generation by geothermal
Geothermal energy can be extracted from geothermal reservoirs that have high
thermal gradients. Fluids, in the form of water or steam, are normally used to extract
geothermal energy from these reservoirs. These fluids are obtained by drilling
production wells to depths of up to 9,100 meters and pumping them to the Earth surface
There are three ways of using geothermal energy for electric power generation,
and all geothermal power plant designs use geothermal fluids to obtain or produce
steam. The steam is used to drive generators that eventually produce electricity
The excess vapor or water at the end of geothermal processes are condensed
into liquid form and is pumped backed into the reservoir using the injection wells. Upon
reinjection to the ground, the geofluid is reheated by the heat of the Earth. It can be
extracted again for utilization which is why geothermal power is considered a renewable
flash steam, and binary cycle geothermal power plants [ CITATION DiP12 \l 13321 ].
The first type of geothermal power plant that was developed for commercial
purposes was dry steam geothermal power plant. Dry steam power plants draw power
from underground steam resources. The geofluid is composed entirely of steam and is
directly connected into the turbine/generator unit which makes it simpler and less
13321 ].
However, dry steam reservoirs are limited. There are only two large dry steam
reservoirs in the world found in Italy and California. Other small dry stream areas are in
Japan, Indonesia, New Zealand, and United States [ CITATION DiP12 \l 13321 ]. Figure
Figure 4. Simplified schematic diagram of dry steam geothermal power plant (CEC, 2015)
the pressure, the geofluid mixture is separated into their vapor and liquid components.
The vapor component is used to drive the turbine [ CITATION DiP12 \l 13321 ]. This
power plant can only be used for geofluids whose temperature is above 182°C (CEC,
2015). Since the geothermal reservoir in Montelago has a temperature range of 180-
200°C, flash steam is the most suitable type of power plant for the project. A simplified
schematic diagram for flash steam geothermal power plants is shown in Figure 5.
Figure 5. Simplified schematic diagram for flash steam geothermal power plants (CEC, 2015)
resources in the world generally have relatively low to moderate temperature. For
low to moderate temperature geothermal resources, the binary cycle geothermal power
In binary cycle geothermal power plants, the geofluid is pumped to the earth
surface below its flashing point. It is sent to a heat exchanger to heat and vaporize a
working fluid with a much lower boiling point than water such as propane, butane,
pentane, or ammonia. The vaporized working fluid is used to drive the turbine
resources. As such, they are the most widely used type of geothermal power plant.
However, they have low average power rating per unit compared to other types of
Figure 6. Simplified schematic diagram for binary cycle geothermal power plants (CEC, 2015).
Although all types of geothermal power plants use geothermal fluids as energy
source, they vary in the way in which energy is extracted from the geofluid. In this
paper, the proposed power plant takes the form of a single flash steam geothermal
power plant. Hence, only the energy source cycle for the said power plant is discussed.
Figure 7 shows the temperature-entropy diagram for single flash steam power
pumped to the Earth’s surface. The flashing process (process 1-2) is considered as an
isenthalpic process as it occurs steadily without heat or work involved and changes in
potential and kinetic energies are considered negligible. After flashing, the liquid and
vapor components are separated isobarically. Process 2-3 accounts for the liquid
component sent back to the well while process 2-4 accounts for the steam being sent to
the turbine. Steam expands in the turbine in process 4-5. Process 4-5s represents the
ideal turbine expansion process. After expansion, the steam is condensed into a
saturated liquid in the condenser as shown by isobaric process 5-6 and pumped back
Figure 7. Temperature-entropy diagram for single flash steam power plant (DiPippo, 2012).
power plants.
Geothermal power plants have several advantages over traditional power plants
plants is its environmental advantage. The use of geothermal energy against fossil fuels
can reduce CO2 emission and air pollutants that harm the environment. The level of CO 2
and pollutants emitted by geothermal power plants are negligible compared to the
generated by Earth through radioactive decay. Although the energy source depends on
reservoir of geofluid, the amount of material extracted is reinjected back to the reservoir.
The market value of fuels fluctuates; hence, fossil fuel power plants are subject
to varying electricity costs and energy price shocks. Since geothermal power plants are
not dependent on fuel, geothermal power plants provide stable electricity costs
power plants are reliable. Once they are operational, geothermal power plants can
provide a steady output of electricity for decades unlike wind and solar power plants
whose operations rely on external factors (ESMAP, 2012)[ CITATION Ave19 \l 13321 ].
Geothermal power plants have great capacities. They can be scaled to produce
several hundred megawatts of power. Land and space are constraints to achieve high
scales as land and space requirements of geothermal power plants are less than of
hydroelectric power plants or coal power plants and are comparable to that of wind or
Geothermal power plants have low operating costs. They require minimal
maintenance compared to other types of power plants. As such, they are one of the
least cost options in producing power (ESMAP, 2012)[ CITATION Ave19 \l 13321 ].
Furthermore, geothermal power generation is an established technology. Hence,
the operational risks and maintenance requirements associated with this type of power
Although geothermal power plants have many advantages, they also have some
limitations.
One of the biggest issues in geothermal power plants is that they are site
specific. Geothermal resources are often located in remote areas. As such transmission
accessible. This can increase the cost of indirect land requirements or rights of way
(ESMAP, 2012).
they also pose some environmental hazards. In some areas, the geofluid may contain
toxic chemicals and even substantial amounts of greenhouse gases (ESMAP, 2012)
power plants are relatively smaller than some types of power plants, the area of the
steam field may increase which can lead to increased land use and environmental
There is also a risk that due to high amount of geofluid withdrawal, geothermal
reservoirs may become depleted. Although proper reinjection may prevent this,
Geothermal power plants are hard to finance. They have high upfront risk and
require huge capital investment, especially in the initial exploration and drilling phases.
This is especially true for large scale geothermal power plants that require extensive
geothermal power plants can be quite sophisticated. Additional costs are often incurred
due to periodic drilling of wells to replace wells that have lost their steam production
Furthermore, it has been suggested that the use of geothermal resources may
seismic activity. Though seismic avitities are often insignificant, there is still a risk that it
production well, a wellhead valve will be used to reduce the pressure of the fluid to the
flash tank pressure. Each well will also have a flash tank where the steam will be
generated. The fluid retained after the flashing process will be reinjected into the
The steam produced from the five well-separator units will be collected in the
steam receiver tank. The steam will then be sent to drive the turbine-generator unit to
produce electricity.
After undergoing expansion, the steam will be turned back into a fluid in the
surface condenser. Cooling water will be used to remove heat from the steam. A cooling
tower will be used to cool the cooling water as it reenters the condenser. Some part of
the condensed fluid will be used as make-up water for the cooling tower. The remaining
The T-s diagram for the proposed geothermal diagram is shown in Figure 10.
liquid, and the corresponding pressure is 1.5538 MPa. The enthalpy of the geofluid is:
kJ
h1 =hf @ 200° C sat . temp=852.45
kg
State 2 represents the liquid-vapor mixture obtained after the flashing process.
The flashing process is assumed to be isenthalpic; hence, the enthalpy and quality at
State 2 are:
kJ
h2 =h1=852.45
kg
kJ kJ
852.45 −670.56
h −h kg kg
x 2= 2 f @ P =600kPa = =0.0872∨8.72%
h fg @ P=600 kPa kJ
2086.3
kg
The liquid-vapor mixture is separated isobarically into its liquid and vapor
component. The separator pressure is set to 600 kPa, adjusted from the average 620
kPa separator pressure for single flash power plants reported from literature
[ CITATION Zar14 \l 13321 ]. State 3 represents the liquid component while State 4
kJ
h3 =hf @ 600 kPa=670.56
kg
kJ
h 4=h g @600 kPa=2756.8
kg
kJ
s4 =s g @ 600 kPa=6.76
kg−K
State 5s represents the working fluid after undergoing the ideal isentropic turbine
expansion process. The condenser pressure is set to 10 kPa, adjusted from the
average 12 kPa condenser pressure for single flash power plants [ CITATION Zar14 \l
kJ
s5 s =s 4 =6.76
kg−K
kJ kJ
6.76 −0.6493
s 5 s−s f @ P =10kPa kg−K kg
x 5 s= = =0.81466∨81.466 %
s fg @ P=10 kPa kJ
7.5009
kg
kJ kJ kJ
h5 s=h f @ P=10 kPa + x 5 s ( hfg @ P =10 kPa ) =191.83
kg (
+ 0.81466 2392.8
kg )
=2141.15
kg
represents the actual state of the wet mixture entering the condenser. Turbines used in
single flash power plants have typical isentropic efficiencies of 81 to 85% [ CITATION
Zar14 \l 13321 ]. Assuming an isentropic efficiency of 85% for the turbine, the actual
h 4−h5
ηt =
h4 −h5 s
kJ kJ kJ kJ
h5 =h4 −ηt ( h4−h5 s ) =2756.8
kg (
−0.85 2756.8 −2141.15
kg kg )
=2233.50
kg
kJ kJ
2233.50 −191.83
h −h kg kg
x 5= 5 f @ P=10kPa = =0.8533∨85.33 %
h fg @ P=10 kPa kJ
2392.8
kg
At the exhaust of the condenser or State 6, it is assumed that the wet mixture
has been converted into a saturated liquid. The enthalpy of the liquid is
kJ
h6 =h f @ 10 kPa sat . press .=191.83
kg
The state working fluid during the entire cycle is summarized in Table 1.
The typical efficiency of single flash power plants at a given reservoir enthalpy is
shown in Figure 11. The enthalpy of the geothermal fluid in the geothermal prospect in
Montelago was determined to be 852.45 kJ/kg (See Table 1). At this enthalpy, the
13321 ]
This efficiency can be used to estimate the total amount of groundwater needed
Power output
η¿−all =
ṁ gw ( h1 )
kg kg
(
ṁ s =x2 ṁ gw =0.0872 700
s )
=61.03
s
kg kg kg
ṁ i=ṁ gw− ṁ s=700 −61.03 =638.97
s s s
Since there are five wells and flash tank separators, the mass flow rates for each
unit are
kg
ṁ gw per production well=140
s
kg
ṁ s per separator=12.2
s
kg
ṁ i per injection well=127.8
s
Manufacturers will be asked to customize flash tanks that will meet the
kg kJ kJ
Ẇ t =ṁ s ( h 4−h 5 )=61.03
s (
2756.8 −2233.50
kg kg)=31,937 kW
The steam turbine must have a rated capacity of 30 MW to sustain the base load
demand. The inlet and outlet pressure of the steam turbine are 600 kPa and 10 kPa,
respectively. The steam entering the turbine has a temperature of 158.85°C, and the
turbine must be able to handle 61.03 kg/s of steam. The specifications required for the
The selected turbine that meets the requirement for this power plant is the
[ CITATION Fuj21 \l 13321 ]. The unit is shown in Figure 12. A cross -sectional view of
Figure 12. Packaged Type Geothermal Power Generation unit [ CITATION Fuj21 \l
13321 ]
Figure 13. Cross-sectional view of the selected turbine [ CITATION Yam10 \l 13321 ]
Only information about the capacity of the turbine (30 MW) is made available by
the manufacturer online. However, the unit has been used in Unit 5 of the geothermal
power plant in Svartsengi, Iceland. The design parameters of the said power plant are
the proposed power plant and the Svartsengi power plant, it can be seen that the
kg 2.20462lb
ṁ s =62
s( 1 kg )
=136.6864 lb/s
0.145038 psi
Pcondenser =10 kPa ( 1 kPa ) =1.45038 psi
T sat =114.4768 ℉
ft 3
v=0.0161679071
lb
The temperature of the cooling water at entering the condenser is set to 80ºF.
The terminal difference between the steam and the cooling water at the outlet is set to
10ºF.
T cw ,out =104.4768℉
Solving for the log mean temperature difference of the condenser,
T cw ,∈¿
log Mean Temperature Difference (θ¿¿ m)=T cw ,out − ¿¿
ln ¿ ¿ ¿
104.4768℉ −80 ℉
θm =
114.4768 ℉−80 ℉
(
ln
114.4768 ℉−104.4768 ℉ )
θm =19.7760° F
The tubes are designed to be 18 BWG, admiralty metal with 7/8” diameter. The
velocity of the cooling water is set to 7 fps. The cleanliness factor is set to 0.85 and the
prime mover is set to 1.0. Other factors are obtained as c=263 , F t=1 ,∧F p =1.
BTU
Ú =c √ vel=263 √ 7 fps=695.8326 2
ft −hr−℉
BTU
(
U =( Ú ) ( Ft )( F m ) ( F c )( F p ) = 695.8326 2
ft −hr−℉ )
(1)(1)(0.85)(1)
BTU
U =591.4577 2
ft −hr−℉
It was suggested by the Heat Exchanger Institute that for surface condensers for
non-reheat turbines, the change in specific enthalpy is h fg =950 BTU /lb . The surface
area required is
BTU
A=
(
(ms ) 950
lb )
(U )(θ m)
lb 3600 s BTU
A=
( 136.6864 )(
s 1hr )( 950
lb )
BTU
(591.4577 ft −hr −℉ )
(19.7760 ° F )
2
A=39,965.8697 ft 2
QR
m cw=
( Cpw ) ( t out −t ¿ )
lb 3600 s BTU
mcw =
( 136.6864 )(
s 1 hr )( 950
lb )
BTU
(1 lb−℉ )( 104.4768 ℉−80 ℉ )
lb
m cw=19,098,390.64
hr
Converting to volume,
mw
Vol w =
ρw
lb 1 hr
Vol w =
19,098,390.64 (
hr 60 min )
gal
(7.48 3 )
lb ft
62.40 3
ft
Solving the number and length of tubes using data shown in Figure 16,
tubes
No .of tubes=3,683.0090
pass
Area 39,965.8697 ft 2
Length of tubes= =
(no . of tubes)(factor) ft 2
(3,683.0090)(0.2297 )
ft
Length of tubes=47.2417 ft
surface area of over 20,000 sq. ft., the length of the tubes must be 22-30 ft. In order to
Length of tubes
Actuallength= +[2 ( tube sheet thickness )]
no . of pass
47.2417 ft 1 1 ft
Actuallength=
2 pass 2(
+[2 inches x
12inches
] )
Actuallength=23.7042 ft=24 ft
tubes
Actual No . of tubes=( 3,683.0090 )(2 pass )
pass
Due to the specificity of the condenser, the developers will find manufacturers for
With a two-pass configuration and a cooling water velocity of 7 fps, the friction
loss on the condenser can be computed using the factors shown in Figure 18.
h f =18.40 ft
The cooling water leaving from the condenser will be discharged into the cooling
tower. The point of discharge within the cooling tower is 10 m (32.81 ft) above the inlet
of the cooling water to the pump. Therefore, the total dynamic head is
1 1 lb
ρ= = =61.8509
v ft 3
ft 3
0.0161679071
lb
With pump efficiency set to 75%, the required brake horsepower of the pump is
go
BP=
( )
(H T )(Vol w )( ρ)
gc
ft 3 −lbf
33,000 (η)
hp−min
ft
32.20
BP=
(
(51.21 ft ) 5,101.0659
ft3
min )( lb
61.8509 3
ft 3−lbf
ft ) ( 32.2
s
lbm−ft
lbf −s2
)
33,000 (0.75)
hp−min
BP=652.81 HP
The summary for the cooling water pump specifications is shown in Table 6.
The selected pump is Goulds Pump 3180, XL-2, 30X30-41 model. The operating
parameters required falls on the hydraulic coverage of the pump as shown in Figure 19.
The dimensions and design of the pump are shown in Figures 20 and 21, respectively.
Figure 19. Hydraulic coverage of the selected pump [ CITATION Gou \l 13321 ]
For the calculations for the cooling tower, the information regarding the cooling water
has been computed in the calculations for the condenser. For the air entering the cooling tower,
the temperature is set to 29°C while and the relative humidity is 76% which are average values
according to online sources [ CITATION Tim21 \l 13321 ]. The air leaving the cooling tower is
assumed to be 27°C and saturated. A system diagram for the cooling tower is shown in Figure
22.
@ water inlet
kJ
h w ,i=168.6542
kg
@ water outlet
kJ
h w ,o=111.3706
kg
kJ
h a ,i=78 ; SH a , i=0.019
kg
kJ
h a ,o=86 ; SH a , o=0.023
kg
kg kJ kJ kJ kJ
2410
s (
168.6542
kg )
− ṁ w, o 111.3706
kg (
=ṁ a 86 −78
kg kg ) ( )
ṁa=50,807.08−13.92 ṁw , o
kg
2410 −ṁ w , o=( 50,807.08−13.92 ṁ w , o ) ( 0.023−0.019 )
s
kg
ṁ w , o=2,336.9
s
kg
ṁ a=50,807.08−13.92 ( 2,336.9 ) =18,277
s
kg
m make−up=m w ,i−mw , o=( 2410−2,336.9 )
s
kg
m make−up=73.1
s
lb BTU
Q= ṁ s h fg =136.6864 (
s
950
lb )( 1.055
1
BTU
kw
)
s
Q=136,993.94 KW
Checking if the air conditions are sufficient to reject this amount of heat,
kg kg kg kg
Q=18,277
s s(
86 −78
s )
=146,216
s
The selected cooling tower is the CING cooling tower, shown in Figure 23, manufactured
by YWCT. The CING-5500-1 model is selected. The cooling capacity for the said unit is
20,000,000 kcal/hr per cell; hence, 6 cells of the cooling tower are needed. The specification for
the model is shown in Figure 24. Additional details are shown in Figure 25.
Typical generator efficiencies used in geothermal plants ranges from 95.7 to 99%
[ CITATION Zar14 \l 13321 ]. Taking 99% as the generator efficiency, the electrical
EP=31,617.63 kW =31.6 MW
EP 31,617.63 kW
η¿−all = x 100= x 100
ṁ gw ( h1 ) kg kJ
700
s(852.45
kg)
η¿−all =5.3 %
This efficiency is close to the typical 3-6% efficiency of single flash steam
geothermal power plant associated with the enthalpy of the geothermal reservoir as
3.1 STANDARDS
Thermometers
E947-15................ Standard Specification for Sampling Single-Phase
Stress
Maximum)
3.2 INSTALLATION
3.2.1 Requirement
A. Install the geothermal system in accordance with the NEC, this section, and
//B. In seismic areas, systems shall be adequately anchored and braced per details on
C. Prior to any excavation, trenching, or drilling, all buried utilities, drainage, and
irrigation systems shall be located and flagged by the appropriate utility and Contractor
representative.
//E. Surface Discharge shall comply with Environmental Protection Agency (EPA) National
wells.//
1. Surface water shall not be used as a source of water during the drilling of a borehole
unless it is obtained from a municipal water supply system. Water used for drilling
purposes shall be potable water that contains a free chlorine residual of no less than 10
milligrams per liter. Chlorine residual level shall be checked with chlorine test strips.
H. Piping installation shall be compliant with ASME B31.1, and ICC IMC Section 1206.
A heat source, a heat sink, and a heat exchanger are the three main components
of a geothermal system. The heat source is usually the earth, and the heat sink is
usually a built environment (in general, a structure). The heat exchanger is made up of
one or more components that contain a fluid and transfer heat from the heat source to
the heat sink. Moreover, a piping system is used to connect the chain of parts and
equipment that serves as a way for the working fluid to circulate in the system.
Heat rejection equipment is used to extract heat from chilled water, refrigeration,
processing, and other types of equipment. Cooling towers, fluid coolers, and
extract heat from the device, air is passed over a coil or wetted medium.With the use of
water cooled condenser, the cooling tower circulates water to the shell and tube
condenser, where it absorbs heat from the condensing refrigerant before falling through
C. Pumps.
pumps are used to move the fluids from underground. Also, it is used to circulate
different kinds of fluid as it adds pressure to the fluid. Water for the cooling system also
D. Radiators
Another option of heat exchangers, are devices that move thermal energy from
Others are: Wiring, Wiring Specialties, DC-AC Inverter, Geothermal Energy Storage,
3.3 Procedure
Visit the proposed site to get a sense of the general topography and geology of
identified faults, and signs of recent and historical flood marks are all evaluated.
Collect and review additional data such as follows: topographic maps and surveys,
geological maps, data on existing power distribution network and demand, current
Power Development Plan for the region, Identify any potential fatal flaws in site location
or physical surroundings.
Oversee the sub-contracted well drilling business, which includes reviewing the
down hole boring logs, ensuring proper casing positioning, grouting, site quality
Review and confirm that the results of geotechnical analysis and test drills on two
pilot wells support the proposed site’s suitability for the geothermal project
construction.
Provide preliminary layout/drawings of the geothermal power plant facility that will
Outline technical description of the geothermal power plant facility, including all
interconnection point(s).
Prepare a full rundown of the project's equipment and materials, such as civil
electrical interconnection.
watersheds, and other factors, and identify likely mitigation strategies for any
Examine all relevant laws and regulations, as well as all permitting standards
of-way provisions, and zoning codes, all of which must be considered before the
Examine the geologist's site geologic conditions, as well as any EIA problems
related to geology (faults, instability, and structure), and estimate depth to 200
degrees Celsius.
Review and confirm the Sponsor's geothermal power plant facility well design,
well field design, and TOP Facility design to ensure their adaptability to site
research.
capping.
With the financial specialist, prepare cost estimates for drilling up to 50 wells.
characterizing the site from a land use and heat source perspective and define
Determine designs for reducing environmental impacts and estimating costs for
Verify and validate the geotechnical study to assess turbine selections, TOP
Facility design, and overall project economics for energy power sales to the grid.
Define the options for turbines and other equipment, as well as the terms,
contracts.
Optimize the layout, considering any restriction zones that might be necessary to
Assist the local environmental consultants and authorities with any technical
Prepare part lists for the preliminary design of the geothermal power plant facility
grids.
Examine the geothermal power plant facility's power quality to see if it complies
Calculate the total energy supplied from the geothermal power plant facility grid
to the main power grid using the grid integration strategy and the facility and
50 geothermal wells.
Incorporate well design into top well pad and overall facility design.
The geothermal power plant top facility design can be adapted to site-specific
conceptual design.
energy supply.
plant facility to the Luzon grid's nearest connection point. Determine if any
Prepare a Grid System Impact Study (SIS) on the geothermal power plant
Transmission plan
Financial Specialist
Examine your existing funding plans and your financing strategy. Make
external variables that could affect the Project's profitability, such as waste costs,
energy costs, interest rates, investment costs, and O&M costs, and outline
3.4 COMMISSIONING
the power plant. Before commercial operation, the final stage is testing and
commissioning to ensure the standards are met for a safe and efficient operation. Also,
development has a high initial investment cost. Location is the first factor that should be
checked to ensure there is ample amount of steam or thermal energy present and ready
to use for geothermal power plant electricity production. Also, future expansion as the
geothermal power plants use renewable energy from the thermal energy of natural
underground fluid, the power plant should be operated in a controlled manner to ensure
that there would be no negative impact on the environment. Furthermore, the safety of
the customers, environment, and power plant itself are tested and checked to ensure
that it operates along with the standards. For geothermal power plants, steam from a
natural underground source of thermal energy and fluids are used to propel the turbine
for electricity generation, thus, the quality of the steam or fluid extracted underground
should be tested to ensure the standards and the power plant requirements are
achieved. Both equipment and facilities must be thoroughly inspected and tested to
ensure that the plant can operate safely, efficiently, and effectively in both normal and
emergency situations. Furthermore, contingency plans are important, and the plant
should foresee future danger and scenarios together with the proper protocols to
In geothermal power plants, the geothermal wells and piping system are one
most vital component. To maximize the efficiency and power output of the geothermal
power plant, pressure valves and steam quality and composition are tested. With the
use of the control system and pressure controlling valves, proper inlet pressure at the
steam turbine is achieved. Drilling well design should be checked to ensure that there
would be no negative impact on the environment like soil degradation. The control and
distribution panels should be tested beforehand in the factory because only external
wiring and cabling can test when the power plant is built (Snaebjorn Jonsson, 2018).
In summary, the geothermal power plant should be checked and tested based on
the standard and the power plant design requirement to ensure the safety and the
efficiency of the operation. In addition, contingency plans and expansion plans making
the power plant “future-proof” are important. Lastly, planned maintenance schedules are
included.
The aim of commissioning and testing is to ensure that the expected and
manufacturing point, most mechanical and electrical equipment used in power plants is
highly standardized (Factory testing). However, for initial startup, it is required to further
test the capability of the equipment and if the system works properly and as expected.
The power plant's start-up and commissioning are the final phase before it goes into full
service. The key goal is to refine the processing and injection systems so that energy
can be recovered and used as efficiently as possible. This reduces operating costs,
increases investment returns, and ensures that geothermal power is delivered reliably.
the resource responds to exploitation, new development and reinjection wells may be
required. It can take several months to fine-tune the performance of the power plant and
The following tests are conducted to ensure the safety, efficiency, and reliability
a. Acceptance tests - applicable for all equipment, cabling, piping etc. These
b. Control system test - these tests are conducted carefully and continuously
Each of the conducted tests are divided into sublevels for more specific test:
vendors after installation at Site. In all cases witnessed by the Owner and
Loop testing of cables and hard-wired connections for control- and protection
etc.). Conducted by Contractors for cabling and connections and witnessed and
Control and Data Acquisition) systems, i.e. HMI displays are pre-tested.
so on are all checked. Real functionality tests are preceded by these tests.
Hard-wired signals are pre-tested at the control system terminals. Inside the
control system, inputs are simulated and tested. The outputs of the control
This stage is not extended to all signals in some projects, but it is used as a sample
Hardwired signals are pre-tested all the way from the control system to the field
equipment. At the field level, inputs are generated and tested by the control
system. The outputs of the control system are tested on the field side.
interaction with the control system. Sensors, control valves, and engines, to
name a few.
Device functional monitoring and contact with the control system This stage
involves an "interlock inspection," in which all security and safety circuits are
Individual machines, processes, and plants are started up by the control system.
parameters within the control system and individual equipment are fine-tuned.
The analysis of alarms, to ensure that alarms are issued and displayed as
concluded with the “performance test”, where the output and efficiency of the
Upon the initial startup, the following important parameters that needs to be checked
to ensure the standards are met base on the geothermal power plant design:
Steam Supply - prior to the start of commissioning of the steam supply, all connected
geothermal wells have been tested and measured to verify that they are able to provide
the necessary pressure and flow needed for the plant. Moreover, Chemical analysis is
often needed to assess the well's characteristics, as well as any risks associated with
silencers for some time before commissioning to reduce the number of solid particles in
the steam supply. Steam wells, steam gathering pipelines, steam separators, steam
pipelines, steam control valves, mist eliminators, reinjection pipeline, and reinjection
wells are commonly used in power plants that use steam from flashed geothermal fluid.
The two-phase fluid from the wells is piped to one or more steam separators, which
isolate the steam from the water. The steam is then piped to the turbine via mist
eliminators. Steam control valves bind to steam pipes and direct steam to team
silencers. The steam separators' water is disposed of in either reinjection wells or open
pounds. The regulation of steam pressure and the control of the liquid level in the steam
separators are the two main control mechanisms, and hence the two main possible
causes of instability. Changes in steam pressure influence the liquid level in the
separators since the systems are connected. The steam supply system must be able to
support the operation of the turbines at variable loads and manage sudden changes in
the power output of the turbine/generator systems without causing any delays in the
operation of the units due to the steam supply system's instability or transient action.
Therefore, to avoid potential steam supply failures, thorough testing of the steam supply
for all possible events and tuning of the control functions to handle these events is
critical.
A. Cooling water emergency supply test - Cooling water is needed for the operation
of thermal power plants in general, and geothermal power plants. This is valid not
only for exhaust steam cooling in condensers, but also for machinery cooling
(e.g. generators, oil units etc.). Thus, it is critical to thoroughly test these systems
B. Dynamic testing of governor and Automatic Voltage Regulator (AVR) - the term
“governor” is used for the regulating system for the rotational speed of the turbine
units, measured in revolutions per minute [rpm] and active power output of the
for the regulating system for the output voltage of the generator units, measured
in kilovolts [kV] and reactive power output of the plant, designated with the letter
system stability during and after transient events. Since geothermal power plants
are usually located in remote areas, the dynamic output of governors and AVR
systems will be put to the test when a geothermal power plant is connected to a
dictate that generation must always equal the number of loads and losses at any
given time. Base load operation, with close to constant power output and thus
geothermal power plants. This enables the power output setpoint to be gradually
valves to be held in balance with a very low opening position. This would
optimize the use of available geothermal steam while reducing geothermal gas
emissions into the atmosphere. The downside is that the plant is unable to
produce a sudden load rise in the event of a frequency decrease under these
found. It may be possible to use geothermal units as a base load if they are
for geothermal plants, the response to frequency deviations on the grid must be
extensively checked, as this will impact, for example, the dynamic response of
the steam supply system and, ultimately, other systems (reinjection system,
cooling water system etc.). This needs to be well-coordinated with the grid
steps on the grid side must be produced by tripping other generators and loads
for full scale testing. The AVR system's responses to system voltage variations,
as well as PSS for transmission system stability, will be included in these studies.
the control system, testing of generator and transformer relay security, testing of
The O&M for the steam field (wells, pipelines, infrastructure, etc.) and the
O&M for the power plant can be divided into two categories (turbine, generator,
cooling system, substation, etc.). To ensure a high availability factor and capacity
factor for the power plant, as well as consistent steam output from the
MW geothermal power plant, about 20 technicians are needed. The steam field's
operations and maintenance entails cleaning existing wells, drilling new ones as
For geothermal power plants, hydrostatic testing is used to test the integrity of
the pipelines and the wellhead. Also, it is used to test the strength of the pipes and to
test for leaks. Hydrostatic testing is conducted before the operation of the geothermal
power plant and it is also part of the maintenance of the geothermal power plant,
however, it can only conduct if the geothermal power plant is not operating.
Furthermore, take note that hydrostatic testing cannot monitor equipment for leaks, but
on-stream equipment integrity is best managed by an effective fixed equipment
Hydrostatic testing is a form of pressure test that involves fully filling the component with
water, removing all air from the structure, and pressurizing the system to 1.5 times the
unit's design pressure maximum. After that, the pressure is maintained for a set period
to visually check the device for leaks. Applying tracer or fluorescent dyes to the liquid to
identify where cracks and leaks are coming from will improve visual inspection.
A. Water Jacket Method - the vessel is filled with water before being loaded into a
sealed chamber (known as the test jacket) that is also filled with water. The
vessel is then pressurized for a set period within the test jacket. As a result of the
vessel expanding inside the test jacket, water is pushed out into a glass tube that
down to its original position. In some instances, the vessel does not return to its
original size called permanent expansion. The difference between total and
permanent expansion decides whether the vessel is fit for service or not. The
greater the percent extension, the more likely the ship is to be decommissioned.
B. Direct Expansion Method - the direct expansion method entails filling a tank or
measuring the amount of water ejected after the pressure is removed. The
amount of water forced into the vessel, the test pressure, and the amount of
water expelled from the vessel are used to calculate the permanent and
assess whether the vessel has any leaks or other weaknesses that might lead to
4.1 OPERATION
processes of plant’s energy generation cycle and these are: Steam system, Water
Electric system, protection system, Fire Safety System, Miscellaneous systems, and
environmental control.
This system processes the delivery of steam to the wells to the entrance point,
turbine, and turbo compressors. Its operation should be coordinated at the well area.
The steam blowing needs to be utilized to clean out the pipes and avoid strange matter
entering the turbine before utilizing this system. When the system has been applied to
a need to verify all installed equipment as no registers have left open. Condenser
purges should be open. All instruments are in operating condition. Once the verifications
have been done, pipes are heated up and pressurized up to turbine stop valves. It is
necessary that purges, and steam traps are draining the condensate as there are no
anomalies in the system. When all the operating conditions are achieved, turbine start-
up maneuvers can start. For enclosing this system on out of service, stop valves are
verification on its operation is that it is ready with the manholes closed and all electrical
panels are energized. After following the standard procedures for verifications, the
corresponding maneuvers are based out from the start-up procedures for this system. It
ought to be made certain that operation boundaries stay inside established limits.
current, cooling, vibrations, suction valves, pump discharge, cooling tower, and
system, turbine’s control system, generator’s seal oil system, generator’s self-excitation
turbogenerator rotating longly, generator’s oil system operating same as for steam
system, circulation water system, and gas extraction system. Starting up a turbine
oil, temperature of metal and the discharge of the bearings, speed, differential
expansion of the casing, eccentricity and vibration of the arrow, and the vacuum and
temperature of the discharge turbine. For normal operation, it is needed to have the unit
work at the most efficiency possible operating at their maximum capacity. When taking
out of service, first it needs to reduce the load to a minimum value, change the auxiliary
equipment.
The substation holds the voltage transformation equipment, equipment for the plant's
association with and detachment from the electric network, buses, current and power
transformers, rods and different elements related with the installed equipment. To
associate the unit to the bus or the bus to the transmission line, synchronization
systems are required prior to shutting off any switch at the substation. The operational
care in this space is the same as that taken at a regular plant however rely upon the
gear installed.
The auxiliary services equipment incorporates all the unit\'s electric equipment:
Transformers, High and low voltage panels, Motor Control Panels, Electric Motors,
Control panels, Direct current system, Measurement and electric protection equipment,
4.1.5 Communication
geothermal power plant is simpler than the conventional thermal power plant because it
doesn’t have an advanced control system for steam generator and auxiliary services. It
can be operated manually. For manual operation, command actions operated manually.
independently.
detects deviations and carries out routine calculations for immediate inspection of
operations personnel.
Automatic plant, where computer and associated controls automatically carry out
operations.
The reason for the fire safety system is to protect human lives and property from
fire. A fire at a plant can harm imperative bits of equipment and truly affect the plant's
Areas of highest fire hazard are: Cooling towers, Hydrogen system, Battery
circuits, Carrying out welding task without the proper protection, Lighting fires or
-Pulverized water
routine reviews and tests ought to be set up to ensure the system is in operating
conditions consistently.
twofold limit equipment, to include with one equipment in activity and another as
a back-up. Fore instruments, air free from humidity and H2S is needed to put
through absorbent H2S filters and air dryers. At the point when pneumatic
supply air for their activity. Operational care for this gear is ordinary. Air pressure,
and temperature, condensate traps, lubrication. Filler and cooling systems, and
so on should be checked.
The water for bathrooms, dining halls and administrations overall ought to
utilization.
-Waste water
-Solids
-Gases
-Noise
4.1.11 Wastewater
Wastewater is produced from the surplus of the circulation water system and
from the plant's drains. Circulation systems with a cooling tower are considered to have
the highest pollution problems, because of the concentration of solids yielding a result of
evaporation. The primary pollutants in the surplus water from the towers are: mineral
acids, sulfates, sulfur, sulfides, and iron oxide. These contaminants can be found as
dissolved solids and in suspension and are produced both from the contaminants in the
steam, same as on the chemical treatment, from the environment through chemical
reactions that occur in the circulating water system. The most widely recognized
contaminants in the plant's drainage system are: organic matter from sanitary drains
and industrial waste gathered by this system, such as oil, detergents, chemical
control waste water pollution as it eliminates other contaminants until it can be released
into the zone's drainage network. Water will be constantly monitored to ensure the
conveyed by the air can result in failures in the substation\ 's and transmission line\'s
4.2 MAINTENANCE
equipment, structures, and other general facilities and services in good working order,
within the limits defined with the company providing the geothermal fluid and the point of
distribution of electric power to the transmission network, in order to ensure the plant's
Both preventive maintenance tasks that are repeated at regular intervals and
follow a work schedule are referred to as routine maintenance. Its aim is to keep
transported in the geothermal steam, can cause scaling, corrosion and erosion
problems in this system to a larger or lesser degree. This will require a specific
Equipment clogging up
Steam leaks
are modules formed by the turbogenerator, lubrication oil and control system, the
generator’s seal oil system, the generator’s H2 and CO2 system, and the turbine’s
steam seal system. with some variations, the equipment of this module corresponds to
that of a conventional plant and its maintenance should be carried out following the
manufacturer’s recommendations.
shutdown of the turbine, caused by the scaling and corrosive action of the
contaminated steam. These elements need to be frequently checked and
Scaling occurs especially in the first row and nozzles, which reduces the pathway
area of the steam and, consequently, the capacity of the turbine. This makes it
possible to use some washing technique with the turbine rolling, to remove this
When water from the cooling tower’s circulation system is used to cool the
lubrication and control oil of the turbogenerator and the hydrogen of the
generator, scaling and corrosion problems could take that require further
attention.
important that the turbine’s seal system be in good operating condition to avoid
C. Condensers
low-level type, normally require little special attention when materials of their internal
elements have been selected well and they receive adequate major maintenance.
When water comes from an external source there are normally few maintenance
problems. In a system using the same condensed steam as a source of water supply for
the circulation system, more or less serious problems could take place with the deposits
Circulation water pumps: lubrication, revision of seals and of the pump’s cooling
gaskets.
E. Cooling Tower
In this facility there are problems of solid deposition, corrosion and degradation of wood.
If water from the circulation system is going to be used for direct cooling, problems
could take place in the oil and hydrogen coolers, as was mentioned above.
If the cooling water is in a closed system and water is used from the circulation system
with a tower, scaling and corrosion problems could take place in the heat exchanger.
as those in any other similar system, with additional problems being the action of the
corrosive environment, such as the area of the cooling tower. If water from the
circulation system is used, there could be problems with the equipment that would be
Major maintenance of a generator unit has the purpose of restoring the original
functioning conditions of all equipment and facilities that integrate it, so the unit will fully
To undertake major maintenance the unit is put out of service, the internal parts
of all equipment are inspected in detail to determine their state, and, if so deemed, the
necessary repairs or replacement are carried out. major maintenance done yearly or
functioning conditions of all equipment and facilities that integrate it, so the unit will fully
To undertake major maintenance the unit is put out of service, the internal parts
of all equipment are inspected in detail to determine their state, and, if so deemed, the
each plant, but can fluctuate between one and two years. There are certain tasks that
The most common tasks undertaken in a major maintenance program are the following:
In this system corrosion and scaling problems may appear which affect the equipment's
life span as well as its performance. Maintenance consists of removing the scales that
have formed and correcting the ware by repairing or replacing the affected parts.
Special care is required with safety valves, pressure regulating valves, humidity traps,
The main problems that may appear in the turbine by effect of geothermal steam are:
Scaling in the blades and nozzles as well as in the emergency stop valves and
control valves resulting from solids carried by the steam. This scaling reduces the
Erosion especially in the last blade stages. originated by the water contained in
the steam.
Corrosion of parts where steam contacts air, such as turbine seals and valve
trees.
alignment.
protection systems.
c. Condenser
In the equipment problems of corrosion and deposit of solids may be present. For
maintenance, the panel doors should be opened, and all internal elements should be
inspected, such as pans, sprinklers, pipes, coatings. etc., and the necessary corrections
should be made.
f. Cooling Tower
Maintenance requirements depend on the kind and features of the tower installed. A
mechanical draft tower demands much attention for its maintenance. At greater
operation time the maintenance requirements are also greater, up to the point that
Special care should be taken regarding chemical treatment of the circulating water since
Since sulphur deposits accumulated at the tower have a very low ignition point, it is
All equipment of this system should be checked: pumps, heat exchangers, filters,
valves. etc.
when any of its units is out of service. Its maintenance should be programmed when all
the units of the plant are in service, always being cautious that at least one pumping
equipment is available.
Distribution switchboards and control centers of low voltage motors: electric and
and of protections.
interruptions of ser-vice besides resulting in high costs for the company, have highly
Even though it is desirable not to have to carry out any corrective maintenance at all,
practi-cally no plant is free of this need in greater or lesser extent. One of the
causes, and secondly to take the necessary corrective measures to prevent it from
occurring again.
the same time, serve as an assessment tool when adjusting the program or deciding on
power plant maintenance team (Figure 29) could be based on criticality/impact and
if the risk of failure is very low and if the consequences of failure are fairly mild or where
Figure 29. Selection of optimum maintenance methods (World Economic Forum, 2014)
Scheduled (time-based) maintenance is the strategy of choice when failures are
costly or safety is critical and when the failure rate is fairly low but tends to increase
over time.
maintenance activity when the asset’s condition falls below a certain threshold. The aim
is to time the maintenance work optimally so that it is not performed more often – and
hence more expensively – than necessary and in a way that it can be undertaken at a
but also the likely consequences of failure. The main aim of this strategy is to reduce
the overall risk and impact of unexpected failures i.e. to ensure high reliability. To put in
a nutshell, maintenance methods need to be customized for each asset and the correct
combination of strategies should be applied for each component of the power plant
construction project would affect the climate, society, and health. Also, it aims to
mitigate the bad effects of the geothermal power plant development in the environment.
there are three main stages in developing geothermal power plant, and each
stage has different impacts to the environment that should be assessed to mitigate the
effects.
1. Preliminary exploration, the search for the right place to build the geothermal
power plant hardly affects the environment, however, if the place is decided, it
2. Drilling. To harness the hot fluid coming from underground, the size of a drill site
is normally between 200 m and 2,500 m . This massive hole could cause soil
2 2
topography of the area. Furthermore, air pollution can result from gas emissions,
smoke exhaust from generators, compressors and vehicles. During well testing,
steam and spray will scald trees and grass, causing damage to the surrounding
vegetation. Dust carried by the wind over exposed surfaces can have a negative
of pipelines throughout the vicinity of the power plant. The main potential
The following are the unwanted environmental effects of geothermal power plant that
should be mitigated.
1. Effects on air. Throughout the life of the power plant, from the construction phase
to the last day it would be used, it will emit dust that could give disturbances in
the vicinity of the plant. Furthermore, during well drilling and testing, as well as
and carbon dioxide (CO ) will be emitted from the geothermal fluid. During all
2
phases of the project, nitrogen oxides, carbon monoxide, and sulfur oxides
oxides of nitrogen released from the drilling rig engine during drilling operation
will be mitigated if one drill rig is used at a given time. Also, hydrogen sulfide will
the international standard level. Also, air filters should be installed to filter the
2. Effects on water. Since the wells are drilled depending on the site, depending on
and can take up to 50 l/s of water for several months. The water removed from
the underground should be replenished by re-injecting the water back to the
underground to avoid land subsidence. Also, this might affect the quality of
groundwater in the area, therefore, the volume of fluid is immense, and it must be
discharged with extreme caution into well-designed sumps. Not all water from
reservoir is re-injected since due to the loss of volume its volume by converting it
water must be used to maintain constant volume of water in the reservoir. Lastly,
cooling towers to reduce discharge of water heat into streams and lakes. It also
plants at the intakes from the condensers and discharge systems as well as the
3. Noise effects. During the construction phase, noise effects are caused by the
drilling and well testing that could affect the wildlife and the vibration of the drilling
could cause low seismic waves that could trigger small earthquakes. The cooling
tower, transformer, and turbine-generator building produce the most noise during
power plant operation. During the geothermal power plant operation, to hold
ambient noise levels below the 65-decibel limit set by the US Geological Survey,
noise mufflers must be used (Kestin et al., 1980). Noise effects to staff, people in
the vicinity, and animals would be mitigated by the decreased noise level.
4. Flora and Fauna. During the drilling, the construction of pipeline and transmission
lines, and road, vegetation and biodiversity could be affected enormously. During
gases exceed the limits set by standards, steps to minimize their levels in the
mitigated.
for any project in the Philippines that poses a possible environmental risk or effect
an ECC. This certificate certifies that the planned project or undertaking would have no
major negative environmental effects in the Philippines. The ECC provides clear
measures and requirements that the project proponent must meet before and during the
project's activity. Conditions are also listed to be carried out during the project's
AND FOR OTHER PURPOSES. This Act shall be known as the “Renewable Energy Act
otherwise known as the “Renewable Energy Safety, Health and Environment Rules and
Regulations”, and in order to ensure adequate safety and protection of health, life,
property, and the environment against the hazards of geothermal operations, the
Prescribing the policy for maintaining the share of renewable energy (re)
resources in the country's installed capacity through the holistic implementation of the
pertinent provisions of republic act no. 9513 or the re act on feed-in tariff (fit) system,
Promulgating the framework for the implementation of must dispatch and priority
Guidelines for the Selection Process of Renewable Energy Projects under Feed-
in Tariff System and the Award of Certificate for Feed-in Tariff Eligibility
statement of authority.
the ECC
Philippine Particulars
Environmental
Regulations
Republic Act Also known as the Clean Air Act that consolidates
(RA) No. 8749 all the rules and regulations on air quality. It also
establishes the standards for ambient air quality
and emission standards for point sources. The Act
contains provisions on empowering ordinary
citizens to address situations involving violators
and government officials who neglect the
performance of their duties. This law mostly
provides a general framework for the new air
pollution requirements.
DENR Administrative Orders (DAO) for the implementation of the Law on Air
Emissions
to diesel or gas power plants. Geothermal power plants, when properly sited and
Geothermal power plants affect the biodiversity around its vicinity. Also, it contributes to
the disruption of waterways, wildlife, vegetation, geological hazard, water quality, and
land use.
plants, the geothermal power plants have lifecycle emissions of 38 gCOeq/kWh. That is
95 percent less than coal (820 gCOeq/kWh) and 92 percent less than gas (490
gCOeq/kWh).
pollution. The production of foul odors and carbon emission contributes to air pollution.
methane, and boron are emitted into the atmosphere. The hydrogen sulfide emission
results in a foul odor known as “rotten egg” smell. Furthermore, hydrogen sulfide
becomes acid particulate once emitted into the atmosphere becoming a sulfur dioxide
that could lead into acid rain contamination that damages crops, soils and bodies of
water. Consequently, it could cause heart and lung disease. In some instances,
geothermal power plants emit mercury. With the use of technologies like scrubbers, the
air pollution emitted by the power plant reduces, however, the chemicals are converted
into a watery sludge composing sulfur, vanadium, silica compounds, chlorides, arsenic,
mercury, nickel, and other heavy metals. These by-products should be disposed
Energy, 2013).
generation. Thus, geothermal power plant contribute to water pollution not only with the
wastewater disposal that affects water quality but also with the water consumption.
Sulfur, salt, and other minerals are commonly found in hot water drained from
after being used for heat or energy output, water is drained back into the geothermal
reservoir. For an open-loop system, the waste water is either disposed of in land or
back into the bodies of water, however, the wastewater includes some of the chemicals
and it also have higher temperature that could disrupt the biodiversity and water quality
Geothermal power plant cause land pollution as it requires wide land areas to be
constructed. Also, soil degradation could happen, and it can disrupt vegetation because
of its waste products. Furthermore, if the power plant uses landfills for its waste
subsidence wherein the land sinks because of the extraction of geothermal fluids. Even
phenomenon could still happen. Since a geothermal power plant needs a hot ground
fluid reservoir, it is located near the “hot spots” which in most cases are near fault
zones. Fault zones are prone to instability and can trigger earthquakes. Some studies
In addition, tiny earthquakes can be triggered by digging deep into the earth and
extracting water and steam. Furthermore, like natural gas hydraulic drilling, water is
pumped at high pressures underground that could crack hot rock reservoirs increasing
Energy, 2013).
and are not viewed as a noise nuisance in encompassing residential communities. All
power facilities should meet nearby noise ordinances on the phase of construction and
phases: the well-drilling and testing phase, the construction phase, and the plant
operation phase. At the construction phase, noise might be produced from the
construction of well pads, transmission towers, and power plant. During the operation
phase, most of the noise is produced from the cooling tower, the transformer, and the
turn of events, yet even construction noise by and large remaining parts underneath the
65 dBA. Besides, noise pollution related with the construction period of geothermal
when construction ends. Well pad construction can take anyplace from half a month or
months to a couple of years, as it depends on the depth of the well. The well-drilling and
testing period of geothermal development for the most part doesn't surpass the noise
guidelines, they are brief, and the noise pollution they produce isn't perpetual. Be that
as it may, well-drilling operations regularly occur 24 hrs each day, seven days every
week. Noise from ordinary power plant activity for the most part comes from the three
segments of the power plant: the cooling tower, the transformer, and the turbine-
and researchers are depended with the errand of checking their effects on the
environment. With a very much planned checking plan, they are kept educated
regarding the states of the system which they are liable for keeping up and a sound
successful way inside the limits of their perception space, as per guideline and best
practices. Similar to the case with the power plant engineer, the environmental
with food of the indigenous habitat. For the operation in geothermal power plants, it
that can draw heat content from rocks beneath the surface of the earth. Geothermal
power plants need to have cooling fluids to dispose of waste heat to the surroundings.
These can be new or salt water that makes a one-time go through a condenser,
conveying the waste heat into a nearby stream, lake or sea. The cooling fluid can
likewise be water that conveys waste heat into the surrounding in latent form through an
evaporative cycle in a cooling tower or air that cools a dry condenser (Environmental
REFENCES
Ahmed, S. J. (2020). Philippines Power Sector Can Reach Resilienceby 2021. Institute
for Energy Economics and Financial Analysis.
Avenston. (2019, February 14). Geothermal power plants: advantages and
disadvantages. Retrieved from Avenston: https://avenston.com/en/articles/geothermal-
pp-pros-cons/
Benito, F. A., Ogena, M., & Stimac, J. (2005). Geothermal energy development in the
Philippines: country update. Retrieved from Research Gate:
https://www.researchgate.net/publication/228575099_Geothermal_energy_development
_in_the_Philippines_country_update
Benito, F. A., Ogena, M., & Stimac, J. (2005). Geothermal energy development in the
Philippines: country update. Retrieved from Research Gate:
https://www.researchgate.net/publication/228575099_Geothermal_energy_development
_in_the_Philippines_country_update
California Energy Commission. (2015). Types of Geothermal Power Plants. Retrieved
from California Energy Commission: https://www.nrel.gov/research/re-geo-elec-
production.html
Commissioning operation and maintenance archives. (2019, March 18). Retrieved April
26, 2021, from https://www.geoenergymarketing.com/tag/commissioning-operation-and-
maintenance/?fbclid=IwAR0E6r6hUFieNv6wyIy3mAyf5ervSVWfWPx-
5Hi8Bwm00ZCcSeyn00GEVjE
Department of Energy. (2020, May 22). 2019 Power Statistics. Retrieved from
Department of Energy:
https://www.doe.gov.ph/sites/default/files/pdf/energy_statistics/2019_power_statistic_01
_summary.pdf
DiPippo, R. (2012). Geothermal Power Plants: Principles, Applications, Case Studies
and Environmental Impact (3 ed.). Elsevier.
Energy Sector Management Assistance Program. (2012). Geothermal handbook:
planning and financing power generation.
Fuji Electric. (2021). Thermal and Geothermal Power Generation. Retrieved from Fuji
Electric:
https://www.fujielectric.com/products/thermal_power_generation/geothermal_power/ind
ex.html
Goulds Pump. (n.d.). Goulds 3180. Retrieved from
https://www.gouldspumps.com/ittgp/medialibrary/goulds/website/Products/3180/Goulds
_3180_Bulletin_Web.pdf?ext=.pdf
How do i get a permit. (n.d.). Retrieved April 26, 2021, from http://ecac.emb.gov.ph/?
page_id=49
International Energy Agency. (2019, November). World Energy Outlook 2019. Retrieved
from International Energy Agency: https://www.iea.org/reports/world-energy-outlook-
2019/electricity
Kebede, H. (2002). Geothermal Training Program. Study of Geothermal Power
Electrical and Control System with Emphasis on Reliability Aspects.
Latin American Energy Organization. (1994, July). Guide for Geothermal Field and Plant
Operation and Maintenance. Pg. 60-75.