Professional Documents
Culture Documents
1. Shallow 2. Deep
Good soil
Bad
OK
Good soil
soil
soil
Rammed Aggregate Pier®
Undulated shape
RESULTS OF CONSTRUCTION
300
800
GW q = 0.7496 (p) + 19.79
2
250 GP 700 R = 0.96
40
Ratio of 35
30
aggregate 25
pier stiffness 20
to matrix soil 15
10
stiffness 5
0
1 2 3
Pressure plate
HISTORY of foundation systems
In early 1990’s a third choice emerged:
INTERMEDIATE Foundation® systems (aka “Geopier”)
Good soils
Bad
Good OK
soil
soil soil
OK
soil
Geopier Foundation Company, Inc.
• Over 20 Years of Foundation Support Experience
• ~ 3,000 Projects Completed
• Projects in > 48 States and > 8 Countries
• Design/build Team at > 25 Locations in U.S.
• Designed by In-house P.E.s
• Internal Peer Review Process on Every Project
• Signed/sealed Drawings Backed by E&O
Asian-Pacific Licensees
1. S. Korea
2. China
3. Taiwan
4. Bangladesh
5. Malaysia
6. Philippines
7. Indonesia
8. Australia
RAMMED AGGREGATE PIER®
SYSTEMS
Geopier® Impact®
System System
Temporary Casing to
Prevent Cave-in
IMPACT® PIER
Displacement Method
DISPLACEMENT Crowd pressure
High-
RAP METHOD FrequencyI from rig weight
and hydraulics
mpact
hammer
After First, mandrel
driven is driven to full
to full Then Then, as hollow depth, with
depth, driven mandrel is raised, sacrificial cap
mandrel back stone flows from covering
is raised down 2 Dense, hopper down tamper foot.
up 3 ft ft 1 ft lifts through mandrel.
APPLICATIONS
• 0.8m diameter
• 2m to 8m deep
• qall: 240 to 480 kPa
• Uplift: 140 to 270 kN
• Places footing steel,
pours footing
FLOOR SLAB SUPPORT
Floor load (p)
o
45
Thickness
New Fill (t)
Soft, compressible
soils RAP
element
d "competent"
soils
spacing (s)
SLOPE, EMBANKMENT, WALL
Global stability improvements
conventional spread
footings: DISPLACED
FOUNDATION
adjacent to footing.
RESISTANCE
MATRIX SOIL
BEARING
GEOPIER PRESSURE
BEARING
PRESSURE
UPLIFT
ELEMENT
• Uplift loads = 3 MN
SETTLEMENT CONTROL - EXAMPLE
D+L=357 kips
D+L=138 kips
D+L=421 kips
D+L=710 kips D+L=710
shearwall
BLOCK 224 D+L=1200 kips each
PARKING STRUCTURE end
SACRAMENTO, CA
D+L=835 kips D+L=510 kips D+L=379 kips
shearwall
D+L=1800 kips
D+L=210 kips each end D+L=210 kips
CL, ML 4m
9m
0.8 m diameter
SP, SC
• 3 to 4 m below footing
• Uplift harnesses
23 m
FLOOR SLAB SUPPORT - EXAMPLE
Soft Clay
3m
SP, SM
FLOOR SLAB SUPPORT - EXAMPLE
Value engineering proposal
Rammed Aggregate Pier Floor Slab
stabilized zone
Pier spacing = 4 m
Boring
Locations
Proposed
MSE Walls
Sienna Parkway MSE Wall
31 ft
c = 180 psf
φ = 18°°
16 ft
c = 200 psf
φ = 20°°
Sienna Parkway MSE Wall
Su (ksf)
0 1.0 2.0 3.0 4.0
0 ft
Variable Clay Fill
15 ft
Clay / Sandy Clay
DESIGN SOLUTION
100
Tank
3 Granular
2 Pad Fill Pad
• Hundreds of towers
supported in
Europe & U.S.
Overburden
~ 10 – 15 ft Soft clay
SOFT GROUND
Very Soft Ground
PGA Geopier
PGA Geopier Philippines Inc.
RAIL Embankment PROJECT
Pre-installation
Post-installation
Pre-installation
Post-installation
Liquefaction Mitigation - Example
Riverside Center, Lacrosse, WI
CPT Test Results
Penetration refusal
between piers!
Liquefaction Mitigation - Example
Riverside Center, Lacrosse, WI
SPT Test Results
WHY CONSIDER RAP SYSTEMS?
Economics:
RAP provides
MORE economy
WHY CONSIDER RAP SYSTEMS?
Construction benefits:
• Easy maintain clean/dry construction site
• Reduce or eliminate spoils (contamination)
• Eliminate dewatering systems
• Eliminate shoring / tie-backs near structures
WHY CONSIDER RAP SYSTEMS?
Schedule: