You are on page 1of 2

Assignment I

Basic Tool
Learning Objective:
 How to use GIS Software (ArcGIS) and its basic tools to perform the basic GIS functions and
generate a desired output.
 Application of GIS on DRM

Data Source:
 Administrative boundaries : Admin.shp
 Building footprint layer : Building.shp
 Police force layer : Poloce_station.shp
 River layer : River.shp
 Road layer : Road.shp

There are 4796 buildings in the Smart City classify into 3 categories based on the size of the
building as define as:

Type of Building Area (m2) Relocation Cost (USD)

Small Building < 150 5,000


Medium Building 150– 300 10,000
Large Building >300 25,000

There was a big flood event in year 2015 and the lots of damage were occurred. Finally, the
government came up with the flood inundation risk zone. It divided into two risk zones (high and
low zone) ‐ High risk zone of the flood inundated 150 meter from the center line of the river ‐
Low risk zone of the flood inundated 300 meter from the center line of the river.

1. What is the total length of the road which exposed into the high flood inundation zone?
…………………………6228.505456m…………………………………………….

2. How many Building Density and population density in each admin boundary?

Admin Boundary No. of Building Pop Density


Admin_1 1493 8916
Admin_2 1998 11713
Admin_3 1305 7708

3. How many buildings exposed to the flood inundated in high zone and Admin 1?
………732 buildings……………………………………………………………….

4. How many buildings exposed to the flood inundated in low zone and Admin 3?
……………499 buildings………………………………………………………….

5. What is the total population exposed to flood in high zone?


……………………9814 population………………………………………………….

6. What is the total population exposed to flood in low zone?


……………………7665 population………………………………………………….

7. If the government needs to relocate all building in high risk of flood zone, how much the
government has to allocate budget (in USD) for relocate those building?
………………………9,655,000……………………………………………….

8. Please find the suitable area to construct the new government complex by using the follow
condition
‐ The complex must close to the main road (not more than 100 meter)
‐ The complex must close to the Police Station (not more than 150 meter)
‐ The complex must not locate in flood inundated area (10 m away from flood inundated
area)
9. Make a final layout for your answer.

You might also like