TAHUN 2019
PROVINSI : JAMBI
KAB/KOTA :-
SEDANG
HARGA SAT
NO. JENIS BAHAN SATUAN KODE
(Rp)
1 Pekerja OH L.01 80,000.00
2 Tukang Batu, Besi, Kayu OH L.02 100,000.00
3 Kepala Tukang OH L.03 120,000.00
4 Mandor OH L.04 120,000.00
4 Operator OH L.05 120,000.00
5 Pembantu Operator/Helper OH L.06 100,000.00
6 Penjaga Malam OH L.07 100,000.00
7 Sopir OH L.08 120,000.00
8 Pembantu Sopir OH L.09 100,000.00
CK Boyolali
DAFTAR HARGA SATUAN BAHAN BANGUNAN
TAHUN 2019
PROVINSI : JAMBI
KAB/KOTA :-
SEDANG
I BAHAN DASAR
1 BATU KALI Bulat Belah M3 320,000.00
Pecah 15/20 - 20/30 M3 320,000.00
Pecah 10/15 M3 320,000.00
2 KERIKIL Sirtu M3 210,000.00
Bulat 0,5/1 M3 350,000.00
Bulat 1/2 M3 350,000.00
Bulat 2/3 M3 350,000.00
3 BATU BATA Bata Bh 500.00
Rooster M2 120,000.00
4 PASIR Urug M3 85,000.00
Pasang M3 95,000.00
Beton M3 95,000.00
5 TANAH Urug M3 65,000.00
6 KAPUR Pasang M3 300,000.00
7 PORTLAND CEMENT
Portland Cement, @50 Kg/Zak, Padang Zak 70,000.00
Portland Cement Kg 1,400.00
Semen warna, Tile Grout AM Kg 15,000.00
8 SPLIT ###
Pecah 1/2 M3 450,000.00
Pecah 2/3 M3 450,000.00
Pecah 3/5 M3 450,000.00
V BAHAN BESI
1 BESI BETON Polos, KSTY, U 24 Kg 11,000.00
Ulir, KSTY, U 32 Kg 12,000.00
Wiremesh Kg 10,000.00
2 BESI PLAT Besi Strip Kg 10,000.00
Besi Strip M 3,000.00
3 BESI PROFIL Besi Profil/Pipa Besi Kg 13,500.00
Besi Profil IWF/H-Beam Kg 13,500.00
4 BESI SIKU All Size Kg 13,500.00
5 KAWAT Kawat Ikat Kg 19,500.00
Kawat Las Kg 55,000.00
6 LAIN-LAIN
Paku Sekrup Gypsum/GRC Kg 40,000.00
Skrup Fixer Bh 1,200.00
Sealant Glazing, Silicon Tube 30,000.00
Besi Hollow 4/4 Hitam T=1,7 mm M 14,000.00
2/4 Hitam T=1,7 mm M 10,000.00
7 RANGKA ATAP
Baja Ringan (Terpasang) C.75.75, Reng 32-45 M2 150,000.00
8 PAGAR BRC
BRC M6 Tiang 1,5 & 2" GIP M2 320,000.00
BRC M8 Tiang 1,5 & 2" GIP M2 370,000.00
Kawat Duri M2 120,000.00
9 RAILING HOLLOW
Besi Hollow Hitam 4/4 & 2/4 M2 425,000.00
Stanless Hollow Stanless 4/4 & 2/4 M2 750,000.00
Besi Pipa Hitam 1 - 3" M2 550,000.00
Stanless Pipa Stanless 1 - 3" M2 860,000.00
Galvanis Pipa Galvanis 1 - 3" M2 700,000.00
NO. J E N I S B A H A N SATUAN HARGA (Rp)
VI BAHAN PIPA
1 Pipa PVC SII, S - 12,5 (10 Bar)
Pipa PVC ( ½" ) AW Wavin/Rucika, @4 m/Btg Btg 21,000.00
Pipa PVC ( ¾" ) AW Wavin/Rucika, @4 m/Btg Btg 29,000.00
Pipa PVC ( 1" ) AW Wavin/Rucika, @4 m/Btg Btg 40,000.00
Pipa PVC (1½" ) AW Wavin/Rucika, @4 m/Btg Btg 70,000.00
Pipa PVC ( 2" ) AW Wavin/Rucika, @4 m/Btg Btg 85,000.00
Pipa PVC ( 3" ) AW Wavin/Rucika, @4 m/Btg Btg 175,000.00
Pipa PVC ( 4" ) AW Wavin/Rucika, @4 m/Btg Btg 270,000.00
2 TEMBOK
- Plamur Giant, @20 Kg/Zak Kg 15,000.00
- Cat Dasar Avitex,@ 20 Kg/Pail Kg 21,000.00
- Cat Penutup Spectrum @ 20 Kg/Pail Kg 35,000.00
- Wallpaper Korea, @53 cm x 30 m M2 85,000.00
3 BESI
- Menie Kg 45,000.00
- Cat Penutup Avian Kg 62,800.00
- Minyak Cat/Thinner/Pengencer Laba-laba Ltr 17,000.00
- Lem Aica Aibon Aibon Kg 35,000.00
- Lem Wallpaper Kg 35,000.00
NO. J E N I S B A H A N SATUAN HARGA (Rp)
IX BAHAN KACA
1 POLOS 3 mm Asahimas M2 92,000.00
5 mm Asahimas M2 108,000.00
8 mm Asahimas M2 185,000.00
10 mm Asahimas M2 340,000.00
12 mm Asahimas M2 480,000.00
2 RAYBAN 5 mm Asahimas M2 113,000.00
8 mm Asahimas M2 190,000.00
10 mm Asahimas M2 350,000.00
12 mm Asahimas M2 495,000.00
3 PINTU TAMPERED 12 mm Complete Fitting , acc, Uk. 80x210 cm Unit 2,100,000.00
12 mm Complete Fitting , acc, Uk. 90x210 cm Unit 2,900,000.00
4 PINTU FRAMELESS 12 mm Complete Fitting , acc, Uk. 80x210 cm Unit 1,400,000.00
12 mm Complete Fitting , acc, Uk. 90x210 cm Unit 1,800,000.00
5 ACP 4 mm Complete Terpasang, PVDF M2 610,000.00
6 PINTU HPL 3,5 cm Rangka Plywood, Uk. 70x200 cm, Complete Unit 900,000.00
3,5 cm Rangka Plywood, Uk. 80x200 cm, Complete Unit 1,300,000.00
7 PARTISI INTERIOR 1 Muka Rangka Plywood 9/12 mm, Penutup 4 mm, HP M2 1,300,000.00
2 Muka Rangka Plywood 9/12 mm, Penutup 4 mm, HP M2 1,950,000.00
8 LEMARI INTERIOR Rangka Plywood 9/12 mm, Penutup 4 mm, HP M2 2,100,000.00
9 HURUF Stanless CM 14,000.00
Akrilik CM 7,000.00
LED Akrilik CM 25,000.00
XI BAHAN SANITAIR
1 KLOSET DUDUK MONOBLOK INA/Toto, Otomatis Bh 1,700,000.00
2 KLOSET JONGKOK American Standard Bh 300,000.00
3 WASTAFEL GANTUNG BULAT INA/Toto, Complete Kran Bebek Bh 670,000.00
4 URINOIR KERAMIK STANDART INA/Toto, Otomatis Bh 1,800,000.00
5 LAIN - LAIN
- Kran Air 1/2" Stanless Bh 45,000.00
- Seal tape Bh 4,000.00
- Floor drain Majesty, 3" Stanless Bh 25,000.00
- Bak Cuci Piring, Stanless 1 Sayap Bh 280,000.00
- Water Drain Bh 50,000.00
- Ball Valve 1" Bh 15,000.00
- Ball Valve 3/4" Bh 10,000.00
- Roof Tank Fiber 800 Liter Unit 950,000.00
Fiber 1000 Liter Unit 1,400,000.00
Fiber 1500 Liter Unit 2,100,000.00
- Shower Bh 280,000.00
- Pompa Air Submersible Kap. 1 L/Det, Merk Franklin, 1,1 KW Unit 9,800,000.00
Jetpump, Wasser Unit 1,600,000.00
Semi-Jetpump, Wasser Unit 1,100,000.00
Celup, Wasser Unit 750,000.00
6 INSTALASI TITIK AIR
-Air Bersih Pipa PVC AW 1/2, 3/4", Fittting Titik 120,000.00
-Air Kotor Pipa PVC AW 3,4", Fitting Titik 150,000.00
NO. J E N I S B A H A N SATUAN HARGA (Rp)
XV BAHAN ALUMUNIUM
1 Alumunium Profil Warna Tebal 1.2 mm M 65,000.00
2 Profil Kaca M 5,000.00
3 Aluminium Foil M2 15,000.00
2 20,01,01,004,04,002 Sirtu
3 20,01,01,004,04,003 Sirtu
4 20,01,01,004,04,004 Sirtu
Jenis Standar 20,01,01,005,01 Batu Gunung Belah
No. Kode Standar Harga Nama BaraMerk / Mo
1 20,01,01,005,01,001 Batu Kali / Gunung
Periode Ta
34 20,01,01,005,01,034 Batu Belah 7-10 cm
9 20,01,01,006,11,009 Aquaproof
10 20,01,01,006,11,010 Aquaproof
11 20,01,01,006,11,011 Aquaproof
12 20,01,01,006,11,012 Aquaproof
Jenis Standar 20,01,01,006,12 Cat Tembok
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,01,01,006,12,001 Cat Tembok Metrolite
Periode Ta
1 20,01,01,015,04,001 Kunci Kualitas Sedang
2 20,01,03,002,12,002 Triplek 3 mm
3 20,01,03,002,12,003 Triplek 3 mm
6 20,01,03,002,12,006 Triplek 5 mm
7 20,01,03,002,12,007 Triplek 5 mm
8 20,01,03,002,12,008 Triplek 5 mm
9 20,01,03,002,12,009 Triplek 8 mm
10 20,01,03,002,12,010 Triplek 8 mm
11 20,01,03,002,12,011 Triplek 8 mm
12 20,01,03,002,12,012 Triplek 8 mm
13 20,01,03,002,12,013 Triplek 10 mm
14 20,01,03,002,12,014 Triplek 10 mm
15 20,01,03,002,12,015 Triplek 10 mm
16 20,01,03,002,12,016 Triplek 10 mm
Jenis Standar 20,01,03,003,01 Paku
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,01,03,003,01,001 Paku Campuran
PEMERINT
Hal 137 dari 240
PEMERINT
Hal 138 dari 240
Periode Ta
6 20,03,05,005,01,006 Kran Air 1/2
2 20,03,05,005,04,002 Wastafel
3 20,03,05,005,04,003 Wastafel
4 20,03,05,005,04,004 Wastafel
5 20,03,05,005,04,005 Washtafel Kualitas 1
Periode Ta
6 20,03,06,002,19,006 Lampu Neon Box Armateur 10 Watt
2 31,01,01,001,01,002 Mandor
3 31,01,01,001,01,003 Mandor
4 31,01,01,001,01,004 Mandor
5 31,01,01,001,01,005 Kepala Tukang
Buah 50 M 655.750
Buah LY - 112T R 99M 70.100
Buah LY - 117SK 15 M 70.000
Buah 15m Switch 70.000
Buah 10 M 79.900
Buah 25 M 74.000
Buah 10 M 160.700
Buah 10 M + Lampu 2104 152.300
Buah 15 M + Lampu 105.000
Buah 15 M + Lampu 2154 141.800
Buah 10 M 104.700
Buah 10 M + Saklar 108.000
Buah 15 M 69.900
Buah 10 M 68.000
Buah 10 M 87.000
Buah 1,5 M 50.100
Buah 5M 75.000
Buah 2 x 20 W 546.500
Buah 1x 20 R 378.500
Buah 1 x 20 W 441.500
Buah 389.000
Buah 384.800
Buah 20 V 533.900
Concentra 75.050
Hal 217 dari 240
Print Out Per-Tangga07-Oktober-2019
PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
Periode Tahun 2019
Buah Clear 10 Watt 47.200
Buah Clear 100 Watt 150.000
Buah Clear 15 watt 37.200
Buah Clear 150 Watt 180.000
Buah Clear 200 Watt 200.300
Buah Clear 25 Watt 64.100
Buah Clear 40 Watt 75.150
Buah Clear 60 Watt 86.500
Buah Clear 75 Watt 98.750
Buah Softone White T 60 135.000
Buah Softone White T 60 94.500
Buah Softone White T 60 130.000
Buah Softone White T 60 140.000
Buah Softone White T60 7 145.000
a dan Sewa
Harga Satuan
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
1 A.2.2.1.2 1 M Pagar Sementara dari Seng Gelombang Tinggi 2,00 m
A TENAGA 60,800.00
L.01 0.200 OH Pekerja 80,000.00 16,000.00
L.02 0.400 OH Tukang Kayu 100,000.00 40,000.00
L.03 0.020 OH Kepala Tukang 120,000.00 2,400.00
L.04 0.020 OH Mandor 120,000.00 2,400.00
B BAHAN 217,275.00
1.250 Btg Kayu Dolken diameter 8 - 10 / 400 cm 6,000.00 7,500.00
2.500 Kg Portland Semen 1,400.00 3,500.00
1.200 Lbr Seng Gelombang 3" - 5" 43,000.00 51,600.00
0.005 M3 Pasir Beton 95,000.00 475.00
0.009 M3 Koral Beton 350,000.00 3,150.00
0.072 M3 Kayu Balok Kelas III/Bouwplank 1,800,000.00 129,600.00
0.060 Kg Paku Biasa 2" - 5" 20,000.00 1,200.00
0.450 Kg Meni Besi 45,000.00 20,250.00
C PERALATAN
D Jumlah A + B + C 278,075.00
E Overhead & Profit 10% 27,807.50
F Harga Satuan Pekerjaan (D+E) 305,882.50
2 A.4.1.1.2 1 M3 Membuat Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78
A TENAGA 172,820.00
L.01 1.650 OH Pekerja 80,000.00 132,000.00
L.02 0.275 OH Tukang Batu 100,000.00 27,500.00
L.03 0.028 OH Kepala Tukang 120,000.00 3,360.00
L.04 0.083 OH Mandor 120,000.00 9,960.00
B BAHAN 715,706.08
276.000 Kg Portland Semen 1,400.00 386,400.00
0.591 M3 Pasir Beton 95,000.00 56,185.71
0.750 M3 Kerikil (maksimum 30 mm) 350,000.00 262,370.37
215.000 Ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 888,526.08
E Overhead & Profit 10% 88,852.61
F Harga Satuan Pekerjaan (D+E) 977,378.69
3 A.4.1.1.3 1 M3 Membuat Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm, w/c = 0,72
A TENAGA 172,820.00
L.01 1.650 OH Pekerja 80,000.00 132,000.00
L.02 0.275 OH Tukang Batu 100,000.00 27,500.00
L.03 0.028 OH Kepala Tukang 120,000.00 3,360.00
L.04 0.083 OH Mandor 120,000.00 9,960.00
B BAHAN 747,234.52
299.000 Kg Portland Semen 1,400.00 418,600.00
0.571 M3 Pasir Beton 95,000.00 54,217.86
0.753 M3 Kerikil (maksimum 30 mm) 350,000.00 263,666.67
215.000 Ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 920,054.52
E Overhead & Profit 10% 92,005.45
F Harga Satuan Pekerjaan (D+E) 1,012,059.98
4 A.4.1.1.4 1 M3 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,87
A TENAGA 165,660.02
L.01 1.200 OH Pekerja 103,877.00 124,652.40
L.02 0.200 OH Tukang Batu 139,036.00 27,807.20
L.03 0.020 OH Kepala Tukang 151,821.00 3,036.42
L.04 0.060 OH Mandor 169,400.00 10,164.00
B BAHAN 1,517,761.17
230.000 Kg Portland Semen 3,240.00 745,200.00
0.638 M3 Pasir Beton 457,100.00 291,564.50
0.761 M3 Kerikil (maksimum 30 mm) 616,500.00 468,996.67
200.000 Ltr Air 60.00 12,000.00
C PERALATAN
D Jumlah A + B + C 1,683,421.19
E Overhead & Profit 10% 168,342.12
F Harga Satuan Pekerjaan (D+E) 1,851,763.31
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
IV A.4.1.1 HARGA SATUAN PEKERJAAN B E T O N
5 A.4.1.1.5 1 M3 Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66
A TENAGA 227,943.14
L.01 1.650 OH Pekerja 103,877.00 171,397.05
L.02 0.275 OH Tukang Batu 139,036.00 38,234.90
L.03 0.028 OH Kepala Tukang 151,821.00 4,250.99
L.04 0.083 OH Mandor 169,400.00 14,060.20
B BAHAN 1,787,190.00
326.000 Kg Portland Semen 3,240.00 1,056,240.00
0.543 M3 Pasir Beton 457,100.00 248,140.00
0.762 M3 Kerikil (maksimum 30 mm) 616,500.00 469,910.00
215.000 Ltr Air 60.00 12,900.00
C PERALATAN
D Jumlah A + B + C 2,015,133.14
E Overhead & Profit 10% 201,513.31
F Harga Satuan Pekerjaan (D+E) 2,216,646.45
6 A.4.1.1.6 1 M3 Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm, w/c = 0,61
A TENAGA 172,820.00
L.01 1.650 OH Pekerja 80,000.00 132,000.00
L.02 0.275 OH Tukang Batu 100,000.00 27,500.00
L.03 0.028 OH Kepala Tukang 120,000.00 3,360.00
L.04 0.083 OH Mandor 120,000.00 9,960.00
B BAHAN 896,820.24
352.000 Kg Portland Semen 1,400.00 492,800.00
0.522 M3 Pasir Beton 95,000.00 49,603.57
0.764 M3 Split 450,000.00 343,666.67
215.000 Ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 1,069,640.24
E Overhead & Profit 10% 106,964.02
F Harga Satuan Pekerjaan (D+E) 1,176,604.26
7 A.4.1.1.7 1 M3 Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58
A TENAGA 172,820.00
L.01 1.650 OH Pekerja 80,000.00 132,000.00
L.02 0.275 OH Tukang Batu 100,000.00 27,500.00
L.03 0.028 OH Kepala Tukang 120,000.00 3,360.00
L.04 0.083 OH Mandor 120,000.00 9,960.00
B BAHAN 926,514.29
371.000 Kg Portland Semen 1,400.00 519,400.00
0.499 M3 Pasir Beton 95,000.00 47,364.29
0.776 M3 Split 450,000.00 349,000.00
215.000 Ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 1,099,334.29
E Overhead & Profit 10% 109,933.43
F Harga Satuan Pekerjaan (D+E) 1,209,267.71
8 A.4.1.1.8 1 M3 Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56
A TENAGA 172,820.00
L.01 1.650 OH Pekerja 80,000.00 132,000.00
L.02 0.275 OH Tukang Batu 100,000.00 27,500.00
L.03 0.028 OH Kepala Tukang 120,000.00 3,360.00
L.04 0.083 OH Mandor 120,000.00 9,960.00
B BAHAN 941,640.48
384.000 Kg Portland Semen 1,400.00 537,600.00
0.494 M3 Pasir Beton 95,000.00 46,957.14
0.770 M3 Split 450,000.00 346,333.33
215.000 Ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 1,114,460.48
E Overhead & Profit 10% 111,446.05
F Harga Satuan Pekerjaan (D+E) 1,225,906.52
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
IV A.4.1.1 HARGA SATUAN PEKERJAAN B E T O N
9 A.4.1.1.9 1 M3 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum (12±2)cm, w/c = 0,53
A TENAGA 172,820.00
L.01 1.650 OH Pekerja 80,000.00 132,000.00
L.02 0.275 OH Tukang Batu 100,000.00 27,500.00
L.03 0.028 OH Kepala Tukang 120,000.00 3,360.00
L.04 0.083 OH Mandor 120,000.00 9,960.00
B BAHAN 967,564.29
406.000 Kg Portland Semen 1,400.00 568,400.00
0.489 M3 Pasir Beton 95,000.00 46,414.29
0.760 M3 Split 450,000.00 342,000.00
215.000 Ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 1,140,384.29
E Overhead & Profit 10% 114,038.43
F Harga Satuan Pekerjaan (D+E) 1,254,422.71
10 A.4.1.1.10 1 M3 Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52
A TENAGA 172,820.00
L.01 1.650 OH Pekerja 80,000.00 132,000.00
L.02 0.275 OH Tukang Batu 100,000.00 27,500.00
L.03 0.028 OH Kepala Tukang 120,000.00 3,360.00
L.04 0.083 OH Mandor 120,000.00 9,960.00
B BAHAN 975,494.05
413.000 Kg Portland Semen 1,400.00 578,200.00
0.486 M3 Pasir Beton 95,000.00 46,210.71
0.756 M3 Split 450,000.00 340,333.33
215.000 Ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 1,148,314.05
E Overhead & Profit 10% 114,831.40
F Harga Satuan Pekerjaan (D+E) 1,263,145.45
11 A.4.1.1.11 1 M3 Membuat Beton mutu f'c=28,8 MPa (K325), slum (12±2)cm, w/c = 0,49
A TENAGA 219,800.00
L.01 2.100 OH Pekerja 80,000.00 168,000.00
L.02 0.350 OH Tukang Batu 100,000.00 35,000.00
L.03 0.035 OH Kepala Tukang 120,000.00 4,200.00
L.04 0.105 OH Mandor 120,000.00 12,600.00
B BAHAN 1,006,147.62
439.000 Kg Portland Semen 1,400.00 614,600.00
0.479 M3 Pasir Beton 95,000.00 45,464.29
0.745 M3 Split 450,000.00 335,333.33
215.000 Ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 1,225,947.62
E Overhead & Profit 10% 122,594.76
F Harga Satuan Pekerjaan (D+E) 1,348,542.38
12 A.4.1.1.12 1 M3 Membuat Beton mutu f'c=31,2 MPa (K350), slum (12±2)cm, w/c = 0,48
A TENAGA 219,800.00
L.01 2.100 OH Pekerja 80,000.00 168,000.00
L.02 0.350 OH Tukang Batu 100,000.00 35,000.00
L.03 0.035 OH Kepala Tukang 120,000.00 4,200.00
L.04 0.105 OH Mandor 120,000.00 12,600.00
B BAHAN 1,016,544.05
448.000 Kg Portland Semen 1,400.00 627,200.00
0.476 M3 Pasir Beton 95,000.00 45,260.71
0.741 M3 Split 450,000.00 333,333.33
215.000 Ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 1,236,344.05
E Overhead & Profit 10% 123,634.40
F Harga Satuan Pekerjaan (D+E) 1,359,978.45
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
IV A.4.1.1 HARGA SATUAN PEKERJAAN B E T O N
13 A.4.1.1.17a 10 Kg Pembesian dg Besi Polos
A TENAGA 18,744.26
L.01 0.070 OH Pekerja 103,877.00 7,271.39
L.02 0.070 OH Tukang Besi 139,036.00 9,732.52
L.03 0.007 OH Kepala Tukang 151,821.00 1,062.75
L.04 0.004 OH Mandor 169,400.00 677.60
B BAHAN 309,000.00
10.500 Kg Besi Beton Polos 29,000.00 304,500.00
0.150 Kg Kawat Beton 30,000.00 4,500.00
C PERALATAN
D Jumlah A + B + C 327,744.26
E Overhead & Profit 10% 32,774.43
F Harga Satuan Pekerjaan (D+E) 360,518.68
3 A.4.2.1.4 1 M2 Pembuatan Pintu Besi Plat Baja Tebal 2 mm Rangkap, Rangka Baja Siku
A TENAGA 207,840.00
L.01 1.050 OH Pekerja 80,000.00 84,000.00
L.02 1.050 OH Tukang Besi 100,000.00 105,000.00
L.03 0.105 OH Kepala Tukang 120,000.00 12,600.00
L.04 0.052 OH Mandor 120,000.00 6,240.00
B BAHAN 533,250.00
15.000 Kg Besi Siku 13,500.00 202,500.00
32.800 Kg Besi Plat Baja 10,000.00 328,000.00
0.050 Kg Kawat Las 55,000.00 2,750.00
C PERALATAN
D Jumlah A + B + C 741,090.00
E Overhead & Profit 10% 74,109.00
F Harga Satuan Pekerjaan (D+E) 815,199.00
16 A.4.2.1.20b 1 M2 Pemasangan Rangka Baja Ringan Canal, modul 60 x 120 cm, dinding partisi
A TENAGA 49,560.00
L.01 0.250 OH Pekerja 80,000.00 20,000.00
L.02 0.250 OH Tukang Besi 100,000.00 25,000.00
L.03 0.025 OH Kepala Tukang 120,000.00 3,000.00
L.04 0.013 OH Mandor 120,000.00 1,560.00
B BAHAN 63,700.00
3.500 M Rangka Canal Baja Ringan 14,000.00 49,000.00
30% x rangka Ls Assesoris (perkuatan, dll) 14,700.00
C PERALATAN
D Jumlah A + B + C 113,260.00
E Overhead & Profit 10% 11,326.00
F Harga Satuan Pekerjaan (D+E) 124,586.00
17 A.4.2.1.21a 1 M2 Pemasangan Rangka Besi Hollow Gypsum, modul 60 x 120 cm, Plafond
A TENAGA 34,680.00
L.01 0.1750 OH Tenaga 80,000.00 14,000.00
L.02 0.1750 OH Pekerja 100,000.00 17,500.00
L.03 0.0175 OH Tukang Besi 120,000.00 2,100.00
L.04 0.0090 OH Kepala Tukang 120,000.00 1,080.00
B BAHAN 52,500.00
3.5000 M Rangka Metal Hollow Gypsum 7,500.00 26,250.00
100% x rangka Ls Assesoris (perkuatan, dll) 26,250.00
C PERALATAN
D Jumlah A + B + C 87,180.00
E Overhead & Profit 10% 8,718.00
F Harga Satuan Pekerjaan (D+E) 95,898.00
2 A.4.4.1.2 1 M2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3PP
A TENAGA 74,000.00
L.01 0.600 OH Pekerja 80,000.00 48,000.00
L.02 0.200 OH Tukang Batu 100,000.00 20,000.00
L.03 0.020 OH Kepala Tukang 120,000.00 2,400.00
L.04 0.030 OH Mandor 120,000.00 3,600.00
B BAHAN 124,775.00
140.000 Bh Bata Merah 500.00 70,000.00
32.950 Kg Portland Semen (PC) 1,400.00 46,130.00
0.091 M3 Pasir Pasang (PP) 95,000.00 8,645.00
C PERALATAN
D Jumlah A + B + C 198,775.00
E Overhead & Profit 10% 19,877.50
F Harga Satuan Pekerjaan (D+E) 218,652.50
3 A.4.4.1.3 1 M2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP
A TENAGA 74,000.00
L.01 0.600 OH Pekerja 80,000.00 48,000.00
L.02 0.200 OH Tukang Batu 100,000.00 20,000.00
L.03 0.020 OH Kepala Tukang 120,000.00 2,400.00
L.04 0.030 OH Mandor 120,000.00 3,600.00
B Bahan 116,005.00
140.000 Bh Bata Merah 500.00 70,000.00
26.550 Kg Portland Semen (PC) 1,400.00 37,170.00
0.093 M3 Pasir Pasang (PP) 95,000.00 8,835.00
C PERALATAN
D Jumlah A + B + C 190,005.00
E Overhead & Profit 10% 19,000.50
F Harga Satuan Pekerjaan (D+E) 209,005.50
4 A.4.4.1.7 1 M2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 2PP
A TENAGA 37,000.00
L.01 0.300 OH Pekerja 80,000.00 24,000.00
L.02 0.100 OH Tukang Batu 100,000.00 10,000.00
L.03 0.010 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
B BAHAN 65,140.00
70.000 Bh Bata Merah 500.00 35,000.00
18.950 Kg Portland Semen (PC) 1,400.00 26,530.00
0.038 M3 Pasir Pasang (PP) 95,000.00 3,610.00
C PERALATAN
D Jumlah A + B + C 102,140.00
E Overhead & Profit 10% 10,214.00
F Harga Satuan Pekerjaan (D+E) 112,354.00
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
VI A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
5 A.4.4.1.8 1 M2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP
A TENAGA 37,000.00
L.01 0.300 OH Pekerja 80,000.00 24,000.00
L.02 0.100 OH Tukang Batu 100,000.00 10,000.00
L.03 0.010 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
B BAHAN 58,918.00
70.000 Bh Bata Merah 500.00 35,000.00
14.370 Kg Portland Semen (PC) 1,400.00 20,118.00
0.040 M3 Pasir Pasang (PP) 95,000.00 3,800.00
C PERALATAN
D Jumlah A + B + C 95,918.00
E Overhead & Profit 10% 9,591.80
F Harga Satuan Pekerjaan (D+E) 105,509.80
6 A.4.4.1.9 1 M2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP
A TENAGA 49,125.91
L.01 0.300 OH Pekerja 103,877.00 31,163.10
L.02 0.100 OH Tukang Batu 139,036.00 13,903.60
L.03 0.010 OH Kepala Tukang 151,821.00 1,518.21
L.04 0.015 OH Mandor 169,400.00 2,541.00
B BAHAN 147,915.30
70.000 Bh Bata Merah 1,300.00 91,000.00
11.500 Kg Portland Semen (PC) 3,240.00 37,260.00
0.043 M3 Pasir Pasang (PP) 457,100.00 19,655.30
C PERALATAN
D Jumlah A + B + C 197,041.21
E Overhead & Profit 10% 19,704.12
F Harga Satuan Pekerjaan (D+E) 216,745.33
7 A.4.4.1.22 1 M2 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 3PP
A TENAGA 37,000.00
L.01 0.300 OH Pekerja 80,000.00 24,000.00
L.02 0.100 OH Tukang Batu 100,000.00 10,000.00
L.03 0.010 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
B BAHAN 138,725.00
1.000 M2 Terawang / Roster 120,000.00 120,000.00
11.000 Kg Portland Semen 1,400.00 15,400.00
0.035 M3 Pasir Pasang 95,000.00 3,325.00
C PERALATAN
D Jumlah A + B + C 175,725.00
E Overhead & Profit 10% 17,572.50
F Harga Satuan Pekerjaan (D+E) 193,297.50
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
1 A.4.4.2.1 1 M2 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm ###
A TENAGA 42,600.00
L.01 0.3 OH Pekerja 80,000.00 24,000.00
L.02 0.15 OH Tukang Batu 100,000.00 15,000.00
L.03 0.015 OH Kepala Tukang 120,000.00 1,800.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
B BAHAN 23,225.60
15.504 Kg Portland Cement 1,400.00 21,705.60
0.016 M3 Pasir Pasang 95,000.00 1,520.00
C PERALATAN
D Jumlah A + B + C 65,825.60
E Overhead & Profit 10% 6,582.56
F Harga Satuan Pekerjaan (D+E) 72,408.16
Overhead & Profit (contoh 10%)
2 A.4.4.2.2 1 M2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm
A TENAGA 42,600.00
L.01 0.3 OH Pekerja 80,000.00 24,000.00
L.02 0.15 OH Tukang Batu 100,000.00 15,000.00
L.03 0.015 OH Kepala Tukang 120,000.00 1,800.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
B BAHAN 16,213.60
10.224 Kg Portland Cement 1,400.00 14,313.60
0.020 M3 Pasir Pasang 95,000.00 1,900.00
C PERALATAN
D Jumlah A + B + C 58,813.60
E Overhead & Profit 10% 5,881.36
F Harga Satuan Pekerjaan (D+E) 64,694.96
C PERALATAN
D Jumlah A + B + C 111,186.00
E Overhead & Profit 10% 11,118.60
F Harga Satuan Pekerjaan (D+E) 122,304.60
2 A.4.6.1.2 1 M3 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu Kelas II
A TENAGA 2,532,000.00
L.01 6.000 OH Pekerja 80,000.00 480,000.00
L.02 18.000 OH Tukang Kayu 100,000.00 1,800,000.00
L.03 1.800 OH Kepala Tukang 120,000.00 216,000.00
L.04 0.300 OH Mandor 120,000.00 36,000.00
B BAHAN 4,012,000.00
1.200 M3 Kayu Balok Kelas II/Kusen 3,300,000.00 3,960,000.00
1.250 Kg Paku Biasa 2" - 5 " 20,000.00 25,000.00
1.000 Kg Lem Kayu 27,000.00 27,000.00
C PERALATAN
D Jumlah A + B + C 6,544,000.00
E Overhead & Profit 10% 654,400.00
F Harga Satuan Pekerjaan (D+E) 7,198,400.00
5 A.4.6.1.6 1 M2 Pembuatan & Pemasangan Pintu & Jendela Kaca Kayu Kelas II
A TENAGA 337,600.00
L.01 0.800 OH Pekerja 80,000.00 64,000.00
L.02 2.400 OH Tukang Kayu 100,000.00 240,000.00
L.03 0.240 OH Kepala Tukang 120,000.00 28,800.00
L.04 0.040 OH Mandor 120,000.00 4,800.00
B BAHAN 87,300.00
0.024 M3 Kayu Papan Kelas II/Kusen 3,300,000.00 79,200.00
0.300 Kg Lem Kayu 27,000.00 8,100.00
C PERALATAN
D Jumlah A + B + C 424,900.00
E Overhead & Profit 10% 42,490.00
F Harga Satuan Pekerjaan (D+E) 467,390.00
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U
6 A.4.6.1.10 1 M2 Pembuatan & Pemasangan Jalusi Mati Kosen Kayu Kelas II
A TENAGA 317,800.00
L.01 0.670 OH Pekerja 80,000.00 53,600.00
L.02 2.000 OH Tukang Kayu 100,000.00 200,000.00
L.03 0.200 OH Kepala Tukang 120,000.00 24,000.00
L.04 0.335 OH Mandor 120,000.00 40,200.00
B BAHAN 201,000.00
0.060 M3 Kayu Papan Kelas II/Kusen 3,300,000.00 198,000.00
0.150 Kg Paku Biasa 20,000.00 3,000.00
C PERALATAN
D Jumlah A + B + C 518,800.00
E Overhead & Profit 10% 51,880.00
F Harga Satuan Pekerjaan (D+E) 570,680.00
2 A.4.7.1.4 1 M2 Pengecatan Bidang Kayu Baru (1 lp Plamur, 1 lp Cat dasar, 2 Lp Cat Penutup) 6.6.1
A TENAGA 7,580.00
L.01 0.0700 OH Pekerja 80,000.00 5,600.00
L.02 0.0090 OH Tukang Cat 100,000.00 900.00
L.03 0.0060 OH Kepala Tukang 120,000.00 720.00
L.04 0.0030 OH Mandor 120,000.00 360.00
B BAHAN 29,148.00
0.1500 Kg Plamuur 15,000.00 2,250.00
0.1700 Kg Cat Dasar 52,000.00 8,840.00
0.2600 Kg Cat Penutup 62,800.00 16,328.00
0.0100 Bh Kuas 12,000.00 120.00
0.0300 Ltr Pengencer 17,000.00 510.00
0.2000 Lbr Amplas 5,500.00 1,100.00
C PERALATAN ###
D Jumlah A + B + C 36,728.00
E Overhead & Profit 10% 3,672.80
F Harga Satuan Pekerjaan (D+E) 40,400.80
###
3 A.4.7.1.9 1 M2 Pelaburan Bidang Dengan Vernis
A TENAGA 31,080.00
L.01 0.1600 OH Pekerja 80,000.00 12,800.00
L.02 0.1600 OH Tukang Cat 100,000.00 16,000.00
L.03 0.0160 OH Kepala Tukang 120,000.00 1,920.00
L.04 0.0030 OH Mandor 120,000.00 360.00
B BAHAN 8,815.00
0.1500 Ltr Vernis 50,100.00 7,515.00
0.0500 Kg Dempul 15,000.00 750.00
0.1000 Lbr Ampelas 5,500.00 550.00
C PERALATAN
D Jumlah A + B + C 39,895.00
E Overhead & Profit 10% 3,989.50
F Harga Satuan Pekerjaan (D+E) 43,884.50
###
4 A.4.7.1.10 1 M2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup)
A TENAGA 12,301.48
L.01 0.0200 OH Pekerja 103,877.00 2,077.54
L.02 0.0630 OH Tukang Cat 139,036.00 8,759.27
L.03 0.0063 OH Kepala Tukang 151,821.00 956.47
L.04 0.0030 OH Mandor 169,400.00 508.20
B BAHAN 16,204.00
0.1000 Kg Plamir 7,200.00 720.00
0.1000 Kg Cat Dasar 42,000.00 4,200.00
0.2600 Kg Cat Penutup, (Metrolite) 43,400.00 11,284.00
C PERALATAN
D Jumlah A + B + C 28,505.48
E Overhead & Profit 10% 2,850.55
F Harga Satuan Pekerjaan (D+E) 31,356.03
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
XIII A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN
5 A.4.7.1.11 1 M2 Pengecatan Tembok Lama (1lap.Cat Dasar, 2lap Cat Penutup)
A TENAGA 7,304.00
L.01 0.0280 OH Pekerja 80,000.00 2,240.00
L.02 0.0420 OH Tukang Cat 100,000.00 4,200.00
L.03 0.0042 OH Kepala Tukang 120,000.00 504.00
L.04 0.0030 OH Mandor 120,000.00 360.00
B BAHAN 8,820.00
0.1200 Kg Cat Dasar 21,000.00 2,520.00
0.1800 Kg Cat Penutup 35,000.00 6,300.00
C PERALATAN
D Jumlah A + B + C 16,124.00
E Overhead & Profit 10% 1,612.40
F Harga Satuan Pekerjaan (D+E) 17,736.40
C PERALATAN
D Jumlah A + B + C 133,300.00
E Overhead & Profit 10% 13,330.00
F Harga Satuan Pekerjaan (D+E) 146,630.00
PEKERJAAN
LOKASI
THN ANGGARAN
VOULME
NO JENIS PEKERJAAN
1 2
I PEKERJAAN PENDAHULUAN
a Pek. Papan Nama Proyek
b Pek. Sewa Barak Kerja
II PEKERJAAN TANAH DAN URUGAN
a Pek. Galian Tanah Pondasi
: PEMBANGUNAN PAGAR
: ……..
: 2020
: 71 M
2 3
PEKERJAAN PENDAHULUAN
Pek. Papan Nama Proyek 1.00
Pek. Sewa Barak Kerja 1.00
PEKERJAAN TANAH DAN URUGAN
Pek. Galian Tanah Pondasi 7.10
Pondasi Bata
- P1
Pek. Urugan Pasir Urug Bawah Pondasi T=5 cm 0.71
Pondasi Bata
- P1
Pek. Lantai Kerja K-100 T=5 cm 0.71
Pondasi Bata
- P1
Pek. Urugan Tanah Kembali 2.37
PEKERJAAN PONDASI & BETON
Pek. Pondasi Bata ad. 1 Pc : 3 Ps 5.68
- P1
Pek. Sloof 15/20 Beton Bertulang K-175 (107 Kg Besi + Bekisting) 2.13
- P1
Pek. Ring Balok Praktis 11/11, Beton Bertulang 71.00
- P1
Pek. Kolom Praktis 11/11, Beton Bertulang 23.40
- P1
PEKERJAAN DINDING & PLESTERAN
Pek. Pas. Setengah Bata ad. 1 Pc : 4 Ps 92.30
- P1
Pek. Plesteran Bata ad. 1 Pc : 4 Ps 184.60
PEKERJAAN PENGECATAN
Pek. Pengecatan Dinding Dengan Cat Tembok 213.00
Dinding
Sloof
BACK UP DATA
NEER'S ESTIMATE (EE)
PARAMETER DATA
M3 71.00 7.100
M3 5.680
71.00 0.20 0.40 5.680
M3 2.130
71.00 0.15 0.20 2.130
M 71.000
71.00 71.000
M 23.400
1.30 18.00 23.400
M2 92.300
71.00 1.30 92.300
M2 184.600
M2 213.000
184.600
71.00 0.20 28.400
12
KET
2
30
1
2 5
0
4
0
60
20
15
2
0
1
02
5
0 1
50
400
400
Berat Besi Per Kilogram :
f 32 = 6.313 Kg/m
f 19 = 2.226 Kg/m
f 16 = 1.578 Kg/m
f 13 = 1.042 Kg/m
f 12 = 0.888 Kg/m
f 10 = 0.617 Kg/m
f 8 = 0.395 Kg/m
f 6 = 0.222 Kg/m
PONDASI SETEMPAT
Panjang = 0.6
Lebar = 0.6
Tebal = 0.12
Volume = 0.0432 M3
Besi 10 mm
Arah X = 1.2 M
Banyak = 4 Bh Panjang 4.8 M
Besi 10 mm
Arah Y = 1.2 M
Banyak = 4 Bh Panjang 4.8 M
Total 9.6 M
Berat Besi 5.9184 Kg
Vol Besi 137 Kg/M3 Dibulatkan 137
SLOOF
Panjang = 1
Lebar = 0.15
Tebal = 0.2
Volume = 0.03 M3
Besi Utama 10 mm
Banyak = 4 Bh
Panjang = 4M Berat Besi 2.466 Kg
Vol Besi 82.2 Kg/M3
Sengkang 6 mm
Banyak = 7 Bh
Panjang = 0.46 M Berat Besi 0.714647 Kg
Vol Besi 23.82156 Kg/M3
Total 106.0216 Dibulatkan 107
KOLOM
Panjang = 1
Lebar = 0.2
Tebal = 0.2
Volume = 0.04 M3
Besi Utama 10 mm
Banyak = 4 Bh
Panjang = 4M Berat Besi 2.466 Kg
Vol Besi 61.65 Kg/M3
Sengkang 6 mm
Banyak = 7 Bh
Panjang = 0.56 M Berat Besi 0.870005 Kg
Vol Besi 21.75012 Kg/M3
Total 83.40012 Dibulatkan 84
BALOK INDUK
Panjang = 1
Lebar = 0.3
Tebal = 0.5
Volume = 0.15 M3
Besi Utama 16 mm
Banyak = 8 Bh
Panjang = 8M Berat Besi 12.62592 Kg
Vol Besi 84.1728 Kg/M3
Besi Utama 10 mm
Banyak = 2 Bh
Panjang = 2M Berat Besi 1.233 Kg
Vol Besi 8.22 Kg/M3
Sengkang 8 mm
Banyak = 8 Bh
Panjang = 1.36 M Berat Besi 4.292813 Kg
Vol Besi 28.61875 Kg/M3
Total 121.0116 Dibulatkan 122
BALOK ANAK
Panjang = 1
Lebar = 0.25
Tebal = 0.4
Volume = 0.1 M3
Besi Utama 16 mm
Banyak = 5 Bh
Panjang = 5M Berat Besi 7.8912 Kg
Vol Besi 78.912 Kg/M3
Besi Utama 10 mm
Banyak = 2 Bh
Panjang = 2M Berat Besi 1.233 Kg
Vol Besi 12.33 Kg/M3
Sengkang 8 mm
Banyak = 8 Bh
Panjang = 1.06 M Berat Besi 3.345869 Kg
Vol Besi 33.45869 Kg/M3
Total 124.7007 Dibulatkan 125
PLAT K-175
Panjang = 1
Lebar = 1
Tebal = 0.12
Volume = 0.12 M3
Besi 10 mm
Arah X = 1M
Banyak = 7 Bh Panjang 7M
Besi 10 mm
Arah Y = 1M
Banyak = 7 Bh Panjang 7M
Total 14 M
Berat Besi 8.631 Kg
Vol Besi 71.925 Kg/M3 Dibulatkan 72
PLAT K-250
Panjang = 1
Lebar = 1
Tebal = 0.12
Volume = 0.12 M3
Besi 10 mm
Arah X = 1M
Banyak = 5 Bh Panjang 2 Lapis 10 M
Besi 10 mm
Arah Y = 1M
Banyak = 5 Bh Panjang 2 Lapis 10 M
Total 20 M
Berat Besi 12.33 Kg
Vol Besi 102.75 Kg/M3 Dibulatkan 103
LANTAI WIREMESH M8
Panjang = 1
Lebar = 1
Tebal = 0.2
Volume = 0.2 M3
Wiremesh M6
Panjang 1M
Lebar 1M
Total 1 M2
Berat Besi 5.448854 Kg
Vol Besi 27.24427 Kg/M3 Dibulatkan 28
Kg/M3
Kg/M3
Kg/M3
Kg/M3
Kg/M3
Kg/M3
Kg/M3
Kg/M3
RENCANA ANGGARAN BIAYA
ENGINEER'S ESTIMATE (EE)
NO JENIS PEKERJAAN
1 2
I PEKERJAAN PENDAHULUAN
a Pek. Papan Nama Proyek
b Pek. Sewa Barak Kerja
SUB JUMLA
II PEKERJAAN TANAH DAN URUGAN
a Pek. Galian Tanah Pondasi
b Pek. Urugan Pasir Urug Bawah Pondasi T=5 cm
c Pek. Lantai Kerja K-100 T=5 cm
d Pek. Urugan Tanah Kembali
SUB JUMLA
III PEKERJAAN PONDASI & BETON
a Pek. Pondasi Bata ad. 1 Pc : 3 Ps
b Pek. Sloof 15/20 Beton Bertulang K-175 (107 Kg Besi + Bekisting)
c Pek. Ring Balok Praktis 11/11, Beton Bertulang
d Pek. Kolom Praktis 11/11, Beton Bertulang
SUB JUMLA
IV PEKERJAAN DINDING & PLESTERAN
a Pek. Pas. Setengah Bata ad. 1 Pc : 4 Ps
b Pek. Plesteran Bata ad. 1 Pc : 4 Ps
SUB JUMLA
V PEKERJAAN PENGECATAN
a Pek. Pengecatan Dinding Dengan Cat Tembok
SUB JUMLA
(A) Jumlah Harga Pekerjaan
(B) Pajak Pertambahan Nilai ( PPN ) = 10% x (A)
(C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B)
(D) DIBULATKAN
TERBILANG : "Seratus Juta Rupiah"
Diperiksa oleh :
Pengelola Teknis Kegiatan
Dinas Pekerjaan Umum dan Perumahan Rakyat
Prov………..
………….
NIP. ..………..
Disetujui oleh :
Pejabat Pembuat Komitmen (PPK)
………
………
……….
NIP. …..
NA ANGGARAN BIAYA (RAB)
ENGINEER'S ESTIMATE (EE)
Dihitung oleh :
……..
…………..
…………
Team Leader
Diketahui oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
………….
………..
RIAN WIDIANTARA, SE
NIP. ………….