You are on page 1of 9

RINCIAN RITASE PENIMBUNAN PROYEK JALAN TOL PEKANBARU -

BANGKINANG STA 15,600 - 16,900

No Tanggal No. Plat Kendaraan Jumlah Rit Volume Satuan Harga Satuan Jumlah Harga

3
1 01 November 2020 BM 8339 ZU 5 20 M Rp 13.000,00 Rp 1.300.000,00

3
2 01 November 2020 BM 8341 ZU 2 20,7 M Rp 13.000,00 Rp 538.200,00
01 November 2020 BM 8341 ZU 2 20 M3 Rp 13.000,00 Rp 520.000,00

3
3 01 November 2020 BM 8670 FU 2 20,7 M Rp 13.000,00 Rp 538.200,00
01 November 2020 BM 8670 FU 3 20 M3 Rp 13.000,00 Rp 780.000,00

4 01 November 2020 BM 8336 ZU 2 20,7 M3 Rp 13.000,00 Rp 538.200,00


01 November 2020 BM 8336 ZU 2 20 M3 Rp 13.000,00 Rp 520.000,00

6 01 November 2020 B 9591 FYT 3 20 M3 Rp 13.000,00 Rp 780.000,00

3
7 01 November 2020 BM 9451 DU 1 20,7 M Rp 13.000,00 Rp 269.100,00
01 November 2020 BM 9451 DU 3 20 M3 Rp 13.000,00 Rp 780.000,00

8 01 November 2020 BM 9443 DU 5 20 M3 Rp 13.000,00 Rp 1.300.000,00

9 01 November 2020 B 9094 NPA 2 20,7 M3 Rp 13.000,00 Rp 538.200,00


01 November 2020 B 9094 NPA 2 20 M3 Rp 13.000,00 Rp 520.000,00
No Tanggal No. Plat Kendaraan Jumlah Rit Volume Satuan Harga Satuan Jumlah Harga

10 01 November 2020 B 9613 TYT 5 20 M3 Rp 13.000,00 Rp 1.300.000,00

11 01 November 2020 BM 8581 AO 3 20,7 M3 Rp 13.000,00 Rp 807.300,00


01 November 2020 BM 8581 AO 1 20 M3 Rp 13.000,00 Rp 260.000,00

12 01 November 2020 BM 9845 FU 3 20 M3 Rp 13.000,00 Rp 780.000,00

13 01 November 2020 BM 9128 JU 2 20,7 M3 Rp 13.000,00 Rp 538.200,00


01 November 2020 BM 9128 JU 3 20 M3 Rp 13.000,00 Rp 780.000,00

14 01 November 2020 B 9658 SYM 1 20,7 M3 Rp 13.000,00 Rp 269.100,00


01 November 2020 B 9658 SYM 3 20 M3 Rp 13.000,00 Rp 780.000,00

15 01 November 2020 BM 8144 FU 1 20,7 M3 Rp 13.000,00 Rp 269.100,00


01 November 2020 BM 8144 FU 2 20 M3 Rp 13.000,00 Rp 520.000,00

16 01 November 2020 BM 9906 FU 1 20,7 M3 Rp 13.000,00 Rp 269.100,00


3
01 November 2020 BM 9906 FU 4 20 M Rp 13.000,00 Rp 1.040.000,00

3
17 01 November 2020 BM 9725 FU 2 20,7 M Rp 13.000,00 Rp 538.200,00
01 November 2020 BM 9725 FU 2 20 M3 Rp 13.000,00 Rp 520.000,00

18 01 November 2020 BM 9049 AH 2 20 M3 Rp 13.000,00 Rp 520.000,00


No Tanggal No. Plat Kendaraan Jumlah Rit Volume Satuan Harga Satuan Jumlah Harga

19 01 November 2020 BM 9908 FU 3 20,7 M3 Rp 13.000,00 Rp 807.300,00


01 November 2020 BM 9908 FU 1 20 M3 Rp 13.000,00 Rp 260.000,00

20 01 November 2020 BM 9724 FU 1 20,7 M3 Rp 13.000,00 Rp 269.100,00


01 November 2020 BM 9724 FU 2 20 M3 Rp 13.000,00 Rp 520.000,00

3
21 01 November 2020 BM 8820 ZU 1 20,7 M Rp 13.000,00 Rp 269.100,00
01 November 2020 BM 8820 ZU 3 20 M3 Rp 13.000,00 Rp 780.000,00

TOTAL 80 689,8 M3 Rp 13.000,00 Rp 21.018.400,00


RINCIAN RITASE PENIMBUNAN PROYEK JALAN TOL PEKANBARU -
BANGKINANG STA 15,600 - 16,900

No Tanggal No. Plat Kendaraan Jumlah Rit Volume Satuan Harga Satuan Jumlah Harga

3
1 01 November 2020 BM 8339 ZU 5 20 M Rp 13.000,00 Rp 1.300.000,00

3
2 01 November 2020 BM 8341 ZU 2 20,7 M Rp 13.000,00 Rp 538.200,00
01 November 2020 BM 8341 ZU 2 20 M3 Rp 13.000,00 Rp 520.000,00

3
3 01 November 2020 BM 8670 FU 2 20,7 M Rp 13.000,00 Rp 538.200,00
01 November 2020 BM 8670 FU 3 20 M3 Rp 13.000,00 Rp 780.000,00

4 01 November 2020 BM 8336 ZU 2 20,7 M3 Rp 13.000,00 Rp 538.200,00


01 November 2020 BM 8336 ZU 2 20 M3 Rp 13.000,00 Rp 520.000,00

6 01 November 2020 B 9591 FYT 3 20 M3 Rp 13.000,00 Rp 780.000,00

3
7 01 November 2020 BM 9451 DU 1 20,7 M Rp 13.000,00 Rp 269.100,00
01 November 2020 BM 9451 DU 3 20 M3 Rp 13.000,00 Rp 780.000,00

8 01 November 2020 BM 9443 DU 5 20 M3 Rp 13.000,00 Rp 1.300.000,00

9 01 November 2020 B 9094 NPA 2 20,7 M3 Rp 13.000,00 Rp 538.200,00


01 November 2020 B 9094 NPA 2 20 M3 Rp 13.000,00 Rp 520.000,00
No Tanggal No. Plat Kendaraan Jumlah Rit Volume Satuan Harga Satuan Jumlah Harga

10 01 November 2020 B 9613 TYT 5 20 M3 Rp 13.000,00 Rp 1.300.000,00

11 01 November 2020 BM 8581 AO 3 20,7 M3 Rp 13.000,00 Rp 807.300,00


01 November 2020 BM 8581 AO 1 20 M3 Rp 13.000,00 Rp 260.000,00

12 01 November 2020 BM 9845 FU 3 20 M3 Rp 13.000,00 Rp 780.000,00

13 01 November 2020 BM 9128 JU 2 20,7 M3 Rp 13.000,00 Rp 538.200,00


01 November 2020 BM 9128 JU 3 20 M3 Rp 13.000,00 Rp 780.000,00

14 01 November 2020 B 9658 SYM 1 20,7 M3 Rp 13.000,00 Rp 269.100,00


01 November 2020 B 9658 SYM 3 20 M3 Rp 13.000,00 Rp 780.000,00

15 01 November 2020 BM 8144 FU 1 20,7 M3 Rp 13.000,00 Rp 269.100,00


01 November 2020 BM 8144 FU 2 20 M3 Rp 13.000,00 Rp 520.000,00

16 01 November 2020 BM 9906 FU 1 20,7 M3 Rp 13.000,00 Rp 269.100,00


3
01 November 2020 BM 9906 FU 4 20 M Rp 13.000,00 Rp 1.040.000,00

3
17 01 November 2020 BM 9725 FU 2 20,7 M Rp 13.000,00 Rp 538.200,00
01 November 2020 BM 9725 FU 2 20 M3 Rp 13.000,00 Rp 520.000,00

18 01 November 2020 BM 9049 AH 2 20 M3 Rp 13.000,00 Rp 520.000,00


No Tanggal No. Plat Kendaraan Jumlah Rit Volume Satuan Harga Satuan Jumlah Harga

19 01 November 2020 BM 9908 FU 3 20,7 M3 Rp 13.000,00 Rp 807.300,00


01 November 2020 BM 9908 FU 1 20 M3 Rp 13.000,00 Rp 260.000,00

20 01 November 2020 BM 9724 FU 1 20,7 M3 Rp 13.000,00 Rp 269.100,00


01 November 2020 BM 9724 FU 2 20 M3 Rp 13.000,00 Rp 520.000,00

3
21 01 November 2020 BM 8820 ZU 1 20,7 M Rp 13.000,00 Rp 269.100,00
01 November 2020 BM 8820 ZU 3 20 M3 Rp 13.000,00 Rp 780.000,00

TOTAL 80 689,8 M3 Rp 13.000,00 Rp 21.018.400,00