Professional Documents
Culture Documents
https://doi.org/10.1007/s10948-020-05508-z
REVIEW
Received: 25 February 2020 / Accepted: 8 April 2020 / Published online: 6 May 2020
# Springer Science+Business Media, LLC, part of Springer Nature 2020
Abstract
This paper introduces the basic situation of the 35-kV domestic high temperature superconducting (HTS) power cable project in
Shanghai. The target of this project is to construct and put into operation the first 35-kV km level three-phase turn-key HTS
power cable project in the world. The cable transmission capacity, cable routing selection, cable structure design, cooling system
configuration, etc. of the project are introduced. The project is implemented by the State Grid Corporation Shanghai Electric
Power Company. A 35-kV, 1.2-km-long 220-kV inter-substation connecting HTS cable line will be constructed in the core urban
area of Shanghai. So far, the type test of the HTS power cable system has been completed, and the construction of the project has
begun. The project is expected to be completed and put into operation in the second half of 2020.
Keywords High temperature superconducting (HTS) . Urban power supply . Power cable
2 Schematics of the Project for large-capacity transmission. The project will build a new
35-kV three-phase AC superconducting cable between
The project has been schemed since 2016, based on the actual 220 kV substation A and substation B in Xuhui District, cen-
demand of the power grid and the rapid development of tral Shanghai. The superconducting cable connects the
Shanghai’s superconducting industry. It takes the advantages busbars of these two substations and will replace the existing
of superconducting strip and cable technology research in four 35-kV conventional cables. The superconducting cable is
Shanghai, utilizing the technology and industrial advantages designed to have a current of 2200 A and a length of 1.2 km
of HTS cable manufacturing, refrigeration system design in- and is scheduled to be completed and put into operation in
tegration, cable joints, and terminal accessory design and December 2020. The normal running current is about 1300 A.
manufacturing. Under special circumstances, the superconducting cable will
Due to the tight underground corridors in the urban center deliver carry the load at the low-voltage side of the main
of Shanghai, in the application scenario of high current, it is transformer to reach full load.
difficult to meet the laying space requirements of multiple The project is under construction by the State Grid
traditional cables. Therefore, superconducting cables are used Shanghai Electric Power Company. The whole process pipe
No. Test item Test equipment Main technical Judgment Referenced Remarks
parameters criterion test method
One terminal thermostat is provided with the inlet for liquid when the pressure along the direction of the cable reaches
nitrogen, and the other one is provided with the outlet for the 3 kN/m2, the polyethylene outer sheath has been destroyed,
liquid nitrogen outlet. The refrigeration system is connected to resulting in an irreversible deformation, and the stainless steel
the superconducting cable thermostat via a terminal thermo- bellow is basically restored. It can be considered that the side
stat. The liquid nitrogen enters from one terminal thermostat, pressure controlled during cable laying should be less than
flows into the cable thermostat, and returns to the refrigeration 3 kN/m2.
system from the other terminal thermostat. The refrigeration The critical current test adopts the four-lead method (sim-
system sends the cooling capacity through the liquid nitrogen ilar to measuring the DC resistance of a cable). A high cur-
to the superconducting cable thermostat to cool the rent Hall sensor and a multimeter are used to test the current
superconducting cable. and voltage, respectively. The critical current test result of
the cable is shown in Fig. 5. The test value is 5769 A, indi-
cating that the critical current of the cable is not degraded
4 Experiment and Test Progress after the manufacturing process of the superconducting
cable.
In order to verify the performance of the cable system de- In addition, a test system consisting of a cable body, an
signed in this project, the critical current and pressure tests intermediate joint, and a terminal was constructed, and a type
were first carried out on the superconducting cable test sam- test was carried out to verify the overall design of the system.
ple. A side pressure test was performed, which tested the abil- The type test items are shown in Table 1. The test items in-
ity of the superconducting cable to withstand the side pressure clude overall pre-cooling, partial discharge test, dielectric loss
along the cable direction. Pressure tests were performed on the test, load voltage cycle test, lightning impulse voltage test,
sample, and the outer diameter or deformation of the sample power frequency withstand voltage test after impact, and pres-
was recorded before and after tests by a displacement sensor. sure test. In the load voltage cycle test, a voltage of 43 kV and
During the tests, a pressure sensor recorded the pressure value a current of 2000 A were applied for a total of 20 cycles. The
when pressure was applied. The result of the pressure test is lightning impulse voltage is ± 200 kV and is applied 10 times.
shown in Fig. 4, where a blue line and a red line represent the The withstand voltage after the impact was 43 kV for 30 min.
deformation condition of the outer insulating tube and outer The pressure test was performed at the 1.1 times operating
sheath, respectively. According to the experiment results, pressure for 10 min.
J Supercond Nov Magn (2020) 33:1927–1931 1931
The type test will be completed in October 2019, and the References
long-distance cable product will be carried out in the future. At
the same time, the cable channel construction of the project 1. Malozemoff, A.P., Yuan, J., Rey, C.M.: High-temperature
superconducting (HTS) AC cables for power grid applications.
will also be carried out.
Superconductors in the Power Grid. Woodhead Publishing. 133–
188 (2015)
2. Malozemoff, A.P.: The power grid and the impact of high-
5 Conclusion temperature superconductor technology: an overview.
Superconductors in the Power Grid. Woodhead Publishing. 3–28
(2015)
This project in Shanghai will be the second km level commer- 3. Rey, C. M., Malozemoff, A. P..: Fundamentals of superconductiv-
cial superconducting cable project in the world [6–8], and it is ity. Superconductors in the power grid. Woodhead Publishing. 29–
also the only superconducting cable project using pipe laying 73 (2015)
for whole process. It will create a blueprint for the application 4. Masuda, T., et al.: High-temperature superconducting cable tech-
nology and development trends. SEI Tech. Rev. 59(7), 13 (2005)
of superconducting cables in the power grid after being devel- 5. Xiao, L. Y., et al.: Implementing high-temperature superconductors
oped smoothly. In high-density load urban areas, the applica- for the power grid in practice: the case of China. Superconductors in
tion of superconducting cables for power transmission has a the Power Grid. Woodhead Publishing. 399–425 (2015)
great practical significance. Compared with traditional cross- 6. Stemmle, M., et al.: AmpaCity—Advanced superconducting medi-
um voltage system for urban area power supply. In: IEEE PES T&D
linked cables, it saves underground corridors and increases conference and exposition, vol. 2014. IEEE (2014)
capacity of main transformers, and it also has some advan- 7. Stemmle, Mark, et al.: Ampacity project-worldwide first
tages in economy. Although the cost of superconducting tape superconducting cable and fault current limiter installation in a
is still higher than that of conventional copper tape, the insu- German city center. : 0742–0742 (2013)
8. Stemmle, M., et al.: AmpaCity—Installation of advanced
lation of cables in liquid nitrogen environment is more reliable
superconducting 10 kV system in city center replaces conventional
than at room temperature, so the service life of 110 kV cables. In: IEEE International Conference on Applied
superconducting cables will be longer than conventional ca- Superconductivity and Electromagnetic Devices, vol. 2013. IEEE
bles. In a comprehensive view, the construction of the km (2013)
9. Stovall, J.P., et al.: Installation and operation of the Southwire 30-
level high temperature superconducting cable project has
meter high-temperature superconducting power cable. IEEE Trans.
strong practical significance for the power grid and upstream Appl. Supercond. 11(1), 2467–2472 (2001)
enterprises. 10. Yumura, H., et al.: Phase II of the Albany HTS cable project. IEEE
Due to the limitation of refrigeration distance, the current Trans. Appl. Supercond. 19(3), 1698–1701 (2009)
demonstration projects are mostly around 1 km. The refriger- 11. Sohn, S.-H., et al.: Installation and power grid demonstration of a
22.9 kV, 50 MVA, high temperature superconducting cable for
ation system needs to be expanded with the expansion of the KEPCO. IEEE Trans. Appl. Supercond. 22(3), 5800804–5800804
distance, increasing the cost in both civil engineering and (2012)
equipment configuration. Although the transmission capacity 12. Ohya, M., et al.: Japan's first operation of high-temperature
of superconducting cables can replace the conventional high superconducting cable systems in live grids (high-temperature
superconducting cable demonstration project). SEI Tech. Rev. 70,
voltage level cables, it is still unable to achieve the continuous 84–93 (2010)
growth of transmission distance. Taking the 500-kV conven- 13. Honjo, S., et al.: Status of superconducting cable demonstration
tional cable as an example, the distance is about 15 km, which project in Japan. IEEE Trans. Appl. Supercond. 21(3), 967–971
is difficult to achieve with superconducting cables. Therefore, (2010)
14. Sohn, S.H., et al.: Design and development of 500 m long HTS
in the future commercial operation, the continuous improve- cable system in the KEPCO power grid, Korea. Phys. C. 470(20),
ment of refrigeration performance is critical, which will open 1567–1571 (2010)
up new avenues for the application of superconducting cables. 15. Lim, J.H., et al.: Performance test of 100 m HTS power cable
system. IEEE Trans. Appl. Supercond. 19(3), 1710–1713 (2009)
Funding Information The project was funded by the State Grid
Corporation of China Science and Technology Project with grant no. Publisher’s note Springer Nature remains neutral with regard to jurisdic-
520940180014. tional claims in published maps and institutional affiliations.