Professional Documents
Culture Documents
CE131 Lec 11 Project Control Solutions
CE131 Lec 11 Project Control Solutions
Project Control
Project Control
• To maintain control of the cost and time budgeted
for the project
• Before construction
– Project cost & schedule estimates
• During construction
– Changes occur
– Measure cost and schedule performance
1
3
2
Cost and Schedule Performance
• The first step in evaluating the status of a
project
– Compute the earned value of the activities
completed during the reporting period
3
Earned Value System
Variance Calculations
4
Variance Example
• Framing Activity
– Budget = $5,000 & Duration = 5 days
• One carpenter
• 40 work-hours (8 hr/day)
– After three days, the job is determined to be 40
percent complete.
– To date, $2,550 has been paid out on the
activity
• What are the schedule and cost variances
and indices?
9
• Schedule Variance
• Cost Variance
10
5
Schedule and Cost Indices
• Schedule Performance Index
11
Productivity Index
• Introduce the credit work-hour factor
– Measuring the actual work being accomplished in the
field
• An error in estimating
– 65 hours instead of the 40 hours estimated
6
How to calculate cost and duration
13
14
7
Labor Unit Price
• The estimated cost of labor for installing
300 ft of conduit
– The unit price of $4.70 for labor
Labor cost = 300 ft x $4.70/ft = $1,410
8
Total Installation Cost
• The estimated cost for installing 300 ft of conduit
– The unit price of $11.55/LF for Total O&P
Labor cost = 300 ft x $4.70/ft = $1,410
Material cost = 300 ft x $4.13/ft = $1,239
O&P cost = 300 ft x $2.72/ft = $816
Total cost = 300 ft x $11.55/ft = $3,465
17
Any Questions?
18