Professional Documents
Culture Documents
CONTENTS
BATTERY
RELAY FAMILY
TYPES OF RELAY
The 110kV Vyttila substation is one of the oldest substations. This substation
is feeding major part of Kochi and three auxiliary substation viz. 66 kV substation
Perumanoor, Panampilly Nagar and Puthencruz and EHT consumers; M/S HOC & M/S
PCBL. The 110kV supply feeding to the substation is from 220kV substation
Kalamassery, through the 110 kV Vyttila single circuit feeder and from 110kV substation,
Newvyttila through 110 kV UG CABLE feeder. Inaddition to this 110 kV feeders there are
two 66 kV incoming feeders from 220 kV substation,Kalamassery.
The 110kV substation New Vyttila is fed from 220KV substation Brahmapuram
through feeders BR- NV ( Brahmapuram – New Vyttila) and BR-KD( Brahmapuram-
Kadavanthra) feeder. BR-NV conductor is HTLS ( High Temperature Low Sag).There are
six 66 kV feeders; Puthencruz I &II and Perumanoor I&II which are outgoing feeders and
Vyttila I&II are the standby feeders from 220kV substation Kalamassery.
The station capacity is 128 MVA, (Including 40 MVA and 63 MVA 110/66
kV transformers and two 12.5 MVA 110/11 kV transformers). The 11 kV distributions is
from the Crompton Greaves make 11 kV VCB panel. There are nine 11 kV outlets other
than auxiliary.
2.FEEDER DETAILS
o/c
Name of feeder Code CT Conductor Relay Permissible
ratio setting load
110kV Kalamassery-
Vyttila 1KLVT 600/1 WOLF 0.75 343A
110kV New Vyttila-
Vyttila 1NVVT 600/1 WOLF 1 600 A
66 kV Vyttila-
Perumanoor I 6VTPN 400/1 DOG 0.75 250A
CABLE CAPACITY
66 kV Vyttila-Perumanoor II 254A
2.1. 11 kV FEEDERS
Load break switches are installed for 11kV Nettoor and Ernakulam feeders. 11 kV
Kadavantra feeder is inter linked with 11 kV Gandhi square feeder from New Vyttila
Substation by installing one CCC RMU (CG LUCY Make) at yard. It has two incoming
supply [one is from Vyttila Substation (Kadavantra feeder) and other from New Vyttila
Substation (Gandhi square feeder). The RMU and load break switches are operated
Muthedam,Panangadu Panangadu,Kadavanthra,
Nettoor
Kundannoor,Maradu, New Vyttila
All city feeders are under the control of Distribution control room ,Ernakulum. Any
operations /interruptions to city feeders should be intimated to control room.
3.POWER TRANSFORMER
The transformer is the most important equipment in the substation; every
effort shall be taken to see that it is in the proper working condition as stipulated. The
periodic check as per the maintenance schedule shall be conducted and corrective action
taken without delay.
TYPES OF TRANSFORMERS
1. Step Up Transformer & Step Down Transformer - Generally used for stepping up
and down the level of power in transmission and distribution power network.
2. Three Phase Transformer & Single Phase Transformer - Former is generally used in
three phase power system as it is cost effective than later but when size matters, it is
preferable to use bank of three single phase transformer as it is easier to transport three
single phase unit separately than one single three phase unit.
4. Two Winding Transformer & - Former is generally used where ratio between high and
low is greater than 2. It is cost effective to use later where the ratio between high and low
is less than 2.
5. Outdoor Transformer & Indoor Transformer - Transformers that are designed for
installing at outdoor are outdoor transformers and transformers designed for installing at
indoor are indoor transformers.
Trip
Wdg.
Transformer Make Fan On Oil Wdg
Temp.Alarm
Temp Temp
12.5 MVA No. I(110/11
TELK 55oc 75-80 75 85
kV)
12.5 MVA No.II
Indotek 55oc 75-80 75 85
(110/11 kV)
63 MVA (110/66 kV) TELK Manual 70-80 75 85
40 MVA (110/66 kV) TELK Manual 75-80 75 85
4.STATION BATTERY
Exide make plante type Lead acid battery with 55 No‟s of cell for 110V DC supply is in
service float voltage is 123.75. Each battery will have output voltage of 2.0V-2.2V at float
mode Another operating mode available in the charger is boot mode. Battery will be
changed to this mode if it is off for some time.
PRECAUTIONS
Battery room should be well ventilated and room temperature should be
<35ºc.Specific gravity of the Lead acid cell is 1.21.
Never allow a flame, light a cigarette or store inflammable material near battery.
Do not wear rings, bracelets or any other metallic object while working on the
battery.
Normal float voltage is 2.25volts/cell.
Specific gravity of cell should be taken in every month.
Specific gravity exceeds the limit add battery water to top up.
If specific gravity is below the limit add acid to top up.
Electrical Circuit Breaker is a switching device which can be operated manually as well as
automatically for controlling and protection of respectively. According to their arc
quenching medium the circuit breaker can be divided as ,SF6,VCB,MOCB etc , .
Different types of CB available in this substation are VCB(11kV) and SF6
CB(66&110kV)
Name of Feeder
Maximum
or Transformer Make Normal Alarm Lockout
filling
Bay
110kV Line (1 0.51
Areva .64Mpa 0.54 Mpa 0.9 Mpa
KLVT) Mpa
110KV NV-VT CGL
63 MVA 0.51
Areva .64 Mpa 0.54 Mpa 0.9 Mpa
trf(110kV side) Mpa
40 MVA 0.60
ABB 0.7Mpa 0.62 Mpa 0.9 Mpa
trf(110kV side) Mpa
12.5MVA trf No. 0.60
ABB 0.7Mpa 0.62 Mpa 0.9 Mpa
1 (110kV side) Mpa
12.5MVA trf No.
BHEL 6.5 bar 5.7 bar 0.9 Mpa
11 (110kV side)
63 MVA
Siemens 6.0 bar 5.2 bar 5.0 bar 0.8 Mpa
trf(66kV side)
40 MVA 0.60
ABB 0.7Mpa 0.62 Mpa 0.8 Mpa
trf(66kV side) Mpa
66kVKLMSY- 0.60
ABB 0.7Mpa 0.62 Mpa 0.8 Mpa
VTLA No I Mpa
66kVKLMSY-
ABB 6kg/cm2 5.5kg/cm2 5kg/cm2 7.2kg/cm2
VTLA No II
66 kV VTLA-
CG 6kg/cm2 5.5kg/cm2 5kg/cm2 7.2kg/cm2
PMNR No I
66 kV VTLA-
CG 6kg/cm2 5.5kg/cm2 5kg/cm2 7.2kg/cm2
PMNR No II
66 kV VTLA-
CG 6kg/cm2 5.5kg/cm2 5kg/cm2 7.2kg/cm2
PCBL
66 kV VTLA-
CG 6kg/cm2 5.5kg/cm2 5kg/cm2 7.2kg/cm2
PTZ
Incoming supply is availed through 110 kV New Vyttila- Vyttila feeder feeder.
110 KV Kalamassery – Vyttila feeder under switch off condition
feeder.
The person posted to the substation as operators should be conversant with all
operational activities of the substation during the parallel shift posting.
Carefully study the layout/single line diagram etc of the station; physically
ascertain the location of various equipment incoming and outgoing feeders etc.
Carefully study the operation/instructions manuals of transformers circuit
breakers, isolators, control panels, station battery, battery charger, L.T panels,
fire fighting equipments etc.
Gain thorough knowledge of 11kV feeders provided from the substation, the
areas to which supply is extended, details of section concerned.
Study the operational problems, if any, peculiarities of functioning of any
peculiar equipment of the station etc. in detail and make personal notes.
Get a precise idea of the wiring details of alarm annunciations related inferences
etc. of the station and control equipments and on various switches and fuses
controlling each circuit/ function.
Properly understand the mode of giving permit to work on feeder, transformers
and other equipments.
Study the safety aspect of the station, operation of fire fighting equipments etc in
detail.
Be conversant with the mode of reporting incidents of various operations to the
higher officers in time and in appropriate manner.
8.OPERATING INSTRUCTIONS
8.1 GENERAL
1. Whenever the HV supply (110 kV) failure occurs, the entire load on LV side may be
switched off except that of auxiliary transformer.
2. Then contact the feeding station immediately and act as per their Instruction.
3. If 11kV feeder trips on heavy fault and it again trip similarly on test charge, further test
charges may be done after contacting the concerned distribution officers.
4. Whenever any alarm is received on any feeder/ equipment or any trouble is noticed switch
off that particular equipment and investigates and report.
5. Healthy trip indication of all feeders and equipment may be tested at the beginning of each
shift
6. Maintain the voltage level, increase or decrease the taps as and when required to maintain
this.
7. When alarm on over current or winding temperature is received due to overload on the
power transformer, reduce the load and wait for resetting the alarm.
8. If winding temperature alarm is received on other than overload condition the transformer
should not be test charged. The fact may be reported to the Station Engineer.
9. If a transformer trips on overload, reduce the load and then test charge.
10.If the transformer trips on buchholz, differential protection, low oil level, control D.C.
failure etc. it should not be test charge and the Station Engineer may be intimated
immediately
11.Transformer should be test charged under no load. Always test charge primary side breaker
first.
1. Each and every operation should be recorded in detail in the operator's diary
2. At 00 hours all meter readings must be recorded in full digits.
3. Write names of shift staff legibly and clearly when taking over charge. The name of
security guard on shift also must be written.
4. Write the actual time of handing over and taking over.
5. Write the date on each top.
6. The station statistics should be recorded in the logbook by each operator during his/her
shift itself, other data's should be filled by the operator on night shift duty.
7. Reason for additional load other than normal should be mentioned in remark column of
logbook.
8. Tripping should always be noted in red ink
9. Switch off should be written in green ink.
10.The permit to work, isolation certificate and switch off should be given only after
confirming the identity of the person if request is over phone.
11.Outages of all EHT feeders should be reported during morning and evening shift before
6.30 am and 6.30 pm to the O/D, 220kV substation, Ambalamugal daily.
12.Enter station statistics on pse.kseb.in without fail.
2. Ensure CB is open.
4. The control circuit plug of the CB shall remain in the control circuit jacket of the cubicle, if
the truck is not required to be moved away from the cubicle for maintenance work.
5. Open the AB switch of the concerned feeder and lock, if necessary.
6. Exhibit `Men at work'/`Permit to work' caution boards in the cubicle as well as in the feeder
structure.
7. Normally the 11 kV feeders are not earthed by the substation personnel at the time of
issuing permit and an Isolation Certificate (IC) is issued instead of PW.
8. `Permit to work'/`Isolation Certificate' card shall be prepared and the original issued to the
authorized person. If PW is issued over phone the operator should ensure the authenticity of
1. When the permit to work is returned by the concerned person ensure that the Certificate
declaring that all men, materials and earthing are cleared from the line is signed by the
person to whom permit to work is issued.
2. The operator on return of PW check for any other PW issued on the line / associated cable /
AB switch.
3. If everything is clear cancel the PW and proceed to charge the line. Remove the caution
boards. Close the AB switch if it is opened, rack in the VCB. Charge the spring electrically
or manually using spring charging handle till the spring is fully charged. Ensure that the
control circuit plug is in the jacket of the cubicle.
4. The circuit breaker shall be electrically closed and check for the current in each phases by
turning the ammeter selector switch.
a. When an 11kV feeder trips, there will be an audible alarm in the 11kV panel.
b. Immediately accept the alarm by pressing the `Alarm Accept' push button switch in
the panel.
c. Check for `Breaker off' indication in any panel. The feeder supplied from that
panel stands now tripped. Note down the relay indication.
d. Reset the relay.
e. Charge the spring and close the breaker electrically after three minutes. (Manual
closing may be resorted to only when there is a snag in the closing system.)
f. If the fault in the feeder was momentary the line will stand charged. Otherwise the
feeder will trip again.
g. If the feeder trips again accept the alarm note down the relay indications and reset
the relay.
h. If the fault is suspected to be heavy, declare the feeder as faulty and exhibit a
feeder `Faulty' board on the VCB panel.
i. Note down all the operations with time in the operators diary.
j. Report the matter to the concerned Electrical section over phone.
k. When the maintenance personnel (Sub Engineer, AE) of the Electrical section
request for a further test charging, ascertain whether
1)the fault has been located and cleared
1. Switch off all outgoing 11kV feeders except auxiliary feeder and contact 220kV
substation Kalamassery. If supply failed from Kalamassery end due to a grid failure, wait
till the supply is resumed and take the auxiliary supply from 110 kV Substation, New
Vyttila through Gandhi square Feeder. When the supply gets restored, contact Kalamassery
Substation and normalize the main supply and auxiliary supply. Also inform 66 kV
substations Perumanoor, Panampilly Nagar and Puthencruz to normalize the supply.
2. If it takes considerable time for resuming the 110kV supply from KLSY, arrange to avail
supply from 110 KV NV-VT after contacting 110kv New vyttila substation(vise-versa)
3. If it takes considerable time for resuming both 110kV supply, arrange to avail supply from
standby 66kV feeders. The 66kV supply can be availed from the standby 66kV
Kalamassery- Vyttila No. I and II feeders as per the instruction from 220kV substation,
Kalamassery. The feeders are to be coupled at this end.
Before charging 66 kV Kalamassery –Vyttila 1 and 2 feeders, it must be ensure that the
110 kV Kalamassery –Vyttila feeder is under switched off condition.
4. Close 66kv line isolators of 66kV KL-VT No. I and II feeders and charge the feeders.
5. In order to reduce load, change over 66kV Perumanoor substation and Panampilly Nagar
substation to 110 kV Substation, Kaloor via 66kV Kaloor -Marine drive GIS UG cable
feeder.
6. Arrange maximum possible back feeding if required.
1. Switched on 110 kV NVVT feeder and simultaneously switched off 110kV KL-VT
1. Close the line isolator IL1 and charge 110kV KL-VY feeder.
I. Permit work on 66 KV KL-VT No:2 feeder should be given after ensuring NBC from
Vyttila, Kakkanadu (tap 2) and HMT,NBC at Kalamassery after switch off, isolate and
earthing confirmation from Kakkanadu, Vyttila and Kalamassery.
II. Permit work on 66 KV KL-VT No.1 feeder – A portion with Kakkanadu- Vyttila does not
exist because in No.1 feeder permit can be availed only in Thrikkakara-Vyttila portion.
11.4 FOR AVAILING SUPPLY FROM STAND BY 66kV VYTTILA FEEDER 1&2
If 110kV KL-VY feeder trips having any Permit to Work, then avail standby 66kV KL-
VT No.II feeder
1. Ensure 110Kv KL-VT feeder is switched off AND line isolator is opened.
2. Charge SF6 CB of 66kV KL-VTNo:II feeder as per the instruction of Operator, 220kV
substation, Kalamassery
3. Before normalizing the feeding, switch off the standby 66KV KL-VT .
4. No.1&2 feeder and open 66KV line isolator I23
Normally 66KV KL-VT-1 is feeding to Thrikakkara. The standby supply can be availed
from 66KV KL-VT-1&2 feeders simultaneously limiting the overloading of 1&2 feeder.
Both feeders can be availed at one bus by doing Bus splitting arrangement
VT feeder
1.1 Switch off all 11kv feeder except AUXILIARY .
1.2 Switch off primary side CB of both 12.5 ,MVA transformer .
1.3 Open the Cross sectional isolator IN 5( CB is not installed ).
1.4 Close line Isolator of 110kv NV-VT feeder.
1.5 Charge 110kv NV-VT Feeder
1.6 Charge both primary side CB of 12.5 MVA Transformer
1.7 Charge all 11kv feeder
WORKS
1. 40MVA Transformer
a. S/off 110kV side and 66kV side SF6 CB of 40 MVA Transformer
b. Open 66 kV Bus isolator I5 and bus coupler isolator I4
c. Open 110 kV transformer isolator I1.
2. 63MVA Transformer
a. S/off 110kV and 66kV side SF6 CB of 63MVA Transformer
b. Open 66kV side Bus isolator I6 and bus coupler isolator I4
c. Open 110kV isolator, I2.
3. 12.5MVA Transformer
a. S/off and rack out the VCB of respective incomer.
b. S/off 110kV SF6 CB of transformer.
c. Open the respective IN1/IN2.
d. Reached out incomer PT.
4. Auxiliary Transformer
a. Change over station auxiliary to the LT supply from 110kV New Vyttila Substation.
This auxiliary stand by supply from Gandhi square feeder (LT supply from OEN
transformer).
b. S/off and rack out the VCB of 11kV auxiliary feeder.
Remove the LT fuse of auxiliary transformer.
OTHERS
1. The control panels, meters, telephones, switch boxes, relays ,battery etc should be
cleaned daily during the 1st shift by the shift staff including overseer and operator.
2. Operators are to inspect the yard equipments periodically during shift duty around the
yard as often as possible especially during peak hours and listen for any change in usual
sound, see for loose connections, verify oil level etc. and report to the station engineer if
there is any abnormality.
3. Operators are to report all messages to the Station Engineer and get his initials in the
message book as soon as the messages are received.
66kV panels are having distance relays. It will be working only if current from CT and
corresponding voltage from PT is given to it. 66kV Bus No.1 and Bus No.2 is having separate
PTs. If the two 66kV buses are in coupled condition then doesn‟t matter which PT connection is
given to each feeder. But if the 66kV Bus No.1 and Bus No.2 are not in coupled condition then
care should be given to select the actual PT of the feeder.PT selection switches are provided at
the backside of feeder panels. The feeders which are fed from bus 1 should be put in bus 1 PT
itself.
advance.
3. Obtain NBC on respective feeders.
Care should be taken while giving permit work to 66kV VTLA-PTZ No1 and
66kV VTLA-PMNR No.1 feeder since cross bus exists between both.
a. For 66kV Vyttila- Puthencruz feeder
Obtain NBC from 66kV substation Puthencruz and the EHT consumer, M/S
HOC, VTLA-Puthencruz No.1.
Earthing confirmation from Puthencruz after switch off isolate and earthing at
Vyttila.
Obtain NBC from 66kV substation and the EHT consumer viz, M/S HOC and
PCBL.
Earthing confirmation from PCBL after switch off isolate and earthing at
PCBL.
c. For VTLA-PTZ No.2 feeders PCBL-PTZ portion
2. Provide earth on both sides of feeder. Note that earthing should be given first at feeding
end.
3. Issue permit to work.
2. Close the isolators and charge the circuit breaker of the respective feeder.
The relay of PT which is live will be in flagged condition. In order to change the Bus PT
selection
1. The switch below the un flagged relay should be put to the reverse position first.
2. Immediately after that put the other switch to reverse position.
3. Now both relays will be in flagged condition. Reset both the relays. The Relay
corresponding to the PT which is not live will get reset.
ALARM:-
Distance relay
TOSHIBA-GRZ100
Operation:To reset the relay
press”RESET” key more than three
110KV KLMSY-VTLA times on the “latest fault” screen
,then trip LED continues to lit.
Backup relay
AREVA-CDD
Distance relay
SIFANG-CSC162
Auxiliary relay
ALIND
REF relay
ALIND-TDZA10
12.5MVA 110/11KV TRANSFORMER NO.1
Backup relay
ALIND-TSRA111
Differential relay
SEL SEL-787
Auxiliary relay
ALIND
REF relay
ALIND-TDZA10
12.5MVA 110/11KV TRANSFORMER NO.2
Backup relay
ALIND-TSRA111
Differential relay
Genisis MIB202
Auxiliary relay
ALIND
63MVA 110/66KV TRANSFORMER NO:2
Backup relay
ALIND-TSRA111
Backup relay
40MVA 110/66KV TRANSFORMER (66KV side)
SEL-SEL-315
Backup relay
63MVA 110/66KV TRANSFORMER (66KV side)
ALIND-TSRA111
In oil immersed transformers, limited arcing under oil originates from poor electrical
connections of conductors and core faults. This might not bedetectable by differential or
ref relay. Buchholz protection gives alarm and tripping during heavy faults due to P/F and
E/F.
All types of faults occurring within oil filled transformer are accompanied
by gas generation. This phenomenon has been effectively utilized by Buchholz Relays to
provide the best-known protection arrangement for transformers.
The high sensitivity and capability of the relay has been successfully
proved to detect faults stated below:-
The gas collected in the relay can, from its colour, odour and
compositions, indicate the nature and location of faults up to a greater extent.
FAULT INFERENCE
REF protection is a unit protection scheme for one winding of the transformer. It is
generally of the high impedance type. The residual current of three line current
transformers is balanced against the output of the neutral conductor.
It is an instantaneous relay with low settings. The whole fault current is measured. Even if
the prospective current level decreases as fault positions progress nearer the neutral end of
the winding, with a low effective setting a large percentage of the winding can be covered.
The main windings and the core and other accessories are mostly oil immersed.
Therefore this equipment develops fault rarely than over head
Lines, but if a fault occur in a transformer. It costs much more time and money than that
required to rectify a fault on the line. The fault on a transformer should there be cleared
fast to protect the equipment or minimize the damage.
TYPES OF FAULT
Through faults
Internal faults
THROUGH FAULTS
o Over current protection: it covers transformer, station, bus bar, and a protection.
o Overload protection : detected through thermal overload protection
o Oil temperature protection
o Winding temperature protection
Long time constant delays oil for getting true winding temperature and hence incorrect
replica used also to start cooler fans.
Sensing through bulb and heating through resistor connected from CT sec. gives hot spot
temperature. Usually shows higher reading during short time heavy overload than long
time higher overload.
BREATHER
OPERATION:-
17.BATTERY
Battery is the heart of power station. It provides the ultimate and final DC back- up
for operating emergency equipments which power the turbo generators. DC power is
required for operation of all switchgears, protection relays, indicating lamps and
annunciators.Switchgear and relays will not operate causing extensive damage to
transformers and power lines.
19.TYPES OF RELAY
19.1 DIRECTIONAL PHASE FAULT OVERCURRENT RELAY
When fault currents can flow in both directions through relay location, it may be necessary
to make the response of the relay directional by the introduction of a directional control
facility. The facility is provided by use additional voltage inputs to the relay.
ADVANTAGES
Fast fault clearance
Fault coverage independent of source impedance variation
Provides primary and backup in single unit
Can be adapted to work like unit protection with signaling channel
PRINCIPLE
A distance relay compares the currents and voltages at the relaying point with current
providing the operating torque and the voltage provides the restraining torque. In other
words an impedance relay is a voltage restrained over current relay.
`CGI 14C
Current relay
CGI 14C Fault No=01 Fault No. & fault trip counter
Fault records Tcntr=-16 indication
Fault duration
Fault duration indication
000.000sec
20. ISOLATOR
Circuit Breaker always trip the circuit but open contacts of breaker cannot be visible
physically from outside of the breaker and that is why it is recommended not to touch any
electrical circuit just by switching off the . So for better safety there must be some
arrangement so that one can see open condition of the section of the circuit before
touching it. Isolator is a mechanical switch which isolates a part of circuit from system as
when required. Electrical isolators separate a part of the system from rest for safe
maintenance.
Isolator is a mechanical switching device capable of opening and closing a circuit
when a negligible current is broken or made or when no significant voltage across the
terminals of each pole exists. Isolators shall be capable of carrying current under normal
conditions and for a specified time short circuit currents. In open position, the isolating
shall provide an isolating distance between the terminals.
22 EARTHING
Earthing is to provide a Zero potential surface in and around and under the area where
the electrical equipment is installed or erected. The non-current carrying parts of the
electrical equipment is connected to the general mass of the earth which prevents the
appearance of dangerous voltage on the enclosures and helps to provide safety to working
staff and public.
station. Unless earthing system are designed carefully, the maximum gradient along the
surface may be great enough to endanger a man walking in the vicinity.
The supporting structures, C.T. chambers, P.T. tanks, Cable glands etc., are to be
connected to earth.
1. POWER TRANSFORMERS:
A) The transformer body or tank is directly connected to earth grid. In addition,
there should be direct connection from the tank to the earth side of the lightning
arresters.
B) The transformer track rail should be earthed separately.
C) The neutral bushing is earthed by a separate connection to the earth grid.
2. POTENTIAL AND CURRENT TRANSFORMERS:
The bases of the CTs and PTs. are to be earthed. All bolted cover plates of the
bushing are also to be connected the earth grid.
3. LIGHTNING ARRESTERS:
The bases of the L.As are to be earthed with conductors as short and straight as
Possible (for reducing impedance). Each L.A. should have individual earth rods,
which are in turn connected to earth grid.
4. CIRCUIT BREAKERS:
The supporting structures, C.T. chambers, P.T. tanks, Cable glands etc., are to be
connected to earth.
5. OTHER EQUIPMENT‟S:
All equipment‟s, structures, and metallic frames of switches and isolators are to be
earthed separately.
6. FENCING:
Providing separate earth or connecting to the station earth depends upon the distance
of the fence the station earth. If the distance is within feet, an inter-connection made
to the station earth. If not, the metallic fences are earthed by means of earth rods
spaced at not more than 200 feet.
7. GROUND WIRES:
The ground wires over the station are connected to the station earth. In order that the
station earth potentials during fault conditions are not applied to transmission line
ground wires and towers, all ground wires coming to the stations shall be broken on
the first tower external to station by means of strain disc insulators.
23. SAFETY
7 steps of safety
1. Permission
2. Isolation
3. Notice
4. Lock
5. Inspection
6. Testing
7. Earthing
A tag used without a lock must be supplemented by at least one additional safety
measure that provides a level of safety equal to that of a lock.
Removal of an isolating circuit element such as a fuse
Blocking of a controlling switch
Opening of an extra disconnecting device