COMPLIANCE STATEMENT

POLGAHAWELA, POTHUHERA AND ALAWWA INTEGRATED WATER


Project
SUPPLY PROJECT
Client NATIONAL WATER SUPPLY & DRAINAGE BOARD, SRI LANKA

Location POLGAHAWELA, SRI LANKA

Doc. Title Submission of Civil GA drawing of WEIR .


Commented Doc.
10P104-X0003-101 Rev No. 6
No.

Comments Ref : PD/PPAIWSP/Design/2020/154 Date – 23/07/2020

Sl No Client Comments WABAG reply

Gabion wall drawings should be


Noted. Gabion wall drawing will be
1. submitted separately together with
submitted separately.
calculations
Fish ladder location is shown in the
Fish ladder drawing should be
2. drawing. detail drawing will be
submitted.
submitted separately.
Embankment protection length should As per the contract document,
3. be 480m as per the contract document embankment protection drawing will be
clause 8.3.2.4 in the volume Ι submitted separately.
Existing Gabion wall height also should
4. match with proposed finished ground Noted.
level in the intake land
All reinforced concrete should be
5. grade 25 as per structural design Noted.

Weir gate location should be at lowest Weir gate location is shifted and shop
6 location as per submitted contour map. drawing is accepted. Same location is
incorporated in this drawing.

Complied by (Signature): Date: 07.10.2020


Page 1
Name: K. Sulakxan Department: Engineering

VA TECH WABAG LTD