NPM : 22001082171
CLASS : A1
COST
ALLOCATION
BASE
COST
COSTOBJECT:
OBJECT: Indirect Costs
JOB
Direct Costs
DIRECT
COST Direct
a. Machining Department:
$9,065,000
= $49 per machine-hour
185,000 machine-hours
b. Finishing Department :
$8.181.000
= 202% of direct manufacturing labor costs
$4.050.000
5. Machining Finishing
Manufacturing overhead incurred (actual) $10,000,000 $7,982,000
Manufacturing overhead allocated
200,000 hours x $49 9,800,000
202% of $4,100,000 8,282,000
Underallocated manufacturing overhead $ 200,000
Overallocated manufacturing overhead $ 300,000
Total overallocated overhead = $300,000 – $200,000 = $100,000