DAFTAR HARGA SATUAN UPAH BANGUNAN

TAHUN 2019

PROVINSI : JAMBI
KAB/KOTA :-

SEDANG
HARGA SAT
NO. JENIS BAHAN SATUAN KODE
(Rp)
1 Pekerja OH L.01 80,000.00
2 Tukang Batu, Besi, Kayu OH L.02 100,000.00
3 Kepala Tukang OH L.03 120,000.00
4 Mandor OH L.04 120,000.00
4 Operator OH L.05 120,000.00
5 Pembantu Operator/Helper OH L.06 100,000.00
6 Penjaga Malam OH L.07 100,000.00
7 Sopir OH L.08 120,000.00
8 Pembantu Sopir OH L.09 100,000.00

CK Boyolali
DAFTAR HARGA SATUAN BAHAN BANGUNAN
TAHUN 2019
PROVINSI : JAMBI
KAB/KOTA :-

SEDANG

NO. J E N I S B A H A N SATUAN HARGA (Rp)

I BAHAN DASAR
1 BATU KALI Bulat Belah M3 320,000.00
Pecah 15/20 - 20/30 M3 320,000.00
Pecah 10/15 M3 320,000.00
2 KERIKIL Sirtu M3 210,000.00
Bulat 0,5/1 M3 350,000.00
Bulat 1/2 M3 350,000.00
Bulat 2/3 M3 350,000.00
3 BATU BATA Bata Bh 500.00
Rooster M2 120,000.00
4 PASIR Urug M3 85,000.00
Pasang M3 95,000.00
Beton M3 95,000.00
5 TANAH Urug M3 65,000.00
6 KAPUR Pasang M3 300,000.00
7 PORTLAND CEMENT
Portland Cement, @50 Kg/Zak, Padang Zak 70,000.00
Portland Cement Kg 1,400.00
Semen warna, Tile Grout AM Kg 15,000.00
8 SPLIT ###
Pecah 1/2 M3 450,000.00
Pecah 2/3 M3 450,000.00
Pecah 3/5 M3 450,000.00

II BAHAN PENUTUP ATAP


1 GENTENG
Genteng Beton Bh 15,000.00
2 NOK
Genteng Beton Bh 20,000.00
Genteng Metal Bh 40,000.00
3 SENG PLAT BJLS 28 Lebar 55 cm M 45,000.00
BJLS 30 Lebar 60 cm M 50,000.00
BJLS 30 Lebar 90 cm M 70,000.00
4 SENG GELOMBANG index
BJLS 20 Lbr 43,000.00
BJLS 30 Lbr 45,000.00
Seng Gelombang 3 x 6" BJLS.28 Lbr 50,000.00
5 GENTENG METAL index
Multiroof T=0,25 mm M2 56,700.00
Multiroof T=0,3 mm M2 81,000.00
Multiroof Berpasir M2 113,400.00

III BAHAN KAYU


1 KAYU KELAS I/KUSEN Papan Bulian,Kulim M3 6,000,000.00
Balok Bulian,Kulim M3 6,000,000.00
2 KAYU KELAS II/KUSEN/PLAFOND Papan Meranti, Medang M3 3,300,000.00
Balok Meranti, Medang M3 3,300,000.00
3 KAYU TAHUN KELAS III BEKISTING/BOUWPLANK Papan Sengon M3 1,800,000.00
Balok Sengon M3 1,800,000.00
4 KAYU TAHUN KELAS II BEKISTING/BOUWPLANK Papan Terentang M3 2,500,000.00
Balok Terentang M3 2,500,000.00
5 DOLKEN Kecil 8 - 10 x 400 cm Btg 6,000.00
Sedang 10 - 15 x 400 cm Btg 8,000.00
6 LAIN -LAIN Formite/Penjaga jarak / Spacer Bh 6,000.00
Perancah Kayu (Untuk Cat) M3 1,400,000.00
NO. J E N I S B A H A N SATUAN HARGA (Rp)

IV BAHAN PENUTUP DINDING / LANTAI


1 KERAMIK 30 X 30 cm Polos (11 Bh/Kotak), Mulia Tile Kotak 60,000.00
30 X 30 cm Kasar/Warna (11 Bh/Kotak) Mulia Tile Kotak 68,000.00
40 X 40 cm Polos (6 Bh/Kotak) Mulia Tile Kotak 60,000.00
40 X 40 cm Kasar/Warna (6 Bh/Kotak) Mulia Tile Kotak 68,000.00
20 X 20 cm Motif/Warna (25 Bh/Kotak) Mulia Tile Kotak 68,000.00
25 X 40 cm Motif/Warna (10 Bh/Kotak) Mulia Tile Kotak 68,000.00
Keramik Plin 10/40 Polos Mulia Tile Bh 5,000.00
Keramik Plin 10/40 Warna Mulia Tile Bh 6,000.00
2 BATU PARAS M2 160,000.00
3 BATU ANDESIT M2 180,000.00
4 BATU TEMPEL HITAM M2 150,000.00
5 GRANIT 40 x 40 cm Polish (6 Bh/Kotak), Garuda Kotak 180,000.00
40 x 40 cm UnPolish (6 Bh/Kotak), Garuda Kotak 210,000.00
60 x 60 cm Polish (4 Bh/Kotak), Garuda Kotak 180,000.00
60 x 60 cm UnPolish (4 Bh/Kotak), Garuda Kotak 210,000.00
Plint Granit 10x40 cm, Polish , Garuda Bh 7,500.00
Plint Granit 10x60 cm, Polish , Garuda Bh 10,000.00
6 PARKIT Parkit Kayu M2 230,000.00
Parkit Vinyl Karet, Taco M2 195,000.00

V BAHAN BESI
1 BESI BETON Polos, KSTY, U 24 Kg 11,000.00
Ulir, KSTY, U 32 Kg 12,000.00
Wiremesh Kg 10,000.00
2 BESI PLAT Besi Strip Kg 10,000.00
Besi Strip M 3,000.00
3 BESI PROFIL Besi Profil/Pipa Besi Kg 13,500.00
Besi Profil IWF/H-Beam Kg 13,500.00
4 BESI SIKU All Size Kg 13,500.00
5 KAWAT Kawat Ikat Kg 19,500.00
Kawat Las Kg 55,000.00
6 LAIN-LAIN
Paku Sekrup Gypsum/GRC Kg 40,000.00
Skrup Fixer Bh 1,200.00
Sealant Glazing, Silicon Tube 30,000.00
Besi Hollow 4/4 Hitam T=1,7 mm M 14,000.00
2/4 Hitam T=1,7 mm M 10,000.00
7 RANGKA ATAP
Baja Ringan (Terpasang) C.75.75, Reng 32-45 M2 150,000.00
8 PAGAR BRC
BRC M6 Tiang 1,5 & 2" GIP M2 320,000.00
BRC M8 Tiang 1,5 & 2" GIP M2 370,000.00
Kawat Duri M2 120,000.00
9 RAILING HOLLOW
Besi Hollow Hitam 4/4 & 2/4 M2 425,000.00
Stanless Hollow Stanless 4/4 & 2/4 M2 750,000.00
Besi Pipa Hitam 1 - 3" M2 550,000.00
Stanless Pipa Stanless 1 - 3" M2 860,000.00
Galvanis Pipa Galvanis 1 - 3" M2 700,000.00
NO. J E N I S B A H A N SATUAN HARGA (Rp)

VI BAHAN PIPA
1 Pipa PVC SII, S - 12,5 (10 Bar)
Pipa PVC ( ½" ) AW Wavin/Rucika, @4 m/Btg Btg 21,000.00
Pipa PVC ( ¾" ) AW Wavin/Rucika, @4 m/Btg Btg 29,000.00
Pipa PVC ( 1" ) AW Wavin/Rucika, @4 m/Btg Btg 40,000.00
Pipa PVC (1½" ) AW Wavin/Rucika, @4 m/Btg Btg 70,000.00
Pipa PVC ( 2" ) AW Wavin/Rucika, @4 m/Btg Btg 85,000.00
Pipa PVC ( 3" ) AW Wavin/Rucika, @4 m/Btg Btg 175,000.00
Pipa PVC ( 4" ) AW Wavin/Rucika, @4 m/Btg Btg 270,000.00

2 Pipa Medium B Galvanis - SII


Pipa Medium B Galvanis 1/2" Galvanis, @6 m/Btg Btg 49,800.00
Pipa Medium B Galvanis 3/4" Galvanis, @6 m/Btg Btg 70,000.00
Pipa Medium B Galvanis 1" Galvanis, @6 m/Btg Btg 144,700.00
Pipa Medium B Galvanis 1 1/2" Galvanis, @6 m/Btg Btg 190,500.00
Pipa Medium B Galvanis 3" Galvanis, @6 m/Btg Btg 397,300.00
Pipa Medium B Galvanis 4" Galvanis, @6 m/Btg Btg 570,300.00

3 Pipa Medium B Hitam - SII


Pipa Medium B Hitam 1/2" Hitam, SIO Bakrie, @6 m/Btg Btg 50,300.00
Pipa Medium B Hitam 3/4" Hitam, SIO Bakrie, @6 m/Btg Btg 70,400.00
Pipa Medium B Hitam 1" Hitam, SIO Bakrie, @6 m/Btg Btg 150,300.00
Pipa Medium B Hitam 1 1/2" Hitam, SIO Bakrie, @6 m/Btg Btg 210,000.00
Pipa Medium B Hitam 3" Hitam, SIO Bakrie, @6 m/Btg Btg 425,000.00
Pipa Medium B Hitam 4" Hitam, SIO Bakrie, @6 m/Btg Btg 580,500.00

VII BAHAN LANGIT - LANGIT


1 LIST KAYU PROFIL Panjang 3 m/Btg M 10,000.00
2 GYPSUM Tebal 9 mm, Knauf/Gyprox Lbr 72,000.00
Tebal 12 mm, Knauf/Gyprox Lbr 96,000.00
3 LISTPLANK GRC L=20 CMConwood T=8 mm, @3 m/Kpg M 19,000.00
L=30 CMConwood T=8 mm, @3 m/Kpg M 32,500.00
4 LIST GYPSUM PROFIL Kode C6,C4, @2 m/Btg M 13,000.00
5 TEPUNG GYPSUM Cornice, Adhesive, A-Plus, Elephant @20 Kg/Zak Kg 3,750.00
6 PLY WOOD
Tripleks
- 120 X 240 Tebal 3 mm, Uk. 1,2 m x 2,4 m, Fortuna Lbr 55,800.00
- 120 X 240 Tebal 4 mm, Uk. 1,2 m x 2,4 m, Fortuna Lbr 62,800.00
Multipleks
- 120 X 240 Tebal 9 mm, Uk. 1,2 m x 2,4 m, Fortuna Lbr 109,000.00
- 120 X 240 Tebal 12 mm, Uk. 1,2 m x 2,4 m, Fortuna Lbr 150,000.00
7 GRC Tebal 4 mm, Uk. 1,2 m x 2,4 m, Verza Lbr 68,000.00

VIII BAHAN FINISHING


1 KAYU
- Dempul Plamur Wallputty, @5 Kg/Kaleng Kg 15,000.00
- Amplas Niken, 15x20 cm/Lbr Lbr 5,500.00
- Cat Dasar Avian Kg 52,000.00
- Cat Penutup Avian Kg 62,800.00
- Kuas Crocodile Bh 12,000.00
- Vernis Propan Ltr 50,100.00

2 TEMBOK
- Plamur Giant, @20 Kg/Zak Kg 15,000.00
- Cat Dasar Avitex,@ 20 Kg/Pail Kg 21,000.00
- Cat Penutup Spectrum @ 20 Kg/Pail Kg 35,000.00
- Wallpaper Korea, @53 cm x 30 m M2 85,000.00

3 BESI
- Menie Kg 45,000.00
- Cat Penutup Avian Kg 62,800.00
- Minyak Cat/Thinner/Pengencer Laba-laba Ltr 17,000.00
- Lem Aica Aibon Aibon Kg 35,000.00
- Lem Wallpaper Kg 35,000.00
NO. J E N I S B A H A N SATUAN HARGA (Rp)

IX BAHAN KACA
1 POLOS 3 mm Asahimas M2 92,000.00
5 mm Asahimas M2 108,000.00
8 mm Asahimas M2 185,000.00
10 mm Asahimas M2 340,000.00
12 mm Asahimas M2 480,000.00
2 RAYBAN 5 mm Asahimas M2 113,000.00
8 mm Asahimas M2 190,000.00
10 mm Asahimas M2 350,000.00
12 mm Asahimas M2 495,000.00
3 PINTU TAMPERED 12 mm Complete Fitting , acc, Uk. 80x210 cm Unit 2,100,000.00
12 mm Complete Fitting , acc, Uk. 90x210 cm Unit 2,900,000.00
4 PINTU FRAMELESS 12 mm Complete Fitting , acc, Uk. 80x210 cm Unit 1,400,000.00
12 mm Complete Fitting , acc, Uk. 90x210 cm Unit 1,800,000.00
5 ACP 4 mm Complete Terpasang, PVDF M2 610,000.00
6 PINTU HPL 3,5 cm Rangka Plywood, Uk. 70x200 cm, Complete Unit 900,000.00
3,5 cm Rangka Plywood, Uk. 80x200 cm, Complete Unit 1,300,000.00
7 PARTISI INTERIOR 1 Muka Rangka Plywood 9/12 mm, Penutup 4 mm, HP M2 1,300,000.00
2 Muka Rangka Plywood 9/12 mm, Penutup 4 mm, HP M2 1,950,000.00
8 LEMARI INTERIOR Rangka Plywood 9/12 mm, Penutup 4 mm, HP M2 2,100,000.00
9 HURUF Stanless CM 14,000.00
Akrilik CM 7,000.00
LED Akrilik CM 25,000.00

X ALAT - ALAT PENGUNCI & PENGGANTUNG


1 KUNCI TANAM Belluci : 1 X slag (Pintu KM) Bh 49,500.00
Belluci : 2 X slag Bh 131,400.00
2 ENGSEL DAN GERENDEL
- Engsel Pintu Ferza 4" Bh 15,000.00
- Engsel Jendela Ferza 3" Bh 11,000.00
- Grendel Pintu/Jendela Biasa Ferza Bh 10,000.00
- Kait Angin Ferza Bh 15,000.00
- Door Closer Bh 210,000.00
- Tarikan Jendela Ferza Bh 15,000.00

XI BAHAN SANITAIR
1 KLOSET DUDUK MONOBLOK INA/Toto, Otomatis Bh 1,700,000.00
2 KLOSET JONGKOK American Standard Bh 300,000.00
3 WASTAFEL GANTUNG BULAT INA/Toto, Complete Kran Bebek Bh 670,000.00
4 URINOIR KERAMIK STANDART INA/Toto, Otomatis Bh 1,800,000.00
5 LAIN - LAIN
- Kran Air 1/2" Stanless Bh 45,000.00
- Seal tape Bh 4,000.00
- Floor drain Majesty, 3" Stanless Bh 25,000.00
- Bak Cuci Piring, Stanless 1 Sayap Bh 280,000.00
- Water Drain Bh 50,000.00
- Ball Valve 1" Bh 15,000.00
- Ball Valve 3/4" Bh 10,000.00
- Roof Tank Fiber 800 Liter Unit 950,000.00
Fiber 1000 Liter Unit 1,400,000.00
Fiber 1500 Liter Unit 2,100,000.00
- Shower Bh 280,000.00
- Pompa Air Submersible Kap. 1 L/Det, Merk Franklin, 1,1 KW Unit 9,800,000.00
Jetpump, Wasser Unit 1,600,000.00
Semi-Jetpump, Wasser Unit 1,100,000.00
Celup, Wasser Unit 750,000.00
6 INSTALASI TITIK AIR
-Air Bersih Pipa PVC AW 1/2, 3/4", Fittting Titik 120,000.00
-Air Kotor Pipa PVC AW 3,4", Fitting Titik 150,000.00
NO. J E N I S B A H A N SATUAN HARGA (Rp)

XII ALAT PENGIKAT KAYU


1 PAKU Ukuran 1-5" Kg 20,000.00
2 PAKU - Sekrup Atap Sekrup Atap Kg 50,000.00
Sekrup Atap Bh 250.00
3 LEM KAYU Kg 27,000.00

XIII PAVING BLOCK


1 BATAKO Bh 4,250.00
2 KONBLOK Tipe Milan, T=6 cm M2 72,000.00
Tipe Milan, T=8 cm M2 90,000.00

XIV LAIN -LAIN


1 Naco Rayban 5 mm Per Daun M2 82,000.00
2 Rolling Door Besi/Pintu Gulung Besi Tebal 0,3 mm M2 410,000.00
3 Rolling Door Almunium/Pintu Gulung Aluminium M2 470,000.00
4 Kusen Almunium ###
Ukuran 4", Alexindo M 72,000.00
Ukuran 3", Alexindo M 65,000.00
5 Besi Holow Rangka Gypsum 2/4, Tebal 0,45 mm M 7,500.00
6 Minyak Beton & Bekisting Ltr 10,000.00
7 Pintu Lipat Besi/Folding Gate 0.4 mm M2 560,000.00
8 Soda Api Kg 27,200.00
9 Air Ltr 50.00
10 Solar (Industri) Ltr 8,700.00
11 Premium (Industri) Ltr 10,500.00
12 Pelumas Ltr 35,000.00
13 Canal Baja Ringan M 14,000.00
14 Papan Nama Proyek 80 x 100 cm Unit 250,000.00
15 Direksi Keet/Barak Kerja Ls 1,500,000.00
16 Sewa Direksi Keet/Barak Kerja Ls 500,000.00

XV BAHAN ALUMUNIUM
1 Alumunium Profil Warna Tebal 1.2 mm M 65,000.00
2 Profil Kaca M 5,000.00
3 Aluminium Foil M2 15,000.00

XVI PERALATAN SEWA


1 Dump Truck Kap. 4 Ton Hari 600,000.00
2 Molen Kap. 0,3-0,5 M3 Hari 250,000.00
3 Stamper Hari 100,000.00

XVII BAHAN LISTRIK


1 MCB C2-C20 Ampere Bh 75,000.00
2 BOX PANEL Panel MCB Kecil, Plastik Bh 30,000.00
Panel MCB Besar Uk. 35/55 Bh 800,000.00
Panel MCB Sedang Uk. 20/20 Bh 400,000.00
3 BOX PANEL ATS Box Panel Besar + MCB + Contactor Unit 1,700,000.00
4 INSTALASI TITIK LISTRIK Kabel NYM 1x2,5 mm (Api) dan NYM 1x1,5 mm (Massa) Titik 150,000.00
5 STOP KONTAK Broco/Pansonic Bh 25,000.00
6 SAKLAR Tunggal Broco/Panasonic Bh 23,000.00
Ganda Broco/Panasonic Bh 25,000.00
Triple Broco/Panasonic Bh 32,000.00
7 LAMPU LED Downlight 9 Watt Bh 55,000.00
LED Downlight 12 Watt Bh 68,000.00
LED Panel Plafond 18 Watt (20 x 20 cm) Bh 80,000.00
LED Panel Plafond 18 Watt (30 x 30 cm) Bh 120,000.00
LED Obor/Api 12 Watt Bh 90,000.00
Selang M 23,000.00
TL 1x40 Watt Bh 80,000.00
SL 18 Watt Bh 35,000.00
SL 40 Watt Bh 68,000.00
Air Mancur RGB 12 Watt Bh 170,000.00
Taman Tiang=1,2-1,5 m, Acc Unit 1,400,000.00
Antik Tiang=5 m, Acc, Hexagonal Unit 5,300,000.00
Jenis Standar 20,01,01,002,01 Semen
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,01,01,002,01,001 Semen PC Tonasa

2 20,01,01,002,01,002 Semen PC Tonasa

3 20,01,01,002,01,003 Semen PC Tonasa

4 20,01,01,002,01,004 Semen PC Tonasa


5 20,01,01,002,01,005 Semen Warna

6 20,01,01,002,01,006 Semen Warna

7 20,01,01,002,01,007 Semen Warna

8 20,01,01,002,01,008 Semen Warna


PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

PEMERINTAH KAB. HALM


DAFTAR STANDAR HARG
Periode Tahun 2019
2 20,01,01,003,02,002 Dudukan Nako

3 20,01,01,003,02,003 Dudukan Nako

4 20,01,01,003,02,004 Dudukan Nako


Jenis Standar 20,01,01,004,01 Tanah urug
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,01,01,004,01,001 Timbunan Biasa / Tanah Urug

2 20,01,01,004,01,002 Timbunan Biasa / Tanah Urug

3 20,01,01,004,01,003 Timbunan Biasa / Tanah Urug

4 20,01,01,004,01,004 Timbunan Biasa / Tanah Urug


5 20,01,01,004,01,005 Timbunan Pilihan/Humus
6 20,01,01,004,01,006 Timbunan Pilihan/Humus

7 20,01,01,004,01,007 Timbunan Pilihan/Humus

8 20,01,01,004,01,008 Timbunan Pilihan/Humus


Jenis Standar 20,01,01,004,02 Pasir Pasang
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,01,01,004,02,001 Pasir Kasar

2 20,01,01,004,02,002 Pasir kasar

3 20,01,01,004,02,003 Pasir Kasar

4 20,01,01,004,02,004 Pasir Kasar


5 20,01,01,004,02,005 Pasir Halus

6 20,01,01,004,02,006 Pasir Halus

7 20,01,01,004,02,007 Pasir Halus

8 20,01,01,004,02,008 Pasir Halus


PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

PEMERINTAH KAB. HALM


DAFTAR STANDAR HARG
Periode Tahun 2019
Jenis Standar 20,01,01,004,03 Pasir Cor
No. Kode Standar Harga Nama BaraMerk / Mo
1 20,01,01,004,03,001 Kerikil Beton

2 20,01,01,004,03,002 Kerikil Beton

3 20,01,01,004,03,003 Kerikil Beton

4 20,01,01,004,03,004 Kerikil Beton


Jenis Standar 20,01,01,004,04 Sirtu
No. Kode Standar Harga Nama BaraMerk / Mo
1 20,01,01,004,04,001 Sirtu

2 20,01,01,004,04,002 Sirtu

3 20,01,01,004,04,003 Sirtu

4 20,01,01,004,04,004 Sirtu
Jenis Standar 20,01,01,005,01 Batu Gunung Belah
No. Kode Standar Harga Nama BaraMerk / Mo
1 20,01,01,005,01,001 Batu Kali / Gunung

2 20,01,01,005,01,002 Batu Kali / Gunung

3 20,01,01,005,01,003 Batu Kali / Gunung

4 20,01,01,005,01,004 Batu Kali / Gunung


5 20,01,01,005,01,005 Batu Belah 2-3 cm

6 20,01,01,005,01,006 Batu Belah 2-3 cm

7 20,01,01,005,01,007 Batu Belah 2-3 cm

8 20,01,01,005,01,008 Batu Belah 2-3 cm


9 20,01,01,005,01,009 Batu Belah 1-2 cm

10 20,01,01,005,01,010 Batu Belah 1-2 cm

PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

PEMERINTAH KAB. HALMAHERA


DAFTAR STANDAR HARGA BARA
Periode Ta 2019
11 20,01,01,005,01,011 Batu Belah 1-2 cm

12 20,01,01,005,01,012 Batu Belah 1-2 cm


13 20,01,01,005,01,013 Batu Belah 0,5-1 cm

14 20,01,01,005,01,014 Batu Belah 0,5-1 cm


15 20,01,01,005,01,015 Batu Belah 0,5-1 cm

16 20,01,01,005,01,016 Batu Belah 0,5-1 cm


17 20,01,01,005,01,017 Batu Alam

18 20,01,01,005,01,018 Batu Alam

19 20,01,01,005,01,019 Batu Alam

20 20,01,01,005,01,020 Batu Alam


25 20,01,01,005,01,025 Batu Belah 15-20 cm

26 20,01,01,005,01,026 Batu Belah 15-20 cm

27 20,01,01,005,01,027 Batu Belah 15-20 cm

28 20,01,01,005,01,028 Batu Belah 15-20 cm


29 20,01,01,005,01,029 Batu Belah 10-15 cm

30 20,01,01,005,01,030 Batu Belah 10-15 cm

31 20,01,01,005,01,031 Batu Belah 10-15 cm

32 20,01,01,005,01,032 Batu Belah 10-15 cm


33 20,01,01,005,01,033 Batu Belah 7-10 cm

PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

Periode Ta
34 20,01,01,005,01,034 Batu Belah 7-10 cm

35 20,01,01,005,01,035 Batu Belah 7-10 cm

36 20,01,01,005,01,036 Batu Belah 7-10 cm


37 20,01,01,005,01,037 Batu Belah 5-7 cm
38 20,01,01,005,01,038 Batu Belah 5-7 cm

39 20,01,01,005,01,039 Batu Belah 5-7 cm

40 20,01,01,005,01,040 Batu Belah 5-7 cm


41 20,01,01,005,01,041 Batu Belah 3-5 cm

42 20,01,01,005,01,042 Batu Belah 3-5 cm

43 20,01,01,005,01,043 Batu Belah 3-5 cm

44 20,01,01,005,01,044 Batu Belah 3-5 cm


Jenis Standar 20,01,01,005,06 Batu Bata
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,01,01,005,06,001 Batu Bata

2 20,01,01,005,06,002 Batu Bata

3 20,01,01,005,06,003 Batu Bata

4 20,01,01,005,06,004 Batu Bata

9 20,01,01,006,11,009 Aquaproof

10 20,01,01,006,11,010 Aquaproof

11 20,01,01,006,11,011 Aquaproof

12 20,01,01,006,11,012 Aquaproof
Jenis Standar 20,01,01,006,12 Cat Tembok
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,01,01,006,12,001 Cat Tembok Metrolite

2 20,01,01,006,12,002 Cat Tembok Dasar Metrolite


3 20,01,01,006,12,003 Cat Tembok Metrolite

4 20,01,01,006,12,004 Cat Tembok Metrolite


5 20,01,01,006,12,005 Cat Tembok Metrolite

6 20,01,01,006,12,006 Cat Tembok Metrolite

7 20,01,01,006,12,007 Cat Tembok Metrolite

8 20,01,01,006,12,008 Cat Tembok Metrolite


9 20,01,01,006,12,009 Cat Tembok (Interior) Dulux

10 20,01,01,006,12,010 Cat Tembok (Interior) Dulux

11 20,01,01,006,12,011 Cat Tembok (Interior) Dulux

12 20,01,01,006,12,012 Cat Tembok (Interior) Dulux


13 20,01,01,006,12,013 Cat Tembok (Exterior) Dulux

14 20,01,01,006,12,014 Cat Tembok (Exterior) Dulux

15 20,01,01,006,12,015 Cat Tembok (Exterior) Dulux

16 20,01,01,006,12,016 Cat Tembok (Exterior) Dulux


Jenis Standar 20,01,01,007,01 Seng Gelombang
No. Kode Standar Harga Nama Barang Standar Merk / Mo
PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

PEMERINTAH KAB. HALMAHERA


DAFTAR STANDAR HARGA BARA
Periode Ta 2019
1 20,01,01,007,01,001 Seng Gelombang 0,2 mm

2 20,01,01,007,01,002 Seng Gelombang 0,2 mm

3 20,01,01,007,01,003 Seng Gelombang 0,2 mm

4 20,01,01,007,01,004 Seng Gelombang 0,2 mm


5 20,01,01,007,01,005 Seng Gelombang 0,25 mm

6 20,01,01,007,01,006 Seng Gelombang 0,25 mm

7 20,01,01,007,01,007 Seng Gelombang 0,25 mm

8 20,01,01,007,01,008 Seng Gelombang 0,25 mm


9 20,01,01,007,01,009 Seng Gelombang 0,3 mm

10 20,01,01,007,01,010 Seng Gelombang 0,3 mm

11 20,01,01,007,01,011 Seng Gelombang 0,3 mm

12 20,01,01,007,01,012 Seng Gelombang 0,3 mm


13 20,01,01,007,01,013 Seng Pelat Bubungan 0,2 mm

14 20,01,01,007,01,014 Seng Pelat Bubungan 0,2 mm

15 20,01,01,007,01,015 Seng Pelat Bubungan 0,2 mm

16 20,01,01,007,01,016 Seng Pelat Bubungan 0,2 mm


17 20,01,01,007,01,017 Seng Pelat Bubungan 0,3 mm

18 20,01,01,007,01,018 Seng Pelat Bubungan 0,3 mm

19 20,01,01,007,01,019 Seng Pelat Bubungan 0,3 mm

20 20,01,01,007,01,020 Seng Pelat Bubungan 0,3 mm


Jenis Standar 20,01,01,014,06 Eternit
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,01,01,014,06,001 Eternit Ex. Kerang
Jenis Standar 20,01,01,015,01 Engsel
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,01,01,015,01,001 Engsel Jendela Kuningan

2 20,01,01,015,01,002 Engsel Jendela Kuningan

3 20,01,01,015,01,003 Engsel Jendela Kuningan


4 20,01,01,015,01,004 Engsel Jendela Kuningan
5 20,01,01,015,01,005 Engsel Pintu Kuningan

6 20,01,01,015,01,006 Engsel Pintu Kuningan

7 20,01,01,015,01,007 Engsel Pintu Kuningan

8 20,01,01,015,01,008 Engsel Pintu Kuningan


Jenis Stand20,01,01,015,02 Grendel
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,01,01,015,02,001 Grendel Jendela / Pintu

2 20,01,01,015,02,002 Grendel Jendela / Pintu

3 20,01,01,015,02,003 Grendel Jendela / Pintu

4 20,01,01,015,02,004 Grendel Jendela / Pintu


Jenis Stand20,01,01,015,04 Kunci
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

Periode Ta
1 20,01,01,015,04,001 Kunci Kualitas Sedang

2 20,01,01,015,04,002 Kunci Kualitas Sedang

3 20,01,01,015,04,003 Kunci Kualitas Sedang

4 20,01,01,015,04,004 Kunci Kualitas Sedang


5 20,01,01,015,04,005 Kunci Kualitas Istimewa

6 20,01,01,015,04,006 Kunci Kualitas Istimewa

7 20,01,01,015,04,007 Kunci Kualitas Istimewa

8 20,01,01,015,04,008 Kunci Kualitas Istimewa


9 20,01,01,015,04,009 Kunci Kualitas Baik

10 20,01,01,015,04,010 Kunci Kualitas Baik

11 20,01,01,015,04,011 Kunci Kualitas Baik

12 20,01,01,015,04,012 Kunci Kualitas Baik


Jenis Standar 20,01,01,016,01 Besi Verkan
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,01,01,016,01,001 Besi Beton

PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

PEMERINTAH KAB. HALMAHERA


DAFTAR STANDAR HARGA BARA
Periode Ta 2019
2 20,01,01,016,01,002 Besi Beton

3 20,01,01,016,01,003 Besi Beton

4 20,01,01,016,01,004 Besi Beton


5 20,01,01,016,01,005 Besi Plat 2mm=120x240mm

6 20,01,01,016,01,006 Besi Plat 2mm=120x240mm

7 20,01,01,016,01,007 Besi Plat 2mm=120x240mm

8 20,01,01,016,01,008 Besi Plat 2mm=120x240mm


9 20,01,01,016,01,009 Besi Plat 3mm=120x240mm

10 20,01,01,016,01,010 Besi Plat 3mm=120x240mm

11 20,01,01,016,01,011 Besi Plat 3mm=120x240mm

12 20,01,01,016,01,012 Besi Plat 3mm=120x240mm


13 20,01,01,016,01,013 Plat Aluminium 0,4 mm

14 20,01,01,016,01,014 Plat Aluminium 0,4 mm


15 20,01,01,016,01,015 Plat Aluminium 0,4 mm

16 20,01,01,016,01,016 Plat Aluminium 0,4 mm


17 20,01,01,016,01,017 Plat Aluminium 0,5 mm

18 20,01,01,016,01,018 Plat Aluminium 0,5 mm

19 20,01,01,016,01,019 Plat Aluminium 0,5 mm

20 20,01,01,016,01,020 Plat Aluminium 0,5 mm


21 20,01,01,016,01,021 Plat Aluminium 0,6 mm

22 20,01,01,016,01,022 Plat Aluminium 0,6 mm

23 20,01,01,016,01,023 Plat Aluminium 0,6 mm

24 20,01,01,016,01,024 Plat Aluminium 0,6 mm


PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur
Jenis Standar 20,01,03,002,01 Kayu Besi
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,01,03,002,01,001 Kayu Balok Kelas 1

2 20,01,03,002,01,002 Kayu Balok Kelas 1

3 20,01,03,002,01,003 Kayu Balok Kelas 1

PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

PEMERINTAH KAB. HALM


DAFTAR STANDAR HARG
Periode Tahun 2019
4 20,01,03,002,01,004 Kayu Balok Kelas 1
5 20,01,03,002,01,005 Kayu Papan Kelas 1

6 20,01,03,002,01,006 Kayu Papan Kelas 1

7 20,01,03,002,01,007 Kayu Papan Kelas 1


8 20,01,03,002,01,008 Kayu Papan Kelas 1
Jenis Standar 20,01,03,002,03 Kayu Kelas II
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,01,03,002,03,001 Kayu Balok Kelas II

2 20,01,03,002,03,002 Kayu Balok Kelas II

3 20,01,03,002,03,003 Kayu Balok Kelas II

4 20,01,03,002,03,004 Kayu Balok Kelas II


5 20,01,03,002,03,005 Kayu Papan Kelas II

6 20,01,03,002,03,006 Kayu Papan Kelas II

7 20,01,03,002,03,007 Kayu Papan Kelas II

8 20,01,03,002,03,008 Kayu Papan Kelas II


9 20,01,03,002,03,009 Dolken Kayu Galam Dia. 8-10/4 m

10 20,01,03,002,03,010 Dolken Kayu Galam Dia. 8-10/4 m

11 20,01,03,002,03,011 Dolken Kayu Galam Dia. 8-10/4 m

12 20,01,03,002,03,012 Dolken Kayu Galam Dia. 8-10/4 m


Jenis Standar 20,01,03,002,12 Triplek
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,01,03,002,12,001 Triplek 3 mm

2 20,01,03,002,12,002 Triplek 3 mm

3 20,01,03,002,12,003 Triplek 3 mm

PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

PEMERINTAH KAB. HALM


DAFTAR STANDAR HARG
Periode Ta
4 20,01,03,002,12,004 Triplek 3 mm
5 20,01,03,002,12,005 Triplek 5 mm

6 20,01,03,002,12,006 Triplek 5 mm

7 20,01,03,002,12,007 Triplek 5 mm

8 20,01,03,002,12,008 Triplek 5 mm
9 20,01,03,002,12,009 Triplek 8 mm

10 20,01,03,002,12,010 Triplek 8 mm

11 20,01,03,002,12,011 Triplek 8 mm

12 20,01,03,002,12,012 Triplek 8 mm
13 20,01,03,002,12,013 Triplek 10 mm

14 20,01,03,002,12,014 Triplek 10 mm

15 20,01,03,002,12,015 Triplek 10 mm

16 20,01,03,002,12,016 Triplek 10 mm
Jenis Standar 20,01,03,003,01 Paku
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,01,03,003,01,001 Paku Campuran

2 20,01,03,003,01,002 Paku Campuran

3 20,01,03,003,01,003 Paku Campuran

4 20,01,03,003,01,004 Paku Campuran


5 20,01,03,003,01,005 Paku Tripleks

6 20,01,03,003,01,006 Paku Tripleks

7 20,01,03,003,01,007 Paku Tripleks

8 20,01,03,003,01,008 Paku Tripleks


9 20,01,03,003,01,009 Paku Seng
10 20,01,03,003,01,010 Paku Seng

11 20,01,03,003,01,011 Paku Seng

12 20,01,03,003,01,012 Paku Seng


PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

13 20,01,03,003,01,013 Paku Beton

14 20,01,03,003,01,014 Paku Beton

15 20,01,03,003,01,015 Paku Beton

16 20,01,03,003,01,016 Paku Beton


Jenis Standar 20,01,03,003,02 Pipa DD Sock
No. Kode Standar Harga Nama Barang Standar Merk / Model
1 20,01,03,003,02,001 Pipa PVC DD1

2 20,01,03,003,02,002 Pipa PVC DD1

3 20,01,03,003,02,003 Pipa PVC DD1

4 20,01,03,003,02,004 Pipa PVC DD1


5 20,01,03,003,02,005 Pipa PVC DD2

6 20,01,03,003,02,006 Pipa PVC DD2

7 20,01,03,003,02,007 Pipa PVC DD2

8 20,01,03,003,02,008 Pipa PVC DD2


9 20,01,03,003,02,009 Pipa PVC DD3

PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur


PEMERINTAH KAB. HALM
DAFTAR STANDAR HARG
Periode Tahun 2019
10 20,01,03,003,02,010 Pipa PVC DD3

11 20,01,03,003,02,011 Pipa PVC DD3

12 20,01,03,003,02,012 Pipa PVC DD3


13 20,01,03,003,02,013 Pipa PVC DD4

14 20,01,03,003,02,014 Pipa PVC DD4

15 20,01,03,003,02,015 Pipa PVC DD4

16 20,01,03,003,02,016 Pipa PVC DD4


Jenis Standar 20,01,03,003,03 Pipa AW Sock
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,01,03,003,03,001 Pipa PVC AW 1/2

2 20,01,03,003,03,002 Pipa PVC AW 1/2

3 20,01,03,003,03,003 Pipa PVC AW 1/2

4 20,01,03,003,03,004 Pipa PVC AW 1/2


5 20,01,03,003,03,005 Pipa PVC AW 3/4

6 20,01,03,003,03,006 Pipa PVC AW 3/4

7 20,01,03,003,03,007 Pipa PVC AW 3/4

8 20,01,03,003,03,008 Pipa PVC AW 3/4


9 20,01,03,003,03,009 Pipa PVC AW 1

10 20,01,03,003,03,010 Pipa PVC AW 1

11 20,01,03,003,03,011 Pipa PVC AW 1

12 20,01,03,003,03,012 Pipa PVC AW 1


13 20,01,03,003,03,013 Pipa PVC AW 2

14 20,01,03,003,03,014 Pipa PVC AW 2

PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

PEMERINTAH KAB. HALMAHERA


DAFTAR STANDAR HARGA BARA
Periode Ta 2019
15 20,01,03,003,03,015 Pipa PVC AW 2

16 20,01,03,003,03,016 Pipa PVC AW 2


17 20,01,03,003,03,017 Pipa PVC AW 2 1/2

18 20,01,03,003,03,018 Pipa PVC AW 2 1/2

19 20,01,03,003,03,019 Pipa PVC AW 2 1/2

20 20,01,03,003,03,020 Pipa PVC AW 2 1/2


21 20,01,03,003,03,021 Pipa PVC AW 3

22 20,01,03,003,03,022 Pipa PVC AW 3

23 20,01,03,003,03,023 Pipa PVC AW 3

24 20,01,03,003,03,024 Pipa PVC AW 3


25 20,01,03,003,03,025 Pipa PVC AW 4

26 20,01,03,003,03,026 Pipa PVC AW 4

27 20,01,03,003,03,027 Pipa PVC AW 4

28 20,01,03,003,03,028 Pipa PVC AW 4


29 20,01,03,003,03,029 Pipa PVC AW 5

30 20,01,03,003,03,030 Pipa PVC AW 5

31 20,01,03,003,03,031 Pipa PVC AW 5


32 20,01,03,003,03,032 Pipa PVC AW 5
33 20,01,03,003,03,033 Pipa PVC AW 6

34 20,01,03,003,03,034 Pipa PVC AW 6

35 20,01,03,003,03,035 Pipa PVC AW 6

36 20,01,03,003,03,036 Pipa PVC AW 6


PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

PEMERINTAH KAB. HALM


DAFTAR STANDAR HARG
Periode Tahun 2019
Jenis Stand20,01,03,003,04 Pipa RR
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,01,03,003,04,001 Pipa PVC RR S 10.63 mm

2 20,01,03,003,04,002 Pipa PVC RR S 10.63 mm

3 20,01,03,003,04,003 Pipa PVC RR S 10.63 mm

4 20,01,03,003,04,004 Pipa PVC RR S 10.63 mm


5 20,01,03,003,04,005 Pipa PVC RR S 10.90 mm

6 20,01,03,003,04,006 Pipa PVC RR S 10.90 mm

7 20,01,03,003,04,007 Pipa PVC RR S 10.90 mm

8 20,01,03,003,04,008 Pipa PVC RR S 10.90 mm


9 20,01,03,003,04,009 Pipa PVC RR S.10.110 mm

10 20,01,03,003,04,010 Pipa PVC RR S.10.110 mm

11 20,01,03,003,04,011 Pipa PVC RR S.10.110 mm

12 20,01,03,003,04,012 Pipa PVC RR S.10.110 mm


13 20,01,03,003,04,013 Pipa PVC RR S.10.160 mm
14 20,01,03,003,04,014 Pipa PVC RR S.10.160 mm

15 20,01,03,003,04,015 Pipa PVC RR S.10.160 mm

16 20,01,03,003,04,016 Pipa PVC RR S.10.160 mm


17 20,01,03,003,04,017 Pipa PVC RR S.10.200 mm

18 20,01,03,003,04,018 Pipa PVC RR S.10.200 mm

19 20,01,03,003,04,019 Pipa PVC RR S.10.200 mm

20 20,01,03,003,04,020 Pipa PVC RR S.10.200 mm

PEMERINT
Hal 137 dari 240

PEMERINTAH KAB. HALM


DAFTAR STANDAR HARG
Periode Tahun 2019
Jenis Standar 20,01,03,003,05 Pipa GIP
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,01,03,003,05,001 Pipa GIP Medium A ALL Flange
Lengkap 1/2
2 20,01,03,003,05,002 Pipa GIP Medium A ALL Flange
Lengkap 1/2
3 20,01,03,003,05,003 Pipa GIP Medium A ALL Flange
Lengkap 1/2
4 20,01,03,003,05,004 Pipa GIP Medium A ALL Flange
Lengkap 1/2
5 20,01,03,003,05,005 Pipa GIP Medium A ALL Flange
Lengkap 3/4
6 20,01,03,003,05,006 Pipa GIP Medium A ALL Flange
Lengkap 3/4
7 20,01,03,003,05,007 Pipa GIP Medium A ALL Flange
Lengkap 3/4
8 20,01,03,003,05,008 Pipa GIP Medium A ALL Flange
Lengkap 3/4
9 20,01,03,003,05,009 Pipa GIP Medium A ALL Flange
Lengkap 1
10 20,01,03,003,05,010 Pipa GIP Medium A ALL Flange
Lengkap 1
11 20,01,03,003,05,011 Pipa GIP Medium A ALL Flange
Lengkap 1
12 20,01,03,003,05,012 Pipa GIP Medium A ALL Flange
Lengkap 1
13 20,01,03,003,05,013 Pipa GIP Medium A ALL Flange
Lengkap 1 1/4
14 20,01,03,003,05,014 Pipa GIP Medium A ALL Flange
Lengkap 1 1/4
15 20,01,03,003,05,015 Pipa GIP Medium A ALL Flange
Lengkap 1 1/4
16 20,01,03,003,05,016 Pipa GIP Medium A ALL Flange
Lengkap 1 1/4
17 20,01,03,003,05,017 Pipa GIP Medium A ALL Flange
Lengkap 1 1/2
18 20,01,03,003,05,018 Pipa GIP Medium A ALL Flange
Lengkap 1 1/2
19 20,01,03,003,05,019 Pipa GIP Medium A ALL Flange
Lengkap 1 1/2

PEMERINT
Hal 138 dari 240

PEMERINTAH KAB. HALMAHERA


DAFTAR STANDAR HARGA BARA
Periode Ta 2019
20 20,01,03,003,05,020 Pipa GIP Medium A ALL Flange
Lengkap 1 1/2
21 20,01,03,003,05,021 Pipa GIP Medium A ALL Flange
Lengkap 2
22 20,01,03,003,05,022 Pipa GIP Medium A ALL Flange
Lengkap 2
23 20,01,03,003,05,023 Pipa GIP Medium A ALL Flange
Lengkap 2
24 20,01,03,003,05,024 Pipa GIP Medium A ALL Flange
Lengkap 2
25 20,01,03,003,05,025 Pipa GIP Medium A ALL Flange
Lengkap 2 1/2
26 20,01,03,003,05,026 Pipa GIP Medium A ALL Flange
Lengkap 2 1/2
27 20,01,03,003,05,027 Pipa GIP Medium A ALL Flange
Lengkap 2 1/2
28 20,01,03,003,05,028 Pipa GIP Medium A ALL Flange
Lengkap 2 1/2
29 20,01,03,003,05,029 Pipa GIP Medium A ALL Flange
Lengkap 3
30 20,01,03,003,05,030 Pipa GIP Medium A ALL Flange
Lengkap 3
31 20,01,03,003,05,031 Pipa GIP Medium A ALL Flange
Lengkap 3
32 20,01,03,003,05,032 Pipa GIP Medium A ALL Flange
Lengkap 3
33 20,01,03,003,05,033 Pipa GIP Medium A ALL Flange
Lengkap 4
34 20,01,03,003,05,034 Pipa GIP Medium A ALL Flenge
Lengkap 4
35 20,01,03,003,05,035 Pipa GIP Medium A ALL Flange
Lengkap 4
36 20,01,03,003,05,036 Pipa GIP Medium A ALL Flange
Lengkap 4
37 20,01,03,003,05,037 Pipa GIP Medium A ALL Flange
Lengkap 6
38 20,01,03,003,05,038 Pipa GIP Medium A ALL Flange
Lengkap 6
39 20,01,03,003,05,039 Pipa GIP Medium A ALL Flange
Lengkap 6
40 20,01,03,003,05,040 Pipa GIP Medium A ALL Flange
Lengkap 6
PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

PEMERINTAH KAB. HALMAHERA


DAFTAR STANDAR HARGA BARA
Periode Ta 2019
41 20,01,03,003,05,041 Pipa GIP Medium B ALL Flange
Lengkap 1/2
42 20,01,03,003,05,042 Pipa GIP Medium B ALL Flange
Lengkap 1/2
43 20,01,03,003,05,043 Pipa GIP Medium B ALL Flange
Lengkap 1/2
44 20,01,03,003,05,044 Pipa GIP Medium B ALL Flange
Lengkap 1/2
45 20,01,03,003,05,045 Pipa GIP Medium B ALL Flange
Lengkap 3/4
46 20,01,03,003,05,046 Pipa GIP Medium B ALL Flange
Lengkap 3/4
47 20,01,03,003,05,047 Pipa GIP Medium B ALL Flange
Lengkap 3/4
48 20,01,03,003,05,048 Pipa GIP Medium B ALL Flange
Lengkap 3/4
49 20,01,03,003,05,049 Pipa GIP Medium B ALL Flange
Lengkap 1
50 20,01,03,003,05,050 Pipa GIP Medium B ALL Flange
Lengkap 1
51 20,01,03,003,05,051 Pipa GIP Medium B ALL Flange
Lengkap 1
52 20,01,03,003,05,052 Pipa GIP Medium B ALL Flange
Lengkap 1
53 20,01,03,003,05,053 Pipa GIP Medium B ALL Flange
Lengkap 1 1/4
54 20,01,03,003,05,054 Pipa GIP Medium B ALL Flange
Lengkap 1 1/4
55 20,01,03,003,05,055 Pipa GIP Medium B ALL Flange
Lengkap 1 1/4
56 20,01,03,003,05,056 Pipa GIP Medium B ALL Flange
Lengkap 1 1/4
57 20,01,03,003,05,057 Pipa GIP Medium B ALL Flange
Lengkap 1 1/2
58 20,01,03,003,05,058 Pipa GIP Medium B ALL Flange
Lengkap 1 1/2
59 20,01,03,003,05,059 Pipa GIP Medium B ALL Flange
Lengkap 1 1/2
60 20,01,03,003,05,060 Pipa GIP Medium B ALL Flange
Lengkap 1 1/2
61 20,01,03,003,05,061 Pipa GIP Medium B ALL Flange
Lengkap 2
PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

PEMERINTAH KAB. HALM


DAFTAR STANDAR HARG
Periode Ta 2019
62 20,01,03,003,05,062 Pipa GIP Medium B ALL Flange
Lengkap 2
63 20,01,03,003,05,063 Pipa GIP Medium B ALL Flange
Lengkap 2
64 20,01,03,003,05,064 Pipa GIP Medium B ALL Flange
Lengkap 2
65 20,01,03,003,05,065 Pipa GIP Medium B ALL Flange
Lengkap 2 1/2
66 20,01,03,003,05,066 Pipa GIP Medium B ALL Flange
Lengkap 2 1/2
67 20,01,03,003,05,067 Pipa GIP Medium B ALL Flange
Lengkap 2 1/2
68 20,01,03,003,05,068 Pipa GIP Medium B ALL Flange
Lengkap 2 1/2
69 20,01,03,003,05,069 Pipa GIP Medium B ALL Flange
Lengkap 3
70 20,01,03,003,05,070 Pipa GIP Medium B ALL Flange
Lengkap 3
71 20,01,03,003,05,071 Pipa GIP Medium B ALL Flange
Lengkap 3
72 20,01,03,003,05,072 Pipa GIP Medium B ALL Flange
Lengkap 3
Jenis Stand20,01,03,003,06 Pipa HDPE
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,01,03,003,06,001 Pipa HDPE PE 100.63 mm

2 20,01,03,003,06,002 Pipa HDPE PE 100.63 mm

3 20,01,03,003,06,003 Pipa HDPE PE 100.63 mm


4 20,01,03,003,06,004 Pipa HDPE PE 100.63 mm
5 20,01,03,003,06,005 Pipa HDPE PE 100.90 mm

6 20,01,03,003,06,006 Pipa HDPE PE 100.90 mm

7 20,01,03,003,06,007 Pipa HDPE PE 100.90 mm

8 20,01,03,003,06,008 Pipa HDPE PE 100.90 mm


9 20,01,03,003,06,009 Pipa HDPE PE 100.110 mm

PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

PEMERINTAH KAB. HALM


DAFTAR STANDAR HARG
Periode Tahun 2019
10 20,01,03,003,06,010 Pipa HDPE PE 100.110 mm

11 20,01,03,003,06,011 Pipa HDPE PE 100.110 mm

12 20,01,03,003,06,012 Pipa HDPE PE 100.110 mm


13 20,01,03,003,06,013 Pipa HDPE PE 100.160 mm

14 20,01,03,003,06,014 Pipa HDPE PE 100.160 mm

15 20,01,03,003,06,015 Pipa HDPE PE 100.160 mm

16 20,01,03,003,06,016 Pipa HDPE PE 100.160 mm


Jenis Standar 20,03,05,005,01 Kran Air
No. Kode Standar Harga Nama BaraMerk / Mo
1 20,03,05,005,01,001 Kran Air 3/4

2 20,03,05,005,01,002 Kran Air 3/4

3 20,03,05,005,01,003 Kran Air 3/4

4 20,03,05,005,01,004 Kran Air 3/4


5 20,03,05,005,01,005 Kran Air 1/2
PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

Periode Ta
6 20,03,05,005,01,006 Kran Air 1/2

7 20,03,05,005,01,007 Kran Air 1/2

8 20,03,05,005,01,008 Kran Air 1/2


9 20,03,05,005,01,009 Kran Air Kw 1

10 20,03,05,005,01,010 Kran Air Kw 1

11 20,03,05,005,01,011 Kran Air Kw 1

12 20,03,05,005,01,012 Kran Air Kw 1


Jenis Standar 20,03,05,005,03 Kloset
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,03,05,005,03,001 Kloset Jongkok Lokal

2 20,03,05,005,03,002 Kloset Jongkok Lokal

PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

PEMERINTAH KAB. HALM


DAFTAR STANDAR HARG
Periode Tahun 2019
3 20,03,05,005,03,003 Kloset Jongkok Lokal

4 20,03,05,005,03,004 Kloset Jongkok Lokal


5 20,03,05,005,03,005 Kloset Jongkok Toto

6 20,03,05,005,03,006 Kloset Jongkok Toto

7 20,03,05,005,03,007 Kloset Jongkok Toto


8 20,03,05,005,03,008 Kloset Jongkok Toto
9 20,03,05,005,03,009 Kloset Duduk

10 20,03,05,005,03,010 Kloset Duduk

11 20,03,05,005,03,011 Kloset Duduk

12 20,03,05,005,03,012 Kloset Duduk


Jenis Standar 20,03,05,005,04 Wastafel
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,03,05,005,04,001 Wastafel

2 20,03,05,005,04,002 Wastafel

3 20,03,05,005,04,003 Wastafel

4 20,03,05,005,04,004 Wastafel
5 20,03,05,005,04,005 Washtafel Kualitas 1

6 20,03,05,005,04,006 Washtafel Kualitas 1

7 20,03,05,005,04,007 Washtafel Kualitas 1

8 20,03,05,005,04,008 Washtafel Kualitas 1


9 20,03,05,005,04,009 Washtafel Kualitas Lux 1

10 20,03,05,005,04,010 Washtafel Kualitas Lux 1

11 20,03,05,005,04,011 Washtafel Kualitas Lux 1

Jenis Standar 20,03,06,001,01 Kabel


No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,03,06,001,01,001 Kabel
2 20,03,06,001,01,002 Kabel
3 20,03,06,001,01,003 Kabel
4 20,03,06,001,01,004 Kabel
5 20,03,06,001,01,005 Kabel
6 20,03,06,001,01,006 Kabel
7 20,03,06,001,01,008 Kabel
8 20,03,06,001,01,009 Kabel Goal NYZ
PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

PEMERINTAH KAB. HALM


DAFTAR STANDAR HARG
Periode Tahun 2019
9 20,03,06,001,01,010 Kabel Cosmic Kawat
10 20,03,06,001,01,011 Kabel Cosmic Kawat
11 20,03,06,001,01,012 Kabel Premium Kawat
12 20,03,06,001,01,013 Kabel Premium Kawat
13 20,03,06,001,01,014 Kabel Enterna Kawat
14 20,03,06,001,01,015 Kabel Enterna Kawat
15 20,03,06,001,01,016 Kabel Comet Kawat
16 20,03,06,001,01,017 Kabel Comet Kawat
17 20,03,06,001,01,018 Kabel Elite Serabut
18 20,03,06,001,01,019 Kabel Comet Merah Puti
Jenis Standar 20,03,06,001,02 Kabel Seling
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,03,06,001,02,001 Kabel Seling
2 20,03,06,001,02,002 Kabel Seling
3 20,03,06,001,02,003 Kabel Seling
4 20,03,06,001,02,004 Kabel Seling
5 20,03,06,001,02,005 Kabel Seling
6 20,03,06,001,02,006 Kabel Seling
Jenis Standar 20,03,06,001,03 Kabel Transparan
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,03,06,001,03,001 Kabel Transparan
2 20,03,06,001,03,002 Kabel Eterna (3x1,5 mm)
Jenis Standar 20,03,06,001,04 Kabel Roll
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,03,06,001,04,001 Kabel Roll
2 20,03,06,001,04,003 Kabel Roll Box Kabel
3 20,03,06,001,04,004 Kabel Roll Brennesthul
4 20,03,06,001,04,005 Kabel Roll Brennesthul
5 20,03,06,001,04,006 Kabel Roll Brennesthul
6 20,03,06,001,04,007 Kabel Roll Brennesthul
7 20,03,06,001,04,008 Kabel Roll Brennesthul
8 20,03,06,001,04,009 Kabel Roll Kemaster
PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

PEMERINTAH KAB. HALMAHERA


DAFTAR STANDAR HARGA BARA
Periode Ta 2019
9 20,03,06,001,04,010 Kabel Roll Kenmater
10 20,03,06,001,04,011 Kabel Roll Loyal
11 20,03,06,001,04,012 Kabel Roll Loyal
12 20,03,06,001,04,013 Kabel Roll Loyal Turbo
13 20,03,06,001,04,014 Kabel Roll Loyal Welto
14 20,03,06,001,04,015 Kabel Roll Meet
15 20,03,06,001,04,016 Kabel Roll Presto
16 20,03,06,001,04,017 Kabel Roll Presto
17 20,03,06,001,04,018 Kabel Roll Presto
18 20,03,06,001,04,019 Kabel Roll Presto
19 20,03,06,001,04,020 Kabel Roll Royal
20 20,03,06,001,04,021 Kabel Roll Royal
21 20,03,06,001,04,022 Kabel Roll Vetto Box Kabel
22 20,03,06,001,04,023 Kabel Roll Vetto Kabel Box
23 20,03,06,001,04,024 Kabel Roll Boss
24 20,03,06,001,04,025 Kabel Roll Kyowa
25 20,03,06,001,04,026 Kabel Roll Kyowa
Jenis Standar 20,03,06,001,05 Kabel NYA / NGA
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,03,06,001,05,001 Kabel NYA / NGA
2 20,03,06,001,05,002 Kabel NYA / NGA
3 20,03,06,001,05,003 Kabel NYA / NGA
4 20,03,06,001,05,004 Kabel NYA
5 20,03,06,001,05,005 Kabel NYA
6 20,03,06,001,05,006 Kabel NYA
Jenis Standar 20,03,06,001,06 Kabel BC
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,03,06,001,06,001 Kabel BC
2 20,03,06,001,06,002 Kabel BC
3 20,03,06,001,06,003 Kabel BC
4 20,03,06,001,06,004 Kabel BC
5 20,03,06,001,06,005 Kabel BC
PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur
PEMERINTAH KAB. HALM
DAFTAR STANDAR HARG
Periode Tahun 2019
Jenis Standar 20,03,06,001,07 Kabel Twisted
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,03,06,001,07,001 Kabel Twisted
2 20,03,06,001,07,002 Kabel Twisted
Jenis Standar 20,03,06,001,08 Kabel NYM
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,03,06,001,08,001 Kabel NYM
Jenis Standar 20,03,06,001,09 Kabel NYY
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,03,06,001,09,001 Kabel NYY
Jenis Standar 20,03,06,001,10 Kabel Telephone
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,03,06,001,10,001 Kabel Telephone Aries Meter
Jenis Standar 20,03,06,001,11 Kabel Roll + Lampu
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,03,06,001,11,001 Kabel Roll + Lampu Presto 2154
2 20,03,06,001,11,002 Kabel Roll + Lampu Presto 2210
Jenis Standar 20,03,06,002,01 Lampu Selang
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,03,06,002,01,001 Lampu Selang
Jenis Standar 20,03,06,002,02 High Pressure Mercury Lamps
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,03,06,002,02,001 High Pressure Mercury Lamps Osram
2 20,03,06,002,02,002 High Pressure Mercury Lamps Osram
3 20,03,06,002,02,003 High Pressure Mercury Lamps Osram
4 20,03,06,002,02,004 High Pressure Mercury Lamps Osram
Jenis Standar 20,03,06,002,03 Light Night
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,03,06,002,03,001 Light Night Kenmaster
2 20,03,06,002,03,002 Light Night Kenmaster
3 20,03,06,002,03,003 Light Night Kenmaster
PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur
Jenis Standar 20,03,06,002,04 Lampu
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,03,06,002,04,001 Lampu Chiyoda
2 20,03,06,002,04,002 Lampu Chiyoda
3 20,03,06,002,04,003 Lampu Chiyoda
4 20,03,06,002,04,004 Lampu Chiyoda
5 20,03,06,002,04,005 Lampu Chiyoda
6 20,03,06,002,04,006 Lampu Chiyoda
7 20,03,06,002,04,007 Lampu Chiyoda
8 20,03,06,002,04,008 Lampu Chiyoda
9 20,03,06,002,04,009 Lampu Chiyoda
10 20,03,06,002,04,010 Lampu Chiyoda
11 20,03,06,002,04,011 Lampu Chiyoda
12 20,03,06,002,04,012 Lampu Chiyoda
13 20,03,06,002,04,013 Lampu Chiyoda
14 20,03,06,002,04,014 Lampu Chiyoda
15 20,03,06,002,04,016 Lampu Chiyoda
16 20,03,06,002,04,017 Lampu Chiyoda
17 20,03,06,002,04,018 Lampu Essential, Philips
18 20,03,06,002,04,019 Lampu Esential
19 20,03,06,002,04,020 Lampu Essential
20 20,03,06,002,04,021 Lampu Essential, Philips
21 20,03,06,002,04,022 Lampu Essential
22 20,03,06,002,04,023 Lampu Essential
23 20,03,06,002,04,024 Lampu Essential
24 20,03,06,002,04,025 Lampu Essential
25 20,03,06,002,04,026 Lampu Hitachi
26 20,03,06,002,04,027 Lampu Hirachi
27 20,03,06,002,04,028 Lampu Hitachi
28 20,03,06,002,04,029 Lampu Hitachi
29 20,03,06,002,04,030 Lampu Hitachi
30 20,03,06,002,04,031 Lampu Osram
31 20,03,06,002,04,032 Lampu Osram
PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur
32 20,03,06,002,04,033 Lampu Osram
33 20,03,06,002,04,034 Lampu Osram
34 20,03,06,002,04,035 Lampu Osram
35 20,03,06,002,04,036 Lampu Osram
36 20,03,06,002,04,037 Lampu Osram
Jenis Standar 20,03,06,002,05 Lampu Bohlam
No. Kode Standar Harga Nama BaraMerk / Mo
1 20,03,06,002,05,001 Lampu Bohlam Chiyoda
2 20,03,06,002,05,002 Lampu Bohlam Chiyoda
3 20,03,06,002,05,003 Lampu Bohlam Chiyoda
4 20,03,06,002,05,004 Lampu Bohlam Chiyoda
5 20,03,06,002,05,005 Lampu Bohlam Chiyoda
6 20,03,06,002,05,006 Lampu Bohlam Chiyoda
7 20,03,06,002,05,007 Lampu Bohlam Chiyoda
8 20,03,06,002,05,008 Lampu Bohlam Chiyoda
9 20,03,06,002,05,009 Lampu Bohlam Philips
10 20,03,06,002,05,010 Lampu Bohlam Philips
11 20,03,06,002,05,011 Lampu Bohlam Philips
12 20,03,06,002,05,012 Lampu Bohlam Philips
13 20,03,06,002,05,013 Lampu Bohlam Philips
14 20,03,06,002,05,014 Lampu Bohlam Philips
15 20,03,06,002,05,015 Lampu Bohlam Philips
16 20,03,06,002,05,016 Lampu Bohlam Philips
17 20,03,06,002,05,017 Lampu Bohlam Philips
18 20,03,06,002,05,018 Lampu Bohlam ARO
19 20,03,06,002,05,019 Lampu Bohlam ARO
Jenis Standar 20,03,06,002,06 Lampu Bohlam Capsul
No. Kode Standar Harga Nama BaraMerk / Mo
1 20,03,06,002,06,001 Lampu Boh Chiyoda
2 20,03,06,002,06,002 Lampu Boh ARO
3 20,03,06,002,06,003 Lampu Boh Chiyoda
4 20,03,06,002,06,004 Lampu Boh Kenmaster
5 20,03,06,002,06,005 Lampu Boh Kenmaster
PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur
PEMERINTAH KAB. HALM
DAFTAR STANDAR HARG
Periode Tahun 2019
6 20,03,06,002,06,006 Lampu Bohlam Capsul Kenmaster
7 20,03,06,002,06,007 Lampu Bohlam Capsul Kenmaster
8 20,03,06,002,06,008 Lampu Bohlam Capsul Everlite
9 20,03,06,002,06,009 Lampu Bohlam Capsul ARO
10 20,03,06,002,06,010 Lampu Bohlam Capsul ARO
11 20,03,06,002,06,011 Lampu Bohlam Capsul ARO
12 20,03,06,002,06,012 Lampu Bohlam Capsul ARO
Jenis Stand20,03,06,002,07 Lampu "EL - N" Energi
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,03,06,002,07,001 Lampu "EL - N" Energi Osram

2 20,03,06,002,07,002 Lampu "EL - N" Energi Osram

3 20,03,06,002,07,003 Lampu "EL - N" Energi Osram

4 20,03,06,002,07,004 Lampu "EL - N" Energi Osram

Jenis Stand20,03,06,002,08 Lampu Dulux


No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,03,06,002,08,001 Lampu Dulux Osram
2 20,03,06,002,08,002 Lampu Dulux Osram
3 20,03,06,002,08,003 Lampu Dulux Osram
4 20,03,06,002,08,004 Lampu Dulux Osram
5 20,03,06,002,08,005 Lampu Dulux Osram
6 20,03,06,002,08,006 Lampu Dulux Osram
7 20,03,06,002,08,007 Lampu Dulux Osram
8 20,03,06,002,08,008 Lampu Dulux Osram
9 20,03,06,002,08,009 Lampu Dulux Osram
10 20,03,06,002,08,010 Lampu Dulux Osram
Jenis Stand20,03,06,002,09 Lampu emergency
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,03,06,002,09,001 Lampu emergency KN 118
2 20,03,06,002,09,002 Lampu emergency KN 218
3 20,03,06,002,09,003 Lampu emergency KN 889
PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur
PEMERINTAH KAB. HALMAHERA
DAFTAR STANDAR HARGA BARA
Periode Ta 2019
4 20,03,06,002,09,004 Lampu emergency URION 922
5 20,03,06,002,09,005 Lampu emergency URION, 300 - 4
6 20,03,06,002,09,006 Lampu emergency Kenmaster, 886
7 20,03,06,002,09,007 Lampu emergency Kenmaster, 200
8 20,03,06,002,09,008 Lampu emergency Kenmaster,
042000
9 20,03,06,002,09,009 Lampu emergency BIO, EB - 208
10 20,03,06,002,09,010 Lampu emergency Kenmaster, 20 A
11 20,03,06,002,09,011 Lampu emergency Love LC 198
12 20,03,06,002,09,012 Lampu emergency BIO - L, LE 999
13 20,03,06,002,09,013 Lampu emergency AKIRA, ELW 210
SN
14 20,03,06,002,09,014 Lampu emergency URION, 2868
15 20,03,06,002,09,015 Lampu emergency Kenmaster, 730
16 20,03,06,002,09,016 Lampu emergency Shimizu, SZ 120 D
17 20,03,06,002,09,017 Lampu emergency Kenmaster, HK - 6
18 20,03,06,002,09,018 Lampu emergency Trikom, Petromax
19 20,03,06,002,09,019 Lampu emergency Success Lantum
Jenis Standar 20,03,06,002,10 Lampu Halogen
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,03,06,002,10,001 Lampu Halogen Philips
2 20,03,06,002,10,002 Lampu Halogen Philips
3 20,03,06,002,10,003 Lampu Halogen Philips
4 20,03,06,002,10,004 Lampu Halogen Philips
5 20,03,06,002,10,005 Lampu Halogen Philips
6 20,03,06,002,10,006 Lampu Halogen Philisp, Pius Line P
Jenis Standar 20,03,06,002,11 Lampu Hemat Listrik
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 20,03,06,002,11,001 Lampu Hemat Listrik Philips
2 20,03,06,002,11,002 Lampu Hemat Listrik Philips
3 20,03,06,002,11,003 Lampu Hemat Listrik Philips
4 20,03,06,002,11,004 Lampu Hemat Listrik Philips
5 20,03,06,002,11,005 Lampu Hemat Listrik Philips
PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur
6 20,03,06,002,11,006 Lampu Hemat Listrik Philips
7 20,03,06,002,11,007 Lampu Hemat Listrik Philips
8 20,03,06,002,11,008 Lampu Hemat Listrik Philips
9 20,03,06,002,11,009 Lampu Hemat Listrik Philips
10 20,03,06,002,11,010 Lampu Hemat Listrik Philips
Jenis Standar 20,03,06,002,12 Lampu Meja
No. Kode Standar Harga Nama BaraMerk / Mo
1 20,03,06,002,12,001 Lampu Meja 1052 A / FAN
2 20,03,06,002,12,002 Lampu Meja 1052 A / FAN
3 20,03,06,002,12,003 Lampu Meja YS - 901
4 20,03,06,002,12,004 Lampu Meja YS - 901
5 20,03,06,002,12,005 Lampu Meja YS - 901C

6 20,03,06,002,12,006 Lampu Meja YS - 901C


Jenis Standar 20,03,06,002,13 Lampu Mercury
No. Kode Standar Harga Nama BaraMerk / Mo
1 20,03,06,002,13,001 Lampu Mercury Philips, HPLN
2 20,03,06,002,13,002 Lampu Mercury Philips, HPLN
3 20,03,06,002,13,003 Lampu Mercury Philips, HPLN
4 20,03,06,002,13,004 Lampu Mercury Philips, HPLN
5 20,03,06,002,13,005 Lampu Mercury Philips, HPLN
Jenis Standar 20,03,06,002,14 Lampu Metal
No. Kode Standar Harga Nama BaraMerk / Mo
1 20,03,06,002,14,001 Lampu Metal Philips, HPIT
2 20,03,06,002,14,002 Lampu Metal Philips, HPIT
Jenis Standar 20,03,06,002,15 Lampu Pijar Umum
No. Kode Standar Harga Nama BaraMerk / Mo
1 20,03,06,002,15,001 Lampu Pijar Umum Osram
2 20,03,06,002,15,002 Lampu Pijar Umum Osram
3 20,03,06,002,15,003 Lampu Pijar Umum Osram
4 20,03,06,002,15,004 Lampu Pijar Umum Osram R - 63 / E -
27

5 20,03,06,002,15,005 Lampu Pijar Umum Osram, R -Buah


PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur
6 20,03,06,002,15,006 Lampu Pijar Umum Philips
7 20,03,06,002,15,007 Lampu Pijar Umum Philips
8 20,03,06,002,15,008 Lampu Pijar Umum Philips
9 20,03,06,002,15,009 Lampu Pijar Umum Philips
10 20,03,06,002,15,010 Lampu Pijar Umum Philips
11 20,03,06,002,15,011 Lampu Pijar Umum Philips
12 20,03,06,002,15,012 Lampu Pijar Umum Philips
13 20,03,06,002,15,013 Lampu Pijar Umum Philips
14 20,03,06,002,15,014 Lampu Pijar Umum Philips
15 20,03,06,002,15,015 Lampu Pijar Umum Philips
16 20,03,06,002,15,016 Lampu Pijar Umum Philips
17 20,03,06,002,15,017 Lampu Pijar Umum Philips
18 20,03,06,002,15,018 Lampu Pijar Umum Philips
19 20,03,06,002,15,019 Lampu Pijar Umum Philips
Jenis Standar 20,03,06,002,16 Lampu Reflector
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,03,06,002,16,001 Lampu Reflector Chiyoda
2 20,03,06,002,16,002 Lampu Reflector Chiyoda
Jenis Standar 20,03,06,002,17 Lampu Study
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,03,06,002,17,001 Lampu Study GML - 2040
2 20,03,06,002,17,002 Lampu Study GML - 2040
3 20,03,06,002,17,003 Lampu Study GML - 500

4 20,03,06,002,17,004 Lampu Study MDL - 906


5 20,03,06,002,17,005 Lampu Study MDL - 906
6 20,03,06,002,17,006 Lampu Study MDL - 903 N
7 20,03,06,002,17,007 Lampu Study MDL - 903 B
8 20,03,06,002,17,008 Lampu Study MDl - 905
9 20,03,06,002,17,009 Lampu Study MDL - 903 B
Jenis Standar 20,03,06,002,18 Lampu TL
No. Kode Standar Harga Nama Barang Standar Merk / Mo
PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur
Periode Ta
1 20,03,06,002,18,001 Lampu TL Lokal Putih

2 20,03,06,002,18,002 Lampu TL Lokal Putih

3 20,03,06,002,18,003 Lampu TL Lokal Putih

4 20,03,06,002,18,004 Lampu TL Lokal Putih


5 20,03,06,002,18,005 Lampu TL Lokal Warna

6 20,03,06,002,18,006 Lampu TL Lokal Warna

7 20,03,06,002,18,007 Lampu TL Lokal Warna

8 20,03,06,002,18,008 Lampu TL Lokal Warna


9 20,03,06,002,18,009 Lampu TL Bulat 20 Watt

10 20,03,06,002,18,010 Lampu TL Bulat 20 Watt

11 20,03,06,002,18,011 Lampu TL Bulat 20 Watt

12 20,03,06,002,18,012 Lampu TL Bulat 20 Watt


13 20,03,06,002,18,013 Lampu Hias Kualitas Baik

14 20,03,06,002,18,014 Lampu Hias Kualitas Baik

15 20,03,06,002,18,015 Lampu Hias Kualitas Baik

16 20,03,06,002,18,016 Lampu Hias Kualitas Baik


Jenis Standar 20,03,06,002,19 Lampu TL Komplit
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,03,06,002,19,001 Lampu TL Bulat 40 Watt

2 20,03,06,002,19,002 Lampu TL Bulat 40 Watt

3 20,03,06,002,19,003 Lampu TL Bulat 40 Watt


4 20,03,06,002,19,004 Lampu TL Bulat 40 Watt
5 20,03,06,002,19,005 Lampu Neon Box Armateur 10 Watt

PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

Periode Ta
6 20,03,06,002,19,006 Lampu Neon Box Armateur 10 Watt

7 20,03,06,002,19,007 Lampu Neon Box Armateur 10 Watt

8 20,03,06,002,19,008 Lampu Neon Box Armateur 10 Watt


9 20,03,06,002,19,009 Lampu Neon Box Armateur 20 Watt

10 20,03,06,002,19,010 Lampu Neon Box Armateur 20 Watt

11 20,03,06,002,19,011 Lampu Neon Box Armateur 20 Watt

12 20,03,06,002,19,012 Lampu Neon Box Armateur 20 Watt


13 20,03,06,002,19,013 Lampu Spotlight

14 20,03,06,002,19,014 Lampu Spotlight

15 20,03,06,002,19,015 Lampu Spotlight

16 20,03,06,002,19,016 Lampu Spotlight


17 20,03,06,002,19,017 Lampu Dinding LDO 7

18 20,03,06,002,19,018 Lampu Dinding LDO 7

19 20,03,06,002,19,019 Lampu Dinding LDO 7

20 20,03,06,002,19,020 Lampu Dinding LDO 7


Jenis Standar 20,03,06,003,01 Stop Kontak
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,03,06,003,01,001 Stop Kontak
2 20,03,06,003,01,002 Stop Kontak

3 20,03,06,003,01,003 Stop Kontak

4 20,03,06,003,01,004 Stop Kontak


5 20,03,06,003,01,005 Stop Kontak Tanam

6 20,03,06,003,01,006 Stop Kontak Tanam

PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

PEMERINTAH KAB. HALMAHERA


DAFTAR STANDAR HARGA BARA
Periode Ta 2019
7 20,03,06,003,01,007 Stop Kontak Tanam

8 20,03,06,003,01,008 Stop Kontak Tanam


9 20,03,06,003,01,009 Box Sekring

10 20,03,06,003,01,010 Box Sekring

11 20,03,06,003,01,011 Box Sekring

12 20,03,06,003,01,012 Box Sekring


13 20,03,06,003,01,013 Sekring 1 Phase

14 20,03,06,003,01,014 Sekring 1 Phase

15 20,03,06,003,01,015 Sekring 1 Phase

16 20,03,06,003,01,016 Sekring 1 Phase


17 20,03,06,003,01,017 Sekring 2 Phase

18 20,03,06,003,01,018 Sekring 2 Phase

19 20,03,06,003,01,019 Sekring 2 Phase


20 20,03,06,003,01,020 Sekring 2 Phase
21 20,03,06,003,01,021 Saklar Tunggal Tanam

22 20,03,06,003,01,022 Saklar Tunggal Tanam

23 20,03,06,003,01,023 Saklar Tunggal Tanam

24 20,03,06,003,01,024 Saklar Tunggal Tanam


25 20,03,06,003,01,025 Saklar Ganda Tanam

26 20,03,06,003,01,026 Saklar Ganda Tanam

27 20,03,06,003,01,027 Saklar Ganda Tanam

28 20,03,06,003,01,028 Saklar Ganda Tanam


Jenis Standar 20,03,06,006,01 Travo
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,03,06,006,01,001 Travo Mercury Philips
Jenis Standar 20,03,06,007,01 Lighting Fitting
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 20,03,06,007,01,001 Fitting Lampu

2 20,03,06,007,01,002 Fitting Lampu

3 20,03,06,007,01,003 Fitting Lampu

4 20,03,06,007,01,004 Fitting Lampu


Jenis Standar Air
No. Kode Standar Harga Nama Barang Standar Merk / Mo
1 Air
2 Kawat Beton
3 Minyak Bekisting
4 Plamir
Bidang 31 Upah
Kelompok31,01 Upah Kerja
Sub Kelom31,01,01 Upah Kerja
Sub-Sub Kelompok 31,01,01,001 Upah Kerja dan Sewa
Jenis Standar 31,01,01,001,01 Upah Kerja
No. Kode Standar Harga Nama Barang Standar Merk / MoBahan / W
1 31,01,01,001,01,001 Mandor

2 31,01,01,001,01,002 Mandor

3 31,01,01,001,01,003 Mandor

4 31,01,01,001,01,004 Mandor
5 31,01,01,001,01,005 Kepala Tukang

6 31,01,01,001,01,006 Kepala Tukang

7 31,01,01,001,01,007 Kepala Tukang

8 31,01,01,001,01,008 Kepala Tukang


9 31,01,01,001,01,009 Tukang Terampil

10 31,01,01,001,01,010 Tukang Terampil

11 31,01,01,001,01,011 Tukang Terampil

12 31,01,01,001,01,012 Tukang Terampil

13 31,01,01,001,01,013 Tukang Setengah Terampil

14 31,01,01,001,01,014 Tukang Setengah Terampil

15 31,01,01,001,01,015 Tukang Setengah Terampil

PEMERINTAH KAB. HALMAHERA TIMUR, Jl. Raya Halmahera Timur

PEMERINTAH KAB. HALMAHERA


DAFTAR STANDAR HARGA BARA
Periode Ta 2019
16 31,01,01,001,01,016 Tukang Setengah Terampil

17 31,01,01,001,01,017 Buruh Lapangan Tidak Terampil

18 31,01,01,001,01,018 Buruh Lapangan Tidak Terampil

19 31,01,01,001,01,019 Buruh Lapangan Tidak Terampil

20 31,01,01,001,01,020 Buruh Lapangan Tidak Terampil


Satuan Spesifikasi Standar Harga Satuan
50 Kg maba selatan,kota maba dan 148.000
maba
50 Kg maba tengah,maba utara dan 162,000.00
wasile utara
50 Kg wasile,wasile timur dan wasile 135.000
tengah
50 Kg wasile Selatan 140.000
Kg maba selatan,kota maba dan 22.000
maba
Kg maba tengah,maba utara dan 24.000
wasile utara
Kg wasile Timur,Wasile 20.000
Tengah,Wasile
Kg wasile Selatan 21.000
Hal 106 dari 240

Print Out Per-Tangga07-Oktober-2019


PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
Periode Tahun 2019
Bh maba tengah,maba ut 53.000
wasile utara
Bh wasile,wasile timur 45.000
tengah
Bh wasile selatan 46.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


M3 maba selatan,kota m 231.000
maba
M3 maba tengah,maba ut 273.300
wasile utara
M3 wasile,wasile timur 145.000
tengah
M3 wasile selatan 144.000
M3 maba selatan,kota m 415.000
maba
M3 maba tengah,maba ut 395.900
wasile utara
M3 wasile,wasile timur 145.000
tengah
M3 wasile selatan 136.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


M3 maba selatan,kota m 446.000
maba
M3 maba tengah,maba ut 457,100.00
wasile utara
M3 wasile,wasile timur 405.000
tengah
M3 wasile selatan 406.000
M3 maba selatan,kota m 446.000
maba
M3 maba tengah,maba ut 457,100.00
wasile utara
M3 wasile,wasile timur 405.000
tengah
M3 wasile selatan 406.000
Hal 107 dari 240

Print Out Per-Tangga07-Oktober-2019


PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
Periode Tahun 2019

Bahan / WSatuan Spesifikasi Standar Harga Satuan


M3 maba selatan,kota m 568.000
maba
M3 maba tengah,maba ut 616,500.00
wasile utara
M3 wasile,wasile timur 368.000
tengah
M3 wasile selatan 575.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


M3 maba selatan,kota m 311.000
maba
M3 maba tengah,maba ut 457.100
wasile utara
M3 wasile,wasile timur 190.000
tengah
M3 wasile selatan 220.000
Batu Gunung Belah
Bahan / WSatuan Spesifikasi Standar Harga Satuan
M2 maba selatan,kota m 446.000
maba
M2 maba tengah,maba ut 641.000
wasile utara
M2 wasile,wasile timur 405.000
tengah
M2 wasile selatan 420.000
M3 maba selatan,kota m 741.000
maba
M3 maba tengah,maba ut 736.600
wasile utara
M3 wasile,wasile timur 487.000
tengah
M3 wasile selatan 741.000
M3 maba selatan,kota m 719.000
maba
M3 maba tengah,maba ut 736.600
wasile utara
Raya Halmahera Timur Hal 108 dari 240

Print Out Per-Tanggal 07-Oktober-2019


NTAH KAB. HALMAHERA TIMUR
STANDAR HARGA BARANG DAN JASA

M3 wasile,wasile timur dan wasile 651.000


tengah
M3 wasile selatan 741.000
M3 maba selatan,kota maba dan 719.000
maba
M3 maba tengah,maba utara dan 736.600
wasile utara
M3 wasile,wasile timur dan wasile 718.000
tengah
M3 wasile selatan 741.000
M2 maba selatan,kota maba dan 142.000
maba
M2 maba tengah,maba utara dan 159.000
wasile utara
M2 wasile,wasile timur dan wasile 132.000
tengah
M2 wasile selatan 137.000
M3 maba selatan,kota maba dan 446.000
maba
M3 maba tengah,maba utara dan 641.000
wasile utara
M3 wasile,wasile timur dan wasile 405.000
tengah
M3 wasile selatan 420.000
M3 maba selatan,kota maba dan 446.000
maba
M3 maba tengah,maba utara dan 641.000
wasile utara
M3 wasile,wasile timur dan wasile 405.000
tengah
M3 wasile selatan 420.000
M3 maba selatan,kota maba dan 446.000
maba
Hal 109 dari 240

Print Out Per-Tangga07-Oktober-2019


PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
2019
M3 maba tengah,maba ut 641.000
wasile utara
M3 wasile,wasile timur 405.000
tengah
M3 wasile selatan 420.000
M3 maba selatan,kota m 446.000
maba
M3 maba tengah,maba ut 641.000
wasile utara
M3 wasile,wasile timur 405.000
tengah
M3 wasile selatan 420.000
M3 maba selatan,kota m 719.000
maba
M3 maba tengah,maba ut 641.000
wasile utara
M3 wasile,wasile timur 450.000
tengah
M3 wasile selatan 437.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Bh maba selatan,kota m 8.000
maba
Bh maba tengah,maba ut 1,300.00
wasile utara
Bh wasile,wasile timur 8.000
tengah
Bh wasile selatan 8.000
Print Out Per-Tangga07-Oktober-2019
PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
Periode Tahun 2019
Kg maba selatan,kota m 97.000
maba
Kg maba tengah,maba ut 108.000
wasile utara
Kg wasile,wasile timur 90.000
tengah
Kg wasile selatan 93.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


1 Kg maba selatan,kota m 38.000
maba
1 Kg maba tengah,maba ut 42,000.00
wasile utara
1 Kg wasile,wasile timur 36.000
tengah
1 Kg wasile selatan 37.000
5 Kg maba selatan,kota m 194.000
maba
5 Kg maba tengah,maba ut 217,000.00
wasile utara
5 Kg wasile,wasile timur 180.000
tengah
5 Kg wasile selatan 187.000
1 Kg maba selatan,kota m 229.000
maba
1 Kg maba tengah,maba ut 257.000
wasile utara
1 Kg wasile,wasile timur 213.000
tengah
1 Kg wasile selatan 220.000
1 Kg maba selatan,kota m 265.000
maba
1 Kg maba tengah,maba ut 297,000.00
wasile utara
1 Kg wasile,wasile timur 246.000
tengah
1 Kg wasile selatan 255.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Raya Halmahera Timur Hal 115 dari 240

Print Out Per-Tanggal 07-Oktober-2019


NTAH KAB. HALMAHERA TIMUR
STANDAR HARGA BARANG DAN JASA

Lbr maba selatan,kota maba dan 114.000


maba
Lbr maba tengah,maba utara dan 88.000
wasile utara
Lbr wasile,wasile timur dan wasile 73.000
tengah
Lbr wasile selatan 76.000
Lbr maba selatan,kota maba dan 128.000
maba
Lbr maba tengah,maba utara dan 112.000
wasile utara
Lbr wasile,wasile timur dan wasile 93.000
tengah
Lbr wasile selatan 96.000
Lbr maba selatan,kota maba dan 135.000
maba
Lbr maba tengah,maba utara dan 135.000
wasile utara
Lbr wasile,wasile timur dan wasile 113.000
tengah
Lbr wasile selatan 117.000
M' maba selatan,kota maba dan 66.000
maba
M' maba tengah,maba utara dan 74.000
wasile utara
M' wasile,wasile timur dan wasile 61.000
tengah
M' wasile selatan 63.000
M' maba selatan,kota maba dan 88.000
maba
M' maba tengah,maba utara dan 98.000
wasile utara
M' wasile,wasile timur dan wasile 81.000
tengah
M' wasile selatan 84.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Ex. Kerang Lembar Uk. 1 x 1 M 23.600

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Bh maba selatan,kota m 48.000
maba
Bh maba tengah,maba ut 53.000
wasile utara
Bh wasile,wasile timur 45.000
tengah
Bh wasile selatan 47.000
Bh maba selatan,kota m 69.000
maba
Bh maba tengah,maba ut 77.000
wasile utara
Bh wasile,wasile timur 64.000
tengah
Bh wasile selatan 67.000

Satuan Spesifikasi Standar Harga Satuan


Bh maba selatan,kota maba dan 45.000
maba
Bh maba tengah,maba utara dan 50.000
wasile utara
Bh wasile,wasile timur dan wasile 42.000
tengah
Bh wasile selatan 43.000

Satuan Spesifikasi Standar Harga Satuan


Hal 124 dari 240

Print Out Per-Tangga07-Oktober-2019


PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
2019
Bh maba selatan,kota m 353.000
maba
Bh maba tengah,maba ut 396.000
wasile utara
Bh wasile,wasile timur 328.000
tengah
Bh wasile selatan 340.000
Bh maba selatan,kota m 667.000
maba
Bh maba tengah,maba ut 749.000
wasile utara
Bh wasile,wasile timur 619.000
tengah
Bh wasile selatan 642.000
Bh maba selatan,kota m 294.000
maba
Bh maba tengah,maba ut 330.000
wasile utara
Bh wasile,wasile timur 273.000
tengah
Bh wasile selatan 283.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Kg maba selatan,kota m 26.000
maba
Raya Halmahera Timur Hal 125 dari 240

Print Out Per-Tanggal 07-Oktober-2019


NTAH KAB. HALMAHERA TIMUR
STANDAR HARGA BARANG DAN JASA

Kg maba tengah,maba utara dan 29,000.00


wasile utara
Kg wasile,wasile timur dan wasile 24.000
tengah
Kg wasile selatan 25.000
Lbr maba selatan,kota maba dan 660.000
maba
Lbr maba tengah,maba utara dan 741.000
wasile utara
Lbr wasile,wasile timur dan wasile 613.000
tengah
Lbr wasile selatan 635.000
Lbr maba selatan,kota maba dan 845.000
maba
Lbr maba tengah,maba utara dan 949.000
wasile utara
Lbr wasile,wasile timur dan wasile 785.000
tengah
Lbr wasile selatan 813.000
Lbr maba selatan,kota maba dan 134.000
maba
Lbr maba tengah,maba utara dan 150.000
wasile utara
Lbr wasile,wasile timur dan wasile 124.000
tengah
Lbr wasile selatan 128.000
Lbr maba selatan,kota maba dan 162.000
maba
Lbr maba tengah,maba utara dan 181.000
wasile utara
Lbr wasile,wasile timur dan wasile 151.000
tengah
Lbr wasile selatan 156.000
Lbr maba selatan,kota maba dan 191.000
maba
Lbr maba tengah,maba utara dan 214.000
wasile utara
Lbr wasile,wasile timur dan wasile 178.000
tengah
Lbr wasile selatan 184.000
Hal 126 dari 240

Bahan / WSatuan Spesifikasi Standar Harga Satuan


M3 maba selatan,kota m 4.824.000
maba
M3 maba tengah,maba ut3.618.000
wasile utara
M3 wasile,wasile timur 4.143.000
tengah
Hal 130 dari 240

Print Out Per-Tangga07-Oktober-2019


PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
Periode Tahun 2019
M3 wasile selatan 4.824.000
M3 maba selatan,kota m 4.824.000
maba
M3 maba tengah,maba ut3.618.000
wasile utara
M3 wasile,wasile timur 4.143.000
tengah
M3 wasile selatan 5.010.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


M3 maba selatan,kota m 2.512.000
maba
M3 maba tengah,maba ut 2,751,100.00
wasile utara
M3 wasile,wasile timur 2.294.000
tengah
M3 wasile selatan 3,218,000.00
M3 maba selatan,kota m 2.512.000
maba
M3 maba tengah,maba ut 2,751,100.00
wasile utara
M3 wasile,wasile timur 2.294.000
tengah
M3 wasile selatan 3.218.000
Btg maba selatan,kota m 94.000
maba
Btg maba tengah,maba ut 71,300.00
wasile utara
Btg wasile,wasile timur 72.000
tengah
Btg wasile selatan 68.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Lbr maba selatan,kota m 131.000
maba
Lbr maba tengah,maba ut 147.000
wasile utara
Lbr wasile,wasile timur 122.000
tengah
Hal 131 dari 240

Print Out Per-Tangga07-Oktober-2019


PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
2019
Lbr wasile selatan 126.000
Lbr maba selatan,kota m 191.000
maba
Lbr maba tengah,maba ut 214.000
wasile utara
Lbr wasile,wasile timur 178.000
tengah
Lbr wasile selatan 184.000
Lbr maba selatan,kota m 565.000
maba
Lbr maba tengah,maba ut 634,000.00
wasile utara
Lbr wasile,wasile timur 524.000
tengah
Lbr wasile selatan 543.000
Lbr maba selatan,kota m 567.000
maba
Lbr maba tengah,maba ut 636.000
wasile utara
Lbr wasile,wasile timur 526.000
tengah
Lbr wasile selatan 545.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Kg maba selatan,kota m 33.000
maba
Kg maba tengah,maba ut 37,000.00
wasile utara
Kg wasile,wasile timur 31.000
tengah
Kg wasile selatan 32.000
Kg maba selatan,kota m 80.000
maba
Kg maba tengah,maba ut 89.000
wasile utara
Kg wasile,wasile timur 74.000
tengah
Kg wasile selatan 77.000
Kg maba selatan,kota m 64.000
maba
Kg maba tengah,maba ut 71.000
wasile utara
Kg wasile,wasile timur 59.000
tengah
Kg wasile selatan 61.000
Hal 133 dari 240

Print Out Per-Tang07-Oktober-2019


PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
Periode Ta 2019
Kg maba selatan,kota 101.000
maba
Kg maba tengah,maba 113.000
wasile utara
Kg wasile,wasile timu 94.000
tengah
Kg wasile selatan 97.000

Merk / Model Bahan / Warna Satuan Spesifikasi StandarHarga Satuan


M' maba selatan,kota 10.000
maba
M' maba tengah,maba 11.000
wasile utara
M' wasile,wasile timu 9.000
tengah
M' wasile selatan 10.000
M' maba selatan,kota 21.000
maba
M' maba tengah,maba 23.000
wasile utara
M' wasile,wasile timu 20.000
tengah
M' wasile selatan 20.000
M' maba selatan,kota 39.000
maba
Hal 134 dari 240
Print Out Per-Tanggal 07-Oktober-2019
PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
Periode Tahun 2019
M' maba tengah,maba utara dan 43.000
wasile utara
M' wasile,wasile timur dan wasile 36.000
tengah
M' wasile selatan 37.000
M' maba selatan,kota maba dan 53.000
maba
M' maba tengah,maba utara dan 59.000
wasile utara
M' wasile,wasile timur dan wasile 49.000
tengah
M' wasile selatan 51.000

Satuan Spesifikasi Standar Harga Satuan


M maba selatan,kota maba dan 7.000
maba
M maba tengah,maba utara dan 7.000
wasile utara
M wasile,wasile timur dan wasile 6.000
tengah
M wasile selatan 6.000
M maba selatan,kota maba dan 10.000
maba
M maba tengah,maba utara dan 11.000
wasile utara
M wasile,wasile timur dan wasile 9.000
tengah
M wasile selatan 9.000
M maba selatan,kota maba dan 11.000
maba
M maba tengah,maba utara dan 12.000
wasile utara
M wasile,wasile timur dan wasile 10.000
tengah
M wasile selatan 11.000
M maba selatan,kota maba dan 33.000
maba
M maba tengah,maba utara dan 37.000
wasile utara
Hal 135 dari 240

Print Out Per-Tanggal 07-Oktober-2019


NTAH KAB. HALMAHERA TIMUR
STANDAR HARGA BARANG DAN JASA

M wasile,wasile timur dan wasile 31.000


tengah
M wasile selatan 32.000
M maba selatan,kota maba dan 26.000
maba
M maba tengah,maba utara dan 29.000
wasile utara
M wasile,wasile timur dan wasile 24.000
tengah
M wasile selatan 25.000
M maba selatan,kota maba dan 59.000
maba
M maba tengah,maba utara dan 66.000
wasile utara
M wasile,wasile timur dan wasile 55.000
tengah
M wasile selatan 57.000
M maba selatan,kota maba dan 96.000
maba
M maba tengah,maba utara dan 107.000
wasile utara
M wasile,wasile timur dan wasile 89.000
tengah
M wasile selatan 93.000
M maba selatan,kota maba dan 59.000
maba
M maba tengah,maba utara dan 66.000
wasile utara
M wasile,wasile timur dan wasile 55.000
tengah
M wasile selatan 57.000
M maba selatan,kota maba dan 96.000
maba
M maba tengah,maba utara dan 107.000
wasile utara
M wasile,wasile timur dan wasile 89.000
tengah
M wasile selatan 93.000
Hal 136 dari 240

Print Out Per-Tanggal 07-Oktober-2019


PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
Periode Tahun 2019

Satuan Spesifikasi Standar Harga Satuan


M maba selatan,kota maba dan 57.000
maba
M maba tengah,maba utara dan 64.000
wasile utara
M wasile,wasile timur dan wasile 53.000
tengah
M wasile selatan 54.000
M maba selatan,kota maba dan 94.000
maba
M maba tengah,maba utara dan 105.000
wasile utara
M wasile,wasile timur dan wasile 87.000
tengah
M wasile selatan 91.000
M maba selatan,kota maba dan 129.000
maba
M maba tengah,maba utara dan 144.000
wasile utara
M wasile,wasile timur dan wasile 120.000
tengah
M wasile selatan 124.000
M maba selatan,kota maba dan 225.000
maba
M maba tengah,maba utara dan 252.000
wasile utara
M wasile,wasile timur dan wasile 209.000
tengah
M wasile selatan 217.000
M maba selatan,kota maba dan 402.000
maba
M maba tengah,maba utara dan 451.000
wasile utara
M wasile,wasile timur dan wasile 373.000
tengah
M wasile selatan 386.000

Print Out Per-Tangga07-Oktober-2019


PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
Periode Tahun 2019

Bahan / WSatuan Spesifikasi Standar Harga Satuan


M maba selatan,kota m 49.000
maba
M maba tengah,maba ut 55.000
wasile utara
M wasile,wasile timur 45.000
tengah
M wasile selatan 47.000

M maba selatan,kota m 115.000


maba
M maba tengah,maba ut 129.000
wasile utara
M wasile,wasile timur 106.000
tengah
M wasile selatan 110.000
M maba selatan,kota m 240.000
maba
M maba tengah,maba ut 269.000
wasile utara
M wasile,wasile timur 223.000
tengah
M wasile selatan 231.000

M maba selatan,kota m 240.000


maba
M maba tengah,maba ut 269.000
wasile utara
M wasile,wasile timur 223.000
tengah
M wasile selatan 231.000

M maba selatan,kota m 240.000


maba
M maba tengah,maba ut 269.000
wasile utara
M wasile,wasile timur 223.000
tengah

Print Out Per-Tanggal 07-Oktober-2019


NTAH KAB. HALMAHERA TIMUR
STANDAR HARGA BARANG DAN JASA

M wasile selatan 231.000

M maba selatan,kota maba dan 240.000


maba
M maba tengah,maba utara dan 269.000
wasile utara
M wasile,wasile timur dan wasile 223.000
tengah
M wasile selatan 231.000
M maba selatan,kota maba dan 240.000
maba
M maba tengah,maba utara dan 269.000
wasile utara
M wasile,wasile timur dan wasile 223.000
tengah
M wasile selatan 231.000

M maba selatan,kota maba dan 291.000


maba
M maba tengah,maba utara dan 326.000
wasile utara
M wasile,wasile timur dan wasile 271.000
tengah
M wasile selatan 280.000

M maba selatan,kota maba dan 371.000


maba
M maba tengah,maba utara dan 416.000
wasile utara
M wasile,wasile timur dan wasile 345.000
tengah
M wasile selatan 357.000

M maba selatan,kota maba dan 598.000


maba
M maba tengah,maba utara dan 671.000
wasile utara
M wasile,wasile timur dan wasile 555.000
tengah
M wasile selatan 575.000

Hal 139 dari 240

Print Out Per-Tanggal 07-Oktober-2019


NTAH KAB. HALMAHERA TIMUR
STANDAR HARGA BARANG DAN JASA
M maba selatan,kota maba dan 49.000
maba
M maba tengah,maba utara dan 55.000
wasile utara
M wasile,wasile timur dan wasile 46.000
tengah
M wasile selatan 47.000

M maba selatan,kota maba dan 115.000


maba
M maba tengah,maba utara dan 129.000
wasile utara
M wasile,wasile timur dan wasile 106.000
tengah
M wasile selatan 110.000

M maba selatan,kota maba dan 240.000


maba
M maba tengah,maba utara dan 269.000
wasile utara
M wasile,wasile timur dan wasile 223.000
tengah
M wasile selatan 231.000

M maba selatan,kota maba dan 240.000


maba
M maba tengah,maba utara dan 269.000
wasile utara
M wasile,wasile timur dan wasile 223.000
tengah
M wasile selatan 231.000

M maba selatan,kota maba dan 240.000


maba
M maba tengah,maba utara dan 269.000
wasile utara
M wasile,wasile timur dan wasile 223.000
tengah
M wasile selatan 231.000
M maba selatan,kota maba dan 240.000
maba
Hal 140 dari 240

Print Out Per-Tanggal 07-Oktober-2019


PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA

M maba tengah,maba utara dan 269.000


wasile utara
M wasile,wasile timur dan wasile 223.000
tengah
M wasile selatan 231.000

M maba selatan,kota maba dan 240.000


maba
M maba tengah,maba utara dan 269.000
wasile utara
M wasile,wasile timur dan wasile 223.000
tengah
M wasile selatan 231.000

M maba selatan,kota maba dan 291.000


maba
M maba tengah,maba utara dan 326.000
wasile utara
M wasile,wasile timur dan wasile 271.000
tengah
M wasile selatan 280.000

Satuan Spesifikasi Standar Harga Satuan


M maba selatan,kota maba dan 75.000
maba
M maba tengah,maba utara dan 84.000
wasile utara
M wasile,wasile timur dan wasile 70.000
tengah
M wasile selatan 72.000
M maba selatan,kota maba dan 141.000
maba
M maba tengah,maba utara dan 158.000
wasile utara
M wasile,wasile timur dan wasile 131.000
tengah
M wasile selatan 135.000
M maba selatan,kota maba dan 209.000
maba
Hal 141 dari 240

Print Out Per-Tanggal 07-Oktober-2019


PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
Periode Tahun 2019
M maba tengah,maba utara dan 234.000
wasile utara
M wasile,wasile timur dan wasile 194.000
tengah
M wasile selatan 201.000
M maba selatan,kota maba dan 239.000
maba
M maba tengah,maba utara dan 268.000
wasile utara
M wasile,wasile timur dan wasile 222.000
tengah
M wasile selatan 230.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Bh maba selatan,kota m 63.000
maba
Bh maba tengah,maba ut 70.000
wasile utara
Bh wasile,wasile timur 59.000
tengah
Bh wasile selatan 61.000
Bh maba selatan,kota m 25.000
maba
Raya Halmahera Timur Hal 194 dari 240

Print Out Per-Tangga07-Oktober-2019


PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
2019
Bh maba tengah,maba ut 28.000
wasile utara
Bh wasile,wasile timur 24.000
tengah
Bh wasile selatan 24.000
Bh maba selatan,kota m 98.000
maba
Bh maba tengah,maba ut 110.000
wasile utara
Bh wasile,wasile timur 91.000
tengah
Bh wasile selatan 94.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Bh maba selatan,kota m 328.000
maba
Bh maba tengah,maba ut 368.000
wasile utara
Raya Halmahera Timur Hal 195 dari 240

Print Out Per-Tangga07-Oktober-2019


PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
Periode Tahun 2019
Bh wasile,wasile timur 305.000
tengah
Bh wasile selatan 316.000
Bh maba selatan,kota m 906.000
maba
Bh maba tengah,maba ut1.017.000
wasile utara
Bh wasile,wasile timur 842.000
tengah
Bh wasile selatan 872.000
Bh maba selatan,kota m 2.476.000
maba
Bh maba tengah,maba ut2.781.000
wasile utara
Bh wasile,wasile timur 2.299.000
tengah
Bh wasile selatan 2.382.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Bh maba selatan,kota m 706.000
maba
Bh maba tengah,maba ut 792.000
wasile utara
Bh wasile,wasile timur 656.000
tengah
Bh wasile selatan 679.000
Bh maba selatan,kota m 1.700.000
maba
Bh maba tengah,maba ut1.909.000
wasile utara
Bh wasile,wasile timur 1.579.000
tengah
Bh wasile selatan 1.636.000
Bh maba selatan,kota m 8.135.000
maba
Bh maba tengah,maba ut9.137.000
wasile utara
Bh wasile,wasile timur 7.555.000
tengah

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Rol Telp 2/ 100Y 1.595.000
Rol Telp 4 / 100Y 2.152.000
Rol Telp Spiral 5 m 201.800
Rol Telp Spiral 2 PC 203.900
Rol Anthena TV - 5 C/10 100.500
Rol Anthena TV - 5C 50 100.200
Rol Anthena TV - 3 C 18 99.200
Goal NYZ Rol 2 x 23 x 90 M 220.000
Hal 209 dari 240

Print Out Per-Tanggal 07-Oktober-2019


PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
Periode Tahun 2019
Rol 2 x 1,5. 50 M 530.600
Rol 2 x 2,5. 50 M 670.500
Rol 2 x 1,5. 50 M 520.200
Rol 2 x 2,5. 50 M 620.000
Rol 2 x 1,5. 50 M 670.100
Rol 2 x 2,5. 50 M 820.000
Rol 1 x 1,5. 50 M 270.000
Rol 2 x 2,5. 50 M 345.000
Rol 2 x 0,75. 50 M 220.000
Rol 110.000

Satuan Spesifikasi Standar Harga Satuan


Buah 2 MM 6 x 7 HC 27.000
Buah PVC 4 x 6 MM 29.600
Buah PVC 12 MM 39.900
Buah PVC 6 MM 6 x 37 IWRC 26.570
Buah PVC 3 x 5 24.520
Buah 8 MM 6 x 12 HC 24.940

Satuan Spesifikasi Standar Harga Satuan


Buah MMA 0,14 2 x 23 56.500
Buah 1M 23.850

Satuan Spesifikasi Standar Harga Satuan


Buah JR 6815 118.500
Buah 15 M Welto LY111 255.200
Buah 10 M 327.000
Buah 15 M 378.550
Buah 20 M 452.000
Buah 25 M 949.700
Buah 50 M 1.165.000
Buah 25 m 547.600
Raya Halmahera Timur Hal 210 dari 240

Print Out Per-Tanggal 07-Oktober-2019


NTAH KAB. HALMAHERA TIMUR
STANDAR HARGA BARANG DAN JASA

Buah 50 M 655.750
Buah LY - 112T R 99M 70.100
Buah LY - 117SK 15 M 70.000
Buah 15m Switch 70.000
Buah 10 M 79.900
Buah 25 M 74.000
Buah 10 M 160.700
Buah 10 M + Lampu 2104 152.300
Buah 15 M + Lampu 105.000
Buah 15 M + Lampu 2154 141.800
Buah 10 M 104.700
Buah 10 M + Saklar 108.000
Buah 15 M 69.900
Buah 10 M 68.000
Buah 10 M 87.000
Buah 1,5 M 50.100
Buah 5M 75.000

Satuan Spesifikasi Standar Harga Satuan


M' 1,5 mm 19.000
M' 2,5 mm 25.000
M' 4 mm 24.400
Roll Uk. 1,5 mm 535.000
Roll Uk. 2,5 mm 745.000
Roll Uk. 4 mm 955.000

Satuan Spesifikasi Standar Harga Satuan


M' 4 mm 35.000
M' 6 mm 45.500
M' 10 mm 47.300
M' Penangkal Petir 16 mm 72.000
M' Penangkal Petir 25 mm 82.000
Hal 211 dari 240
Print Out Per-Tanggal 07-Oktober-2019
PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
Periode Tahun 2019

Satuan Spesifikasi Standar Harga Satuan


Meter Uk. 2 x 10 mm 37.300
Meter Uk. 2 x 16 mm 45.000

Satuan Spesifikasi Standar Harga Satuan


Meter Uk. 2 x 2.5 mm 44.100

Satuan Spesifikasi Standar Harga Satuan


Meter Uk. 4 x 6 mm 80.100

Satuan Spesifikasi Standar Harga Satuan


Buah 3 x 0,6 MM 80.100

Satuan Spesifikasi Standar Harga Satuan


Buah 15 M 190.000
Buah 10 M 188.500

Satuan Spesifikasi Standar Harga Satuan


Meter 127.000
sure Mercury Lamps
Satuan Spesifikasi Standar Harga Satuan
Buah Hql 80 Watt Fitting 27 149.200
Buah HQL 125 Watt Fitting 27 156.000
Buah HQL 250 Watt Fitting 40 151.000
Buah HQL 400 Watt Fitting 40 110000 225.000

Satuan Spesifikasi Standar Harga Satuan


Buah Mini Dmo 3 W 26.000
Buah Switch 2001 - 008 28.300
Buah Mini Light 3 W 37.500
Hal 212 dari 240

Print Out Per-Tangga07-Oktober-2019


PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
Periode Tahun 2019

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Buah Candle 15 Watt 25.100
Buah MG 45/220 V 15 Wat 28.600
Buah MG 45/50 220 V 25 37.700
Buah C 35/E 14 Candle 10 37.300
Buah MG 45 220 V 10 Wat 27.380
Buah MG 50 22 V 40 Watt 27.480
Buah C 35/E 14 Candle 15 27.480
Buah C35/E14 Candle 25 27.480
Buah G 40 220 V 4 Watt 26.220
Buah PS 60 220V 15 Watt 30.000
Buah PS 60 220 V 25 Watt 30.000
Buah PS 60 220 V 40 Watt 35.000
Buah PS 60 x 220 V 60 Wa 35.000
Buah PS 70 220 V 10 Watt 35.000
Set BBL 2 V Eb 27 Watt 137.000
Buah PL 3 V EC 26 Watt 43.550
Essential, Philips Buah Yellow 18 W 63.500
Buah Yellow 14 W 74.000
Buah Yellow 15 W 68.700
Essential, Philips Buah Tomado 20 W 89.700
Buah Tornado 11 W 69.800
Buah Genit 5 W 65.600
Buah Genit 8 W 64.550
Buah Genit 11 W 68.750
Buah EFH 8 W 20.000
Buah EFD 9 W 22.000
Buah EFH 11 W 22.000
Buah EFD 11 W 64.550
Buah EFH 14 W 25.000
Buah Clear E - 27/ES 60 25.000
Buah Clear E - 27/ES 25 20.000
Hal 213 dari 240

Print Out Per-Tangga07-Oktober-2019


PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
Periode Tahun 2019
Buah Clear E - 14/ES 15 23.000
Buah Clear E - 27/ES 5 W 18.000
Buah Clear E - 27/ES 40 W 20.000
Buah Clear E - 27/ES 10 W 25.000
Buah Clear E - 27/ES 10 W 25.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Buah Cdl C 35 / E 14 Clea 20.000
Buah C - 35 CC 25 W 30.000
Buah Torpedo 10 W 25.000
Buah Bulat G 40 5 W 23.000
Buah Bulat G 40 Merah 5 20.000
Buah PS60 Clear 15 W 25.000
Pcs T45 / 25 W 35.000
Pcs MG50 Frost 25 W 35.000
Pcs Clear 75 W 120.000
Pcs Potore R63 / 25 W 78.750
Pcs Superlux 75 W 99.200
Pcs Softone 75 W White 125.000
Pcs Clear 40 W 74.000
Pcs Mini Softone 40 W 74.000
Pcs Cardle Clear 74.000
Pcs 60 W 90.300
Pcs Softone 60 W 95.000
Pcs T 60 Softwhite 60 W 64.500
Pcs P 560 Clear 25 W 63.600
Lampu Bohlam Capsul
Bahan / WSatuan Spesifikasi Standar Harga Satuan
Pcs SRE 60 Capsule 15 90.270
Pcs FO 2 W / Warmwhit 84.500
Pcs PL 2 VEB 9 W 70.750
Kenmaster Pcs L Hemat 10 W 70.000
Kenmaster Pcs Ken - 01 11 W 68.750
Raya Halmahera Timur Hal 214 dari 240

Print Out Per-Tanggal 07-Oktober-2019


PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
Periode Tahun 2019
Pcs Ken - 01 18 W 69.800
Pcs SRE Lamp H.Ene 20 W 66.650
Pcs 20 W 63.500
Pcs EUS 9 W / Daylight 242.000
Pcs EUS 15 W / Daylight 257.700
Pcs EUS 15 W / Daylight 263.000
Pcs EUS 20 W / Daylight 428.900
L - N" Energi
Satuan Spesifikasi Standar Harga Satuan
Buah Saving Super Comp (8000 h) 92.800
Base E 27
Buah Saving Super Comp (8000 h) 96.000
Base E 27
Buah Saving Super Comp (8000 h) 88.600
Base E 27
Buah Saving Super Comp (8000 h) 67.500
Base E 27

Satuan Spesifikasi Standar Harga Satuan


Buah S 11 Watt 11 / 14 48.700
Buah S 7 Watt 41 44.500
Buah S 5 Watt 21 / 41 49.800
Buah EL ELO 8 Watt 21 Eco 100.000
Buah EL ELO 12 Watt 41 Eco 100.000
Buah EL ELO 15 Watt 41 168.500
Buah EL ELO 23 Watt 189.500
Buah EL 60 Watt 12 116.000
Buah EL 75 Watt 16 137.000
Buah EL 100 Watt 21 147.500

Satuan Spesifikasi Standar Harga Satuan


Buah Mini Wall 1 x 8 W 200.000
Buah Flour Rescent 2 x 8 W 200.000
Buah P Handy Light 11 W 242.000
Hal 215 dari 240
Print Out Per-Tanggal 07-Oktober-2019
NTAH KAB. HALMAHERA TIMUR
STANDAR HARGA BARANG DAN JASA

Buah 1x9W 148.800


Buah 20 W 218.900
Buah 2x8W 229.800
Buah 1x9W 294.500
Buah 1x9W 300.100

Buah 2x8W 218.900


Buah 1 x20 W 373.200
Buah 2x6W 536.000
Buah 2 x 20 W 396.300
Buah 2 x 20 W 431.000

Buah 2 x 20 W 546.500
Buah 1x 20 R 378.500
Buah 1 x 20 W 441.500
Buah 389.000
Buah 384.800
Buah 20 V 533.900

Satuan Spesifikasi Standar Harga Satuan


Buah 20 Watt 12 V Esen 58.200
Buah 20 Watt 53.000
Buah 35 Watt 63.500
Buah 50 Watt 12 V Esen 68.700
Buah 50 Watt 72.900
Buah 500 Watt (Prancis) 179.000
mat Listrik
Satuan Spesifikasi Standar Harga Satuan
Buah Esential Type 82 / 86, 8 Watt 84.500
Buah Essential Type 82 / 86, 14 Watt 89.700
Buah Essential Type 82 / 86, 18 Watt 95.000
Buah Type PL - S 82 / 84 / 86, 5 Watt 63.500
Buah Type PL - S 82 / 84 / 86, 7 Watt 68.700
Hal 216 dari 240
Print Out Per-Tangga07-Oktober-2019
PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
Periode Tahun 2019
Buah Type PL - S 82 / 84 / 69.800
Buah Type PL - S 82 / 84 / 74.000
Buah Type PL - C 82 / 84 / 74.000
Buah Type PL - C 82 / 84 / 79.200
Buah Type PL - C 82 / 84 / 72.900

Bahan / WSatuan Spesifikasi Standar Harga Satuan


1052 A / FAN Buah 220 V 95.000
1052 A / FAN Buah DV 95.000
Buah Tanpa TL/220 V Mp 120.000
Buah Tanpa TL / 220 V 125.000
YS - 901C DOP (220 V) 96.000
Mps
YS - 901C Buah DOP 110 (220 V) 114.900

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Philips, HPLN Buah 50 Watt 163.200
Philips, HPLN Buah 80 Watt 200.200
Philips, HPLN Buah 125 Watt 242.000
Philips, HPLN Buah 250 Watt 300.900
Philips, HPLN Buah 400 Watt 395.300

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Philips, HPIT Buah 250 Watt 400.500
Philips, HPIT Buah 400 Watt 429.700
Lampu Pijar Umum
Bahan / WSatuan Spesifikasi Standar Harga Satuan
Buah 10/15 Watt E - 27 Cla 25.000
Buah 25/40 Watt E - 27 A 25.000
Buah 29 wat E - 27 Classi 35.000
Osram R - 63 / E - Buah 40 Watt 40.000

Concentra 75.050
Hal 217 dari 240
Print Out Per-Tangga07-Oktober-2019
PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
Periode Tahun 2019
Buah Clear 10 Watt 47.200
Buah Clear 100 Watt 150.000
Buah Clear 15 watt 37.200
Buah Clear 150 Watt 180.000
Buah Clear 200 Watt 200.300
Buah Clear 25 Watt 64.100
Buah Clear 40 Watt 75.150
Buah Clear 60 Watt 86.500
Buah Clear 75 Watt 98.750
Buah Softone White T 60 135.000
Buah Softone White T 60 94.500
Buah Softone White T 60 130.000
Buah Softone White T 60 140.000
Buah Softone White T60 7 145.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Buah 200Watt 120.000
Buah 60 Watt 80.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


GML - 2040 Buah 110V / 220V + Trav 185.800
GML - 2040 Buah 110V / 220V +TT 157.500
GML - 500 Buah + TL (Maspion, Halo 263.500
240V)
MDL - 906 Buah (220V) Mps 136.500
MDL - 906 Buah (110V / 220V) 162.700
MDL - 903 N Buah N (220V) Mps 189.000
MDL - 903 B Buah (220 V) Mps 189.000
MDl - 905 Buah ( 220 V ) 183.750
MDL - 903 B Buah ( 110V / 220V ) 178.200

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Hal 218 dari 240
Print Out Per-Tangga07-Oktober-2019
PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
2019
Bh maba selatan,kota m 75.000
maba
Bh maba tengah,maba ut 84.000
wasile utara
Bh wasile,wasile timur 69.000
tengah
Bh wasile selatan 72.000
Bh maba selatan,kota m 48.000
maba
Bh maba tengah,maba ut 53.000
wasile utara
Bh wasile,wasile timur 45.000
tengah
Bh wasile selatan 46.000
Bh maba selatan,kota m 90.000
maba
Bh maba tengah,maba ut 101.000
wasile utara
Bh wasile,wasile timur 84.000
tengah
Bh wasile selatan 87.000
Bh maba selatan,kota m 3.664.000
maba
Bh maba tengah,maba ut4.115.000
wasile utara
Bh wasile,wasile timur 3.402.000
tengah
Bh wasile selatan 3.524.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Bh maba selatan,kota m 90.000
maba
Bh maba tengah,maba ut 101.000
wasile utara
Bh wasile,wasile timur 84.000
tengah
Bh wasile selatan 87.000
Bh maba selatan,kota m 175.000
maba
Hal 219 dari 240

Print Out Per-Tangga07-Oktober-2019


PEMERINTAH KAB. HALMAHERA TIMUR
DAFTAR STANDAR HARGA BARANG DAN JASA
2019
Bh maba tengah,maba ut 196.000
wasile utara
Bh wasile,wasile timur 163.000
tengah
Bh wasile selatan 169.000
Bh maba selatan,kota m 175.000
maba
Bh maba tengah,maba ut 196.000
wasile utara
Bh wasile,wasile timur 163.000
tengah
Bh wasile selatan 169.000
Bh maba selatan,kota m 525.000
maba
Bh maba tengah,maba ut 589.000
wasile utara
Bh wasile,wasile timur 487.000
tengah
Bh wasile selatan 505.000
Bh maba selatan,kota m 378.000
maba
Bh maba tengah,maba ut 424.000
wasile utara
Bh wasile,wasile timur 351.000
tengah
Bh wasile selatan 364.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Bh maba selatan,kota m 40.000
maba
Bh maba tengah,maba ut 44.000
wasile utara
Bh wasile,wasile timur 38.000
tengah
Bh wasile selatan 39.000
Bh maba selatan,kota m 40.000
maba
Bh maba tengah,maba ut 44.000
wasile utara
Raya Halmahera Timur Hal 220 dari 240

Print Out Per-Tanggal 07-Oktober-2019


NTAH KAB. HALMAHERA TIMUR
STANDAR HARGA BARANG DAN JASA

Bh wasile,wasile timur dan wasile 38.000


tengah
Bh wasile selatan 39.000
Bh maba selatan,kota maba dan 463.000
maba
Bh maba tengah,maba utara dan 520.000
wasile utara
Bh wasile,wasile timur dan wasile 430.000
tengah
Bh wasile selatan 446.000
Bh maba selatan,kota maba dan 68.000
maba
Bh maba tengah,maba utara dan 76.000
wasile utara
Bh wasile,wasile timur dan wasile 63.000
tengah
Bh wasile selatan 65.000
Bh maba selatan,kota maba dan 136.000
maba
Bh maba tengah,maba utara dan 152.000
wasile utara
Bh wasile,wasile timur dan wasile 126.000
tengah
Bh wasile selatan 131.000
Bh maba selatan,kota maba dan 40.000
maba
Bh maba tengah,maba utara dan 44.000
wasile utara
Bh wasile,wasile timur dan wasile 38.000
tengah
Bh wasile selatan 39.000
Bh maba selatan,kota maba dan 68.000
maba
Bh maba tengah,maba utara dan 76.000
wasile utara
Bh wasile,wasile timur dan wasile 63.000
tengah
Bh wasile selatan 65.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Buah 250 W 760.600

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Bh maba selatan,kota m 18.000
maba
Bh maba tengah,maba ut 20.000
wasile utara
Bh wasile,wasile timur 17.000
tengah
Bh wasile selatan 17.000

Bahan / WSatuan Spesifikasi Standar Harga Satuan


Liter maba tengah,maba ut 60.00
Kg maba tengah,maba ut 30,000.00
Liter maba tengah,maba ut 13,000.00
Kg maba tengah,maba ut 7,200.00

a dan Sewa

Satuan Spesifikasi Standar Harga Satuan


OH maba selatan,kota maba dan 169.400
maba
OH maba tengah,maba utara dan 169,400.00
wasile utara
OH wasile,wasile timur dan wasile 169.400
tengah
OH wasile selatan 169.000
OH maba selatan,kota maba dan 151.821
maba
OH maba tengah,maba utara dan 151,821.00
wasile utara
OH wasile,wasile timur dan wasile 151.821
tengah
OH wasile selatan 151.000
OH maba selatan,kota maba dan 139.036
maba Kayu,Batu , Besi , Pipa &
Cat
OH maba tengah,maba utara dan 139,036.00
wasile utara Kayu,Batu , Besi ,
Pipa & Cat
OH wasile,wasile timur dan wasile 139.036
tengah Kayu,Batu , Besi , Pipa &
Cat
OH wasile selatan Kayu,Batu , Besi , 139.000
Pipa & Cat
OH maba selatan,kota maba dan 122.895
maba Kayu,Batu , Besi , Pipa &
Cat
OH maba tengah,maba utara dan 122.895
wasile utara Kayu,Batu , Besi ,
Pipa & Cat
OH wasile,wasile timur dan wasile 122.895
tengah Kayu,Batu , Besi , Pipa &
Cat
Hal 237 dari 240

Print Out Per-Tanggal 07-Oktober-2019


NTAH KAB. HALMAHERA TIMUR
STANDAR HARGA BARANG DAN JASA
OH wasile selatan Kayu,Batu , Besi , 122.000
Pipa & Cat
OH maba selatan,kota maba dan 103.877
maba
OH maba tengah,maba utara dan 103,877.00
wasile utara
OH wasile,wasile timur dan wasile 103.877
tengah
OH wasile selatan 103.000
07-Oktober-2019

Harga Satuan

Hal 134 dari 240


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
BIDANG CIPTA KARYA

HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
1 A.2.2.1.2 1 M Pagar Sementara dari Seng Gelombang Tinggi 2,00 m
A TENAGA 60,800.00
L.01 0.200 OH Pekerja 80,000.00 16,000.00
L.02 0.400 OH Tukang Kayu 100,000.00 40,000.00
L.03 0.020 OH Kepala Tukang 120,000.00 2,400.00
L.04 0.020 OH Mandor 120,000.00 2,400.00
B BAHAN 217,275.00
1.250 Btg Kayu Dolken diameter 8 - 10 / 400 cm 6,000.00 7,500.00
2.500 Kg Portland Semen 1,400.00 3,500.00
1.200 Lbr Seng Gelombang 3" - 5" 43,000.00 51,600.00
0.005 M3 Pasir Beton 95,000.00 475.00
0.009 M3 Koral Beton 350,000.00 3,150.00
0.072 M3 Kayu Balok Kelas III/Bouwplank 1,800,000.00 129,600.00
0.060 Kg Paku Biasa 2" - 5" 20,000.00 1,200.00
0.450 Kg Meni Besi 45,000.00 20,250.00
C PERALATAN
D Jumlah A + B + C 278,075.00
E Overhead & Profit 10% 27,807.50
F Harga Satuan Pekerjaan (D+E) 305,882.50

2 A.2.2.1.4 1 M Pengukuran dan Pemasangan Bouwplank


A TENAGA 26,656.51
L.01 0.100 OH Pekerja 103,877.00 10,387.70
L.02 0.100 OH Tukang Kayu 139,036.00 13,903.60
L.03 0.010 OH Kepala Tukang 151,821.00 1,518.21
L.04 0.005 OH Mandor 169,400.00 847.00
B BAHAN 53,010.90
0.012 M3 Kayu Balok Kelas II/Bouwplank 2,751,100.00 33,013.20
0.020 Kg Paku Biasa 2" - 5" 37,000.00 740.00
0.007 M3 Kayu Papan Kelas II/Bouwplank 2,751,100.00 19,257.70
C PERALATAN
D Jumlah A + B + C 79,667.41
E Overhead & Profit 10% 7,966.74
F Harga Satuan Pekerjaan (D+E) 87,634.15

3 A.2.2.1.9 1 M2 Membersihkan Lapangan dan Perataan


A TENAGA 14,000.00
L.01 0.100 OH Pekerja 80,000.00 8,000.00
L.04 0.050 OH Mandor 120,000.00 6,000.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 14,000.00
E Overhead & Profit 10% 1,400.00
F Harga Satuan Pekerjaan (D+E) 15,400.00

4 A.2.2.1.13 1 M3 Bongkaran Beton Bertulang


A TENAGA 1,146,640.00
L.01 13.334 OH Pekerja 80,000.00 1,066,720.00
L.04 0.666 OH Mandor 120,000.00 79,920.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 1,146,640.00
E Overhead & Profit 10% 114,664.00
F Harga Satuan Pekerjaan (D+E) 1,261,304.00
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
5 A.2.2.1.14 1 M3 Bongkaran Dinding Tembok Bata Merah
B TENAGA 573,320.00
L.01 6.667 OH Pekerja 80,000.00 533,360.00
L.04 0.333 OH Mandor 120,000.00 39,960.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 573,320.00
E Overhead & Profit 10% 57,332.00
F Harga Satuan Pekerjaan (D+E) 630,652.00
G Harga Satuan Pekerjaan Per M2 6,306.52
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
1 A.2.3.1.1 1 M3 Menggali Tanah Biasa Sedalam 1 m
A TENAGA 82,142.75
L.01 0.750 OH Pekerja 103,877.00 77,907.75
L.04 0.025 OH Mandor 169,400.00 4,235.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 82,142.75
E Overhead & Profit 10% 8,214.28
F Harga Satuan Pekerjaan (D+E) 90,357.03

2 A.2.3.1.2 1 M3 Menggali Tanah Biasa Sedalam 2 m


A TENAGA 77,400.00
L.01 0.900 OH Pekerja 80,000.00 72,000.00
L.04 0.045 OH Mandor 120,000.00 5,400.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 77,400.00
E Overhead & Profit 10% 7,740.00
F Harga Satuan Pekerjaan (D+E) 85,140.00

3 A.2.3.1.3 1 M3 Menggali Tanah Biasa Sedalam 3 m


A TENAGA 92,040.00
L.01 1.050 OH Pekerja 80,000.00 84,000.00
L.04 0.067 OH Mandor 120,000.00 8,040.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 92,040.00
E Overhead & Profit 10% 9,204.00
F Harga Satuan Pekerjaan (D+E) 101,244.00

4 A.2.3.1.6 1 M3 Menggali Tanah Lumpur Sedalam 1 m


A TENAGA 101,400.00
L.01 1.200 OH Pekerja 80,000.00 96,000.00
L.04 0.045 OH Mandor 120,000.00 5,400.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 101,400.00
E Overhead & Profit 10% 10,140.00
F Harga Satuan Pekerjaan (D+E) 111,540.00

5 A.2.3.1.7 1 M2 Mengerjakan Striping Tebing Setinggi 1 m


A TENAGA 4,600.00
L.01 0.050 OH Pekerja 80,000.00 4,000.00
L.04 0.005 OH Mandor 120,000.00 600.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 4,600.00
E Overhead & Profit 10% 460.00
F Harga Satuan Pekerjaan (D+E) 5,060.00

6 A.2.3.1.8 1 M3 Membuang Tanah Sejauh 30 m'


A TENAGA 27,600.00
L.01 0.330 OH Pekerja 80,000.00 26,400.00
L.04 0.010 OH Mandor 120,000.00 1,200.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 27,600.00
E Overhead & Profit 10% 2,760.00
F Harga Satuan Pekerjaan (D+E) 30,360.00
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
7 A.2.3.1.9 1 M3 Pengurugan Kembali Galian Tanah
Pengurugan 1/3 Galian Tanah
A TENAGA 27,380.92
L.01 0.250 OH Pekerja 103,877.00 25,969.25
L.04 0.0083 OH Mandor 169,400.00 1,411.67
B BAHAN
C PERALATAN
D Jumlah A + B + C 27,380.92
E Overhead & Profit 10% 2,738.09
F Harga Satuan Pekerjaan (D+E) 30,119.01

8 A.2.3.1.10 1 M3 Pemadatan Tanah (per 20 cm)


A TENAGA 46,000.00
L.01 0.500 OH Pekerja 80,000.00 40,000.00
L.04 0.050 OH Mandor 120,000.00 6,000.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 46,000.00
E Overhead & Profit 10% 4,600.00
F Harga Satuan Pekerjaan (D+E) 50,600.00

9 Modified 1 M3 Urugan Tanah Didatangkan (Pemadatan 20 cm)


OH Mandor 67,000.00
L.01 0.750 OH Pekerja 80,000.00 60,000.00
L.04 0.058 OH Mandor 120,000.00 7,000.00
D Jumlah A + B + C 78,000.00
1.2 M3 Tanah Urug 65,000.00 78,000.00
C PERALATAN
D Harga Satuan Pekerjaan (D+E) 145,000.00
E Overhead & Profit 10% 14,500.00
F Harga Satuan Pekerjaan (D+E) 159,500.00

10 A.2.3.1.11 1 M3 Urugan Pasir


A TENAGA 32,857.10
L.01 0.300 OH Pekerja 103,877.00 31,163.10
L.04 0.010 OH Mandor 169,400.00 1,694.00
B BAHAN 548,520.00
1.2 M3 Pasir Urug 457,100.00 548,520.00
C PERALATAN
D Jumlah A + B + C 581,377.10
E Overhead & Profit 10% 58,137.71
F Harga Satuan Pekerjaan (D+E) 639,514.81

11 A.2.3.1.14 1 M3 Mengurug Sirtu Padat


A TENAGA 23,000.00
L.01 0.250 OH Pekerja 80,000.00 20,000.00
L.04 0.025 OH Mandor 120,000.00 3,000.00
B BAHAN 252,000.00
1.2 M3 Sirtu 210,000.00 252,000.00
C PERALATAN
D Jumlah A + B + C 275,000.00
E Overhead & Profit 10% 27,500.00
F Harga Satuan Pekerjaan (D+E) 302,500.00
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 1 M3 Pemasangan Pondasi Batu Belah 1SP : 3 PP
A TENAGA 213,000.00
L.01 1.500 OH Pekerja 80,000.00 120,000.00
L.02 0.750 OH Tukang Batu 100,000.00 75,000.00
L.03 0.075 OH Kepala Tukang 120,000.00 9,000.00
L.04 0.075 OH Mandor 120,000.00 9,000.00
B BAHAN 712,875.00
1.200 M3 Batu Belah 320,000.00 384,000.00
202.000 Kg Portland Cement 1,400.00 282,800.00
0.485 M3 Pasir Pasang 95,000.00 46,075.00
C PERALATAN
D Jumlah A + B + C 925,875.00
E Overhead & Profit 10% 92,587.50
F Harga Satuan Pekerjaan (D+E) 1,018,462.50

2 A.3.2.1.2 1 M3 Pemasangan Pondasi Batu Belah 1SP : 4 PP


A TENAGA 213,000.00
L.01 1.500 OH Pekerja 80,000.00 120,000.00
L.02 0.750 OH Tukang Batu 100,000.00 75,000.00
L.03 0.075 OH Kepala Tukang 120,000.00 9,000.00
L.04 0.075 OH Mandor 120,000.00 9,000.00
B BAHAN 661,600.00
1.200 M3 Batu Belah 320,000.00 384,000.00
163.000 M3 Portland Cement 1,400.00 228,200.00
0.520 M3 Pasir Pasang 95,000.00 49,400.00
C PERALATAN
D Jumlah A + B + C 874,600.00
E Overhead & Profit 10% 87,460.00
F Harga Satuan Pekerjaan (D+E) 962,060.00

3 A.3.2.1.9 1 M3 Pemasang Batu Kosong/Anstamping


A TENAGA 110,760.00
L.01 0.780 OH Pekerja 80,000.00 62,400.00
L.02 0.390 OH Tukang Batu 100,000.00 39,000.00
L.03 0.039 OH Kepala Tukang 120,000.00 4,680.00
L.04 0.039 OH Mandor 120,000.00 4,680.00
B BAHAN 420,720.00
1.200 M3 Batu Belah 320,000.00 384,000.00
0.432 M3 Pasir Urug 85,000.00 36,720.00
C PERALATAN
D Jumlah A + B + C 531,480.00
E Overhead & Profit 10% 53,148.00
F Harga Satuan Pekerjaan (D+E) 584,628.00

4 Modified 1 M3 Pemasangan Pondasi Batu Bata ad. 1 SP : 3 PP


A TENAGA 491,259.10
L.01 3.000 OH Pekerja 103,877.00 311,631.00
L.02 1.000 OH Tukang Batu 139,036.00 139,036.00
L.03 0.100 OH Kepala Tukang 151,821.00 15,182.10
L.04 0.150 OH Mandor 169,400.00 25,410.00
B BAHAN 1,558,428.00
700.000 Bh Batu Bata 1,300.00 910,000.00
143.700 Kg Portland Cement 3,240.00 465,588.00
0.400 M3 Pasir Pasang 457,100.00 182,840.00
C PERALATAN
D Jumlah A + B + C 2,049,687.10
E Overhead & Profit 10% 204,968.71
F Harga Satuan Pekerjaan (D+E) 2,254,655.81
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
IV A.4.1.1 HARGA SATUAN PEKERJAAN B E T O N
1 A.4.1.1.1 1 M3 Membuat Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c = 0,87
A TENAGA 172,820.00
L.01 1.650 OH Pekerja 80,000.00 132,000.00
L.02 0.275 OH Tukang Batu 100,000.00 27,500.00
L.03 0.028 OH Kepala Tukang 120,000.00 3,360.00
L.04 0.083 OH Mandor 120,000.00 9,960.00
B BAHAN 674,517.86
247.000 Kg Portland Semen 1,400.00 345,800.00
0.621 M3 Pasir Beton 95,000.00 58,967.86
0.740 M3 Kerikil (maksimum 30 mm) 350,000.00 259,000.00
215.000 Ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 847,337.86
E Overhead & Profit 10% 84,733.79
F Harga Satuan Pekerjaan (D+E) 932,071.64

2 A.4.1.1.2 1 M3 Membuat Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78
A TENAGA 172,820.00
L.01 1.650 OH Pekerja 80,000.00 132,000.00
L.02 0.275 OH Tukang Batu 100,000.00 27,500.00
L.03 0.028 OH Kepala Tukang 120,000.00 3,360.00
L.04 0.083 OH Mandor 120,000.00 9,960.00
B BAHAN 715,706.08
276.000 Kg Portland Semen 1,400.00 386,400.00
0.591 M3 Pasir Beton 95,000.00 56,185.71
0.750 M3 Kerikil (maksimum 30 mm) 350,000.00 262,370.37
215.000 Ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 888,526.08
E Overhead & Profit 10% 88,852.61
F Harga Satuan Pekerjaan (D+E) 977,378.69

3 A.4.1.1.3 1 M3 Membuat Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm, w/c = 0,72
A TENAGA 172,820.00
L.01 1.650 OH Pekerja 80,000.00 132,000.00
L.02 0.275 OH Tukang Batu 100,000.00 27,500.00
L.03 0.028 OH Kepala Tukang 120,000.00 3,360.00
L.04 0.083 OH Mandor 120,000.00 9,960.00
B BAHAN 747,234.52
299.000 Kg Portland Semen 1,400.00 418,600.00
0.571 M3 Pasir Beton 95,000.00 54,217.86
0.753 M3 Kerikil (maksimum 30 mm) 350,000.00 263,666.67
215.000 Ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 920,054.52
E Overhead & Profit 10% 92,005.45
F Harga Satuan Pekerjaan (D+E) 1,012,059.98

4 A.4.1.1.4 1 M3 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,87
A TENAGA 165,660.02
L.01 1.200 OH Pekerja 103,877.00 124,652.40
L.02 0.200 OH Tukang Batu 139,036.00 27,807.20
L.03 0.020 OH Kepala Tukang 151,821.00 3,036.42
L.04 0.060 OH Mandor 169,400.00 10,164.00
B BAHAN 1,517,761.17
230.000 Kg Portland Semen 3,240.00 745,200.00
0.638 M3 Pasir Beton 457,100.00 291,564.50
0.761 M3 Kerikil (maksimum 30 mm) 616,500.00 468,996.67
200.000 Ltr Air 60.00 12,000.00
C PERALATAN
D Jumlah A + B + C 1,683,421.19
E Overhead & Profit 10% 168,342.12
F Harga Satuan Pekerjaan (D+E) 1,851,763.31
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
IV A.4.1.1 HARGA SATUAN PEKERJAAN B E T O N
5 A.4.1.1.5 1 M3 Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66
A TENAGA 227,943.14
L.01 1.650 OH Pekerja 103,877.00 171,397.05
L.02 0.275 OH Tukang Batu 139,036.00 38,234.90
L.03 0.028 OH Kepala Tukang 151,821.00 4,250.99
L.04 0.083 OH Mandor 169,400.00 14,060.20
B BAHAN 1,787,190.00
326.000 Kg Portland Semen 3,240.00 1,056,240.00
0.543 M3 Pasir Beton 457,100.00 248,140.00
0.762 M3 Kerikil (maksimum 30 mm) 616,500.00 469,910.00
215.000 Ltr Air 60.00 12,900.00
C PERALATAN
D Jumlah A + B + C 2,015,133.14
E Overhead & Profit 10% 201,513.31
F Harga Satuan Pekerjaan (D+E) 2,216,646.45

6 A.4.1.1.6 1 M3 Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm, w/c = 0,61
A TENAGA 172,820.00
L.01 1.650 OH Pekerja 80,000.00 132,000.00
L.02 0.275 OH Tukang Batu 100,000.00 27,500.00
L.03 0.028 OH Kepala Tukang 120,000.00 3,360.00
L.04 0.083 OH Mandor 120,000.00 9,960.00
B BAHAN 896,820.24
352.000 Kg Portland Semen 1,400.00 492,800.00
0.522 M3 Pasir Beton 95,000.00 49,603.57
0.764 M3 Split 450,000.00 343,666.67
215.000 Ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 1,069,640.24
E Overhead & Profit 10% 106,964.02
F Harga Satuan Pekerjaan (D+E) 1,176,604.26

7 A.4.1.1.7 1 M3 Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58
A TENAGA 172,820.00
L.01 1.650 OH Pekerja 80,000.00 132,000.00
L.02 0.275 OH Tukang Batu 100,000.00 27,500.00
L.03 0.028 OH Kepala Tukang 120,000.00 3,360.00
L.04 0.083 OH Mandor 120,000.00 9,960.00
B BAHAN 926,514.29
371.000 Kg Portland Semen 1,400.00 519,400.00
0.499 M3 Pasir Beton 95,000.00 47,364.29
0.776 M3 Split 450,000.00 349,000.00
215.000 Ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 1,099,334.29
E Overhead & Profit 10% 109,933.43
F Harga Satuan Pekerjaan (D+E) 1,209,267.71

8 A.4.1.1.8 1 M3 Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56
A TENAGA 172,820.00
L.01 1.650 OH Pekerja 80,000.00 132,000.00
L.02 0.275 OH Tukang Batu 100,000.00 27,500.00
L.03 0.028 OH Kepala Tukang 120,000.00 3,360.00
L.04 0.083 OH Mandor 120,000.00 9,960.00
B BAHAN 941,640.48
384.000 Kg Portland Semen 1,400.00 537,600.00
0.494 M3 Pasir Beton 95,000.00 46,957.14
0.770 M3 Split 450,000.00 346,333.33
215.000 Ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 1,114,460.48
E Overhead & Profit 10% 111,446.05
F Harga Satuan Pekerjaan (D+E) 1,225,906.52
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
IV A.4.1.1 HARGA SATUAN PEKERJAAN B E T O N
9 A.4.1.1.9 1 M3 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum (12±2)cm, w/c = 0,53
A TENAGA 172,820.00
L.01 1.650 OH Pekerja 80,000.00 132,000.00
L.02 0.275 OH Tukang Batu 100,000.00 27,500.00
L.03 0.028 OH Kepala Tukang 120,000.00 3,360.00
L.04 0.083 OH Mandor 120,000.00 9,960.00
B BAHAN 967,564.29
406.000 Kg Portland Semen 1,400.00 568,400.00
0.489 M3 Pasir Beton 95,000.00 46,414.29
0.760 M3 Split 450,000.00 342,000.00
215.000 Ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 1,140,384.29
E Overhead & Profit 10% 114,038.43
F Harga Satuan Pekerjaan (D+E) 1,254,422.71

10 A.4.1.1.10 1 M3 Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52
A TENAGA 172,820.00
L.01 1.650 OH Pekerja 80,000.00 132,000.00
L.02 0.275 OH Tukang Batu 100,000.00 27,500.00
L.03 0.028 OH Kepala Tukang 120,000.00 3,360.00
L.04 0.083 OH Mandor 120,000.00 9,960.00
B BAHAN 975,494.05
413.000 Kg Portland Semen 1,400.00 578,200.00
0.486 M3 Pasir Beton 95,000.00 46,210.71
0.756 M3 Split 450,000.00 340,333.33
215.000 Ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 1,148,314.05
E Overhead & Profit 10% 114,831.40
F Harga Satuan Pekerjaan (D+E) 1,263,145.45

11 A.4.1.1.11 1 M3 Membuat Beton mutu f'c=28,8 MPa (K325), slum (12±2)cm, w/c = 0,49
A TENAGA 219,800.00
L.01 2.100 OH Pekerja 80,000.00 168,000.00
L.02 0.350 OH Tukang Batu 100,000.00 35,000.00
L.03 0.035 OH Kepala Tukang 120,000.00 4,200.00
L.04 0.105 OH Mandor 120,000.00 12,600.00
B BAHAN 1,006,147.62
439.000 Kg Portland Semen 1,400.00 614,600.00
0.479 M3 Pasir Beton 95,000.00 45,464.29
0.745 M3 Split 450,000.00 335,333.33
215.000 Ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 1,225,947.62
E Overhead & Profit 10% 122,594.76
F Harga Satuan Pekerjaan (D+E) 1,348,542.38

12 A.4.1.1.12 1 M3 Membuat Beton mutu f'c=31,2 MPa (K350), slum (12±2)cm, w/c = 0,48
A TENAGA 219,800.00
L.01 2.100 OH Pekerja 80,000.00 168,000.00
L.02 0.350 OH Tukang Batu 100,000.00 35,000.00
L.03 0.035 OH Kepala Tukang 120,000.00 4,200.00
L.04 0.105 OH Mandor 120,000.00 12,600.00
B BAHAN 1,016,544.05
448.000 Kg Portland Semen 1,400.00 627,200.00
0.476 M3 Pasir Beton 95,000.00 45,260.71
0.741 M3 Split 450,000.00 333,333.33
215.000 Ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 1,236,344.05
E Overhead & Profit 10% 123,634.40
F Harga Satuan Pekerjaan (D+E) 1,359,978.45
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
IV A.4.1.1 HARGA SATUAN PEKERJAAN B E T O N
13 A.4.1.1.17a 10 Kg Pembesian dg Besi Polos
A TENAGA 18,744.26
L.01 0.070 OH Pekerja 103,877.00 7,271.39
L.02 0.070 OH Tukang Besi 139,036.00 9,732.52
L.03 0.007 OH Kepala Tukang 151,821.00 1,062.75
L.04 0.004 OH Mandor 169,400.00 677.60
B BAHAN 309,000.00
10.500 Kg Besi Beton Polos 29,000.00 304,500.00
0.150 Kg Kawat Beton 30,000.00 4,500.00
C PERALATAN
D Jumlah A + B + C 327,744.26
E Overhead & Profit 10% 32,774.43
F Harga Satuan Pekerjaan (D+E) 360,518.68

14 A.4.1.1.17b 10 Kg Pembesian dg Besi Ulir


A TENAGA 13,920.00
L.01 0.070 OH Pekerja 80,000.00 5,600.00
L.02 0.070 OH Tukang Besi 100,000.00 7,000.00
L.03 0.007 OH Kepala Tukang 120,000.00 840.00
L.04 0.004 OH Mandor 120,000.00 480.00
B BAHAN 128,925.00
10.500 Kg Besi Beton Ulir 12,000.00 126,000.00
0.150 Kg Kawat Beton 19,500.00 2,925.00
C PERALATAN
D Jumlah A + B + C 142,845.00
E Overhead & Profit 10% 14,284.50
F Harga Satuan Pekerjaan (D+E) 157,129.50

15 A.4.1.1.19 10 Kg Pemasangan Jaring Kawat Baja (Wiremesh)


A TENAGA 7,620.00
L.01 0.025 OH Pekerja 80,000.00 2,000.00
L.02 0.025 OH Tukang Besi 100,000.00 2,500.00
L.03 0.025 OH Kepala Tukang 120,000.00 3,000.00
L.04 0.001 OH Mandor 120,000.00 120.00
B BAHAN 102,975.00
10.20 Kg Wiremesh 10,000.00 102,000.00
0.050 Kg Kawat Beton 19,500.00 975.00
C PERALATAN
D Jumlah A + B + C 110,595.00
E Overhead & Profit 10% 11,059.50
F Harga Satuan Pekerjaan (D+E) 121,654.50

16 A.4.1.1.20 1 M2 Memasang Bekisting untuk Pondasi


A TENAGA 73,840.00
L.01 0.520 OH Pekerja 80,000.00 41,600.00
L.02 0.260 OH Tukang Kayu 100,000.00 26,000.00
L.03 0.026 OH Kepala Tukang 120,000.00 3,120.00
L.04 0.026 OH Mandor 120,000.00 3,120.00
B BAHAN 79,000.00
0.040 M3 Kayu Papan Klas III/Bekisting 1,800,000.00 72,000.00
0.300 Kg Paku Biasa 2" - 5" 20,000.00 6,000.00
0.100 Ltr Minyak Bekisting 10,000.00 1,000.00
C PERALATAN
D Jumlah A + B + C 152,840.00
E Overhead & Profit 10% 15,284.00
F Harga Satuan Pekerjaan (D+E) 168,124.00

17 A.4.1.1.21 1 M2 Memasang Bekisting untuk Sloof


A TENAGA 98,517.15
L.01 0.520 OH Pekerja 103,877.00 54,016.04
L.02 0.260 OH Tukang Kayu 139,036.00 36,149.36
L.03 0.026 OH Kepala Tukang 151,821.00 3,947.35
L.04 0.026 OH Mandor 169,400.00 4,404.40
B BAHAN 136,199.50
0.045 M3 Kayu Papan Klas III/Bekisting 2,751,100.00 123,799.50
0.300 Kg Paku Biasa 2" - 5" 37,000.00 11,100.00
0.100 Ltr Minyak Bekisting 13,000.00 1,300.00
C PERALATAN
D Jumlah A + B + C 234,716.65
E Overhead & Profit 10% 23,471.66
F Harga Satuan Pekerjaan (D+E) 258,188.31
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
IV A.4.1.1 HARGA SATUAN PEKERJAAN B E T O N
18 A.4.1.1.22 1 M2 Memasang Bekisting untuk Kolom
A TENAGA 125,040.99
L.01 0.660 OH Pekerja 103,877.00 68,558.82
L.02 0.330 OH Tukang Kayu 139,036.00 45,881.88
L.03 0.033 OH Kepala Tukang 151,821.00 5,010.09
L.04 0.033 OH Mandor 169,400.00 5,590.20
B BAHAN 533,210.50
0.040 M3 Kayu Papan Klas III/Bekisting 2,751,100.00 110,044.00
0.400 Kg Paku Biasa 2" - 5" 37,000.00 14,800.00
0.200 Ltr Minyak Bekisting 13,000.00 2,600.00
0.015 M3 Kayu Balok Klas II/Bekisting 2,751,100.00 41,266.50
0.350 Lbr Multiplek Tebal 9 mm 634,000.00 221,900.00
2.000 Btg Dolken Kayu diameter 8 - 10 cm / 4 m 71,300.00 142,600.00
C PERALATAN
D Jumlah A + B + C 658,251.49
E Overhead & Profit 10% 65,825.15
F Harga Satuan Pekerjaan (D+E) 724,076.64

19 A.4.1.1.23 1 M2 Memasang Bekisting untuk Balok


A TENAGA 93,720.00
L.01 0.660 OH Pekerja 80,000.00 52,800.00
L.02 0.330 OH Tukang Kayu 100,000.00 33,000.00
L.03 0.033 OH Kepala Tukang 120,000.00 3,960.00
L.04 0.033 OH Mandor 120,000.00 3,960.00
B BAHAN 177,150.00
0.040 M3 Kayu Papan Klas III/Bekisting 1,800,000.00 72,000.00
0.400 Kg Paku Biasa 2" - 5" 20,000.00 8,000.00
0.200 Ltr Minyak Bekisting 10,000.00 2,000.00
0.018 M3 Kayu Balok Klas II/Bekisting 2,500,000.00 45,000.00
0.350 Lbr Multiplek Tebal 9 mm 109,000.00 38,150.00
2.000 Btg Dolken Kayu diameter 8 - 10 cm / 4 m 6,000.00 12,000.00
C PERALATAN
D Jumlah A + B + C 270,870.00
E Overhead & Profit 10% 27,087.00
F Harga Satuan Pekerjaan (D+E) 297,957.00

20 A.4.1.1.24 1 M2 Memasang Bekisting untuk Lantai


A TENAGA 93,720.00
L.01 0.660 OH Pekerja 80,000.00 52,800.00
L.02 0.330 OH Tukang Kayu 100,000.00 33,000.00
L.03 0.033 OH Kepala Tukang 120,000.00 3,960.00
L.04 0.033 OH Mandor 120,000.00 3,960.00
B BAHAN 193,650.00
0.040 M3 Kayu Papan Klas III/Bekisting 1,800,000.00 72,000.00
0.400 Kg Paku Biasa 2" - 5" 20,000.00 8,000.00
0.200 Ltr Minyak Bekisting 10,000.00 2,000.00
0.015 M3 Kayu Balok Klas II/Bekisting 2,500,000.00 37,500.00
0.350 Lbr Multiplek Tebal 9 mm 109,000.00 38,150.00
6.000 Btg Dolken Kayu diameter 8 - 10 cm / 4 m 6,000.00 36,000.00
C PERALATAN
D Jumlah A + B + C 287,370.00
E Overhead & Profit 10% 28,737.00
F Harga Satuan Pekerjaan (D+E) 316,107.00

21 A.4.1.1.25 1 M2 Memasang Bekisting untuk Dinding


A TENAGA 93,720.00
L.01 0.660 OH Pekerja 80,000.00 52,800.00
L.02 0.330 OH Tukang Kayu 100,000.00 33,000.00
L.03 0.033 OH Kepala Tukang 120,000.00 3,960.00
L.04 0.033 OH Mandor 120,000.00 3,960.00
B BAHAN 194,150.00
0.030 M3 Kayu Papan Klas III/Bekisting 1,800,000.00 54,000.00
0.400 Kg Paku Biasa 2" - 5" 20,000.00 8,000.00
0.200 Ltr Minyak Bekisting 10,000.00 2,000.00
0.020 M3 Kayu Balok Klas II/Bekisting 2,500,000.00 50,000.00
0.350 Lbr Multiplek Tebal 9 mm 109,000.00 38,150.00
3.000 Btg Dolken Kayu diameter 8 - 10 cm / 4 m 6,000.00 18,000.00
4.000 Buah Formite/Penjaga jarak / Spacer 6,000.00 24,000.00
C PERALATAN
D Jumlah A + B + C 287,870.00
E Overhead & Profit 10% 28,787.00
F Harga Satuan Pekerjaan (D+E) 316,657.00
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
IV A.4.1.1 HARGA SATUAN PEKERJAAN B E T O N
22 A.4.1.1.26 1 M2 Memasang Bekisting untuk Tangga
A TENAGA 93,720.00
L.01 0.660 OH Pekerja 80,000.00 52,800.00
L.02 0.330 OH Tukang Kayu 100,000.00 33,000.00
L.03 0.033 OH Kepala Tukang 120,000.00 3,960.00
L.04 0.033 OH Mandor 120,000.00 3,960.00
B BAHAN 151,150.00
0.030 M3 Kayu Papan Klas III/Bekisting 1,800,000.00 54,000.00
0.400 Kg Paku Biasa 2" - 5" 20,000.00 8,000.00
0.150 Ltr Minyak Bekisting 10,000.00 1,500.00
0.015 M3 Kayu Balok Klas II/Bekisting 2,500,000.00 37,500.00
0.350 Lbr Multiplek Tebal 9 mm 109,000.00 38,150.00
2.000 Btg Dolken Kayu diameter 8 - 10 cm / 4 m 6,000.00 12,000.00
C PERALATAN
D Jumlah A + B + C 244,870.00
E Overhead & Profit 10% 24,487.00
F Harga Satuan Pekerjaan (D+E) 269,357.00

23 A.4.1.1.28 1 M3 Membuat Pondasi Beton Bertulang (150 kg Besi + Bekisting)


A TENAGA 749,740.00
L.01 5.300 OH Pekerja 80,000.00 424,000.00
L.02 0.275 OH Tukang batu 100,000.00 27,500.00
L.02 1.300 OH Tukang Kayu 100,000.00 130,000.00
L.02 1.050 OH Tukang Besi 100,000.00 105,000.00
L.03 0.262 OH Kepala Tukang 120,000.00 31,440.00
L.04 0.265 OH Mandor 120,000.00 31,800.00
B BAHAN 2,975,575.00
0.200 M3 Kayu Papan Klas III/Bekisting 1,800,000.00 360,000.00
1.500 Kg Paku Biasa 2" - 5" 20,000.00 30,000.00
0.400 Ltr Minyak Bekisting 10,000.00 4,000.00
157.500 Kg Besi Beton Polos 11,000.00 1,732,500.00
2.250 Kg Kawat Beton 19,500.00 43,875.00
336.000 Kg Portland Semen 1,400.00 470,400.00
0.540 M3 Pasir Beton 95,000.00 51,300.00
0.810 M3 Kerikil (Maks 30 mm) 350,000.00 283,500.00
C PERALATAN
D Jumlah A + B + C 3,725,315.00
E Overhead & Profit 10% 372,531.50
F Harga Satuan Pekerjaan (D+E) 4,097,846.50

24 A.4.1.1.29a 1 M3 Membuat Sloof Beton Bertulang (200 kg Besi + Bekisting)


A TENAGA 848,220.00
L.01 5.650 OH Pekerja 80,000.00 452,000.00
L.02 0.275 OH Tukang batu 100,000.00 27,500.00
L.02 1.560 OH Tukang Kayu 100,000.00 156,000.00
L.02 1.400 OH Tukang Besi 100,000.00 140,000.00
L.03 0.323 OH Kepala Tukang 120,000.00 38,760.00
L.04 0.283 OH Mandor 120,000.00 33,960.00
B BAHAN 3,705,700.00
0.270 M3 Kayu Papan Klas III/Bekisting 1,800,000.00 486,000.00
2.000 Kg Paku Biasa 2" - 5" 20,000.00 40,000.00
0.600 Ltr Minyak Bekisting 10,000.00 6,000.00
210.000 Kg Besi Beton Polos 11,000.00 2,310,000.00
3.000 Kg Kawat Beton 19,500.00 58,500.00
336.000 Kg Portland Semen 1,400.00 470,400.00
0.540 M3 Pasir Beton 95,000.00 51,300.00
0.810 M3 Kerikil (Maks 30 mm) 350,000.00 283,500.00
C PERALATAN
D Jumlah A + B + C 4,553,920.00
E Overhead & Profit 10% 455,392.00
F Harga Satuan Pekerjaan (D+E) 5,009,312.00
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
IV A.4.1.1 HARGA SATUAN PEKERJAAN B E T O N
25 A.4.1.1.29b 1 M3 Membuat Sloof Beton Bertulang (150 kg Besi + Bekisting)
A TENAGA 778,620.00
L.01 5.300 OH Pekerja 80,000.00 424,000.00
L.02 0.275 OH Tukang batu 100,000.00 27,500.00
L.02 1.560 OH Tukang Kayu 100,000.00 156,000.00
L.02 1.050 OH Tukang Besi 100,000.00 105,000.00
L.03 0.288 OH Kepala Tukang 120,000.00 34,560.00
L.04 0.263 OH Mandor 120,000.00 31,560.00
B BAHAN 3,113,575.00
0.270 M3 Kayu Papan Klas III/Bekisting 1,800,000.00 486,000.00
2.000 Kg Paku Biasa 2" - 5" 20,000.00 40,000.00
0.600 Ltr Minyak Bekisting 10,000.00 6,000.00
157.500 Kg Besi Beton Polos 11,000.00 1,732,500.00
2.250 Kg Kawat Beton 19,500.00 43,875.00
336.000 Kg Portland Semen 1,400.00 470,400.00
0.540 M3 Pasir Beton 95,000.00 51,300.00
0.810 M3 Kerikil (Maks 30 mm) 350,000.00 283,500.00
C PERALATAN
D Jumlah A + B + C 3,892,195.00
E Overhead & Profit 10% 389,219.50
F Harga Satuan Pekerjaan (D+E) 4,281,414.50

26 A.4.1.1.30a 1 M3 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting)


A TENAGA 1,057,220.00
L.01 7.050 OH Pekerja 80,000.00 564,000.00
L.02 0.275 OH Tukang batu 100,000.00 27,500.00
L.02 1.650 OH Tukang Kayu 100,000.00 165,000.00
L.02 2.100 OH Tukang Besi 100,000.00 210,000.00
L.03 0.403 OH Kepala Tukang 120,000.00 48,360.00
L.04 0.353 OH Mandor 120,000.00 42,360.00
B BAHAN 6,054,450.00
0.400 M3 Kayu Papan Klas III/Bekisting 1,800,000.00 720,000.00
4.000 Kg Paku Biasa 2" - 5" 20,000.00 80,000.00
2.000 Ltr Minyak Bekisting 10,000.00 20,000.00
315.000 Kg Besi Beton Polos 11,000.00 3,465,000.00
4.500 Kg Kawat Beton 19,500.00 87,750.00
336.000 Kg Portland Semen 1,400.00 470,400.00
0.540 M3 Pasir Beton 95,000.00 51,300.00
0.810 M3 Kerikil Beton 350,000.00 283,500.00
0.150 M3 Kayu Balok Klas II/Bekisting 2,500,000.00 375,000.00
3.500 Lbr Plywood 9 mm 109,000.00 381,500.00
20.000 Btg Dolken diameter 8-10 / 4 m 6,000.00 120,000.00
C PERALATAN
D Jumlah A + B + C 7,111,670.00
E Overhead & Profit 10% 711,167.00
F Harga Satuan Pekerjaan (D+E) 7,822,837.00

27 A.4.1.1.30b 1 M3 Membuat Kolom Beton Bertulang (150 kg Besi + Bekisting)


A TENAGA 848,420.00
L.01 6.000 OH Pekerja 80,000.00 480,000.00
L.02 0.275 OH Tukang batu 100,000.00 27,500.00
L.02 1.650 OH Tukang Kayu 100,000.00 165,000.00
L.02 1.050 OH Tukang Besi 100,000.00 105,000.00
L.03 0.298 OH Kepala Tukang 120,000.00 35,760.00
L.04 0.293 OH Mandor 120,000.00 35,160.00
B BAHAN 4,278,075.00
0.400 M3 Kayu Papan Klas III/Bekisting 1,800,000.00 720,000.00
4.000 Kg Paku Biasa 2" - 5" 20,000.00 80,000.00
2.000 Ltr Minyak Bekisting 10,000.00 20,000.00
157.500 Kg Besi Beton Polos 11,000.00 1,732,500.00
2.250 Kg Kawat Beton 19,500.00 43,875.00
336.000 Kg Portland Semen 1,400.00 470,400.00
0.540 M3 Pasir Beton 95,000.00 51,300.00
0.810 M3 Kerikil Beton 350,000.00 283,500.00
0.150 M3 Kayu Balok Klas II/Bekisting 2,500,000.00 375,000.00
3.500 Lbr Plywood 9 mm 109,000.00 381,500.00
20.000 Btg Dolken diameter 8 / 4rm 6,000.00 120,000.00
C PERALATAN
D Jumlah A + B + C 5,126,495.00
E Overhead & Profit 10% 512,649.50
F Harga Satuan Pekerjaan (D+E) 5,639,144.50
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON
28 A.4.1.1.31a 1 M3 Membuat Balok Beton Bertulang (200 kg Besi + Bekisting)
A TENAGA 918,620.00
L.01 6.350 OH Pekerja 80,000.00 508,000.00
L.02 0.275 OH Tukang batu 100,000.00 27,500.00
L.02 1.650 OH Tukang Kayu 100,000.00 165,000.00
L.02 1.400 OH Tukang Besi 100,000.00 140,000.00
L.03 0.333 OH Kepala Tukang 120,000.00 39,960.00
L.04 0.318 OH Mandor 120,000.00 38,160.00
B BAHAN 4,580,900.00
0.320 M3 Kayu Papan Klas III/Bekisting 1,800,000.00 576,000.00
3.200 Kg Paku Biasa 2" - 5" 20,000.00 64,000.00
1.600 Ltr Minyak Bekisting 10,000.00 16,000.00
210.000 Kg Besi Beton Polos 11,000.00 2,310,000.00
3.000 Kg Kawat Beton 19,500.00 58,500.00
336.000 Kg Portland Semen 1,400.00 470,400.00
0.540 M3 Pasir Beton 95,000.00 51,300.00
0.810 M3 Kerikil Beton 350,000.00 283,500.00
0.140 M3 Kayu Balok Klas II/Bekisting 2,500,000.00 350,000.00
2.800 Lbr Plywood 9 mm 109,000.00 305,200.00
16.000 Btg Dolken diameter 8 / 4rm 6,000.00 96,000.00
C PERALATAN
D Jumlah A + B + C 5,499,520.00
E Overhead & Profit 10% 549,952.00
F Harga Satuan Pekerjaan (D+E) 6,049,472.00

29 A.4.1.1.31b 1 M3 Membuat Balok Beton Bertulang (150 kg Besi + Bekisting)


A TENAGA 849,020.00
L.01 6.000 OH Pekerja 80,000.00 480,000.00
L.02 0.275 OH Tukang batu 100,000.00 27,500.00
L.02 1.650 OH Tukang Kayu 100,000.00 165,000.00
L.02 1.050 OH Tukang Besi 100,000.00 105,000.00
L.03 0.298 OH Kepala Tukang 120,000.00 35,760.00
L.04 0.298 OH Mandor 120,000.00 35,760.00
B BAHAN 3,988,775.00
0.320 M3 Kayu Papan Klas III/Bekisting 1,800,000.00 576,000.00
3.200 Kg Paku Biasa 2" - 5" 20,000.00 64,000.00
1.600 Ltr Minyak Bekisting 10,000.00 16,000.00
157.500 Kg Besi Beton Polos 11,000.00 1,732,500.00
2.250 Kg Kawat Beton 19,500.00 43,875.00
336.000 Kg Portland Semen 1,400.00 470,400.00
0.540 M3 Pasir Beton 95,000.00 51,300.00
0.810 M3 Kerikil Beton 350,000.00 283,500.00
0.140 M3 Kayu Balok Klas II/Bekisting 2,500,000.00 350,000.00
2.800 Lbr Plywood 9 mm 109,000.00 305,200.00
16.000 Btg Dolken diameter 8 / 4rm 6,000.00 96,000.00
C PERALATAN
D Jumlah A + B + C 4,837,795.00
E Overhead & Profit 10% 483,779.50
F Harga Satuan Pekerjaan (D+E) 5,321,574.50

30 A.4.1.1.32 1 M3 Membuat Plat Beton Bertulang (150 kg besi + bekisting)


A TENAGA 750,100.00
L.01 5.300 OH Pekerja 80,000.00 424,000.00
L.02 0.275 OH Tukang batu 100,000.00 27,500.00
L.02 1.300 OH Tukang Kayu 100,000.00 130,000.00
L.02 1.050 OH Tukang Besi 100,000.00 105,000.00
L.03 0.265 OH Kepala Tukang 120,000.00 31,800.00
L.04 0.265 OH Mandor 120,000.00 31,800.00
B BAHAN 4,034,775.00
0.320 M3 Kayu Papan Klas III/Bekisting 1,800,000.00 576,000.00
3.200 Kg Paku Biasa 2" - 5" 20,000.00 64,000.00
1.600 Ltr Minyak Bekisting 10,000.00 16,000.00
157.500 Kg Besi Beton Polos 11,000.00 1,732,500.00
2.250 Kg Kawat Beton 19,500.00 43,875.00
336.000 Kg Portland Semen 1,400.00 470,400.00
0.540 M3 Pasir Beton 95,000.00 51,300.00
0.810 M3 Kerikil Beton 350,000.00 283,500.00
0.120 M3 Kayu Balok Klas II/Bekisting 2,500,000.00 300,000.00
2.800 Lbr Plywood 9 mm 109,000.00 305,200.00
32.000 Btg Dolken diameter 8 / 4rm 6,000.00 192,000.00
C PERALATAN
D Jumlah A + B + C 4,784,875.00
E Overhead & Profit 10% 478,487.50
F Harga Satuan Pekerjaan (D+E) 5,263,362.50
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
IV A.4.1.1 HARGA SATUAN PEKERJAAN B E T O N
31 A.4.1.1.33 1 M3 Membuat Dinding Beton Bertulang (150 kg Besi + Bekisting)
A TENAGA 749,740.00
L.01 5.300 OH Pekerja 80,000.00 424,000.00
L.02 0.275 OH Tukang batu 100,000.00 27,500.00
L.02 1.300 OH Tukang Kayu 100,000.00 130,000.00
L.02 1.050 OH Tukang Besi 100,000.00 105,000.00
L.03 0.262 OH Kepala Tukang 120,000.00 31,440.00
L.04 0.265 OH Mandor 120,000.00 31,800.00
B BAHAN 3,942,775.00
0.240 M3 Kayu Papan Klas III/Bekisting 1,800,000.00 432,000.00
3.200 Kg Paku Biasa 2" - 5" 20,000.00 64,000.00
1.600 Ltr Minyak Bekisting 10,000.00 16,000.00
157.500 Kg Besi Beton Polos 11,000.00 1,732,500.00
2.250 Kg Kawat Beton 19,500.00 43,875.00
336.000 Kg Portland Semen 1,400.00 470,400.00
0.540 M3 Pasir Beton 95,000.00 51,300.00
0.810 M3 Kerikil Beton 350,000.00 283,500.00
0.160 M3 Kayu Balok Klas II/Bekisting 2,500,000.00 400,000.00
2.800 Lbr Plywood 9 mm 109,000.00 305,200.00
24.000 Btg Dolken diameter 8 / 4rm 6,000.00 144,000.00
C PERALATAN
D Jumlah A + B + C 4,692,515.00
E Overhead & Profit 10% 469,251.50
F Harga Satuan Pekerjaan (D+E) 5,161,766.50

32 A.4.1.1.35 1 M Membuat Kolom Praktis Beton Bertulang (11 x 11) cm


A TENAGA 29,475.55
L.01 0.180 OH Pekerja 103,877.00 18,697.86
L.02 0.020 OH Tukang batu 139,036.00 2,780.72
L.02 0.020 OH Tukang Kayu 139,036.00 2,780.72
L.02 0.020 OH Tukang Besi 139,036.00 2,780.72
L.03 0.006 OH Kepala Tukang 151,821.00 910.93
L.04 0.009 OH Mandor 169,400.00 1,524.60
B BAHAN 115,473.30
0.002 M3 Kayu Papan Klas III/Bekisting 2,751,100.00 5,502.20
0.010 Kg Paku Biasa 2" - 5" 37,000.00 370.00
3.000 Kg Besi Beton Polos 29,000.00 87,000.00
0.045 Kg Kawat Beton 30,000.00 1,350.00
4.000 Kg Portland Semen 3,240.00 12,960.00
0.006 M3 Pasir Beton 457,100.00 2,742.60
0.009 M3 Kerikil Beton 616,500.00 5,548.50
C PERALATAN
D Jumlah A + B + C 144,948.85
E Overhead & Profit 10% 14,494.88
F Harga Satuan Pekerjaan (D+E) 159,443.73

33 A.4.1.1.36 1 M Membuat Ring Balok Beton Bertulang (10 x 15) cm


A TENAGA 36,660.00
L.01 0.297 OH Pekerja 80,000.00 23,760.00
L.02 0.033 OH Tukang batu 100,000.00 3,300.00
L.02 0.033 OH Tukang Kayu 100,000.00 3,300.00
L.02 0.033 OH Tukang Besi 100,000.00 3,300.00
L.03 0.010 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
B BAHAN 60,180.00
0.003 M3 Kayu Papan Klas III/Bekisting 1,800,000.00 5,400.00
0.020 Kg Paku Biasa 2" - 5" 20,000.00 400.00
3.600 Kg Besi Beton Polos 11,000.00 39,600.00
0.050 Kg Kawat Beton 19,500.00 975.00
5.500 Kg Portland Semen 1,400.00 7,700.00
0.009 M3 Pasir Beton 95,000.00 855.00
0.015 M3 Kerikil Beton 350,000.00 5,250.00
C PERALATAN
D Jumlah A + B + C 96,840.00
E Overhead & Profit 10% 9,684.00
F Harga Satuan Pekerjaan (D+E) 106,524.00
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
IV A.4.1.1 HARGA SATUAN PEKERJAAN B E T O N
34 Modified 1 M3 Membuat Beton 1Pc : 2Ps : 3Kr
A TENAGA 172,820.00
L.01 1.650 OH Pekerja 80,000.00 132,000.00
L.02 0.275 OH Tukang Batu 100,000.00 27,500.00
L.03 0.028 OH Kepala Tukang 120,000.00 3,360.00
L.04 0.083 OH Mandor 120,000.00 9,960.00
B BAHAN 805,200.00
336.000 Kg Portland Semen 1,400.00 470,400.00
0.540 M3 Pasir Beton 95,000.00 51,300.00
0.810 M3 Kerikil Beton 350,000.00 283,500.00
C PERALATAN
D Jumlah A + B + C 978,020.00
E Overhead & Profit 10% 97,802.00
F Harga Satuan Pekerjaan (D+E) 1,075,822.00

35 Modified 1 M3 Membuat Pondasi Beton K-175 Beton Bertulang (137 Kg)


1.000 M3 Beton K-175 2,216,646.45 2,216,646.45
137.000 Kg Pembesian Polos 36,051.87 4,939,105.95
Jumlah 7,155,752.40
36 Modified 1 M3 Membuat Sloof Beton K-175 Beton Bertulang (107 Kg)
1.000 M3 Beton K-175 2,216,646.45 2,216,646.45
4.000 M2 Bekisting Sloof 258,188.31 1,032,753.24
107.000 Kg Pembesian Polos 36,051.87 3,857,549.90
Jumlah 7,106,949.60

37 Modified 1 M3 Membuat Kolom Beton K-175 Beton Bertulang (84 Kg + Bekisting)


1.000 M3 Beton K-175 2,216,646.45 2,216,646.45
8.000 M2 Bekisting Kolom 724,076.64 5,792,613.14
84.000 Kg Pembesian Polos 36,051.87 3,028,356.93
Jumlah 11,037,616.52

38 Modified 1 M3 Membuat Balok Beton K-225 Beton Bertulang (150 Kg + Bekisting)


1.000 M3 Beton K-225 1,209,267.71 1,209,267.71
6.000 M2 Bekisting Balok 297,957.00 1,787,742.00
150.000 Kg Pembesian Polos 36,051.87 5,407,780.24
Jumlah 8,404,789.95

39 Modified 1 M3 Membuat Plat Beton K-225 Beton Bertulang (150 Kg + Bekisting)


1.000 M3 Beton K-225 1,209,267.71 1,209,267.71
8.000 M2 Bekisting Plat 316,107.00 2,528,856.00
150.000 Kg Pembesian Polos 36,051.87 5,407,780.24
Jumlah 9,145,903.95

40 Modified 1 M3 Membuat Dinding Beton K-225 Beton Bertulang (150 Kg + Bekisting)


1.000 M3 Beton K-225 1,209,267.71 1,209,267.71
8.000 M2 Bekisting Dinding 316,657.00 2,533,256.00
150.000 Kg Pembesian Polos 36,051.87 5,407,780.24
Jumlah 9,150,303.95

41 Modified 1 M3 Membuat Tangga Beton K-225 Beton Bertulang (150 Kg + Bekisting)


1.000 M3 Beton K-225 1,209,267.71 1,209,267.71
10.000 M2 Bekisting Tangga 269,357.00 2,693,570.00
150.000 Kg Pembesian Polos 36,051.87 5,407,780.24
Jumlah 9,310,617.95
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
V A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM
1 A.4.2.1.1 1 Kg Pemasangan Besi Profil
A TENAGA 11,880.00
L.01 0.060 OH Pekerja 80,000.00 4,800.00
L.02 0.060 OH Tukang Besi 100,000.00 6,000.00
L.03 0.006 OH Kepala Tukang 120,000.00 720.00
L.04 0.003 OH Mandor 120,000.00 360.00
B BAHAN 15,525.00
1.150 Kg Besi Profil 13,500.00 15,525.00
C PERALATAN
D Jumlah A + B + C 27,405.00
E Overhead & Profit 10% 2,740.50
F Harga Satuan Pekerjaan (D+E) 30,145.50

2 A.4.2.1.2 1 Kg Pemasangan Rangka Kuda-kuda Baja IWF


A TENAGA 11,880.00
L.01 0.060 OH Pekerja 80,000.00 4,800.00
L.02 0.060 OH Tukang Besi 100,000.00 6,000.00
L.03 0.006 OH Kepala Tukang 120,000.00 720.00
L.04 0.003 OH Mandor 120,000.00 360.00
B BAHAN 15,525.00
1.150 Kg Besi Baja IWF 13,500.00 15,525.00
C PERALATAN ###
D Jumlah A + B + C 27,405.00
E Overhead & Profit 10% 2,740.50
F Harga Satuan Pekerjaan (D+E) 30,145.50

3 A.4.2.1.4 1 M2 Pembuatan Pintu Besi Plat Baja Tebal 2 mm Rangkap, Rangka Baja Siku
A TENAGA 207,840.00
L.01 1.050 OH Pekerja 80,000.00 84,000.00
L.02 1.050 OH Tukang Besi 100,000.00 105,000.00
L.03 0.105 OH Kepala Tukang 120,000.00 12,600.00
L.04 0.052 OH Mandor 120,000.00 6,240.00
B BAHAN 533,250.00
15.000 Kg Besi Siku 13,500.00 202,500.00
32.800 Kg Besi Plat Baja 10,000.00 328,000.00
0.050 Kg Kawat Las 55,000.00 2,750.00
C PERALATAN
D Jumlah A + B + C 741,090.00
E Overhead & Profit 10% 74,109.00
F Harga Satuan Pekerjaan (D+E) 815,199.00

4 A.4.2.1.5 10 Cm Pengerjaan Pengelasan dengan Las Listrik


A TENAGA 5,680.00
L.01 0.040 OH Pekerja 80,000.00 3,200.00
L.02 0.020 OH Tukang Besi 100,000.00 2,000.00
L.03 0.002 OH Kepala Tukang 120,000.00 240.00
L.04 0.002 OH Mandor 120,000.00 240.00
B BAHAN 26,010.00
0.400 Kg Kawat Las 55,000.00 22,000.00
0.300 Ltr Solar 8,700.00 2,610.00
0.040 Ltr Minyak Pelumas 35,000.00 1,400.00
C PERALATAN
D Jumlah A + B + C 31,690.00
E Overhead & Profit 10% 3,169.00
F Harga Satuan Pekerjaan (D+E) 34,859.00
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
V A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM
5 A.4.2.1.7 1 M2 Pemasangan Pintu Rolling Door Besi
A TENAGA 231,120.00
L.01 1.200 OH Pekerja 80,000.00 96,000.00
L.02 1.200 OH Tukang Besi 100,000.00 120,000.00
L.03 0.120 OH Kepala Tukang 120,000.00 14,400.00
L.04 0.006 OH Mandor 120,000.00 720.00
B BAHAN 410,000.00
1.000 M2 Pintu Gulung Besi 410,000.00 410,000.00
C PERALATAN
D Jumlah A + B + C 641,120.00
E Overhead & Profit 10% 64,112.00
F Harga Satuan Pekerjaan (D+E) 705,232.00

6 A.4.2.1.8 1 M2 Pemasangan Pintu Lipat (Folding Gate)


A TENAGA 87,120.00
L.01 0.440 OH Pekerja 80,000.00 35,200.00
L.02 0.440 OH Tukang Besi 100,000.00 44,000.00
L.03 0.044 OH Kepala Tukang 120,000.00 5,280.00
L.04 0.022 OH Mandor 120,000.00 2,640.00
B BAHAN 560,000.00
1.000 M2 Pintu Lipat/Folding Gate 560,000.00 560,000.00
C PERALATAN
D Jumlah A + B + C 647,120.00
E Overhead & Profit 10% 64,712.00
F Harga Satuan Pekerjaan (D+E) 711,832.00

7 A.4.2.1.10 1 M2 Pemasangan Rolling Door Allumunium


A TENAGA 198,000.00
L.01 1.000 OH Pekerja 80,000.00 80,000.00
L.02 1.000 OH Tukang Besi 100,000.00 100,000.00
L.03 0.100 OH Kepala Tukang 120,000.00 12,000.00
L.04 0.050 OH Mandor 120,000.00 6,000.00
B BAHAN 470,000.00
1.000 M2 Rolling Door Allumunium 470,000.00 470,000.00
C PERALATAN
D Jumlah A + B + C 668,000.00
E Overhead & Profit 10% 66,800.00
F Harga Satuan Pekerjaan (D+E) 734,800.00

8 A.4.2.1.11a 1 M Pemasangan Kusen Pintu Allumunium 4"


A TENAGA 8,508.00
L.01 0.043 OH Pekerja 80,000.00 3,440.00
L.02 0.043 OH Tukang Besi 100,000.00 4,300.00
L.03 0.004 OH Kepala Tukang 120,000.00 516.00
L.04 0.002 OH Mandor 120,000.00 252.00
B BAHAN 83,400.00
1.100 M Kusen Almunium 4" 72,000.00 79,200.00
2.000 Bh Skrup Fixer 1,200.00 2,400.00
0.060 Tube Sealant 30,000.00 1,800.00
C PERALATAN
D Jumlah A + B + C 91,908.00
E Overhead & Profit 10% 9,190.80
F Harga Satuan Pekerjaan (D+E) 101,098.80

9 A.4.2.1.11b 1 M Pemasangan Kusen Pintu Allumunium 3"


A TENAGA 8,508.00
L.01 0.043 OH Pekerja 80,000.00 3,440.00
L.02 0.043 OH Tukang Besi 100,000.00 4,300.00
L.03 0.004 OH Kepala Tukang 120,000.00 516.00
L.04 0.002 OH Mandor 120,000.00 252.00
B BAHAN 75,700.00
1.100 M Kusen Almunium 3" 65,000.00 71,500.00
2.000 Bh Skrup Fixer 1,200.00 2,400.00
0.060 Tube Sealant 30,000.00 1,800.00
C PERALATAN
D Jumlah A + B + C 84,208.00
E Overhead & Profit 10% 8,420.80
F Harga Satuan Pekerjaan (D+E) 92,628.80
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
V A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM
10 A.4.2.1.13 1 M2 Pemasangan Pintu Kaca Rangka Allumunium
A TENAGA 16,980.00
L.01 0.085 OH Pekerja 80,000.00 6,800.00
L.02 0.085 OH Tukang Besi 100,000.00 8,500.00
L.03 0.009 OH Kepala Tukang 120,000.00 1,080.00
L.04 0.005 OH Mandor 120,000.00 600.00
B BAHAN 316,600.00
4.400 M Alumunium Profil 65,000.00 286,000.00
4.500 M Profil Kaca 5,000.00 22,500.00
0.270 Tube Sealant 30,000.00 8,100.00
C PERALATAN
D Jumlah A + B + C 333,580.00
E Overhead & Profit 10% 33,358.00
F Harga Satuan Pekerjaan (D+E) 366,938.00

11 A.4.2.1.15a 1 M2 Pemasangan Terali Besi Strip (2x3) cm


A TENAGA 330,600.00
L.01 1.670 OH Pekerja 80,000.00 133,600.00
L.02 1.670 OH Tukang Las 100,000.00 167,000.00
L.03 0.167 OH Kepala Tukang 120,000.00 20,040.00
L.04 0.083 OH Mandor 120,000.00 9,960.00
B BAHAN 147,586.52
6.177 Kg Besi Strip 2x3 10,000.00 61,770.00
27.080 Cm Pengelasan 3,169.00 85,816.52
C PERALATAN
D Jumlah A + B + C 478,186.52
E Overhead & Profit 10% 47,818.65
F Harga Satuan Pekerjaan (D+E) 526,005.17

12 A.4.2.1.15b 1 M2 Pemasangan Terali Besi Hollow 4/4 & 2/4, Jarak 10 cm


A TENAGA 330,600.00
L.01 1.670 OH Pekerja 80,000.00 133,600.00
L.02 1.670 OH Tukang Las 100,000.00 167,000.00
L.03 0.167 OH Kepala Tukang 120,000.00 20,040.00
L.04 0.083 OH Mandor 120,000.00 9,960.00
B BAHAN 267,384.00
4.200 M Besi Hollow 4/4 14,000.00 58,800.00
9.450 M Besi Hollow 2/4 10,000.00 94,500.00
36.000 Cm Pengelasan 3,169.00 114,084.00
C PERALATAN
D Jumlah A + B + C 597,984.00
E Overhead & Profit 10% 59,798.40
F Harga Satuan Pekerjaan (D+E) 657,782.40

13 A.4.2.1.17 1 M2 Pemasangan Jendela Nako Rayban 5 mm & Tralis


A TENAGA 38,520.00
L.01 0.200 OH Pekerja 80,000.00 16,000.00
L.02 0.200 OH Tukang Kayu 100,000.00 20,000.00
L.03 0.020 OH Kepala Tukang 120,000.00 2,400.00
L.04 0.001 OH Mandor 120,000.00 120.00
B BAHAN 113,700.00
1.100 M2 Jendela Nako Rayban 82,000.00 90,200.00
10.000 Bh Paku Skrup 1 - 2,5 cm 250.00 2,500.00
7.000 M Besi Strip 2x3 3,000.00 21,000.00
C PERALATAN
D Jumlah A + B + C 152,220.00
E Overhead & Profit 10% 15,222.00
F Harga Satuan Pekerjaan (D+E) 167,442.00

14 A.4.2.1.18 1 M Pemasangan Talang Datar/Jurai , Seng BJLS 30 Lebar 90 cm


A TENAGA 39,600.00
L.01 0.200 OH Pekerja 80,000.00 16,000.00
L.02 0.200 OH Tukang Kayu 100,000.00 20,000.00
L.03 0.020 OH Kepala Tukang 120,000.00 2,400.00
L.04 0.010 OH Mandor 120,000.00 1,200.00
B BAHAN 121,300.00
1.050 M Seng BJLS 30 Lebar 90 cm 70,000.00 73,500.00
0.015 Kg Paku Biasa 2 - 5" 20,000.00 300.00
0.019 M3 Kayu Papan Klas II/Bekisting 2,500,000.00 47,500.00
C PERALATAN
D Jumlah A + B + C 160,900.00
E Overhead & Profit 10% 16,090.00
F Harga Satuan Pekerjaan (D+E) 176,990.00
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
V A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM
15 A.4.2.1.20a 1 M2 Pemasangan Rangka Besi Hollow Gypsum, modul 60 x 120 cm, dinding partisi
A TENAGA 49,560.00
L.01 0.250 OH Pekerja 80,000.00 20,000.00
L.02 0.250 OH Tukang Besi 100,000.00 25,000.00
L.03 0.025 OH Kepala Tukang 120,000.00 3,000.00
L.04 0.013 OH Mandor 120,000.00 1,560.00
B BAHAN 52,500.00
3.500 M Rangka Metal Hollow Gypsum 7,500.00 26,250.00
100% x rangka Ls Assesoris (perkuatan, dll) 26,250.00
C PERALATAN
D Jumlah A + B + C 102,060.00
E Overhead & Profit 10% 10,206.00
F Harga Satuan Pekerjaan (D+E) 112,266.00

16 A.4.2.1.20b 1 M2 Pemasangan Rangka Baja Ringan Canal, modul 60 x 120 cm, dinding partisi
A TENAGA 49,560.00
L.01 0.250 OH Pekerja 80,000.00 20,000.00
L.02 0.250 OH Tukang Besi 100,000.00 25,000.00
L.03 0.025 OH Kepala Tukang 120,000.00 3,000.00
L.04 0.013 OH Mandor 120,000.00 1,560.00
B BAHAN 63,700.00
3.500 M Rangka Canal Baja Ringan 14,000.00 49,000.00
30% x rangka Ls Assesoris (perkuatan, dll) 14,700.00
C PERALATAN
D Jumlah A + B + C 113,260.00
E Overhead & Profit 10% 11,326.00
F Harga Satuan Pekerjaan (D+E) 124,586.00

17 A.4.2.1.21a 1 M2 Pemasangan Rangka Besi Hollow Gypsum, modul 60 x 120 cm, Plafond
A TENAGA 34,680.00
L.01 0.1750 OH Tenaga 80,000.00 14,000.00
L.02 0.1750 OH Pekerja 100,000.00 17,500.00
L.03 0.0175 OH Tukang Besi 120,000.00 2,100.00
L.04 0.0090 OH Kepala Tukang 120,000.00 1,080.00
B BAHAN 52,500.00
3.5000 M Rangka Metal Hollow Gypsum 7,500.00 26,250.00
100% x rangka Ls Assesoris (perkuatan, dll) 26,250.00
C PERALATAN
D Jumlah A + B + C 87,180.00
E Overhead & Profit 10% 8,718.00
F Harga Satuan Pekerjaan (D+E) 95,898.00

18 A.4.2.1.21b 1 M2 Pemasangan Rangka Besi Hollow Gypsum, modul 60 x 60 cm, Plafond


A TENAGA 69,360.00
L.01 0.350 OH Tenaga 80,000.00 28,000.00
L.02 0.350 OH Pekerja 100,000.00 35,000.00
L.03 0.035 OH Tukang Besi 120,000.00 4,200.00
L.04 0.018 OH Kepala Tukang 120,000.00 2,160.00
B BAHAN 60,000.00
4.000 M Rangka Metal Hollow Gypsum 7,500.00 30,000.00
100% x rangka Ls Assesoris (perkuatan, dll) 30,000.00
C PERALATAN
D Jumlah A + B + C 129,360.00
E Overhead & Profit 10% 12,936.00
F Harga Satuan Pekerjaan (D+E) 142,296.00
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
VI A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
1 A.4.4.1.1 1 M2 Pemasangan Dinding Bata Merah ukuran (5x11x22) cm Tebal 1 bata Camp. 1SP: 2PP ###
A TENAGA 74,000.00
L.01 0.600 OH Pekerja 80,000.00 48,000.00
L.02 0.200 OH Tukang Batu 100,000.00 20,000.00
L.03 0.020 OH Kepala Tukang 120,000.00 2,400.00
L.04 0.030 OH Mandor 120,000.00 3,600.00
B BAHAN 138,500.00
140.000 Bh Bata Merah 500.00 70,000.00
43.500 Kg Portland Semen (PC) 1,400.00 60,900.00
0.080 M3 Pasir Pasang (PP) 95,000.00 7,600.00
C PERALATAN
D Jumlah A + B + C 212,500.00
E Overhead & Profit 10% 21,250.00
F Harga Satuan Pekerjaan (D+E) 233,750.00

2 A.4.4.1.2 1 M2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3PP
A TENAGA 74,000.00
L.01 0.600 OH Pekerja 80,000.00 48,000.00
L.02 0.200 OH Tukang Batu 100,000.00 20,000.00
L.03 0.020 OH Kepala Tukang 120,000.00 2,400.00
L.04 0.030 OH Mandor 120,000.00 3,600.00
B BAHAN 124,775.00
140.000 Bh Bata Merah 500.00 70,000.00
32.950 Kg Portland Semen (PC) 1,400.00 46,130.00
0.091 M3 Pasir Pasang (PP) 95,000.00 8,645.00
C PERALATAN
D Jumlah A + B + C 198,775.00
E Overhead & Profit 10% 19,877.50
F Harga Satuan Pekerjaan (D+E) 218,652.50

3 A.4.4.1.3 1 M2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP
A TENAGA 74,000.00
L.01 0.600 OH Pekerja 80,000.00 48,000.00
L.02 0.200 OH Tukang Batu 100,000.00 20,000.00
L.03 0.020 OH Kepala Tukang 120,000.00 2,400.00
L.04 0.030 OH Mandor 120,000.00 3,600.00
B Bahan 116,005.00
140.000 Bh Bata Merah 500.00 70,000.00
26.550 Kg Portland Semen (PC) 1,400.00 37,170.00
0.093 M3 Pasir Pasang (PP) 95,000.00 8,835.00
C PERALATAN
D Jumlah A + B + C 190,005.00
E Overhead & Profit 10% 19,000.50
F Harga Satuan Pekerjaan (D+E) 209,005.50

4 A.4.4.1.7 1 M2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 2PP
A TENAGA 37,000.00
L.01 0.300 OH Pekerja 80,000.00 24,000.00
L.02 0.100 OH Tukang Batu 100,000.00 10,000.00
L.03 0.010 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
B BAHAN 65,140.00
70.000 Bh Bata Merah 500.00 35,000.00
18.950 Kg Portland Semen (PC) 1,400.00 26,530.00
0.038 M3 Pasir Pasang (PP) 95,000.00 3,610.00
C PERALATAN
D Jumlah A + B + C 102,140.00
E Overhead & Profit 10% 10,214.00
F Harga Satuan Pekerjaan (D+E) 112,354.00
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
VI A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
5 A.4.4.1.8 1 M2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP
A TENAGA 37,000.00
L.01 0.300 OH Pekerja 80,000.00 24,000.00
L.02 0.100 OH Tukang Batu 100,000.00 10,000.00
L.03 0.010 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
B BAHAN 58,918.00
70.000 Bh Bata Merah 500.00 35,000.00
14.370 Kg Portland Semen (PC) 1,400.00 20,118.00
0.040 M3 Pasir Pasang (PP) 95,000.00 3,800.00
C PERALATAN
D Jumlah A + B + C 95,918.00
E Overhead & Profit 10% 9,591.80
F Harga Satuan Pekerjaan (D+E) 105,509.80

6 A.4.4.1.9 1 M2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP
A TENAGA 49,125.91
L.01 0.300 OH Pekerja 103,877.00 31,163.10
L.02 0.100 OH Tukang Batu 139,036.00 13,903.60
L.03 0.010 OH Kepala Tukang 151,821.00 1,518.21
L.04 0.015 OH Mandor 169,400.00 2,541.00
B BAHAN 147,915.30
70.000 Bh Bata Merah 1,300.00 91,000.00
11.500 Kg Portland Semen (PC) 3,240.00 37,260.00
0.043 M3 Pasir Pasang (PP) 457,100.00 19,655.30
C PERALATAN
D Jumlah A + B + C 197,041.21
E Overhead & Profit 10% 19,704.12
F Harga Satuan Pekerjaan (D+E) 216,745.33

7 A.4.4.1.22 1 M2 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 3PP
A TENAGA 37,000.00
L.01 0.300 OH Pekerja 80,000.00 24,000.00
L.02 0.100 OH Tukang Batu 100,000.00 10,000.00
L.03 0.010 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
B BAHAN 138,725.00
1.000 M2 Terawang / Roster 120,000.00 120,000.00
11.000 Kg Portland Semen 1,400.00 15,400.00
0.035 M3 Pasir Pasang 95,000.00 3,325.00
C PERALATAN
D Jumlah A + B + C 175,725.00
E Overhead & Profit 10% 17,572.50
F Harga Satuan Pekerjaan (D+E) 193,297.50
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
1 A.4.4.2.1 1 M2 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm ###
A TENAGA 42,600.00
L.01 0.3 OH Pekerja 80,000.00 24,000.00
L.02 0.15 OH Tukang Batu 100,000.00 15,000.00
L.03 0.015 OH Kepala Tukang 120,000.00 1,800.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
B BAHAN 23,225.60
15.504 Kg Portland Cement 1,400.00 21,705.60
0.016 M3 Pasir Pasang 95,000.00 1,520.00
C PERALATAN
D Jumlah A + B + C 65,825.60
E Overhead & Profit 10% 6,582.56
F Harga Satuan Pekerjaan (D+E) 72,408.16
Overhead & Profit (contoh 10%)
2 A.4.4.2.2 1 M2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm
A TENAGA 42,600.00
L.01 0.3 OH Pekerja 80,000.00 24,000.00
L.02 0.15 OH Tukang Batu 100,000.00 15,000.00
L.03 0.015 OH Kepala Tukang 120,000.00 1,800.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
B BAHAN 16,213.60
10.224 Kg Portland Cement 1,400.00 14,313.60
0.020 M3 Pasir Pasang 95,000.00 1,900.00
C PERALATAN
D Jumlah A + B + C 58,813.60
E Overhead & Profit 10% 5,881.36
F Harga Satuan Pekerjaan (D+E) 64,694.96

3 A.4.4.2.3 1 M2 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm


A TENAGA 42,600.00
L.01 0.3 OH Pekerja 80,000.00 24,000.00
L.02 0.15 OH Tukang batu 100,000.00 15,000.00
L.03 0.015 OH Kepala Tukang 120,000.00 1,800.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
B BAHAN 13,071.40
7.776 Kg Portland Cement 1,400.00 10,886.40
0.023 M3 Pasir Pasang 95,000.00 2,185.00
C PERALATAN
D Jumlah A + B + C 55,671.40
E Overhead & Profit 10% 5,567.14
F Harga Satuan Pekerjaan (D+E) 61,238.54

4 A.4.4.2.4 1 M2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm


A TENAGA 56,836.82
L.01 0.3 OH Pekerja 103,877.00 31,163.10
L.02 0.15 OH Tukang batu 139,036.00 20,855.40
L.03 0.015 OH Kepala Tukang 151,821.00 2,277.32
L.04 0.015 OH Mandor 169,400.00 2,541.00
B BAHAN 31,188.00
6.240 Kg Portland Cement 3,240.00 20,217.60
0.024 M3 Pasir Pasang 457,100.00 10,970.40
C PERALATAN
D Jumlah A + B + C 88,024.82
E Overhead & Profit 10% 8,802.48
F Harga Satuan Pekerjaan (D+E) 96,827.30

5 A.4.4.2.5 1 M2 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm


A TENAGA 42,600.00
L.01 0.3 OH Pekerja 80,000.00 24,000.00
L.02 0.15 OH Tukang batu 100,000.00 15,000.00
L.03 0.015 OH Kepala Tukang 120,000.00 1,800.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
B BAHAN 9,727.60
5.184 Kg Portland Cement 1,400.00 7,257.60
0.026 M3 Pasir Pasang 95,000.00 2,470.00
C PERALATAN
D Jumlah A + B + C 52,327.60
E Overhead & Profit 10% 5,232.76
F Harga Satuan Pekerjaan (D+E) 57,560.36
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
6 A.4.4.2.23 1 M2 Pemasangan Plesteran Ciprat 1Pc : 2 Pp
TENAGA 37,000.00
L.01 0.30 OH Pekerja 80,000.00 24,000.00
L.02 0.1 OH Tukang batu 100,000.00 10,000.00
L.03 0.01 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
BAHAN 6,618.00
4.32 Kg Portland Cement 1,400.00 6,048.00
0.006 M3 Pasir Pasang 95,000.00 570.00
C PERALATAN
D Jumlah A + B + C 43,618.00
E Overhead & Profit 10% 4,361.80
F Harga Satuan Pekerjaan (D+E) 47,979.80

7 A.4.4.2.23 1 M2 Pemasangan Finishing Siar Pasangan Dinding Bata Merah


A TENAGA 21,420.00
L.01 0.15 OH Pekerja 80,000.00 12,000.00
L.02 0.075 OH Tukang batu 100,000.00 7,500.00
L.03 0.008 OH Kepala Tukang 120,000.00 960.00
L.04 0.008 OH Mandor 120,000.00 960.00
B BAHAN 4,351.20
3.108 Kg Portland Cement 1,400.00 4,351.20
C PERALATAN
D Jumlah A + B + C 25,771.20
E Overhead & Profit 10% 2,577.12
F Harga Satuan Pekerjaan (D+E) 28,348.32

8 A.4.4.2.25 1 M2 Pemasangan Finishing Siar Pasangan Dinding Conblock ekspose


A TENAGA 10,060.00
L.01 0.070 OH Pekerja 80,000.00 5,600.00
L.02 0.035 OH Tukang batu 100,000.00 3,500.00
L.03 0.004 OH Kepala Tukang 120,000.00 480.00
L.04 0.004 OH Mandor 120,000.00 480.00
B BAHAN 2,240.00
1.600 Kg Portland Cement 1,400.00 2,240.00
C PERALATAN
D Jumlah A + B + C 12,300.00
E Overhead & Profit 10% 1,230.00
F Harga Satuan Pekerjaan (D+E) 13,530.00

9 A.4.4.2.26 1 M2 Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc : 2Pp


TENAGA 42,600.00
L.01 0.3 OH Pekerja 80,000.00 24,000.00
L.02 0.15 OH Tukang batu 100,000.00 15,000.00
L.03 0.015 OH Kepala Tukang 120,000.00 1,800.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
BAHAN 10,016.00
6.34 Kg Portland Cement 1,400.00 8,876.00
0.012 M3 Pasir Pasang 95,000.00 1,140.00
C PERALATAN
D Jumlah A + B + C 52,616.00
E Overhead & Profit 10% 5,261.60
F Harga Satuan Pekerjaan (D+E) 57,877.60

10 A.4.4.2.27 1 M2 Pemasangan Acian


TENAGA 28,400.00
L.01 0.20 OH Pekerja 80,000.00 16,000.00
L.02 0.10 OH Tukang batu 100,000.00 10,000.00
L.03 0.010 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.010 OH Mandor 120,000.00 1,200.00
BAHAN 4,550.00
3.25 Kg Portland Cement 1,400.00 4,550.00
C PERALATAN
D Jumlah A + B + C 32,950.00
E Overhead & Profit 10% 3,295.00
F Harga Satuan Pekerjaan (D+E) 36,245.00
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
VIII A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING
1 A.4.4.3.3.4a 1 M2 Pemasangan Lantai Keramik 40 x 40 cm Polos
A TENAGA 35,620.00
L.01 0.250 OH Pekerja 80,000.00 20,000.00
L.02 0.125 OH Tukang Batu 100,000.00 12,500.00
L.03 0.013 OH Kepala Tukang 120,000.00 1,560.00
L.04 0.013 OH Mandor 120,000.00 1,560.00
B BAHAN 93,295.00
6.630 Buah Ubin Keramik 40 x 40 cm Keramik Polos 10,000.00 66,300.00
9.800 Kg Portland Semen 1,400.00 13,720.00
0.045 M3 Pasir Pasang 95,000.00 4,275.00
0.600 Kg Semen Warna 15,000.00 9,000.00
C PERALATAN ###
D Jumlah A + B + C 128,915.00
E Overhead & Profit 10% 12,891.50
F Harga Satuan Pekerjaan (D+E) 141,806.50

2 A.4.4.3.3.4b 1 M2 Pemasangan Lantai Keramik 40 x 40 cm Warna/Kasar


A TENAGA 35,620.00
L.01 0.250 OH Pekerja 80,000.00 20,000.00
L.02 0.125 OH Tukang Batu 100,000.00 12,500.00
L.03 0.013 OH Kepala Tukang 120,000.00 1,560.00
L.04 0.013 OH Mandor 120,000.00 1,560.00
B BAHAN 102,135.00
6.630 Buah Ubin Keramik 40 x 40 cm Keramik Warna/Kasar 11,333.33 75,140.00
9.800 Kg Portland Semen 1,400.00 13,720.00
0.045 M3 Pasir Pasang 95,000.00 4,275.00
0.600 Kg Semen Warna 15,000.00 9,000.00
C PERALATAN ###
D Jumlah A + B + C 137,755.00
E Overhead & Profit 10% 13,775.50
F Harga Satuan Pekerjaan (D+E) 151,530.50

3 A.4.4.3.3.5a 1 M2 Pemasangan Lantai Keramik 30 x 30 cm Polos


A TENAGA 36,920.00
L.01 0.260 OH Pekerja 80,000.00 20,800.00
L.02 0.130 OH Tukang Batu 100,000.00 13,000.00
L.03 0.013 OH Kepala Tukang 120,000.00 1,560.00
L.04 0.013 OH Mandor 120,000.00 1,560.00
B BAHAN 92,020.45
11.870 Buah Ubin Keramik 30 x 30 cm Keramik Polos 5,454.55 64,745.45
10.000 Kg Portland Semen 1,400.00 14,000.00
0.045 M3 Pasir Pasang 95,000.00 4,275.00
0.600 Kg Semen Warna 15,000.00 9,000.00
C PERALATAN
D Jumlah A + B + C 128,940.45
E Overhead & Profit 10% 12,894.05
F Harga Satuan Pekerjaan (D+E) 141,834.50

4 A.4.4.3.3.5b 1 M2 Pemasangan Lantai Keramik 30 x 30 cm Kasar/Warna


A TENAGA 36,920.00
L.01 0.260 OH Pekerja 80,000.00 20,800.00
L.02 0.130 OH Tukang Batu 100,000.00 13,000.00
L.03 0.013 OH Kepala Tukang 120,000.00 1,560.00
L.04 0.013 OH Mandor 120,000.00 1,560.00
B BAHAN 100,653.18
11.870 Buah Ubin Keramik 30 x 30 cm Keramik Kasar/Warna 6,181.82 73,378.18
10.000 Kg Portland Semen 1,400.00 14,000.00
0.045 M3 Pasir Pasang 95,000.00 4,275.00
0.600 Kg Semen Warna 15,000.00 9,000.00
C PERALATAN
D Jumlah A + B + C 137,573.18
E Overhead & Profit 10% 13,757.32
F Harga Satuan Pekerjaan (D+E) 151,330.50

5 A.4.4.3.3.9a 1 M2 Pemasangan Lantai Granit 40 x 40 cm Polish


A TENAGA 35,620.00
L.01 0.250 OH Pekerja 80,000.00 20,000.00
L.02 0.125 OH Tukang Batu 100,000.00 12,500.00
L.03 0.013 OH Kepala Tukang 120,000.00 1,560.00
L.04 0.013 OH Mandor 120,000.00 1,560.00
B BAHAN 236,395.00
6.630 Buah Granit 40 x 40 cm Polish 30,000.00 198,900.00
9.800 Kg Portland Semen 1,400.00 13,720.00
1.300 Kg Semen Warna 15,000.00 19,500.00
0.045 M3 Pasir Pasang 95,000.00 4,275.00
C PERALATAN
D Jumlah A + B + C 272,015.00
E Overhead & Profit 10% 27,201.50
F Harga Satuan Pekerjaan (D+E) 299,216.50
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
VIII A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING
6 A.4.4.3.3.9b 1 M2 Pemasangan Lantai Granit 40 x 40 cm UnPolish
A TENAGA 35,620.00
L.01 0.250 OH Pekerja 80,000.00 20,000.00
L.02 0.125 OH Tukang Batu 100,000.00 12,500.00
L.03 0.013 OH Kepala Tukang 120,000.00 1,560.00
L.04 0.013 OH Mandor 120,000.00 1,560.00
B BAHAN 269,545.00
6.630 Buah Granit 40 x 40 cm UnPolish 35,000.00 232,050.00
9.800 Kg Portland Semen 1,400.00 13,720.00
1.300 Kg Semen Warna 15,000.00 19,500.00
0.045 M3 Pasir Pasang 95,000.00 4,275.00
C PERALATAN
D Jumlah A + B + C 305,165.00
E Overhead & Profit 10% 30,516.50
F Harga Satuan Pekerjaan (D+E) 335,681.50

7 A.4.4.3.3.13a 1 M2 Pemasangan Lantai Granit 60 x 60 cm Polish


A TENAGA 34,080.00
L.01 0.240 OH Pekerja 80,000.00 19,200.00
L.02 0.120 OH Tukang Batu 100,000.00 12,000.00
L.03 0.012 OH Kepala Tukang 120,000.00 1,440.00
L.04 0.012 OH Mandor 120,000.00 1,440.00
B BAHAN 238,215.00
4.400 Buah Granit 60 x 60 cm Polish 45,000.00 198,000.00
9.600 Kg Portland Semen 1,400.00 13,440.00
1.500 Kg Semen Warna 15,000.00 22,500.00
0.045 M3 Pasir Pasang 95,000.00 4,275.00
C PERALATAN
D Jumlah A + B + C 272,295.00
E Overhead & Profit 10% 27,229.50
F Harga Satuan Pekerjaan (D+E) 299,524.50

8 A.4.4.3.3.13b 1 M2 Pemasangan Lantai Granit 60 x 60 cm UnPolish


A TENAGA 34,080.00
L.01 0.240 OH Pekerja 80,000.00 19,200.00
L.02 0.120 OH Tukang Batu 100,000.00 12,000.00
L.03 0.012 OH Kepala Tukang 120,000.00 1,440.00
L.04 0.012 OH Mandor 120,000.00 1,440.00
B BAHAN 271,215.00
4.400 Buah Granit 60 x 60 cm UnPolish 52,500.00 231,000.00
9.600 Kg Portland Semen 1,400.00 13,440.00
1.500 Kg Semen Warna 15,000.00 22,500.00
0.045 M3 Pasir Pasang 95,000.00 4,275.00
C PERALATAN
D Jumlah A + B + C 305,295.00
E Overhead & Profit 10% 30,529.50
F Harga Satuan Pekerjaan (D+E) 335,824.50

9 A.4.4.3.3.21a 1 M Pemasangan Plint Keramik 10 x 40 cm, Polos


A TENAGA 17,880.00
L.01 0.090 OH Pekerja 80,000.00 7,200.00
L.02 0.090 OH Tukang Batu 100,000.00 9,000.00
L.03 0.009 OH Kepala Tukang 120,000.00 1,080.00
L.04 0.005 OH Mandor 120,000.00 600.00
B BAHAN 16,631.00
2.650 Buah Plint Keramik 10x40 cm Polos 5,000.00 13,250.00
1.140 Kg Portland Semen 1,400.00 1,596.00
0.100 Kg Semen Warna 15,000.00 1,500.00
0.003 M3 Pasir Pasang 95,000.00 285.00
C PERALATAN
D Jumlah A + B + C 34,511.00
E Overhead & Profit 10% 3,451.10
F Harga Satuan Pekerjaan (D+E) 37,962.10

10 A.4.4.3.3.21b 1 M Pemasangan Plint Keramik 10 x 40 cm, Warna


A TENAGA 17,880.00
L.01 0.090 OH Pekerja 80,000.00 7,200.00
L.02 0.090 OH Tukang Batu 100,000.00 9,000.00
L.03 0.009 OH Kepala Tukang 120,000.00 1,080.00
L.04 0.005 OH Mandor 120,000.00 600.00
B BAHAN 19,281.00
2.650 Buah Plint Keramik 10x40 cm Warna 6,000.00 15,900.00
1.140 Kg Portland Semen 1,400.00 1,596.00
0.100 Kg Semen Warna 15,000.00 1,500.00
0.003 M3 Pasir Pasang 95,000.00 285.00
C PERALATAN
D Jumlah A + B + C 37,161.00
E Overhead & Profit 10% 3,716.10
F Harga Satuan Pekerjaan (D+E) 40,877.10
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
VIII A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING
11 A.4.4.3.3.24 1 M Pemasangan Plint Granit 10 x 40 cm, Polish
A TENAGA 17,880.00
L.01 0.090 OH Pekerja 80,000.00 7,200.00
L.02 0.090 OH Tukang Batu 100,000.00 9,000.00
L.03 0.009 OH Kepala Tukang 120,000.00 1,080.00
L.04 0.005 OH Mandor 120,000.00 600.00
B BAHAN 23,256.00
2.650 Buah Plint Granit 10x40 cm Polish 7,500.00 19,875.00
1.140 Kg Portland Semen 1,400.00 1,596.00
0.100 Kg Semen Warna 15,000.00 1,500.00
0.003 M3 Pasir Pasang 95,000.00 285.00
C PERALATAN
D Jumlah A + B + C 41,136.00
E Overhead & Profit 10% 4,113.60
F Harga Satuan Pekerjaan (D+E) 45,249.60

12 A.4.4.3.3.28 1 M Pemasangan Plint Granit 10 x 60 cm, Polish


A TENAGA 17,880.00
L.01 0.090 OH Pekerja 80,000.00 7,200.00
L.02 0.090 OH Tukang Batu 100,000.00 9,000.00
L.03 0.009 OH Kepala Tukang 120,000.00 1,080.00
L.04 0.005 OH Mandor 120,000.00 600.00
B BAHAN 20,381.00
1.700 Buah Plint Granit 10x60 cm Polish 10,000.00 17,000.00
1.140 Kg Portland Semen 1,400.00 1,596.00
0.100 Kg Semen Warna 15,000.00 1,500.00
0.003 M3 Pasir Pasang 95,000.00 285.00
C PERALATAN
D Jumlah A + B + C 38,261.00
E Overhead & Profit 10% 3,826.10
F Harga Satuan Pekerjaan (D+E) 42,087.10

13 A.4.4.3.3.36 1 M2 Pemasangan Lantai Keramik 20 x 20 cm Motif


A TENAGA 99,400.00
L.01 0.700 OH Pekerja 80,000.00 56,000.00
L.02 0.350 OH Tukang Batu 100,000.00 35,000.00
L.03 0.035 OH Kepala Tukang 120,000.00 4,200.00
L.04 0.035 OH Mandor 120,000.00 4,200.00
B BAHAN 98,415.00
26.500 Buah Ubin Keramik 20 x 20 cm Motif 2,720.00 72,080.00
10.400 Kg Portland Semen 1,400.00 14,560.00
0.500 Kg Semen Warna 15,000.00 7,500.00
0.045 M3 Pasir Pasang 95,000.00 4,275.00
C PERALATAN
D Jumlah A + B + C 197,815.00
E Overhead & Profit 10% 19,781.50
F Harga Satuan Pekerjaan (D+E) 217,596.50

14 A.4.4.3.3.46a 1 M2 Pemasangan Lantai Parkit Kayu


A TENAGA 99,400.00
L.01 0.700 OH Pekerja 80,000.00 56,000.00
L.02 0.350 OH Tukang Batu 100,000.00 35,000.00
L.03 0.035 OH Kepala Tukang 120,000.00 4,200.00
L.04 0.035 OH Mandor 120,000.00 4,200.00
B BAHAN 262,500.00
1.050 M2 Parkit Kayu 230,000.00 241,500.00
0.600 Kg Lem Aibon 35,000.00 21,000.00
C PERALATAN
D Jumlah A + B + C 361,900.00
E Overhead & Profit 10% 36,190.00
F Harga Satuan Pekerjaan (D+E) 398,090.00

15 A.4.4.3.3.46b 1 M2 Pemasangan Lantai Parkit Vinyl Karet


A TENAGA 99,400.00
L.01 0.700 OH Pekerja 80,000.00 56,000.00
L.02 0.350 OH Tukang Batu 100,000.00 35,000.00
L.03 0.035 OH Kepala Tukang 120,000.00 4,200.00
L.04 0.035 OH Mandor 120,000.00 4,200.00
B BAHAN 225,750.00
1.050 M2 Parkit Vinyl Karet 195,000.00 204,750.00
0.600 Kg Lem Aibon 35,000.00 21,000.00
C PERALATAN
D Jumlah A + B + C 325,150.00
E Overhead & Profit 10% 32,515.00
F Harga Satuan Pekerjaan (D+E) 357,665.00
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
VIII A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING
16 A.4.4.3.54 1 M2 Pemasangan Dinding Keramik 20x20 cm, Warna
A TENAGA 127,800.00
L.01 0.900 OH Pekerja 80,000.00 72,000.00
L.02 0.450 OH Tukang Batu 100,000.00 45,000.00
L.03 0.045 OH Kepala Tukang 120,000.00 5,400.00
L.04 0.045 OH Mandor 120,000.00 5,400.00
B BAHAN 115,910.00
26.500 Buah Keramik 20 x 20 cm Warna 2,720.00 72,080.00
9.300 Kg Portland Semen 1,400.00 13,020.00
0.018 M3 Pasir Pasang 95,000.00 1,710.00
1.940 Kg Semen Warna 15,000.00 29,100.00
C PERALATAN
D Jumlah A + B + C 243,710.00
E Overhead & Profit 10% 24,371.00
F Harga Satuan Pekerjaan (D+E) 268,081.00

17 Modified 1 M2 Pemasangan Dinding Keramik 25x40 cm, Warna


A TENAGA 63,900.00
L.01 0.450 OH Pekerja 80,000.00 36,000.00
L.02 0.225 OH Tukang Batu 100,000.00 22,500.00
L.03 0.023 OH Kepala Tukang 120,000.00 2,700.00
L.04 0.023 OH Mandor 120,000.00 2,700.00
B BAHAN 104,080.00
11.000 Buah Keramik 25 x 40 cm Warna 6,800.00 74,800.00
9.300 Kg Portland Semen 1,400.00 13,020.00
0.018 M3 Pasir Pasang 95,000.00 1,710.00
0.970 Kg Semen Warna 15,000.00 14,550.00
C PERALATAN
D Jumlah A + B + C 167,980.00
E Overhead & Profit 10% 16,798.00
F Harga Satuan Pekerjaan (D+E) 184,778.00

18 Modified 1 M2 Pemasangan Dinding Granit 40x40 cm, Polish


A TENAGA 63,900.00
L.01 0.450 OH Pekerja 80,000.00 36,000.00
L.02 0.225 OH Tukang Batu 100,000.00 22,500.00
L.03 0.023 OH Kepala Tukang 120,000.00 2,700.00
L.04 0.023 OH Mandor 120,000.00 2,700.00
B BAHAN 220,905.00
6.630 Buah Granit 40x40 cm, Polish 30,000.00 198,900.00
9.300 Kg Portland Semen 1,400.00 13,020.00
0.018 M3 Pasir Pasang 95,000.00 1,710.00
0.485 Kg Semen Warna 15,000.00 7,275.00
C PERALATAN
D Jumlah A + B + C 284,805.00
E Overhead & Profit 10% 28,480.50
F Harga Satuan Pekerjaan (D+E) 313,285.50

19 Modified 1 M2 Pemasangan Dinding Granit 60x60 cm, Polish


A TENAGA 63,900.00
L.01 0.450 OH Pekerja 80,000.00 36,000.00
L.02 0.225 OH Tukang Batu 100,000.00 22,500.00
L.03 0.023 OH Kepala Tukang 120,000.00 2,700.00
L.04 0.023 OH Mandor 120,000.00 2,700.00
B BAHAN 217,580.00
4.400 Buah Granit 60x60 cm, Polish 45,000.00 198,000.00
9.300 Kg Portland Semen 1,400.00 13,020.00
0.018 M3 Pasir Pasang 95,000.00 1,710.00
0.323 Kg Semen Warna 15,000.00 4,850.00
C PERALATAN
D Jumlah A + B + C 281,480.00
E Overhead & Profit 10% 28,148.00
F Harga Satuan Pekerjaan (D+E) 309,628.00

20 A.4.4.3.57 1 M2 Pemasangan Dinding Batu Paras


A TENAGA 99,400.00
L.01 0.700 OH Pekerja 80,000.00 56,000.00
L.02 0.350 OH Tukang Batu 100,000.00 35,000.00
L.03 0.035 OH Kepala Tukang 120,000.00 4,200.00
L.04 0.035 OH Mandor 120,000.00 4,200.00
B BAHAN 195,775.00
1.100 M2 Batu Paras 160,000.00 176,000.00
11.750 Kg Portland Semen 1,400.00 16,450.00
0.035 M3 Pasir Pasang 95,000.00 3,325.00
C PERALATAN
D Jumlah A + B + C 295,175.00
E Overhead & Profit 10% 29,517.50
F Harga Satuan Pekerjaan (D+E) 324,692.50
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
VIII A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING
21 A.4.4.3.58a 1 M2 Pemasangan Dinding Batu Andesit
A TENAGA 99,400.00
L.01 0.700 OH Pekerja 80,000.00 56,000.00
L.02 0.350 OH Tukang Batu 100,000.00 35,000.00
L.03 0.035 OH Kepala Tukang 120,000.00 4,200.00
L.04 0.035 OH Mandor 120,000.00 4,200.00
B BAHAN 217,775.00
1.100 M2 Batu Andesit 180,000.00 198,000.00
11.750 Kg Portland Semen 1,400.00 16,450.00
0.035 M3 Pasir Pasang 95,000.00 3,325.00
C PERALATAN
D Jumlah A + B + C 317,175.00
E Overhead & Profit 10% 31,717.50
F Harga Satuan Pekerjaan (D+E) 348,892.50

22 A.4.4.3.58b 1 M2 Pemasangan Dinding Batu Tempel Hitam 312,592.50


A TENAGA 99,400.00
L.01 0.700 OH Pekerja 80,000.00 56,000.00
L.02 0.350 OH Tukang Batu 100,000.00 35,000.00
L.03 0.035 OH Kepala Tukang 120,000.00 4,200.00
L.04 0.035 OH Mandor 120,000.00 4,200.00
B BAHAN 184,775.00
1.100 M2 Batu Tempel Hitam 150,000.00 165,000.00
11.750 Kg Portland Semen 1,400.00 16,450.00
0.035 M3 Pasir Pasang 95,000.00 3,325.00
C PERALATAN
D Jumlah A + B + C 284,175.00
E Overhead & Profit 10% 28,417.50
F Harga Satuan Pekerjaan (D+E) 312,592.50

23 A.4.4.3.64 1 M2 Pas. Paving Block/Konblok abu-abu Tebal 6 cm


A TENAGA 34,216.00
L.01 0.250 Oh Pekerja 80,000.00 20,000.00
L.02 0.125 Oh Tukang Batu 100,000.00 12,500.00
L.03 0.013 Oh Kepala Tukang 120,000.00 1,560.00
L.04 0.001 Oh Mandor 120,000.00 156.00
B BAHAN 76,970.00
1.010 M2 Paving abu-abu 6 cm 72,000.00 72,720.00
0.050 M3 Pasir urug 85,000.00 4,250.00

C PERALATAN
D Jumlah A + B + C 111,186.00
E Overhead & Profit 10% 11,118.60
F Harga Satuan Pekerjaan (D+E) 122,304.60

24 A.4.4.3.65 1 M2 Pas. Paving Block/Konblok abu-abu Tebal 8 cm


A TENAGA 68,300.00
L.01 0.500 Oh Pekerja 80,000.00 40,000.00
L.02 0.250 Oh Tukang Batu 100,000.00 25,000.00
L.03 0.025 Oh Kepala Tukang 120,000.00 3,000.00
L.04 0.003 Oh Mandor 120,000.00 300.00
B BAHAN 95,520.00
1.050 M2 Paving abu-abu 8 cm 90,000.00 94,500.00
0.012 M3 Pasir urug 85,000.00 1,020.00
C PERALATAN
D Jumlah A + B + C 163,820.00
E Overhead & Profit 10% 16,382.00
F Harga Satuan Pekerjaan (D+E) 180,202.00
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp

1 A.4.5.1.5 1 M2 Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 4 mm


A TENAGA 19,800.00
L.01 0.10 OH Pekerja 80,000.00 8,000.00
L.02 0.10 OH Tukang Kayu 100,000.00 10,000.00
L.03 0.01 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.005 OH Mandor 120,000.00 600.00
B BAHAN 24,150.00
0.375 Lbr Tripleks (4 mm) 62,800.00 23,550.00
0.03 Kg Paku Tripleks 20,000.00 600.00
C PERALATAN
D Jumlah A + B + C 43,950.00
E Overhead & Profit 10% 4,395.00
F Harga Satuan Pekerjaan (D+E) 48,345.00

2 A.4.5.1.7a 1 M2 Memasang Langit-langit Gypsum Board, Uk (120x240) Tebal 9 mm


A TENAGA 14,200.00
L.01 0.1 OH Pekerja 80,000.00 8,000.00
L.02 0.05 OH Tukang Kayu 100,000.00 5,000.00
L.03 0.005 OH Kepala Tukang 120,000.00 600.00
L.04 0.005 OH Mandor 120,000.00 600.00
B BAHAN 30,608.00
0.364 Lbr Gypsum Board 72,000.00 26,208.00
0.11 Kg Paku Sekrup 40,000.00 4,400.00
C PERALATAN
D Jumlah A + B + C 44,808.00
E Overhead & Profit 10% 4,480.80
F Harga Satuan Pekerjaan (D+E) 49,288.80

3 A.4.5.1.7b 1 M2 Memasang Langit-langit GRC Board, Uk (120x240) Tebal 4 mm


A TENAGA 14,200.00
L.01 0.1 OH Pekerja 80,000.00 8,000.00
L.02 0.05 OH Tukang Kayu 100,000.00 5,000.00
L.03 0.005 OH Kepala Tukang 120,000.00 600.00
L.04 0.005 OH Mandor 120,000.00 600.00
B BAHAN 34,102.00
0.364 Lbr GRC Board (4 mm) 68,000.00 24,752.00
0.11 Kg Paku Sekrup 85,000.00 9,350.00
C PERALATAN
D Jumlah A + B + C 48,302.00
E Overhead & Profit 10% 4,830.20
F Harga Satuan Pekerjaan (D+E) 53,132.20

4 A.4.5.1.9a 1 M List Langit-Langit Kayu Profil


A TENAGA 9,960.00
L.01 0.05 OH Pekerja 80,000.00 4,000.00
L.02 0.05 OH Tukang Kayu 100,000.00 5,000.00
L.03 0.005 OH Kepala Tukang 120,000.00 600.00
L.04 0.003 OH Mandor 120,000.00 360.00
B BAHAN 10,700.00
1.05 M List Kayu Profil 10,000.00 10,500.00
0.01 Kg Paku 20,000.00 200.00
C PERALATAN
D Jumlah A + B + C 20,660.00
E Overhead & Profit 10% 2,066.00
F Harga Satuan Pekerjaan (D+E) 22,726.00

5 A.4.5.1.9b 1 M List Langit-Langit Gypsum


A TENAGA 9,960.00
L.01 0.05 OH Pekerja 80,000.00 4,000.00
L.02 0.05 OH Tukang Kayu 100,000.00 5,000.00
L.03 0.005 OH Kepala Tukang 120,000.00 600.00
L.04 0.003 OH Mandor 120,000.00 360.00
B BAHAN 14,025.00
1.05 M List Gypsum 13,000.00 13,650.00
0.10 Kg Tepung Gypsum 3,750.00 375.00
C PERALATAN
D Jumlah A + B + C 23,985.00
E Overhead & Profit 10% 2,398.50
F Harga Satuan Pekerjaan (D+E) 26,383.50
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp

X A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP


1 A.4.5.2.30 1 M2 Pemasangan Atap Genteng Beton
A TENAGA 28,400.00
L.01 0.200 OH Pekerja 80,000.00 16,000.00
L.02 0.100 OH Tukang Kayu 100,000.00 10,000.00
L.03 0.010 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.010 OH Mandor 120,000.00 1,200.00
B BAHAN 165,600.00
11.000 Buah Genteng Beton 15,000.00 165,000.00
0.030 Kg Paku 2"-5" 20,000.00 600.00
C PERALATAN
D Jumlah A + B + C 194,000.00
E Overhead & Profit 10% 19,400.00
F Harga Satuan Pekerjaan (D+E) 213,400.00

1 A.4.5.2.32a 1 M2 Pemasangan Atap Genteng Metal T=0,25 mm


A TENAGA 27,320.00
L.01 0.200 OH Pekerja 80,000.00 16,000.00
L.02 0.100 OH Tukang Kayu 100,000.00 10,000.00
L.03 0.010 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.001 OH Mandor 120,000.00 120.00
B BAHAN 67,834.00
1.020 M2 Genteng Metal Multiroof T=0,25 mm 56,700.00 57,834.00
0.200 Kg Paku Skrup 50,000.00 10,000.00
C PERALATAN
D Jumlah A + B + C 95,154.00
E Overhead & Profit 10% 9,515.40
F Harga Satuan Pekerjaan (D+E) 104,669.40

1 A.4.5.2.32b 1 M2 Pemasangan Atap Genteng Metal T=0,3 mm


A TENAGA 27,320.00
L.01 0.200 OH Pekerja 80,000.00 16,000.00
L.02 0.100 OH Tukang Kayu 100,000.00 10,000.00
L.03 0.010 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.001 OH Mandor 120,000.00 120.00
B BAHAN 92,620.00
1.020 M2 Genteng Metal Multiroof T=0,3 mm 81,000.00 82,620.00
0.200 Kg Paku Skrup 50,000.00 10,000.00
C PERALATAN
D Jumlah A + B + C 119,940.00
E Overhead & Profit 10% 11,994.00
F Harga Satuan Pekerjaan (D+E) 131,934.00

1 A.4.5.2.32c 1 M2 Pemasangan Atap Genteng Metal Berpasir


A TENAGA 27,320.00
L.01 0.200 OH Pekerja 80,000.00 16,000.00
L.02 0.100 OH Tukang Kayu 100,000.00 10,000.00
L.03 0.010 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.001 OH Mandor 120,000.00 120.00
B BAHAN 125,668.00
1.020 M2 Genteng Metal Berpasir 113,400.00 115,668.00
0.200 Kg Paku Skrup 50,000.00 10,000.00
C PERALATAN
D Jumlah A + B + C 152,988.00
E Overhead & Profit 10% 15,298.80
F Harga Satuan Pekerjaan (D+E) 168,286.80

1 A.4.5.2.35 1 M2 Pemasangan Nok Genteng Beton


A TENAGA 56,800.00
L.01 0.400 OH Pekerja 80,000.00 32,000.00
L.02 0.200 OH Tukang Kayu 100,000.00 20,000.00
L.03 0.020 OH Kepala Tukang 120,000.00 2,400.00
L.04 0.020 OH Mandor 120,000.00 2,400.00
B BAHAN 104,160.00
3.500 Buah Nok Genteng Beton 20,000.00 70,000.00
0.050 Kg Paku Biasa 20,000.00 1,000.00
10.800 Kg Semen Portland 1,400.00 15,120.00
0.032 M3 Pasir Pasang 95,000.00 3,040.00
1.000 Kg Semen Warna 15,000.00 15,000.00
C PERALATAN
D Jumlah A + B + C 160,960.00
E Overhead & Profit 10% 16,096.00
F Harga Satuan Pekerjaan (D+E) 177,056.00
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp

X A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP


1 A.4.5.2.37 1 M2 Pemasangan Nok Genteng Metal
A TENAGA 38,360.00
L.01 0.250 OH Pekerja 80,000.00 20,000.00
L.02 0.150 OH Tukang Kayu 100,000.00 15,000.00
L.03 0.015 OH Kepala Tukang 120,000.00 1,800.00
L.04 0.013 OH Mandor 120,000.00 1,560.00
B BAHAN 46,500.00
1.100 Buah Nok Genteng Metal 40,000.00 44,000.00
0.050 Kg Paku Sekrup Atap 50,000.00 2,500.00
C PERALATAN
D Jumlah A + B + C 84,860.00
E Overhead & Profit 10% 8,486.00
F Harga Satuan Pekerjaan (D+E) 93,346.00

11 A.4.5.2.39 1 M2 Pemasangan Atap Seng Gelombang ###


A TENAGA 17,040.00
L.01 0.120 OH Pekerja 80,000.00 9,600.00
L.02 0.060 OH Tukang Kayu 100,000.00 6,000.00
L.03 0.006 OH Kepala Tukang 120,000.00 720.00
L.04 0.006 OH Mandor 120,000.00 720.00
B BAHAN 35,400.00
0.700 Lbr Seng Gelombang 3" x 6" BJLS 28 50,000.00 35,000.00
0.020 Kg Paku Biasa 20,000.00 400.00
C PERALATAN
D Jumlah A + B + C 52,440.00
E Overhead & Profit 10% 5,244.00
F Harga Satuan Pekerjaan (D+E) 57,684.00

12 A.4.5.2.40 1 M Pemasangan Atap Nok Seng


A TENAGA 20,560.00
L.01 0.150 OH Pekerja 80,000.00 12,000.00
L.02 0.070 OH Tukang Kayu 100,000.00 7,000.00
L.03 0.007 OH Kepala Tukang 120,000.00 840.00
L.04 0.006 OH Mandor 120,000.00 720.00
B BAHAN 14,300.00
0.300 Lbr Seng Plaat 3" x 6" BJLS 28 45,000.00 13,500.00
0.040 Kg Paku Biasa 20,000.00 800.00
C PERALATAN
D Jumlah A + B + C 34,860.00
E Overhead & Profit 10% 3,486.00
F Harga Satuan Pekerjaan (D+E) 38,346.00

5 A.4.5.2.43 1 M2 Pemasangan Aluminium Foil


A TENAGA 18,560.00
L.01 0.150 OH Pekerja 80,000.00 12,000.00
L.02 0.050 OH Tukang Kayu 100,000.00 5,000.00
L.03 0.005 OH Kepala Tukang 120,000.00 600.00
L.04 0.008 OH Mandor 120,000.00 960.00
B BAHAN 15,750.00
1.050 M2 Aluminium Foil 15,000.00 15,750.00
C PERALATAN
D Jumlah A + B + C 34,310.00
E Overhead & Profit 10% 3,431.00
F Harga Satuan Pekerjaan (D+E) 37,741.00
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U
1 A.4.6.1.1 1 M3 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu Kelas I
TENAGA 2,954,000.00
L.01 7.000 OH Pekerja 80,000.00 560,000.00
L.02 21.000 OH Tukang Kayu 100,000.00 2,100,000.00
L.03 2.100 OH Kepala Tukang 120,000.00 252,000.00
L.04 0.350 OH Mandor 120,000.00 42,000.00
BAHAN 6,652,000.00
1.100 M3 Kayu Balok Kelas I/Kusen 6,000,000.00 6,600,000.00
1.250 Kg Paku Biasa 2" - 5 " 20,000.00 25,000.00
1.000 Kg Lem Kayu 27,000.00 27,000.00
C PERALATAN
D Jumlah A + B + C 9,606,000.00
E Overhead & Profit 10% 960,600.00
F Harga Satuan Pekerjaan (D+E) 10,566,600.00

2 A.4.6.1.2 1 M3 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu Kelas II
A TENAGA 2,532,000.00
L.01 6.000 OH Pekerja 80,000.00 480,000.00
L.02 18.000 OH Tukang Kayu 100,000.00 1,800,000.00
L.03 1.800 OH Kepala Tukang 120,000.00 216,000.00
L.04 0.300 OH Mandor 120,000.00 36,000.00
B BAHAN 4,012,000.00
1.200 M3 Kayu Balok Kelas II/Kusen 3,300,000.00 3,960,000.00
1.250 Kg Paku Biasa 2" - 5 " 20,000.00 25,000.00
1.000 Kg Lem Kayu 27,000.00 27,000.00
C PERALATAN
D Jumlah A + B + C 6,544,000.00
E Overhead & Profit 10% 654,400.00
F Harga Satuan Pekerjaan (D+E) 7,198,400.00

3 A.4.6.1.5a 1 M2 Pembuatan & Pemasangan Daun Pintu Panel, Kayu Kelas I


A TENAGA 422,000.00
L.01 1.000 OH Pekerja 80,000.00 80,000.00
L.02 3.000 OH Tukang Kayu 100,000.00 300,000.00
L.03 0.300 OH Kepala Tukang 120,000.00 36,000.00
L.04 0.050 OH Mandor 120,000.00 6,000.00
B BAHAN 253,500.00
0.040 M3 Kayu Papan Kelas I/Kusen 6,000,000.00 240,000.00
0.500 Kg Lem Kayu 27,000.00 13,500.00
C PERALATAN
D Jumlah A + B + C 675,500.00
E Overhead & Profit 10% 67,550.00
F Harga Satuan Pekerjaan (D+E) 743,050.00

4 A.4.6.1.5b 1 M2 Pembuatan & Pemasangan Daun Pintu Panel, Kayu Kelas II


A TENAGA 422,000.00
L.01 1.000 OH Pekerja 80,000.00 80,000.00
L.02 3.000 OH Tukang Kayu 100,000.00 300,000.00
L.03 0.300 OH Kepala Tukang 120,000.00 36,000.00
L.04 0.050 OH Mandor 120,000.00 6,000.00
B BAHAN 145,500.00
0.040 M3 Kayu Papan Kelas II/Kusen 3,300,000.00 132,000.00
0.500 kg Lem Kayu 27,000.00 13,500.00
C PERALATAN
D Jumlah A + B + C 567,500.00
E Overhead & Profit 10% 56,750.00
F Harga Satuan Pekerjaan (D+E) 624,250.00

5 A.4.6.1.6 1 M2 Pembuatan & Pemasangan Pintu & Jendela Kaca Kayu Kelas II
A TENAGA 337,600.00
L.01 0.800 OH Pekerja 80,000.00 64,000.00
L.02 2.400 OH Tukang Kayu 100,000.00 240,000.00
L.03 0.240 OH Kepala Tukang 120,000.00 28,800.00
L.04 0.040 OH Mandor 120,000.00 4,800.00
B BAHAN 87,300.00
0.024 M3 Kayu Papan Kelas II/Kusen 3,300,000.00 79,200.00
0.300 Kg Lem Kayu 27,000.00 8,100.00
C PERALATAN
D Jumlah A + B + C 424,900.00
E Overhead & Profit 10% 42,490.00
F Harga Satuan Pekerjaan (D+E) 467,390.00
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U
6 A.4.6.1.10 1 M2 Pembuatan & Pemasangan Jalusi Mati Kosen Kayu Kelas II
A TENAGA 317,800.00
L.01 0.670 OH Pekerja 80,000.00 53,600.00
L.02 2.000 OH Tukang Kayu 100,000.00 200,000.00
L.03 0.200 OH Kepala Tukang 120,000.00 24,000.00
L.04 0.335 OH Mandor 120,000.00 40,200.00
B BAHAN 201,000.00
0.060 M3 Kayu Papan Kelas II/Kusen 3,300,000.00 198,000.00
0.150 Kg Paku Biasa 20,000.00 3,000.00
C PERALATAN
D Jumlah A + B + C 518,800.00
E Overhead & Profit 10% 51,880.00
F Harga Satuan Pekerjaan (D+E) 570,680.00

7 A.4.6.1.13a 1 M3 Pembuatan&Memasang Konstruksi Kuda-kuda Konvensional Kayu Kelas I Bentang 6 meter


A TENAGA 1,688,000.00
L.01 4.000 OH Pekerja 80,000.00 320,000.00
L.02 12.000 OH Tukang Kayu 100,000.00 1,200,000.00
L.03 1.200 OH Kepala Tukang 120,000.00 144,000.00
L.04 0.200 OH Mandor 120,000.00 24,000.00
B BAHAN 6,862,000.00
1.100 M3 Kayu Balok Kelas I/Kusen 6,000,000.00 6,600,000.00
15.000 Kg Besi Strip 10,000.00 150,000.00
5.600 Kg Paku Biasa 2" - 5" 20,000.00 112,000.00
C PERALATAN
D Jumlah A + B + C 8,550,000.00
E Overhead & Profit 10% 855,000.00
F Harga Satuan Pekerjaan (D+E) 9,405,000.00

8 A.4.6.1.13b 1 M3 Pembuatan&Memasang Konstruksi Kuda-kuda Konvensional Kayu Kelas II Bentang 6 meter


A TENAGA 1,688,000.00
L.01 4.000 OH Pekerja 80,000.00 320,000.00
L.02 12.000 OH Tukang Kayu 100,000.00 1,200,000.00
L.03 1.200 OH Kepala Tukang 120,000.00 144,000.00
L.04 0.200 OH Mandor 120,000.00 24,000.00
B BAHAN 3,892,000.00
1.100 M3 Kayu Balok Kelas II/Kusen 3,300,000.00 3,630,000.00
15.000 Kg Besi Strip 10,000.00 150,000.00
5.600 Kg Paku Biasa 2" - 5" 20,000.00 112,000.00
C PERALATAN
D Jumlah A + B + C 5,580,000.00
E Overhead & Profit 10% 558,000.00
F Harga Satuan Pekerjaan (D+E) 6,138,000.00

9 A.4.6.1.15 1 M3 Pemasangan Konstruksi Gording, Kayu Klas II


A TENAGA 2,827,400.00
L.01 6.700 OH Pekerja 80,000.00 536,000.00
L.02 20.100 OH Tukang Kayu 100,000.00 2,010,000.00
L.03 2.010 OH Kepala Tukang 120,000.00 241,200.00
L.04 0.335 OH Mandor 120,000.00 40,200.00
B BAHAN 3,840,000.00
1.100 M3 Kayu Balok Kelas II/Kusen 3,300,000.00 3,630,000.00
15.000 Kg Besi Strip 10,000.00 150,000.00
3.000 Kg Paku Biasa 2" - 5" 20,000.00 60,000.00
C PERALATAN
D Jumlah A + B + C 6,667,400.00
E Overhead & Profit 10% 666,740.00
F Harga Satuan Pekerjaan (D+E) 7,334,140.00

10 A.4.6.1.16 1 M2 Pemasangan Rangka Atap Genteng Keramik, Kayu Kelas II


A TENAGA 19,800.00
L.01 0.100 OH Pekerja 80,000.00 8,000.00
L.02 0.100 OH Tukang Kayu 100,000.00 10,000.00
L.03 0.010 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.005 OH Mandor 120,000.00 600.00
B BAHAN 170,000.00
0.014 M3 Kayu Klas II Balok, Kaso-kaso (5x7) cm 3,300,000.00 46,200.00
0.036 M3 Kayu Kelas II Balok Reng (2x3) cm 3,300,000.00 118,800.00
0.250 Kg Paku Biasa 2" - 5" 20,000.00 5,000.00
C PERALATAN
D Jumlah A + B + C 189,800.00
E Overhead & Profit 10% 18,980.00
F Harga Satuan Pekerjaan (D+E) 208,780.00
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U
11 A.4.6.1.17 1 M2 Pemasangan Rangka Atap Genteng Beton, Kayu Kelas II 285,010.00
A TENAGA 19,800.00
L.01 0.100 OH Pekerja 80,000.00 8,000.00
L.02 0.100 OH Tukang Kayu 100,000.00 10,000.00
L.03 0.010 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.005 OH Mandor 120,000.00 600.00
B BAHAN 239,300.00
0.014 M3 Kayu Klas II Balok, Kaso-kaso (5x7) cm 3,300,000.00 46,200.00
0.057 M3 Kayu Kelas II Balok Reng (2x3) cm 3,300,000.00 188,100.00
0.250 Kg Paku Biasa 2" - 5" 20,000.00 5,000.00
C PERALATAN
D Jumlah A + B + C 259,100.00
E Overhead & Profit 10% 25,910.00
F Harga Satuan Pekerjaan (D+E) 285,010.00

12 A.4.6.1.19 1 M2 Pemasangan Rangka Langit-langit (60 x 120) Cm, Kayu Kelas II


A TENAGA 54,600.00
L.01 0.150 OH Pekerja 80,000.00 12,000.00
L.02 0.300 OH Tukang Kayu 100,000.00 30,000.00
L.03 0.030 OH Kepala Tukang 120,000.00 3,600.00
L.04 0.075 OH Mandor 120,000.00 9,000.00
B BAHAN 54,820.00
0.015 M3 Kayu Balok Kelas II/Kusen 3,300,000.00 50,820.00
0.200 Kg Paku Biasa 2" - 5" 20,000.00 4,000.00
C PERALATAN
D Jumlah A + B + C 109,420.00
E Overhead & Profit 10% 10,942.00
F Harga Satuan Pekerjaan (D+E) 120,362.00

13 A.4.6.1.21 1 M Pemasangan Listplank Uk. (3x20)cm Kayu Kelas II


A TENAGA 31,000.00
L.01 0.100 OH Pekerja 80,000.00 8,000.00
L.02 0.200 OH Tukang Kayu 100,000.00 20,000.00
L.03 0.020 OH Kepala Tukang 120,000.00 2,400.00
L.04 0.005 OH Mandor 120,000.00 600.00
B BAHAN 37,640.00
0.011 M3 Kayu Papan Kelas II/Kusen 3,300,000.00 35,640.00
0.100 Kg Paku Biasa 2" - 5" 20,000.00 2,000.00
C PERALATAN
D Jumlah A + B + C 68,640.00
E Overhead & Profit 10% 6,864.00
F Harga Satuan Pekerjaan (D+E) 75,504.00

14 A.4.6.1.22 1 M Pemasangan Listplank Uk. (3x30)cm KayuKelas II


A TENAGA 31,000.00
L.01 0.100 OH Pekerja 80,000.00 8,000.00
L.02 0.200 OH Tukang Kayu 100,000.00 20,000.00
L.03 0.020 OH Kepala Tukang 120,000.00 2,400.00
L.04 0.005 OH Mandor 120,000.00 600.00
B BAHAN 37,300.00
0.011 M3 Kayu Papan Kelas II/Kusen 3,300,000.00 36,300.00
0.050 Kg Paku Biasa 2" - 5" 20,000.00 1,000.00
C PERALATAN
D Jumlah A + B + C 68,300.00
E Overhead & Profit 10% 6,830.00
F Harga Satuan Pekerjaan (D+E) 75,130.00

15 A.4.6.1.23 1 M2 Pemasangan Rangka Dinding Pemisah (60x120) cm Kayu Kelas II


A TENAGA 63,360.00
L.01 0.150 OH Pekerja 80,000.00 12,000.00
L.02 0.450 OH Tukang Kayu 100,000.00 45,000.00
L.03 0.045 OH Kepala Tukang 120,000.00 5,400.00
L.04 0.008 OH Mandor 120,000.00 960.00
B BAHAN 95,400.00
0.028 M3 Kayu Balok Kelas II/Kusen 3,300,000.00 92,400.00
0.150 Kg Paku Biasa 2" - 5" 20,000.00 3,000.00
C PERALATAN
D Jumlah A + B + C 158,760.00
E Overhead & Profit 10% 15,876.00
F Harga Satuan Pekerjaan (D+E) 174,636.00
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U
16 A.4.6.1.25 1 M2 Pemasangan Dinding Pemisah Plywood Rangkap Rangka Kayu Kelas II
A TENAGA 70,000.00
L.01 0.020 OH Pekerja 80,000.00 1,600.00
L.02 0.600 OH Tukang Kayu 100,000.00 60,000.00
L.03 0.060 OH Kepala Tukang 120,000.00 7,200.00
L.04 0.010 OH Mandor 120,000.00 1,200.00
B BAHAN 164,528.00
0.028 M3 Kayu Balok Kelas II/Kusen 3,300,000.00 92,400.00
0.150 Kg Paku Biasa 2" - 5" 20,000.00 3,000.00
0.860 Lbr Plywood 120 x 240 cm (4mm) 62,800.00 54,008.00
0.560 Kg Lem Kayu 27,000.00 15,120.00
C PERALATAN
D Jumlah A + B + C 234,528.00
E Overhead & Profit 10% 23,452.80
F Harga Satuan Pekerjaan (D+E) 257,980.80

17 Modified 1 M Pasang Lisplank GRC lebar 20 cm


A TENAGA 15,320.00
L.01 0.050 OH Pekerja 80,000.00 4,000.00
L.02 0.100 OH Tukang Atap 100,000.00 10,000.00
L.03 0.010 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.001 OH Mandor 120,000.00 120.00
B BAHAN 20,950.00
1.050 M Lisplank GRC Lebar 20 cm 19,000.00 19,950.00
4.000 Pcs Paku Sekrup Atap 250.00 1,000.00
C PERALATAN
D Jumlah A + B + C 36,270.00
E Overhead & Profit 10% 3,627.00
F Harga Satuan Pekerjaan (D+E) 39,897.00

18 Modified 1 M Pasang Lisplank GRC lebar 30 cm


A TENAGA 15,320.00
L.01 0.050 OH Pekerja 80,000.00 4,000.00
L.02 0.100 OH Tukang Atap 100,000.00 10,000.00
L.03 0.010 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.001 OH Mandor 120,000.00 120.00
B BAHAN 35,125.00
1.050 M Lisplank GRC Lebar 30 cm 32,500.00 34,125.00
4.000 Pcs Paku Sekrup Atap 250.00 1,000.00
C PERALATAN
D Jumlah A + B + C 50,445.00
E Overhead & Profit 10% 5,044.50
F Harga Satuan Pekerjaan (D+E) 55,489.50
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
XII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA
1 A.4.6.2.2 1 Buah Pemasangan Kunci Tanam Biasa 2 Slag
A TENAGA 57,400.00
L.01 0.0100 OH Pekerja 80,000.00 800.00
L.02 0.5000 OH Tukang Kayu 100,000.00 50,000.00
L.03 0.0500 OH Kepala Tukang 120,000.00 6,000.00
L.04 0.0050 OH Mandor 120,000.00 600.00
B BAHAN 131,400.00
1.0000 Buah Kunci Tanam Biasa 131,400.00 131,400.00
C PERALATAN
D Jumlah A + B + C 188,800.00
E Overhead & Profit 10% 18,880.00
F Harga Satuan Pekerjaan (D+E) 207,680.00

2 A.4.6.2.3 1 Buah Pemasangan Kunci Kamar Mandi


A TENAGA 56,760.00
L.01 0.0050 OH Pekerja 80,000.00 400.00
L.02 0.5000 OH Tukang Kayu 100,000.00 50,000.00
L.03 0.0500 OH Kepala Tukang 120,000.00 6,000.00
L.04 0.0030 OH Mandor 120,000.00 360.00
B BAHAN 49,500.00
1.0000 Buah Kunci Tanam Kamar Mandi 49,500.00 49,500.00
C PERALATAN
D Jumlah A + B + C 106,260.00
E Overhead & Profit 10% 10,626.00
F Harga Satuan Pekerjaan (D+E) 116,886.00

3 A.4.6.2.5 1 Buah Pemasangan Engsel Pintu


A TENAGA 18,096.00
L.01 0.0150 OH Pekerja 80,000.00 1,200.00
L.02 0.1500 OH Tukang Kayu 100,000.00 15,000.00
L.03 0.0150 OH Kepala Tukang 120,000.00 1,800.00
L.04 0.0008 OH Mandor 120,000.00 96.00
B BAHAN 15,000.00
1.0000 Buah Engsel pintu 15,000.00 15,000.00
C PERALATAN
D Jumlah A + B + C 33,096.00
E Overhead & Profit 10% 3,309.60
F Harga Satuan Pekerjaan (D+E) 36,405.60

4 A.4.6.2.6 1 Buah Pemasangan Engsel Jendela Kupu-kupu 25,366.00


A TENAGA 12,060.00
L.01 0.0100 OH Pekerja 80,000.00 800.00
L.02 0.1000 OH Tukang Kayu 100,000.00 10,000.00
L.03 0.0100 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.0005 OH Mandor 120,000.00 60.00
B BAHAN 11,000.00
1.0000 Buah Engsel Jendela 11,000.00 11,000.00
C PERALATAN
D Jumlah A + B + C 23,060.00
E Overhead & Profit 10% 2,306.00
F Harga Satuan Pekerjaan (D+E) 25,366.00

5 A.4.6.2.9 1 Buah Pemasangan Kait Angin


A TENAGA 18,960.00
L.01 0.0150 OH Pekerja 80,000.00 1,200.00
L.02 0.1500 OH Tukang Kayu 100,000.00 15,000.00
L.03 0.0150 OH Kepala Tukang 120,000.00 1,800.00
L.04 0.0080 OH Mandor 120,000.00 960.00
B BAHAN 15,000.00
1.0000 Buah Kait Angin 15,000.00 15,000.00
C PERALATAN
D Jumlah A + B + C 33,960.00
E Overhead & Profit 10% 3,396.00
F Harga Satuan Pekerjaan (D+E) 37,356.00
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
XII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA
6 A.4.6.2.10 1 Buah Pemasangan Door Closer
A TENAGA 60,360.00
L.01 0.0500 OH Pekerja 80,000.00 4,000.00
L.02 0.5000 OH Tukang Kayu 100,000.00 50,000.00
L.03 0.0500 OH Kepala Tukang 120,000.00 6,000.00
L.04 0.0030 OH Mandor 120,000.00 360.00
B BAHAN 210,000.00
1.0000 Buah Door Closer 210,000.00 210,000.00
C PERALATAN
D Jumlah A + B + C 270,360.00
E Overhead & Profit 10% 27,036.00
F Harga Satuan Pekerjaan (D+E) 297,396.00

7 A.4.6.2.11 1 Buah Pemasangan Kunci Selot (Grendel)


A TENAGA 24,120.00
L.01 0.0200 OH Pekerja 80,000.00 1,600.00
L.02 0.2000 OH Tukang Kayu 100,000.00 20,000.00
L.03 0.0200 OH Kepala Tukang 120,000.00 2,400.00
L.04 0.0010 OH Mandor 120,000.00 120.00
B BAHAN 10,000.00
1.0000 Buah Kunci Selot (Grendel) 10,000.00 10,000.00
C PERALATAN
D Jumlah A + B + C 34,120.00
E Overhead & Profit 10% 3,412.00
F Harga Satuan Pekerjaan (D+E) 37,532.00

8 A.4.6.2.12 1 Buah Pemasangan Tarikan Jendela


A TENAGA 18,960.00
L.01 0.0150 OH Pekerja 80,000.00 1,200.00
L.02 0.1500 OH Tukang Kayu 100,000.00 15,000.00
L.03 0.0150 OH Kepala Tukang 120,000.00 1,800.00
L.04 0.0080 OH Mandor 120,000.00 960.00
B BAHAN 15,000.00
1.0000 Buah Tarikan Jendela 15,000.00 15,000.00
C PERALATAN
D Jumlah A + B + C 33,960.00
E Overhead & Profit 10% 3,396.00
F Harga Satuan Pekerjaan (D+E) 37,356.00

9 A.4.6.2.16 1 M2 Pemasangan Kaca Bening Tebal 3 mm


A TENAGA 18,096.00
L.01 0.0150 OH Pekerja 80,000.00 1,200.00
L.02 0.1500 OH Tukang Kayu 100,000.00 15,000.00
L.03 0.0150 OH Kepala Tukang 120,000.00 1,800.00
L.04 0.0008 OH Mandor 120,000.00 96.00
B BAHAN 101,200.00
1.1000 M2 Kaca Tebal 3 mm 92,000.00 101,200.00
C PERALATAN
D Jumlah A + B + C 119,296.00
E Overhead & Profit 10% 11,929.60
F Harga Satuan Pekerjaan (D+E) 131,225.60

10 A.4.6.2.17a 1 M2 Pemasangan Kaca Bening Tebal 5 mm


A TENAGA 18,096.00
L.01 0.0150 OH Pekerja 80,000.00 1,200.00
L.02 0.1500 OH Tukang Kayu 100,000.00 15,000.00
L.03 0.0150 OH Kepala Tukang 120,000.00 1,800.00
L.04 0.0008 OH Mandor 120,000.00 96.00
B BAHAN 118,800.00
1.1000 M2 Kaca Bening Tebal 5mm 108,000.00 118,800.00
C PERALATAN
D Jumlah A + B + C 136,896.00
E Overhead & Profit 10% 13,689.60
F Harga Satuan Pekerjaan (D+E) 150,585.60

11 A.4.6.2.17b 1 M2 Pemasangan Kaca Rayban Tebal 5 mm


A TENAGA 18,096.00
L.01 0.0150 OH Pekerja 80,000.00 1,200.00
L.02 0.1500 OH Tukang Kayu 100,000.00 15,000.00
L.03 0.0150 OH Kepala Tukang 120,000.00 1,800.00
L.04 0.0008 OH Mandor 120,000.00 96.00
B BAHAN 124,300.00
1.1000 M2 Kaca Rayban Tebal 5 mm 113,000.00 124,300.00
C PERALATAN
D Jumlah A + B + C 142,396.00
E Overhead & Profit 10% 14,239.60
F Harga Satuan Pekerjaan (D+E) 156,635.60
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
XII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA
12 A.4.6.2.18a 1 M2 Pemasangan Kaca Bening Tebal 8 mm
A TENAGA 20,508.00
L.01 0.0170 OH Pekerja 80,000.00 1,360.00
L.02 0.1700 OH Tukang Kayu 100,000.00 17,000.00
L.03 0.0170 OH Kepala Tukang 120,000.00 2,040.00
L.04 0.0009 OH Mandor 120,000.00 108.00
B BAHAN 203,500.00
1.1000 M2 Kaca Bening Tebal 8 mm 185,000.00 203,500.00
C PERALATAN
D Jumlah A + B + C 224,008.00
E Overhead & Profit 10% 22,400.80
F Harga Satuan Pekerjaan (D+E) 246,408.80

13 A.4.6.2.18b 1 M2 Pemasangan Kaca Rayban Tebal 8 mm


A TENAGA 20,508.00
L.01 0.0170 OH Pekerja 80,000.00 1,360.00
L.02 0.1700 OH Tukang Kayu 100,000.00 17,000.00
L.03 0.0170 OH Kepala Tukang 120,000.00 2,040.00
L.04 0.0009 OH Mandor 120,000.00 108.00
B BAHAN 209,000.00
1.1000 M2 Kaca Rayban Tebal 8 mm 190,000.00 209,000.00
C PERALATAN
D Jumlah A + B + C 229,508.00
E Overhead & Profit 10% 22,950.80
F Harga Satuan Pekerjaan (D+E) 252,458.80

14 Modified 1 M2 Pemasangan Kaca Bening Tebal 10 mm


A TENAGA 25,332.00
L.01 0.0210 OH Pekerja 80,000.00 1,680.00
L.02 0.2100 OH Tukang Kayu 100,000.00 21,000.00
L.03 0.0210 OH Kepala Tukang 120,000.00 2,520.00
L.04 0.0011 OH Mandor 120,000.00 132.00
B BAHAN 374,000.00
1.1000 M2 Kaca Bening Tebal 10 mm 340,000.00 374,000.00
C PERALATAN
D Jumlah A + B + C 399,332.00
E Overhead & Profit 10% 39,933.20
F Harga Satuan Pekerjaan (D+E) 439,265.20

15 Modified 1 M2 Pemasangan Kaca Rayban Tebal 10 mm


A TENAGA 25,332.00
L.01 0.0210 OH Pekerja 80,000.00 1,680.00
L.02 0.2100 OH Tukang Kayu 100,000.00 21,000.00
L.03 0.0210 OH Kepala Tukang 120,000.00 2,520.00
L.04 0.0011 OH Mandor 120,000.00 132.00
B BAHAN 385,000.00
1.1000 M2 Kaca Rayban Tebal 10 mm 350,000.00 385,000.00
C PERALATAN
D Jumlah A + B + C 410,332.00
E Overhead & Profit 10% 41,033.20
F Harga Satuan Pekerjaan (D+E) 451,365.20

16 A.4.6.2.19a 1 M2 Pemasangan Kaca Bening Tebal 12 mm


A TENAGA 30,156.00
L.01 0.0250 OH Pekerja 80,000.00 2,000.00
L.02 0.2500 OH Tukang Kayu 100,000.00 25,000.00
L.03 0.0250 OH Kepala Tukang 120,000.00 3,000.00
L.04 0.0013 OH Mandor 120,000.00 156.00
B BAHAN 528,000.00
1.1000 M2 Kaca Bening Tebal 12 mm 480,000.00 528,000.00
C PERALATAN
D Jumlah A + B + C 558,156.00
E Overhead & Profit 10% 55,815.60
F Harga Satuan Pekerjaan (D+E) 613,971.60

17 A.4.6.2.19b 1 M2 Pemasangan Kaca Rayban Tebal 12 mm


A TENAGA 30,156.00
L.01 0.0250 OH Pekerja 80,000.00 2,000.00
L.02 0.2500 OH Tukang Kayu 100,000.00 25,000.00
L.03 0.0250 OH Kepala Tukang 120,000.00 3,000.00
L.04 0.0013 OH Mandor 120,000.00 156.00
B BAHAN 544,500.00
1.1000 M2 Kaca Rayban Tebal 12 mm 495,000.00 544,500.00
C PERALATAN
D Jumlah A + B + C 574,656.00
E Overhead & Profit 10% 57,465.60
F Harga Satuan Pekerjaan (D+E) 632,121.60
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
XIII A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN
1 A.4.7.1.1 1 M2 Pengikisan / Pengerokan Permukaan Cat Tembok Lama
A TENAGA 12,360.00
L.01 0.1500 OH Pekerja 80,000.00 12,000.00
L.04 0.0030 OH Mandor 120,000.00 360.00
B BAHAN 1,360.00
0.0500 Kg Soda Api 27,200.00 1,360.00
C PERALATAN
D Jumlah A + B + C 13,720.00
E Overhead & Profit 10% 1,372.00
F Harga Satuan Pekerjaan (D+E) 15,092.00

2 A.4.7.1.4 1 M2 Pengecatan Bidang Kayu Baru (1 lp Plamur, 1 lp Cat dasar, 2 Lp Cat Penutup) 6.6.1
A TENAGA 7,580.00
L.01 0.0700 OH Pekerja 80,000.00 5,600.00
L.02 0.0090 OH Tukang Cat 100,000.00 900.00
L.03 0.0060 OH Kepala Tukang 120,000.00 720.00
L.04 0.0030 OH Mandor 120,000.00 360.00
B BAHAN 29,148.00
0.1500 Kg Plamuur 15,000.00 2,250.00
0.1700 Kg Cat Dasar 52,000.00 8,840.00
0.2600 Kg Cat Penutup 62,800.00 16,328.00
0.0100 Bh Kuas 12,000.00 120.00
0.0300 Ltr Pengencer 17,000.00 510.00
0.2000 Lbr Amplas 5,500.00 1,100.00
C PERALATAN ###
D Jumlah A + B + C 36,728.00
E Overhead & Profit 10% 3,672.80
F Harga Satuan Pekerjaan (D+E) 40,400.80
###
3 A.4.7.1.9 1 M2 Pelaburan Bidang Dengan Vernis
A TENAGA 31,080.00
L.01 0.1600 OH Pekerja 80,000.00 12,800.00
L.02 0.1600 OH Tukang Cat 100,000.00 16,000.00
L.03 0.0160 OH Kepala Tukang 120,000.00 1,920.00
L.04 0.0030 OH Mandor 120,000.00 360.00
B BAHAN 8,815.00
0.1500 Ltr Vernis 50,100.00 7,515.00
0.0500 Kg Dempul 15,000.00 750.00
0.1000 Lbr Ampelas 5,500.00 550.00
C PERALATAN
D Jumlah A + B + C 39,895.00
E Overhead & Profit 10% 3,989.50
F Harga Satuan Pekerjaan (D+E) 43,884.50
###
4 A.4.7.1.10 1 M2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup)
A TENAGA 12,301.48
L.01 0.0200 OH Pekerja 103,877.00 2,077.54
L.02 0.0630 OH Tukang Cat 139,036.00 8,759.27
L.03 0.0063 OH Kepala Tukang 151,821.00 956.47
L.04 0.0030 OH Mandor 169,400.00 508.20
B BAHAN 16,204.00
0.1000 Kg Plamir 7,200.00 720.00
0.1000 Kg Cat Dasar 42,000.00 4,200.00
0.2600 Kg Cat Penutup, (Metrolite) 43,400.00 11,284.00
C PERALATAN
D Jumlah A + B + C 28,505.48
E Overhead & Profit 10% 2,850.55
F Harga Satuan Pekerjaan (D+E) 31,356.03
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
XIII A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN
5 A.4.7.1.11 1 M2 Pengecatan Tembok Lama (1lap.Cat Dasar, 2lap Cat Penutup)
A TENAGA 7,304.00
L.01 0.0280 OH Pekerja 80,000.00 2,240.00
L.02 0.0420 OH Tukang Cat 100,000.00 4,200.00
L.03 0.0042 OH Kepala Tukang 120,000.00 504.00
L.04 0.0030 OH Mandor 120,000.00 360.00
B BAHAN 8,820.00
0.1200 Kg Cat Dasar 21,000.00 2,520.00
0.1800 Kg Cat Penutup 35,000.00 6,300.00
C PERALATAN
D Jumlah A + B + C 16,124.00
E Overhead & Profit 10% 1,612.40
F Harga Satuan Pekerjaan (D+E) 17,736.40

6 A.4.7.1.15 1 M2 Pemasangan Wallpaper


A TENAGA 24,300.00
L.01 0.0200 OH Pekerja 80,000.00 1,600.00
L.02 0.2000 OH Tukang Cat 100,000.00 20,000.00
L.03 0.0200 OH Kepala Tukang 120,000.00 2,400.00
L.04 0.0025 OH Mandor 120,000.00 300.00
B BAHAN 109,000.00
1.2000 M2 Wall Paper 85,000.00 102,000.00
0.2000 kg Lem Wallpaper 35,000.00 7,000.00

C PERALATAN
D Jumlah A + B + C 133,300.00
E Overhead & Profit 10% 13,330.00
F Harga Satuan Pekerjaan (D+E) 146,630.00

7 A.4.7.1.16 1 M2 Pengecatan Permukaan Baja dg Meni Besi


A TENAGA 24,300.00
L.01 0.0200 OH Pekerja 80,000.00 1,600.00
L.02 0.2000 OH Tukang Cat 100,000.00 20,000.00
L.03 0.0200 OH Kepala Tukang 120,000.00 2,400.00
L.04 0.0025 OH Mandor 120,000.00 300.00
B BAHAN 4,620.00
0.1000 Kg Meni Besi 45,000.00 4,500.00
0.0100 Bh Kuas 12,000.00 120.00
C PERALATAN
D Jumlah A + B + C 28,920.00
E Overhead & Profit 10% 2,892.00
F Harga Satuan Pekerjaan (D+E) 31,812.00
###
8 A.4.7.1.17 1 M2 Pengecatan Permukaan Baja dg Meni Besi & Perancah 6.21.1
A TENAGA 46,100.00
L.01 0.2500 OH Pekerja 80,000.00 20,000.00
L.02 0.2250 OH Tukang Cat 100,000.00 22,500.00
L.03 0.0225 OH Kepala Tukang 120,000.00 2,700.00
L.04 0.0075 OH Mandor 120,000.00 900.00
B BAHAN 7,590.00
0.1000 Kg Meni Besi 45,000.00 4,500.00
0.0100 Ltr Pengencer 17,000.00 170.00
0.0100 Bh Kuas 12,000.00 120.00
0.0020 M3 Perancah Kayu 1,400,000.00 2,800.00
C PERALATAN
D Jumlah A + B + C 53,690.00
E Overhead & Profit 10% 5,369.00
F Harga Satuan Pekerjaan (D+E) 59,059.00
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
XIII A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN
9 A.4.7.1.19 1 M2 Pengecatan Permukaan Baja/Besi Dg Meni & Cat Penutup 6.21.1
A TENAGA 12,600.00
L.01 0.0600 OH Pekerja 80,000.00 4,800.00
L.02 0.0600 OH Tukang Cat 100,000.00 6,000.00
L.03 0.0120 OH Kepala Tukang 120,000.00 1,440.00
L.04 0.0030 OH Mandor 120,000.00 360.00
B BAHAN 23,750.00
0.1000 Kg Meni Besi 45,000.00 4,500.00
0.0200 Bh Kuas 12,000.00 240.00
0.0100 Ltr Pengencer 17,000.00 170.00
0.3000 Kg Cat Penutup 62,800.00 18,840.00
C PERALATAN
D Jumlah A + B + C 36,350.00
E Overhead & Profit 10% 3,635.00
F Harga Satuan Pekerjaan (D+E) 39,985.00
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
XIV A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
1 A.5.1.1.1 1 Unit Memasang Closet Duduk / Mono Blok
A TENAGA 394,400.00
L.01 3.3000 OH Pekerja 80,000.00 264,000.00
L.02 1.1000 OH Tukang Batu 100,000.00 110,000.00
L.03 0.0100 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.1600 OH Mandor 120,000.00 19,200.00
B BAHAN 1,802,000.00
1.0000 Buah Kloset Duduk / Monoblok 1,700,000.00 1,700,000.00
0.0600 Kelengkapan 6% dari harga Kloset 1,700,000.00 102,000.00
C PERALATAN
D Jumlah A + B + C 2,196,400.00
E Overhead & Profit 10% 219,640.00
F Harga Satuan Pekerjaan (D+E) 2,416,040.00

2 A.5.1.1.2 1 Unit Memasang Closet Jongkok Porselen


A TENAGA 267,200.00
L.01 1.0000 OH Pekerja 80,000.00 80,000.00
L.02 1.5000 OH Tukang Batu 100,000.00 150,000.00
L.03 0.1500 OH Kepala Tukang 120,000.00 18,000.00
L.04 0.1600 OH Mandor 120,000.00 19,200.00
B BAHAN 309,350.00
1.0000 Buah Kloset Jongkok 300,000.00 300,000.00
6.0000 Kg Portland Semen 1,400.00 8,400.00
0.0100 M3 Pasir Pasang 95,000.00 950.00
C PERALATAN
D Jumlah A + B + C 576,550.00
E Overhead & Profit 10% 57,655.00
F Harga Satuan Pekerjaan (D+E) 634,205.00

3 A.5.1.1.4 1 Unit Memasang Urinoir


A TENAGA 198,000.00
L.01 1.0000 OH Pekerja 80,000.00 80,000.00
L.02 1.0000 OH Tukang Batu 100,000.00 100,000.00
L.03 0.1000 OH Kepala Tukang 120,000.00 12,000.00
L.04 0.0500 OH Mandor 120,000.00 6,000.00
B BAHAN 2,349,350.00
1.0000 Buah Urinoir 1,800,000.00 1,800,000.00
0.3000 - Perlengkapan 30% Harga Urinoir 1,800,000.00 540,000.00
6.0000 Kg Portland Semen 1,400.00 8,400.00
0.0100 M3 Pasir Pasang 95,000.00 950.00
C PERALATAN
D Jumlah A + B + C 2,547,350.00
E Overhead & Profit 10% 254,735.00
F Harga Satuan Pekerjaan (D+E) 2,802,085.00

4 A.5.1.1.5 1 Unit Memasang Wastafel


A TENAGA 266,200.00
L.01 1.2000 OH Pekerja 80,000.00 96,000.00
L.02 1.4500 OH Tukang Batu 100,000.00 145,000.00
L.03 0.1500 OH Kepala Tukang 120,000.00 18,000.00
L.04 0.0600 OH Mandor 120,000.00 7,200.00
B BAHAN 759,750.00
1.0000 Buah Wastafel 670,000.00 670,000.00
0.1200 - Perlengkapan 12% Harga Wastafel 670,000.00 80,400.00
6.0000 Kg Portland Semen 1,400.00 8,400.00
0.0100 m3 Pasir Pasang 95,000.00 950.00
C PERALATAN
D Jumlah A + B + C 1,025,950.00
E Overhead & Profit 10% 102,595.00
F Harga Satuan Pekerjaan (D+E) 1,128,545.00
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
XIV A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
5 A.5.1.1.12 1 Unit Memasang Bak Cuci Piring Stanless
A TENAGA 37,800.00
L.01 0.0300 OH Pekerja 80,000.00 2,400.00
L.02 0.3000 OH Tukang Batu 100,000.00 30,000.00
L.03 0.0300 OH Kepala Tukang 120,000.00 3,600.00
L.04 0.0150 OH Mandor 120,000.00 1,800.00
B BAHAN 330,000.00
1.0000 Buah Bak Cuci Piring Stanless 280,000.00 280,000.00
1.0000 Buah Waterdrain 50,000.00 50,000.00
C PERALATAN
D Jumlah A + B + C 367,800.00
E Overhead & Profit 10% 36,780.00
F Harga Satuan Pekerjaan (D+E) 404,580.00

6 A.5.1.1.14 1 Buah Memasang Floor Drain


A TENAGA 12,600.00
L.01 0.0100 OH Pekerja 80,000.00 800.00
L.02 0.1000 OH Tukang Batu 100,000.00 10,000.00
L.03 0.0100 OH Kepala Tukang 120,000.00 1,200.00
L.04 0.0050 OH Mandor 120,000.00 600.00
B BAHAN 25,000.00
1.0000 Buah Floor Drain 25,000.00 25,000.00
C PERALATAN
D Jumlah A + B + C 37,600.00
E Overhead & Profit 10% 3,760.00
F Harga Satuan Pekerjaan (D+E) 41,360.00

7 A.5.1.1.18 1 M Pemasangan Pipa Galvanis Ø ½"


A TENAGA 17,640.00
L.01 0.0540 OH Pekerja 80,000.00 4,320.00
L.02 0.0900 OH Tukang Batu 100,000.00 9,000.00
L.03 0.0090 OH Kepala Tukang 120,000.00 1,080.00
L.04 0.0270 OH Mandor 120,000.00 3,240.00
B BAHAN 12,865.00
1.2000 M Pipa Galvanis Ø ½" 8,300.00 9,960.00
0.3500 Ls Perlengkapan 35% x pipa 8,300.00 2,905.00
C PERALATAN
D Jumlah A + B + C 30,505.00
E Overhead & Profit 10% 3,050.50
F Harga Satuan Pekerjaan (D+E) 33,555.50

8 A.5.1.1.19 1 M Pemasangan Kran Air 1/2"


A TENAGA 46,200.00
L.01 0.0100 OH Pekerja 80,000.00 800.00
L.02 0.4000 OH Tukang Batu 100,000.00 40,000.00
L.03 0.0400 OH Kepala Tukang 120,000.00 4,800.00
L.04 0.0050 OH Mandor 120,000.00 600.00
B BAHAN 45,100.00
1.0000 Bh Kran Air 45,000.00 45,000.00
0.0250 Bh Sealtape 4,000.00 100.00
C PERALATAN
D Jumlah A + B + C 91,300.00
E Overhead & Profit 10% 9,130.00
F Harga Satuan Pekerjaan (D+E) 100,430.00

9 A.5.1.1.20 1 M Pemasangan Pipa Galvanis Ø ¾"


A TENAGA 17,640.00
L.01 0.0540 OH Pekerja 80,000.00 4,320.00
L.02 0.0900 OH Tukang Batu 100,000.00 9,000.00
L.03 0.0090 OH Kepala Tukang 120,000.00 1,080.00
L.04 0.0270 OH Mandor 120,000.00 3,240.00
B BAHAN 18,083.33
1.2000 M Pipa Galvanis Ø ¾" 11,666.67 14,000.00
0.3500 Ls Perlengkapan 35% x pipa 11,666.67 4,083.33
C PERALATAN
D Jumlah A + B + C 35,723.33
E Overhead & Profit 10% 3,572.33
F Harga Satuan Pekerjaan (D+E) 39,295.67
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
XIV A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
10 A.5.1.1.21 1 M Pemasangan Pipa Galvanis Ø 1"
A TENAGA 17,640.00
L.01 0.0540 OH Pekerja 80,000.00 4,320.00
L.02 0.0900 OH Tukang Batu 100,000.00 9,000.00
L.03 0.0090 OH Kepala Tukang 120,000.00 1,080.00
L.04 0.0270 OH Mandor 120,000.00 3,240.00
B BAHAN 37,380.83
1.2000 M Pipa Galvanis Ø 1" 24,116.67 28,940.00
0.3500 Ls Perlengkapan 35% x pipa 24,116.67 8,440.83
C PERALATAN
D Jumlah A + B + C 55,020.83
E Overhead & Profit 10% 5,502.08
F Harga Satuan Pekerjaan (D+E) 60,522.92

11 A.5.1.1.22 1 M Pemasangan Pipa Galvanis Ø 1½ "


A TENAGA 29,400.00
L.01 0.1080 OH Pekerja 80,000.00 8,640.00
L.02 0.1800 OH Tukang Batu 100,000.00 18,000.00
L.03 0.0180 OH Kepala Tukang 120,000.00 2,160.00
L.04 0.0050 OH Mandor 120,000.00 600.00
B BAHAN 49,212.50
1.2000 M Pipa Galvanis Ø 1½" 31,750.00 38,100.00
0.3500 Ls Perlengkapan 35% x pipa 31,750.00 11,112.50
C PERALATAN
D Jumlah A + B + C 78,612.50
E Overhead & Profit 10% 7,861.25
F Harga Satuan Pekerjaan (D+E) 86,473.75

12 A.5.1.1.23 1 M Pemasangan Pipa Galvanis Ø 3"


A TENAGA 36,900.00
L.01 0.1350 OH Pekerja 80,000.00 10,800.00
L.02 0.2250 OH Tukang Batu 100,000.00 22,500.00
L.03 0.0230 OH Kepala Tukang 120,000.00 2,760.00
L.04 0.0070 OH Mandor 120,000.00 840.00
B BAHAN 102,635.83
1.2000 M Pipa Galvanis Ø 3" 66,216.67 79,460.00
0.3500 Ls Perlengkapan 35% x pipa 66,216.67 23,175.83
C PERALATAN
D Jumlah A + B + C 139,535.83
E Overhead & Profit 10% 13,953.58
F Harga Satuan Pekerjaan (D+E) 153,489.42

13 A.5.1.1.24 1 M Pemasangan Pipa Galvanis Ø 4"


A TENAGA 36,900.00
L.01 0.1350 OH Pekerja 80,000.00 10,800.00
L.02 0.2250 OH Tukang Batu 100,000.00 22,500.00
L.03 0.0230 OH Kepala Tukang 120,000.00 2,760.00
L.04 0.0070 OH Mandor 120,000.00 840.00
B BAHAN 147,327.50
1.2000 M Pipa Galvanis Ø 4" 95,050.00 114,060.00
0.3500 Ls Perlengkapan 35% x pipa 95,050.00 33,267.50
C PERALATAN
D Jumlah A + B + C 184,227.50
E Overhead & Profit 10% 18,422.75
F Harga Satuan Pekerjaan (D+E) 202,650.25

14 A.5.1.1.25 1 M Pemasangan Pipa PVC tipe AW Ø ½"


A TENAGA 9,840.00
L.01 0.0360 OH Pekerja 80,000.00 2,880.00
L.02 0.0600 OH Tukang Batu 100,000.00 6,000.00
L.03 0.0060 OH Kepala Tukang 120,000.00 720.00
L.04 0.0020 OH Mandor 120,000.00 240.00
B BAHAN 8,137.50
1.2000 M Pipa PVC Ø ½" 5,250.00 6,300.00
0.3500 Ls Perlengkapan 35% x pipa 5,250.00 1,837.50
C PERALATAN
D Jumlah A + B + C 17,977.50
E Overhead & Profit 10% 1,797.75
F Harga Satuan Pekerjaan (D+E) 19,775.25
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
XIV A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
15 A.5.1.1.26 1 M Pemasangan Pipa PVC tipe AW Ø ¾"
A TENAGA 9,840.00
L.01 0.0360 OH Pekerja 80,000.00 2,880.00
L.02 0.0600 OH Tukang Batu 100,000.00 6,000.00
L.03 0.0060 OH Kepala Tukang 120,000.00 720.00
L.04 0.0020 OH Mandor 120,000.00 240.00
B BAHAN 11,237.50
1.2000 M Pipa PVC Ø ¾" 7,250.00 8,700.00
0.3500 Ls Perlengkapan 35% x pipa 7,250.00 2,537.50
C PERALATAN
D Jumlah A + B + C 21,077.50
E Overhead & Profit 10% 2,107.75
F Harga Satuan Pekerjaan (D+E) 23,185.25

16 A.5.1.1.27 1 M Pemasangan Pipa PVC tipe AW Ø 1"


A TENAGA 9,840.00
L.01 0.0360 OH Pekerja 80,000.00 2,880.00
L.02 0.0600 OH Tukang Batu 100,000.00 6,000.00
L.03 0.0060 OH Kepala Tukang 120,000.00 720.00
L.04 0.0020 OH Mandor 120,000.00 240.00
B BAHAN 15,500.00
1.2000 M Pipa PVC Ø 1" 10,000.00 12,000.00
0.3500 Ls Perlengkapan 35% x pipa 10,000.00 3,500.00
C PERALATAN
D Jumlah A + B + C 25,340.00
E Overhead & Profit 10% 2,534.00
F Harga Satuan Pekerjaan (D+E) 27,874.00

17 A.5.1.1.28 1 M Pemasangan Pipa PVC tipe AW Ø 1½"


A TENAGA 14,760.00
L.01 0.0540 OH Pekerja 80,000.00 4,320.00
L.02 0.0900 OH Tukang Batu 100,000.00 9,000.00
L.03 0.0090 OH Kepala Tukang 120,000.00 1,080.00
L.04 0.0030 OH Mandor 120,000.00 360.00
B BAHAN 27,125.00
1.2000 M Pipa PVC Ø 1½" 17,500.00 21,000.00
0.3500 Ls Perlengkapan 35% x pipa 17,500.00 6,125.00
C PERALATAN
D Jumlah A + B + C 41,885.00
E Overhead & Profit 10% 4,188.50
F Harga Satuan Pekerjaan (D+E) 46,073.50

18 A.5.1.1.29 1 M Pemasangan Pipa PVC tipe AW Ø 2"


A TENAGA 14,760.00
L.01 0.0540 OH Pekerja 80,000.00 4,320.00
L.02 0.0900 OH Tukang Batu 100,000.00 9,000.00
L.03 0.0090 OH Kepala Tukang 120,000.00 1,080.00
L.04 0.0030 OH Mandor 120,000.00 360.00
B BAHAN 32,937.50
1.2000 M Pipa PVC Ø 2" 21,250.00 25,500.00
0.3500 Ls Perlengkapan 35% x pipa 21,250.00 7,437.50
C PERALATAN
D Jumlah A + B + C 47,697.50
E Overhead & Profit 10% 4,769.75
F Harga Satuan Pekerjaan (D+E) 52,467.25

19 A.5.1.1.31 1 M Pemasangan Pipa PVC tipe AW Ø 3"


A TENAGA 22,080.00
L.01 0.0810 OH Pekerja 80,000.00 6,480.00
L.02 0.1350 OH Tukang Batu 100,000.00 13,500.00
L.03 0.0135 OH Kepala Tukang 120,000.00 1,620.00
L.04 0.0040 OH Mandor 120,000.00 480.00
B BAHAN 67,812.50
1.2000 M Pipa PVC Ø 3" 43,750.00 52,500.00
0.3500 Ls Perlengkapan 35% x pipa 43,750.00 15,312.50
C PERALATAN
D Jumlah A + B + C 89,892.50
E Overhead & Profit 10% 8,989.25
F Harga Satuan Pekerjaan (D+E) 98,881.75
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
XIV A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
20 A.5.1.1.32 1 M Pemasangan Pipa PVC tipe AW Ø 4"
A TENAGA 22,080.00
L.01 0.0810 OH Pekerja 80,000.00 6,480.00
L.02 0.1350 OH Tukang Batu 100,000.00 13,500.00
L.03 0.0135 OH Kepala Tukang 120,000.00 1,620.00
L.04 0.0040 OH Mandor 120,000.00 480.00
B BAHAN 104,625.00
1.2000 M Pipa PVC Ø 4" 67,500.00 81,000.00
0.3500 Ls Perlengkapan 35% x pipa 67,500.00 23,625.00
C PERALATAN
D Jumlah A + B + C 126,705.00
E Overhead & Profit 10% 12,670.50
F Harga Satuan Pekerjaan (D+E) 139,375.50
BA
ENGINE

PEKERJAAN
LOKASI
THN ANGGARAN
VOULME

NO JENIS PEKERJAAN

1 2
I PEKERJAAN PENDAHULUAN
a Pek. Papan Nama Proyek
b Pek. Sewa Barak Kerja
II PEKERJAAN TANAH DAN URUGAN
a Pek. Galian Tanah Pondasi

b Pek. Urugan Pasir Urug Bawah Pondasi T=5 cm

c Pek. Lantai Kerja K-100 T=5 cm

d Pek. Urugan Tanah Kembali


III PEKERJAAN PONDASI & BETON
a Pek. Pondasi Bata ad. 1 Pc : 3 Ps

b Pek. Sloof 15/20 Beton Bertulang K-175 (107 Kg Besi + Bekisting)

c Pek. Ring Balok Praktis 11/11, Beton Bertulang

d Pek. Kolom Praktis 11/11, Beton Bertulang

IV PEKERJAAN DINDING & PLESTERAN


a Pek. Pas. Setengah Bata ad. 1 Pc : 4 Ps

b Pek. Plesteran Bata ad. 1 Pc : 4 Ps


V PEKERJAAN PENGECATAN
a Pek. Pengecatan Dinding Dengan Cat Tembok
BACK UP DATA
ENGINEER'S ESTIMATE (EE)

: PEMBANGUNAN PAGAR
: ……..
: 2020
: 71 M

JENIS PEKERJAAN VOL

2 3
PEKERJAAN PENDAHULUAN
Pek. Papan Nama Proyek 1.00
Pek. Sewa Barak Kerja 1.00
PEKERJAAN TANAH DAN URUGAN
Pek. Galian Tanah Pondasi 7.10
Pondasi Bata
- P1
Pek. Urugan Pasir Urug Bawah Pondasi T=5 cm 0.71
Pondasi Bata
- P1
Pek. Lantai Kerja K-100 T=5 cm 0.71
Pondasi Bata
- P1
Pek. Urugan Tanah Kembali 2.37
PEKERJAAN PONDASI & BETON
Pek. Pondasi Bata ad. 1 Pc : 3 Ps 5.68
- P1
Pek. Sloof 15/20 Beton Bertulang K-175 (107 Kg Besi + Bekisting) 2.13
- P1
Pek. Ring Balok Praktis 11/11, Beton Bertulang 71.00
- P1
Pek. Kolom Praktis 11/11, Beton Bertulang 23.40
- P1
PEKERJAAN DINDING & PLESTERAN
Pek. Pas. Setengah Bata ad. 1 Pc : 4 Ps 92.30
- P1
Pek. Plesteran Bata ad. 1 Pc : 4 Ps 184.60
PEKERJAAN PENGECATAN
Pek. Pengecatan Dinding Dengan Cat Tembok 213.00
Dinding
Sloof
BACK UP DATA
NEER'S ESTIMATE (EE)

PARAMETER DATA

SAT RASIO BANYAK VOLUME


PANJANG LEBAR TINGGI
LUAS (M2) BESI
(M) (M) (M)
(KG/M)
4 5 6 7 8 9 10 11

Unit 1.00 1.000


Unit 1.00 1.000

M3 71.00 7.100

71.00 0.20 0.50 7.100


M3 0.710

71.00 0.20 0.05 0.710


M3 0.710

71.00 0.20 0.05 0.710


M3 2.367

M3 5.680
71.00 0.20 0.40 5.680
M3 2.130
71.00 0.15 0.20 2.130
M 71.000
71.00 71.000
M 23.400
1.30 18.00 23.400
M2 92.300
71.00 1.30 92.300
M2 184.600

M2 213.000
184.600
71.00 0.20 28.400
12
KET

2
30

1
2 5
0

4
0

60
20

15
2
0

1
02

5
0 1
50

400
400
Berat Besi Per Kilogram :
f 32 = 6.313 Kg/m
f 19 = 2.226 Kg/m
f 16 = 1.578 Kg/m
f 13 = 1.042 Kg/m
f 12 = 0.888 Kg/m
f 10 = 0.617 Kg/m
f 8 = 0.395 Kg/m
f 6 = 0.222 Kg/m

PONDASI SETEMPAT
Panjang = 0.6
Lebar = 0.6
Tebal = 0.12

Volume = 0.0432 M3

Besi 10 mm
Arah X = 1.2 M
Banyak = 4 Bh Panjang 4.8 M

Besi 10 mm
Arah Y = 1.2 M
Banyak = 4 Bh Panjang 4.8 M
Total 9.6 M
Berat Besi 5.9184 Kg
Vol Besi 137 Kg/M3 Dibulatkan 137

SLOOF
Panjang = 1
Lebar = 0.15
Tebal = 0.2

Volume = 0.03 M3

Besi Utama 10 mm
Banyak = 4 Bh
Panjang = 4M Berat Besi 2.466 Kg
Vol Besi 82.2 Kg/M3
Sengkang 6 mm
Banyak = 7 Bh
Panjang = 0.46 M Berat Besi 0.714647 Kg
Vol Besi 23.82156 Kg/M3
Total 106.0216 Dibulatkan 107

KOLOM
Panjang = 1
Lebar = 0.2
Tebal = 0.2

Volume = 0.04 M3
Besi Utama 10 mm
Banyak = 4 Bh
Panjang = 4M Berat Besi 2.466 Kg
Vol Besi 61.65 Kg/M3
Sengkang 6 mm
Banyak = 7 Bh
Panjang = 0.56 M Berat Besi 0.870005 Kg
Vol Besi 21.75012 Kg/M3
Total 83.40012 Dibulatkan 84

BALOK INDUK
Panjang = 1
Lebar = 0.3
Tebal = 0.5

Volume = 0.15 M3

Besi Utama 16 mm
Banyak = 8 Bh
Panjang = 8M Berat Besi 12.62592 Kg
Vol Besi 84.1728 Kg/M3
Besi Utama 10 mm
Banyak = 2 Bh
Panjang = 2M Berat Besi 1.233 Kg
Vol Besi 8.22 Kg/M3
Sengkang 8 mm
Banyak = 8 Bh
Panjang = 1.36 M Berat Besi 4.292813 Kg
Vol Besi 28.61875 Kg/M3
Total 121.0116 Dibulatkan 122

BALOK ANAK
Panjang = 1
Lebar = 0.25
Tebal = 0.4

Volume = 0.1 M3

Besi Utama 16 mm
Banyak = 5 Bh
Panjang = 5M Berat Besi 7.8912 Kg
Vol Besi 78.912 Kg/M3
Besi Utama 10 mm
Banyak = 2 Bh
Panjang = 2M Berat Besi 1.233 Kg
Vol Besi 12.33 Kg/M3
Sengkang 8 mm
Banyak = 8 Bh
Panjang = 1.06 M Berat Besi 3.345869 Kg
Vol Besi 33.45869 Kg/M3
Total 124.7007 Dibulatkan 125
PLAT K-175
Panjang = 1
Lebar = 1
Tebal = 0.12

Volume = 0.12 M3

Besi 10 mm
Arah X = 1M
Banyak = 7 Bh Panjang 7M

Besi 10 mm
Arah Y = 1M
Banyak = 7 Bh Panjang 7M
Total 14 M
Berat Besi 8.631 Kg
Vol Besi 71.925 Kg/M3 Dibulatkan 72

PLAT K-250
Panjang = 1
Lebar = 1
Tebal = 0.12

Volume = 0.12 M3

Besi 10 mm
Arah X = 1M
Banyak = 5 Bh Panjang 2 Lapis 10 M

Besi 10 mm
Arah Y = 1M
Banyak = 5 Bh Panjang 2 Lapis 10 M
Total 20 M
Berat Besi 12.33 Kg
Vol Besi 102.75 Kg/M3 Dibulatkan 103

LANTAI WIREMESH M8
Panjang = 1
Lebar = 1
Tebal = 0.2

Volume = 0.2 M3

Wiremesh M6

Panjang 1M
Lebar 1M
Total 1 M2
Berat Besi 5.448854 Kg
Vol Besi 27.24427 Kg/M3 Dibulatkan 28
Kg/M3

Kg/M3
Kg/M3

Kg/M3

Kg/M3
Kg/M3

Kg/M3

Kg/M3
RENCANA ANGGARAN BIAYA
ENGINEER'S ESTIMATE (EE)

PEKERJAAN : PEMBANGUNAN PAGAR


LOKASI : ……..
THN ANGGARAN : 2020
VOULME : 71 M

NO JENIS PEKERJAAN

1 2
I PEKERJAAN PENDAHULUAN
a Pek. Papan Nama Proyek
b Pek. Sewa Barak Kerja
SUB JUMLA
II PEKERJAAN TANAH DAN URUGAN
a Pek. Galian Tanah Pondasi
b Pek. Urugan Pasir Urug Bawah Pondasi T=5 cm
c Pek. Lantai Kerja K-100 T=5 cm
d Pek. Urugan Tanah Kembali
SUB JUMLA
III PEKERJAAN PONDASI & BETON
a Pek. Pondasi Bata ad. 1 Pc : 3 Ps
b Pek. Sloof 15/20 Beton Bertulang K-175 (107 Kg Besi + Bekisting)
c Pek. Ring Balok Praktis 11/11, Beton Bertulang
d Pek. Kolom Praktis 11/11, Beton Bertulang
SUB JUMLA
IV PEKERJAAN DINDING & PLESTERAN
a Pek. Pas. Setengah Bata ad. 1 Pc : 4 Ps
b Pek. Plesteran Bata ad. 1 Pc : 4 Ps
SUB JUMLA
V PEKERJAAN PENGECATAN
a Pek. Pengecatan Dinding Dengan Cat Tembok
SUB JUMLA
(A) Jumlah Harga Pekerjaan
(B) Pajak Pertambahan Nilai ( PPN ) = 10% x (A)
(C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B)
(D) DIBULATKAN
TERBILANG : "Seratus Juta Rupiah"

Diperiksa oleh :
Pengelola Teknis Kegiatan
Dinas Pekerjaan Umum dan Perumahan Rakyat
Prov………..

………….
NIP. ..………..

Disetujui oleh :
Pejabat Pembuat Komitmen (PPK)
………
………

……….
NIP. …..
NA ANGGARAN BIAYA (RAB)
ENGINEER'S ESTIMATE (EE)

JUMLAH HARGA SAT


VOL SAT HARGA SAT (Rp) KET
(Rp)
3 4 5 6 7

1.00 Unit 65,000.00 65,000.00


1.00 Unit 810,000.00 810,000.00
SUB JUMLAH 875,000.00

7.10 M3 90,357.03 641,534.88


0.71 M3 639,514.81 454,055.52
0.71 M3 1,851,763.31 1,314,751.95
2.37 M3 30,119.01 71,281.65
SUB JUMLAH 2,481,623.99

5.68 M3 2,254,655.81 12,806,445.00


2.13 M3 7,106,949.60 15,137,802.65
71.00 M 159,443.73 11,320,504.87
23.40 M 159,443.73 3,730,983.30
SUB JUMLAH 42,995,735.82

92.30 M2 216,745.33 20,005,594.05


184.60 M2 96,827.30 17,874,318.93
SUB JUMLAH 37,879,912.99

213.00 M2 31,356.03 6,678,834.03


SUB JUMLAH 6,678,834.03
90,911,106.83
9,091,110.68
100,002,217.51
100,000,000.00

….. , ........................ 2020

Dihitung oleh :
……..
…………..

…………
Team Leader

Diketahui oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
………….
………..

RIAN WIDIANTARA, SE
NIP. ………….