You are on page 1of 8

An Update on the Scaled Span Concept for Dimensioning Surface Crown

Pillars for New or Abandoned Mine Workings


T.G. Carter
Golder Associates, Toronto, Canada.

ABSTRACT: The empirical scaled span approach for assessing the stability of surface crown pillars for mined
openings has been in use for over a decade. In this time it has been widely used not only for dimensioning new
crown pillars but also for assessing the stability of often abandoned crowns. This paper re-evaluates and
updates the original database compiled in 1989/1990 and re-examines the basic mechanisms considered of
relevance to the development of the Scaled Span concept. Improvements to current methodology for properly
dimensioning a crown pillar over a shallow mine or tunnel opening are presented, based on updated knowledge
of the behaviour of some of the case records.

Some observations and inferences on long term stability are provided, together with discussion of possible
correlations that may exist with respect to the age of the pillars that have remained stable, as compared with
those that failed. On the basis of observations on the time from original excavation to failure, some
suggestions are given on application of the scaled span concept for assessing pillar longevity.

1 INTRODUCTION using this as a basis for comparison with an assessed


rock mass quality, was further spurred by having to
The Scaled Span concept was developed over a address the remediation of several catastrophic
decade ago, as a procedure for empirically collapses (Carter et al., 1988).
dimensioning the geometry of crown pillars over
near-surface mined openings, based on precedent
experience, (Carter, 1989, 1992). At the time of its
initial development, no acceptable method existed
for assessing the stability of the many hundreds of
existing mined openings, many of which were found
to be sited in locations where collapse posed
significant risks to the General Public, (Figure 1).

As crown pillar design for most hard rock mines in


the past had been arbitrary at best, and random at
worst, based simply on "leaving just one more round
to surface" some more logical method of surface
crown pillar dimensioning was required. Available
"Rules of Thumb" and theoretical methods were
evaluated and none were found capable of dealing
with the complexities of the rock masses generally
found in these crown areas.

A need was recognized, therefore, for developing a


simple, yet credible method for evaluating the
stability of near-surface crowns over mined
Figure 1: Geometry of 1987 Cave-in below Highway
openings. The concept of scaling crown spans with
11B in Cobalt, Ontario, Canada.
respect to their three - dimensional geometry and
Carter - Update on the Scaled Span Concept 1
During the past ten years, the “scaled span” hence longevity is much more difficult. Accordingly,
methodology has been widely employed, and more heavy reliance has had to be placed on examination
than 100 extra case records have been added to the of old failures as a key to understanding mechanistic
original 1989/1990 database of over 200 case processes that may provide insight into prediction of
records. This database initially included thirty future behaviour.
documented failures and another dozen have now
been added. In 1987, the catastrophic collapse of part of a major
Provincial Highway into an old mine working
2 STABILITY ASSESSMENT APPROACH attracted national media attention, (Figure 1). This
collapse, and the follow-up studies which identified
As the primary purpose of a crown pillar is to several other hazard sites close to or beneath
protect surface land users, the mine, and those municipal buildings and schools in other parts of the
working in it, from inflows of water, soil and rock; old mining community (Carter et al., 1995),
it is vital that such surface pillars remain stable focussed attention at the highest political levels for
throughout their life. Maintaining the stability of the developing cost-effective solutions for assessing and
crown is critical, not only to the success of the mine, dealing with this legacy (Mackasey, 1989).
but also to ensuring the safety of any community or
infrastructure that exists above it. As part of this focus, an extensive study of the
factors that controlled crown pillar stability was
A number of approaches have been proposed over initiated and various methods of structural analysis
the years to assist miners in dimensioning crown were examined, (Bétournay, 1987, 1996, Carter,
pillars and addressing their stability. However, 1989, and Golder Associates, 1990). These studies
because of the significant differences that exist in demonstrated that for any given rock quality,
behaviour between identified failure mechanisms, stability depended principally on geometry. The
(Carter, 1989, Bétournay, 1987) most of these span, thickness, and weight of the rock mass
approaches, have been specifically addressed to one comprising the crown were found to be the most
or other of the various characteristic failure critical characterizing parameters. (Figure 2). This
behaviours, (eg., Goel and Page, 1982, Hoek, 1989, led to initial attempts at normalizing controlling
parameters, recognizing that:
( t σh θ)
Crown Stability = f
SL γ u
where increased stability for any rock mass quality
would be reflected by an increase in ...
t, the crown pillar thickness
σh, the horizontal insitu stress
and/or ..in θ, the dip (of the foliation or
of the underlying stope walls), and
where decreased stability for any crown would
result from increases in
S, the crown pillar span
L, the overall strike length of the stope
γ, the mass (specific gravity) of the crown
Figure 2: Geometry Definitions for Scaled and/or ..in u, the groundwater pressure.
Span Crown Pillar Stability Assessment.
Bétournay et al, 1994). Others have attempted to From examination of this grouping, it was evident
examine the resulting influence zone or the actual that all parameters except σh and u were related
sinkhole geometry as a function of the collapse solely to the geometry of the crown pillar. In order,
process (Szwedzicki, 1999) therefore to normalize the relationship to be only
geometry and weight dependent, it was decided that
While assessing current stability is problematical both these terms should be handled as part of rock
enough, attempting to predict future behaviour and mass classification, as both the NGI-Q and the

Carter - Update on the Scaled Span Concept 2


Geomechanics RMR systems take groundwater into the stope is no longer the ore zone width but rather
consideration (Bieniawski, 1973, 1989; Barton et al, the hangingwall dip length. It should also be noted
1974) while the effects of in situ confining stress are that the CS expression has been normalized in such a
well covered in the Q–system (Barton, 1976, way that for characteristic stope spans of 4 - 5m,
Grimstad and Barton, 1993). Accordingly, the final with a crown rock specific gravity of 3.0g/cc,
empirical expression, termed the Scaled Crown typical of many ore zone conditions, once the strike
Span was formulated as follows: length of the stope significantly exceeds the span (as
 γ 
0.5 reflected by a very small span ratio, SR) the CS
C S = S  expression essentially devolves to the 2D case,
 t (1 + S R )(1 − 0.4cos(è ))  thereby allowing direct comparison with standard
where: S = crown pillar span (m) civil tunnel and cavern case record data.
γ = specific gravity of the rock mass
This then allowed comparison of failed versus stable
t = thickness of crown pillar (m)
cases, which led to the development of the “Critical
SR = span ratio = S / L (crown pillar span /
crown pillar strike length), and Span” limit line shown on Figure 3. This limit line,
θ = dip of the orebody or foliation (degrees) which, for any given rock quality, defines the widest
stable scaled span value for unsupported ground
was defined with relation to Q, as follows:

S C = 3.3x Q 0.43 x sinh 0.0016 (Q)


where: SC = Critical Span (m)
Q = NGI-Q value = exp (RMR – 44)
9
and RMR = CSIR Rock Mass Rating

As discussed in the papers introducing this concept,


(ref. Carter, 1992, Carter and Miller, 1995 or the
original Golder Associates' 1990 report to Canmet),
the hyperbolic sinh term in the above expression
was introduced to account for the non-linear trend
to increasing stability recognized for very good
quality rock masses.

3 APPLICATION OF THE METHOD

At its simplest, the Scaled Span method can be


deterministically applied by comparing the scaled
crown pillar span (CS) for any pillar of concern to
the critical span (SC) value deemed appropriate for
the controlling rock mass. When the scaled crown
Figure 3: Concept of probabilistic application pillar span, CS, is determined to be less than the
of the Scaled Span Approach, critical span, SC, the crown pillar would be
(after Carter & Miller, 1995) considered stable. If, on the other hand, the scaled
span, CS, was calculated as greater than the critical
span, SC, unless the crown had been sufficiently
Although detailed discussion of the full development supported or fill approaches had been used in
of this expression is beyond the scope of this current mining, likelihood of failure would be high.
paper, it should be noted that foliation dip in the
above expression reflects the span controlling While straightforward, such deterministic
hangingwall dip, (Figure 2). Moreover, as the dip of application does not provide direct assessment of
the foliation and hence of the stope sidewalls the risk level posed by the proposed geometry.
shallows from 90o to past 45o the effective span of Establishing an exact Factor of Safety, or Safety
Carter - Update on the Scaled Span Concept 3
Margin, however, is not trivial. This is because assessment of failure likelihood if the method is
crown failures have been found to have occurred in applied probabilistically. This then, not only allows
a wide variety of ways, ranging from disaggregation definition of minimum acceptable crown
and ravelling forms of collapse to intact block slides thicknesses, it also better takes into account
or chimney failures (Bétournay, 1996). Thus, heterogeneities within the rock mass. Applied
several quite different controls on failure probabilistically, the approach can also better help in
mechanisms exist. defining acceptable or allowable risk for a given
situation as per Table 1.
Failure in pure shear is relatively rare based on the
database records, but is the easiest to analyze, so Although it is now becoming commonplace for a
has led to development of the most straightforward new mine design to collect appropriate data, and
analytical methods (e.g. Hoek, 1989). Ravelling then analyse crown stability using numerical
failure mechanisms are common in the degradable methods as an adjunct to carrying out Monte Carlo
rocks, but it is virtually impossible to analytically, or or similar probabilistic evaluations using the scaled
even numerically predict rates of ravelling. Nor is it span method; often, at an early concept assessment
easy to determine a safety factor for any stage in the stage, there is a need to rapidly assess likelihood of
ravelling process, except perhaps on a case specific failure. Some insight gained from evaluation of
basis using sophisticated, computationally intensive some of the case records while attempting to define
approaches, by means of distinct element or particle what might control longevity, has led to an
flow code modelling (eg., Lorig et al, 1995). approach which may help to facilitate such
Because of its empirical basis, application of the assessments, (Carter and Miller, 1996). As shown
Scaled Span method allows at least a rational on Figure 4, it was found that, if, rather than

Table 1: Comparative Significance of Crown Pillar Failure (from Carter & Miller, 1995)

Class Prob. of Minimum ESR Design Criteria for Acceptable Probability of Failure
Failure Factor of
(%) Safety Excavtion Serviceable Life Years Public Access Regulatory Operating
Support Position on Surveillance
Ratio Closure Required

A 50-100 <1 >5 Effectively zero <0.5 Forbidden Totally Ineffective


unacceptable

B 20-50 1.0 3 Very, very short term 1.0 Forcibly Not Continuous
(temporary mining purposes prevented acceptable sophisticated
only; unacceptable risk of monitoring
failure for temporary civil
tunnel portals)

C 10-20 1.2 1.6 Very, short term (quasi- 2-5 Actively High level of Continuous
temporary stope crowns; prevented concern monitoring with
undesirable risk of failure for instruments
temporary civil works)

D 5-10 1.5 1.4 Short term (semi-temporary 5-10 Prevented Moderate Continuous simple
crowns, e.g. under non- level of monitoring
sensitive mine infrastructure) concern

E 1.5-5 1.8 1.3 Medium term (semi-permanent 15-20 Discouraged Low to Conscious
crowns, possibly under moderate level superficial
structures) of concern monitoring

F 0.5-1.5 2 1 Long term (quasi-permanent 50-100 Allowed Of limited Incidental


crowns, civil portals, near- concern superficial
surface sewer tunnels) monitoring

G <0.5 >>2 0.8 Very long term (permanent >100 Free Of no concern No monitoring
crowns over civil tunnels required
slopes)

Carter - Update on the Scaled Span Concept 4


plotting the crown geometry of all the case records, 4 LONGEVITY CONSIDERATIONS
(expressed as Scaled Crown Span, CS values) versus
rock quality, each CS value was directly compared Despite the usefulness of such probabilistic methods
with the appropriate Critical Span, SC value for the for assessing current pillar stability, the approach
given rock quality and the ratio was plotted with falls far short when it comes to addressing
longevity, a key question now frequently requiring
discussion in closure documents. Further, although
it has long been known that changes in stability state
occur as an excavated opening deteriorates by
ravelling of the stope walls or crown, thereby
leading to wider spans or thinner crown conditions,
little quantitative is known about rates of ravelling.

Although limited use was made at the time of the


1990 compilation of the original database of
information pertaining to the time to failure, some
basic data was collected on longevity of the crowns.

Experience gained from a decade of applying the


Figure 4: Probability of Failure plotted with crown pillar scaled span approach for both new
respect to (SC/CS) ratios mine situations and in analysis of existing and failed
older crowns has further added to this
understanding of crown behaviour, with the most
respect to probability of failure, then a cumulative interesting result being that a marked disparity in
probability graph could be drawn. As the behaviour seems to exist between crowns in hard
distribution on this graph is approximately normal, non-degradable rock masses compared with those in
an error function relationship can be formulated
the more breakdown-prone degradable lithologies.
between Pf and the quotient SC/CS (designated as FC
Based on some limited data on progressive failures,
in the following expression, where FC can be
some tentative correlations have been drawn
considered as a crude crown pillar stability safety
between initial rock quality, potential caving rates
factor):
and survival probability as shown on Figure 5(after
 2.9 Fc − 1 Carter and Miller, 1996).
Pf = 1 − erf  
 4 
Examination of the case records that give rise to the
where Pf = Probability of failure trends shown in Figure 5, suggests that initial
and FC = SC/CS

In utilizing this expression, it should be realized


firstly that matching of this trend line to the case
record data has been targetted to the low probability
end of the scale, (Pf <<50%, FC>1) as this is
generally the area of the distribution of most
importance for practical applications. As a
consequence, calculation of Pf values where FC<<1,
tend to be overestimated due to the characteristics
of the error function used in the curve-fit equation.
Secondly, the relationship assumes a mid-line to the
spread of the plotted case record database
information, which generally suggests rock quality
variation to typically be well defined by a standard Figure 5 : Percentage of Crown Pillar Case
deviation of 10 RMR units. Records that Survived, plotted by decade

Carter - Update on the Scaled Span Concept 5


geometry, irrespective of rock quality, controls comparing these records with other well known data
short term stability (of the order of 0-20 years) but sets on stand-up time available from civil tunnelling
that rock competence controls later stages in the experience (eg. Bieniawski, 1973, 1989, Barton,
failure process. The data furthermore shows two 1974, 1976).
classic periods where failures are more common.
One period occurs at less than 20 years from initial As is apparent from Figure 6, if, rather than plotting
excavation, the other at about 60 years. In some of the data as span versus stand-time, as classically
the earlier period failure cases, surface breakthrough portrayed, the data is plotted against rock quality,
or crown collapse is known to have developed then a remarkable disparity becomes evident
simply because the overburden/bedrock profile between some of the “short-term” tunnelling
above the crown of a particular stope was irregular stability cases and most of the “long-term” crown
and much deeper than anticipated by the miners. pillar failure cases. On this diagram, the two major
The second period, by contrast seems to be much data groups plot as two bands. The data points
more related to progressive ravelling failures. extending diagonally across the centre of the graph
are the tunnelling and mining drift case records from
The plot on Figure 5 of survival probability for the Bieniawski and Barton and other sources, while the
database case records, seems to show a classic set extending across the complete width of the
initial exponential increase in failure probabilities graph at fairly long stand times is the crown pillar
(possibly due to "defects", e.g. cavalier mining too data set.
close to surface), with a Weibull type of decay
behaviour for the later decades, (possibly reflecting As is apparent a fundamental difference in the
an increase in failures due to "wearing out" effects, effective definition of time to failure exists between
e.g. degradation due to progressive ravelling and these two data sets. Time to failure for the
weathering), (Carter and Miller, 1996). tunnelling cases, plotted as triangles and circles, is
defined as the point of original initiation of spalling,
ie., the traditional concept of Lauffer (1958), which,
expressed in terms of rock quality, RMR, can be
estimated from Is = 0.0156e0.165RMR as summarized
in the following table.
Table 2: Spalling Time and Span relationships

R Spalling Initiation Time, Is (Hours) Threshold


M Span (m)
0.165RMR
Figure 6 Bieniawski Is = 0.0156e Bieniawski &
R Equation
20 0.22 0.90 0.42 1/2 hr 2.4 2.7
40 8.17 14.00 11.47 12 hr 6.6 6.3
60 299.03 200.00 310.91 2 wks 15.0 14.7
80 10943.8 8000.00 8429.6 1 year 31.0 34.3
100 400525 ? 228551 25 yrs ? 79.8

Figure 6: Crown Pillar Collapse Time


plotted with respect to initiation of spalling
While there is enough data available to make some
(Stand-up Time) for various rock qualities
estimate of initial spalling initiation times, it is much
harder for a surface crown pillar case to estimate
This suggests that while many of the crowns that
"time to failure", defined as breakthrough to
plot in the "safe", stable section of the graphs on
surface. Examination of the failure case records,
Figures 3 and 4, (i.e. with FC values >1) may well
which are plotted as squares on Figure 6 suggests,
stand indefinitely, some of the other crowns may
however, that whether a stope caves through to
ultimately fail. Estimating the likely stand-up time
surface or not, depends on not only the thickness of
for any given crown pillar in the stable section of the
the crown pillar, but also the volume of void
distribution on Figure 4 is not trivial. Some insight
existing in the stope to accept any spalling rock, and
can be gained however from plotting the case
the effective bulking of the rock as it spalls into the
records directly with respect to rock quality and
stope. For the poorest quality rock masses, mean
Carter - Update on the Scaled Span Concept 6
block size is very small and effective bulking is low crown pillar rock mass behavioural characteristics;
(in the 10 to 15% range). For better quality rock i.e.,
masses where the blocks fall out in cobble to
boulder sizes upwards, bulking exceeds 40%. For • the essentially non-degradable, competent rock
both cases, some estimate of the limiting height of types (hard igneous and metamorphic types and
potential cave development is achievable based on well cemented sedimentary units) which exist,
Laubscher's and others caving recommendations for tend not to spall and hence seem to survive,
different bulking conditions, (eg. Laubscher and while
Taylor, 1976, Just and Free, 1971). These caving • the degradable, weathering susceptible, weak or
prediction approaches, in turn can be tied to block highly fragmented rock types, most commonly
size vs. rock quality relationships (such as are fail in due course of time, due to disaggregation
suggested by work by Barton,1974, Franklin and and spalling.
Palassi,1993 and others.)
The history plots of the crown pillar data suggest
As is evident from inspection of Figure 6, the that there are two periods of most common failure,
difference between the two data sets also provides a one fairly soon after excavation and one at a much
direct measure of the "rate of ravelling", the data later time, probably when the progressive failure
groupings pointing to the fact that the maximum cases break through to surface. The plots suggest
divergence between the two trends occurs for very that the likelihood for ultimate failure (i.e.,
poor quality rock masses where initial stand-up uncontrollable breakthrough to surface) depends on
times are extremely limited once a critical threshold (a) governing rock quality and particularly the
span is exceeded (This limiting threshold span, propensity of the rock to degradation due to time-
which can be estimated from Smax = 7.5Q0.38 should dependent effects and (b) crown thickness.
not be confused with the Critical Span, SC line, as
the latter defines a lower probability of failure Although the examples included in this paper
condition for unsupported ground, for which illustrate the application of the Scaled Span concept
support could still be installed, while the former for crown pillar dimensioning and for starting to
defines an upper bound "immediate collapse" limit assess longevity, it must be stressed that these charts
line beyond which support would be largely and derived relationships are all based on limited
ineffective. data, and on various cases which are assumed to be
at an ultimate limit state. In consequence, this type
5 CONCLUSIONS of approach should not be used without
considerable caution as a design guideline.
The concept of scaling the three dimensional Estimating a minimum stable crown thickness for a
geometry of a mine crown pillar in terms of its given situation depends not only on the rock mass
characteristic span was first introduced in 1990 in an properties of the crown and wall rocks, it also is
attempt to advance the then available methods of influenced by more practical considerations such as
crown pillar stability assessment. From the data excavation method, rock reinforcement sequencing,
collected over the years since the initial studies on stress regime and weathering effects. All these
crown stability were done in 1988/1989, it has been factors must be considered, and some compensation
found that failure of individual surface crown pillars made during design to account for such effects.
can be related more rationally to rock mass
characteristics than to discrete failure mechanisms. ACKNOWLEDGEMENTS
The data set suggests that in blocky rock masses,
failures can occur where the intersection of several Part of the original work to develop the Scaled Span
adversely oriented discontinuities occur, or where a concept was funded by CANMET under Contract
particular suite of major joints or faults provides a No.23440-8-9074/01-SQ, other parts were funded
release mechanism for gravity collapse. By by the Ontario Ministry of Northern Development
contrast, where rock quality is poor, and block size and Mines or conducted as part of programmes
is small, failure seems to occur by ravelling and funded by various mining companies. Over the past
breakdown of the blocks comprising the crown and decade, studies for many of these same mining
hangingwall. This suggests two basic, quite different companies have contributed to advances in current
Carter - Update on the Scaled Span Concept 7
understanding. While specific thanks is due to these Carter, T.G., Mackasey, W.O. and Steed, C.M. (1995). Co-
organisations that have supported the work by ordinated approach to Remediation of Abandoned Mine
Hazards. Proc. Sudbury 95 Conf. on Mining and the
supplying unpublished, often confidential,
Environment, Vol. 1 pp. 349-358.
information to form a case study data base,
acknowledgements must also go to many colleagues Carter, T.G. and Miller, R.I. (1996). Some Observations on
at Golder Associates who have made major the Time Dependency of Collapse of Surface Crown Pillars.
contributions to the formulation and testing of some Proc. 2nd North American Rock Mechanics Symposium
of the methods outlined herein. Montreal, Vol. 1, pp.285-294.

Grimstad, E. and Barton, N. (1993) Updating the Q-System


REFERENCES for NMT. Proc. Int. Symp on Sprayed Concrete, fagernes,
Norway, 21pp
Barton, N., Lien, R. and Lunde, J. (1974). Engineering
Classification of Rock Masses for the Design of Tunnel Franklin, J.A. and Palassi M. (1993). Maximum Span and
Support, Rock Mechanics. Vol.6, pp.183-236. Stand-Time of Underground Excavations. In Proc. Int.
Congr. Innovative Mine Design for the 21st Century,
Barton, N. (1976). Recent Experiences with the Q-system of Kingston, Ontario, Bawden W.F. and Archibald J.F. eds.
Tunnel Support Design. Proc. Symp. on Exploration for (Rotterdam: Balkema), pp. 443-453.
Rock Engineering, Johannesburg, pp.107-117.
Goel S.C. and Page, C.H. (1982). An Empirical Method for
Bétournay, M.C. (1987). A Design Philosophy for Surface Predicting the Probability of Chimney Cave Occurrence over
Crown Pillars of Hard Rock Mines, CIM Bulletin, Vol. 80, a Mining Area. Int. F. Rock Mech. Min. Sci. & Geomech.
No. 903, pp.45-61. Abst., 19, pp. 325-37.
Betournay, M.C. Mitri, H.S. and Hasani, F. (1994). Golder Associates (1990). Report 881-1739 to Canmet on
Chimneying Disintegration Mechanisms of Hard Rock "Crown Pillar Stability Back-Analysis". Contract
Mines. Proc. 1st NARM Symposium, pp. 987-996. No.#23440-8-9074/01-SQ, Canada Centre for Mineral and
Energy Technology, pp. 90.
Bétournay, M.C. (1996) Lessons Learnt from Stability
Analysis of Case Studies of Shallow Stopes of Hard Rock Hoek, E. (1989). A Limit Equilibrium Analysis of Surface
Mines. Proc. 2nd North American Rock Mechanics Crown Pillar stability. Proc. Int. Conf. on Surface Crown
Symposium Montreal, Vol. 2, pp.1849-1856. Pillars for Active and Abandoned Metal Mines, Timmins, pp.
3-13.
Bieniawski, Z.T. (1973). Engineering Classification of
Jointed Rock Masses. Trans. South African Inst. of Civil Just, G.D. and Free, G.D. (1971). The Gravity Flow of
Engineers, Vol. 15, No. 12, pp. 335-344. Material in the Sublevel Caving Mining System. Proc. of the
First Australian-New Zealand Conference on Geomechanics,
Bieniawski, Z.T. (1989). Engineering Rock Mass Melbourne, p. 88-97.
Classifications. John Wiley & Sons, 251 pp.
Laubscher, D.H. and Taylor, H.W. (1976). The Importance
Carter, T.G., Busbridge, J.R., Mackasey, W.O., and Annan, of Geomechanics Classification of Jointed Rock Masses in
A.P., (1988). Investigations and Remedial Measures for Mining Operations. Proceedings of the Symposium on
Reinstatement of Highway Collapse over Old Mine Exploration for Rock Engineering, Johannesburg, pp.119-
Workings. Proc. 2nd. Int. Conf. on Construction in Areas of 128.
Abandoned Mineworkings, Edinburgh, pp.289-297.
Lauffer, H. (1958). Gebirgsklassiziziering fur den
Carter, T.G. (1989). Design Lessons from Evaluation of Old Stollendau. Geologie und Bauwesen, Vol. 24, No. 1 pp. 46-
Crown Pillar Failures. Proc. International Conference on 51.
Surface Crown Pillars for Active and Abandoned Metal
Mines, Timmins, Canada. pp.177-187. Lorig, L.J., Board, M.P, Potyondy, D.O and Coetzee, M.J.,
(1995) Numerical Modelling of Caving using Continuum and
Carter, T.G. (1992). A New Approach to Surface Crown Micro-Mechanical Models, Proc. 3rd Can. Conf. On
Pillar Design. Proc. 16th Can. Rock Mechanics Symposium, Computer Applications in the Mineral Industry, pp 416-425.
Sudbury, pp. 75-83.
Mackasey, W.O., (1989) Concepts on Dealing with
Carter, T.G., and Miller, R.I. (1995) Crown Pillar Risk Abandoned Mine Hazards
Assessment - Cost Effective Measures for Mine Closure
Remediation Planning. Trans. Inst. Min. Metl, Vol 104, pp. Szwedzicki, T. (1999). Sinkhole Formation Over Hard Rock
A41-A57. Mining Areas and its Risk Implications. Trans. Instn. Min.
Metall (Section A), Vol. 108, pp.A27-A36.
Carter - Update on the Scaled Span Concept 8

You might also like