SOME ASPECTS OF GEOTECHNICAL CONSIDERATION
IN THE HOUSING DEVELOPMENT ON EX-MINING LAND
Yeow Thit Sang Executive Director
Bandar Sunway Sdn Bhd
Wong Boon Chong Principal
Wong Boon Chong Consultant
Dr Ooi Teik Aun Director
‘Transfield Construction Malaysia
SUMMARY
In the development of ex-mining land for housing purposes, the earthwork and
* foundation system must be carefully considered in accordance with sound engineering
practice with little constraint on cost.” Detailed site investigation and monitoring of
ground settlement are important to provide essential data for planning and design to
arrive at an economical and sound engineering solution. It is thus important that the
Management of the housing development must be placed under the charge of an
experienced professional engineer to ensure its successful implementation.
This paper describes some aspects of the geotechnical engineering works
carried out in a large scale housing development of an ex-mining land.
L INTRODUCTION,
Bandar Sunway is a self contained development built on an extensively mined
out land of approximately 500 acres. It is bounded by Sungei Klang on the east and
stretched to the border of Subang Jaya on the west. It is about 20 km from the Kuala
Lumpur City, Fig. 1 shows the location of the site. The land was originally a tin
mine worked over by dredging’ method. The dredgers were unable to recover the tin
concentrates deposited in the crevices between the pinnacles of ‘the limestone
formation. Fig. 2 shows some features of Karstic limestone bedrock. ‘The exposed
limestone left behind by the open east mining led to the operation of a limestone,
quarry in 1974, A large depression was created with an area of approximately 80
acres and 2 depth of 45m by the time the site was alienated to Bandar Sunway for
Housing Development in 1986/1987. ‘Thus the development of this wasteland into a
housing estate started during the recession time and amidst a spate of failures reported
on houses built on ex-mining land. It, therefore posed a great challenge to the
Developer and its Engineers in making this ambitious development a success. Table
1 shows the type of development planned for the area.
a4Bb
‘Type of Development
A. Residential
Terrace house (2-storey 22’ X°
Terrace house (2-storey 20’ X ¢
Terrace house (1-storey 20° X ¢
Medium cost apartment (960 sq
Low-cost flat (600 sq. ft.)
B. Industrial
Terrace type (25° X 80°)
‘Terrace type (30° X 80°)
Semi-detached type (65° X 150”
Decached type
C. Commercial
Shep office: (4-storey)
Shop office (2-storey)
Pearl station
Hovel
Commercial complex (Plot ratio
Office complex (Plot ratio 1:3
D. Institution
College campus
Primary and secondary schools
E. — Weter Theme Park
of Ui
1400
919
530
208
1120
nae
19.33 acres
6.24 acres
16.92 acres
14.80 acres
190 acres
‘The entire development is plan
2000.” Fig. 3 shows the layout plan of tl
cast methad of mining resulted in grea
distance of deposition from the Palong.
after mining activities. Fig. 5 shows 2
in 1986.
In order to overcome the eng
development in ex-mining land, vari
foundation systems were adopted. ‘This
investigation is carried out in relation b
ar construction from 1987 to the year
ious phases of development. The open
ation of soil deposit depending on the
4 shows a typical profile of the ground
al view of the site before development
ng problems associated with housing
aethods of ground improvement and
ssible only when carefully planned soil
known mining history of the ground,‘The development of the ex-quarry crater into a water theme park and the
surrounding area into a Town Centre requires exterisive stabilisation work on the rock
face. This is because the quarrying operation caused extensive damage to the rock
slope making it unstable. ‘The unfavourable jointing of the rock mass further
aggravate the stability problem. Thus the investigation and detail design for rock
slope stabilisation was a major task. Fig. 6 shows the plan view of the ex-quarty.
In this paper only the earthwork and foundation system will be discussed in the
subsequent section,
2 SOIL INVESTIGATION
In view of the complexity of the site, preliminary soil investigation consisting
of some forty (40) boreholes and fifty (50) Dutch Cone Deep Sounding were carried
out in July 1986 to January 1987 to provide ground information for subsequent
detailed planning of the work. Figs. 7 and 8 show examples of the subsucface
investigation results where the presence of slime were detected below the sand layer.
3. EARTHWORK AND GROUND IMPROVEMENT
The principle of earthwork for this project is to use all available material
within the site including the slime. The slime within a depth of 6m is removed,
spread to dry and then compacted between two sand layers. ‘The process is repeated
until formation if reached. ‘The top 0.6m of the formation is filled with compacted
sandy clay fill from nearby soutce, Settlement plates installed showed insignificant
post construction settlement of the area treated. ‘The use of slime as fill material also
avoided discharging it into the Klang river thus alleviate environmental pollution.
Where the slime are fresh and in great depth, controlled containment
displacement method was used to remove the slime for drying. ‘The areas were
surcharged with or without vertical drains depending on the results of the soil
investigation after slime extraction. :
In contrast to the method of treatment of slime ponds in Kampong Pandan
where the water level need to be to be maintained, the slime pond in Bandar Sunway
was first pumped dried then filled with 1.5m of sand layer as working platform. Any
displaced slime during the filling process was removed for drying in another area.
Three sets of soil investigation were carried out at three different stages of the filling
operation. ‘The results of the soil investigation were compared for design and
planning purposes.
Deep settlement plates were installed during the filling operation to monitor
the ground settlement. ‘The location of these settlement plates are as shown in Fig.
9. The settlements recorded for the settlement plates in the pond area were large and
in some area exceeding 1m. Fig. 10 shows the settlement of some of the settlement
plates. The settlement was recorded for a total of 76 weeks. Surface settlement
Bauges were installed to’monitor the settlement behaviour of the fill area for the
purpose of delineating the area requiring ground improvement.
43Prefabricated vertical drains were installed on area where settlement is
continuing and the area surcharged with Sm height of sand fill for a period of 4
months. Fig. 11 shows the settlement behaviour of the surcharged area.
BUILDING FOUNDATION
The foundation of each type of development is discussed separately in the
following sections.
41
42
4.3
44
‘Two storey terrace residential houses
The ground condition is variable and filled to various. depths in controlled
manner as described previously. Most of the type of houses are designed on
raft foundation stiffened with intermediate beamis beneath party walls and
partition walis so as to minimise differential settlement. The structural design
of raft foundation takes into consideration the combination of dead and live
loads and the variation of soil condition. It is not uncommon to have one part
of structure on a compressible soil and the other part on incompressible soil.
Settlement monitoring during the construction stage shows that the foundation
settlement is of the range of 20mm to 33mm. resulting in a differential
settlements of 13mm. The angular distortion thus calculated is about 1/460
which is less than 1/300, the limit at which architectural damage occurs,
Regular field inspection of the completed and occupied houses revealed that
the newly added lean-to by the owner has visible crack at the connection area.
The lean-to, being on isolated footings and not designed professionally, settles
more than the building proper which is on developer designed raft foundation.
S-storey medium cost apartment
Four blocks of five storey concrete framed medium: cost apartment are
founded on square reinforced concrete piles of sizes 230mm and 275mm
driven to required sets. Every pile record was studied for any irregularity or
abnormality by the engineer. Beside the conventional static load test carried
‘out oni selected piles, dynamic pile testing was also conducted on piles to
detect suspected pile defects. If found necessary, additional piles were
installed as replacement piles.
Office Complex
‘The structural frame of the high rise office building is founded on prestressed
concrete spun piles of 500mm diameter. “The ground condition is generally
sand over limestone bedrock.
Hotel
anh45
4.6
47,
48
‘The twenty storey concrete frame building is proposed to be founded on sound.
rock formation which has been flattened by former quarrying activities where
limestone bedrock is overtain by sol overburden, micropile will be introduced
to transfer the foundation load to rock.
Sunway Technology Park
Light industrial building consisting of 1% storey terrace and semi-detached
factory with mezzanine floor and column-free layout are located over the
mined out area containing thick layer of slime. Having considered the several
ground improvement methods, prefabricated vertical band drain was used with
surcharge to accelerate the consolidation of the slime. ‘The slime which
consists essentially of clay-silt and sand mixture will be sufficiently stable
after 90% of primary consolidation. Although the calculated surcharge
required is 4m, some areas were given a 6m surcharge to shorten the
consolidation period. Settlement measurements were taken at regular
intervals. “The readings taken over a six month period showed settlement
tapering off and coincided with the estimated settlement calculation.
After the removal of surcharge, the area was compacted by one ton falling
weight dropped through a height of 6m, “This is to compact the formation
layer of the granular soil layer. Raft foundation was used for the heavier
‘mezzanine floor portion of the building and isolated spread foundation was
adopted for the lightly loaded columns.
Post construction monitoring by visual inspections of the already occupied
factory showed no visible sign of any structural distress. Additions of steel
or concrete floor by the owners themselves also did not show any sign of
distress thus indicating the allowable bearing pressure is greater than that
assumed in the design,
Suaway College and Hostel
The structural frames of these medium rise buildings are supported on precast
square reinforced concrete piles of sizes ranging from 200mm to 400mm.
Water Theme Park
Apart from the stabilisation’of rock slope which is outside the scope of this
paper, the Water Theme Park consisting of, among others, children’s play
pool, fin pool, wave pool, and slow river are water retaining structures sitting
on rock formation or on well compacted granular fill over rack.
Pedestrian Suspension Bridge
‘The pedestrian suspension bridge is @ unique feature of the Water Theme
Park. The suspension bridge is supported by cables which are in tension and
fixed to Structural Anchorages. The Anchorages are provided by rock
anchors installed into sound rock so to provide the required resistance to theaia
5.2
53
5.4
55
5.6
5.7
5.8
cable pull, Where the rock joints are closely spaced, rock dowels were used
to stabilise the small scale slab and wedge of the closely jointed rock. Fig.
12 shows an isometric view of the suspension bridge.
CONCLUSION
Bandar Sunway is an example of multiple land use where the tin was first
mined, the exposed limestone quarried for rock product and the ex-mining
land carefully planned for an integrated commercial, residential, educational
and recreational development.
The successful development of ex-mining land requires careful soil”
investigation, systematic ground settlement monitoring and suitable treatment
of soil and ground improvement works.
The reuse of slime by method of drying and sand sandwiching has been
effective in rehabilitating the slime which can be a potential source of
environmental .pollution if discharged into rivers, If left in place it is a
constant sourcé of settlement problem’ when left untreated.
Ground improvement method using prefabricated band drain and surcharge is
effective in treating slime at great depth,
For ‘medium to low rise structures, raft foundation or isolated spread
foundation can be used after soil treatment/improvement. ~
Pile driving in limestone formation can give rise to problem due to Karstic
nature of limestone bedcock or obstruction by boulders. Dynamic pile load
test can be used to assess the possible pile damage.
‘The overall performance of building settlement is generally satisfactory thus
demonstrating the successful implementation of the various geotechnical
engincering method adopted for this development.
‘The importance of experienced professional engineer to control the
development of ex-mining land is emphasised.
AGBIS 40 NoIWOOT - Fold
aragoyl
AYE3O¥I
ae OWT ap
VANE
ORIG
209 ONY SNSMOOUOSE BNOISZWM OUSUYH 40 SIRINIWAI BNOS - Z “OL!
J
savin
|
SRVHEAG:
Trawns OND
amPHASES OF DEVELOPMENT.
Fig. 3 -Fig. 4 - Possible Soil Profile of &x-Mining Land
“4-10 ceajuawdojenag 2.0}98 91S 10 HALA lONBY -—S “DLA
4-1says Auonp 39 Jo maIALoIg = 9b30
60
20
tos:
120
138
15.0
18s
10.0
198
a0
22s
240
2s
20
0
50/0.25
e
x
unestowe
4-13
LEGEND
160
res
300
sur
cur
sano
crave,
‘saxoy
stay
coy
caver
uuesroner I
00bs = 008@ =o
09)
2N10/0x NI BONWASISSY BNOO
Orr oz! cor 80s" °
289/04 MI NOUOIA aAaETS
BMJANW NI’ HLa30uw
UMS 7/2,
THEI FS Ife
t
Igebbbdad
af EERE
{ORSIE PIS
Sle $8 WWE so *
Ub sed Wt
aa i/t sre urn
Ps 1/0
massess YN
‘eievos unsie
: jas
Tome ners = 100
Fis.SHABA 9A LNBNTULIS TWLOL 40 AVE
S¥SNOH 1609 wnIGSH ABHOLS Twnod ~ ve SsvHd - o1°D1d
wy
ANzWELIBs Tied
oa
(wy Fg Jo LH
loozt ,
oot
A-16eng
i
e oe
BSVHa - HdyuO INSWSULL3S
Ee @
5
4-17BOVYOHONY
ape
Apiomed YSMOL FIBYO:
‘UQHONY
ALS dell
SLOadSY “WENLONULS ~ZI “91d
“wgONBESNS py
3d0u Su WUE |
i a
] SNVUINS |
M18 BOHONY aii Sede PEE BOGIua
aevo voHONY > | ra ) SONY
1 ‘ONISSRULS
enous HORz mievd Soave | f
i is
| byt
“|
Wie |
“W TSE
4-18