Slack value is the difference between ES and LS. The calculation is given below

Slack 
Activity ES EF LS LF
(LS-ES)

0
A 0 2 0 2
(0-0)

0
B 2 8 2 8
(2-2)

2
C 2 6 4 8
(4-2)

D 8 10 8 10 0
E 8 11 10 13 2
F 2 4 11 13 9
G 10 12 10 12 0
H 12 13 12 13 0
I 13 14 13 12 0
Based on the above table, the slack value for activity A, B, ,C, D, E, F, G, H, I as 0, 0, 2, 0, 2, 9, 0, 0,
and 0 respectively. Here, we can identify the critical path as A-B-D-G-H-I based on selecting
activities which indicating 0 as their slack values.