You are on page 1of 11

Allocation and Management of Cost Contingency

in Projects
Mohammed Wajdi Hammad 1; Alireza Abbasi, Ph.D. 2; and Michael J. Ryan, Ph.D. 3

Abstract: Contingency is crucial for successfully managing projects since it provides a buffer against risk development. This research
introduces a new methodology to estimate and allocate cost contingency during the planning phase, as well as managing cost contingency
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 04/29/16. Copyright ASCE. For personal use only; all rights reserved.

during the execution phase of the project. The cost contingency allocation technique is based on the activity’s contribution to the overall cost
variance of the project, which includes the cost, uncertainty, and whether the activity is on the critical path or not. New measures have been
introduced in the proposed cost contingency management method to control the expenditure and balance of activities’ cost contingency and
estimate future need. The new cost contingency management method is applied to a real-life bridge maintenance project. The result shows that
the proposed cost contingency methodology is adaptive and robust enough to accommodate typical disruptions in the project environment.
DOI: 10.1061/(ASCE)ME.1943-5479.0000447. © 2016 American Society of Civil Engineers.
Author keywords: Project management; Cost contingency; Contingency estimation; Contingency allocation; Contingency management;
Project control; Monte Carlo simulation.

Introduction experiences with similar projects. Subjectivity is the main disad-


vantage of this technique as the skill, knowledge, and motivation
Construction projects intrinsically involve many uncertainties and of the experts may vary widely (Burroughs and Juntima 2004) or
risks throughout all phases from start-up to completion. These the nature of the project might be very different from the ones the
uncertainties can be classified as predictable (known unknowns) expert has experienced.
and unpredictable (unknown unknowns). Contingency reserve is Contingency may have a tremendous impact on project outcome
a managerial tool to control such identifiable (and unidentifiable) for project participants (Dey et al. 1994; Baccarini 2004). Therefore,
uncertainties/risks. Contingency reserve is defined as “the amount accurate contingency estimates would help project managers/
of funds, budget, or time needed above the estimate to reduce the owners avoid undesirable results when managing projects. Modern
risk of overruns of project objectives to a level acceptable to the estimating textbooks usually represent contingency as a fixed per-
organisation” (Project Management Institute 2013). Construction centage of the estimated contract amount using this method. The per-
participants including owners, contractors, and designers add cost centage reported is generally around 5–10% of the contract amount
contingency reserve in order to cover intangible costs from unpre- (Smith and Bohn 1999). However, according to Terje Karlsen and
dictable changes in the base cost estimate. Lereim (2005), this method has several weaknesses: (1) it is overly
Research has shown that one of the main factors that contributes simplistic and heavily dependent on estimators’ faiths in their own
to the projects’ success is the improvements in the cost estimation past experiences; (2) the percentage is broadly estimated and not ap-
techniques (Uzzafer 2013) including cost contingency estimation. propriate for a specific project; and (3) there is a tendency to double
The contingency budget is not established to cover changes in count risks. In order to complement these disadvantages, several
scope; rather, its purpose is to cope with cost increases resulting methods for estimating an optimal contingency have been proposed
from the uncertain nature of some construction activities. Alloca- and studied as discussed by Günhan and Arditi (2007).
tion of low amounts of contingency for projects with high risks The aim of this research is to develop a methodology that can
may result in significant losses. On the other hand, high amounts assist project managers/owners in making decisions about issues
of contingency may decrease the chances of winning the contract. regarding costs in the project. This paper presents a methodology
Expert judgment is generally used to determine the bidding con- to estimate, allocate, and manage cost contingency in a project. This
tingency reserve. Expert decision is mainly based on the previous research focuses on the predictable uncertainties, otherwise known
as the known unknowns and not the unpredictable uncertainties.
1 The paper is organized as follows. In the next section, the liter-
Ph.D. Candidate, School of Engineering and IT, Univ. of New South
Wales (UNSW Australia), Canberra, ACT 2610, Australia. E-mail:
ature on different models used for estimating, allocating, and man-
Mohammed.Hammad@student.adfa.edu.au aging cost contingency in projects is reviewed; this is followed
2
Lecturer, School of Engineering and IT, Univ. of New South Wales by the proposed new metrics. After that, the new methodology
(UNSW Australia), P.O. Box 7916, Canberra, ACT 2610, Australia is applied to a real-life bridge maintenance project. The discussion
(corresponding author). E-mail: a.abbasi@unsw.edu.au section follows and finally, the authors draw conclusions on the
3
Senior Lecturer, School of Engineering and IT, Univ. of New South research, summarize findings, and suggest future work.
Wales (UNSW Australia), Canberra, ACT 2610, Australia. E-mail:
m.ryan@adfa.edu.au
Note. This manuscript was submitted on March 4, 2015; approved on Review of Models for Estimating and Managing
January 19, 2016; published online on April 25, 2016. Discussion period Project Cost Contingency
open until September 25, 2016; separate discussions must be submitted for
individual papers. This paper is part of the Journal of Management in Touran (2003) proposed a probabilistic model that considers the
Engineering, © ASCE, ISSN 0742-597X. random nature of change orders and their impact on the cost

© ASCE 04016014-1 J. Manage. Eng.

J. Manage. Eng., 04016014


and schedule of a construction project. The model incorporates un- with two different project teams was used to compare and validate
certainties in project cost and schedule and also calculates the con- findings from one project team to another. Gharaibeh (2014) found
tingency based on the level of confidence specified by the project that the lack of cost contingency and escalation for material and
owner. The proposed model depends on the following variables: construction labor costs in the initial estimate are considered im-
estimate for the rate of change, project duration, average cost per portant problems in managing the project cost.
change, and coefficient of variation of cost of change. He found Uzzafer (2013) presented a contingency estimation model for
that the logical way to address project uncertainties is by using a a software development project. The proposed model considered
method that explicitly considers uncertainty, rather than the more the estimated cost and the risk of software projects to estimate con-
commonly used deterministic approaches. tingency resources; hence, contingency estimates are correlated to
Barraza and Bueno (2007) presented a methodology for using the cost and risk of software projects. The model considers the risk
Monte Carlo simulation (MCS) for cost contingency management, tolerance of software organizations to estimate the contingency and
which also includes heuristics for contingency assignment alloca- helps to decrease the maximum impacts of risk events within the
tion among project activities. They stated that if independent perfor- risk tolerance. Data were analyzed from 19 software projects of
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 04/29/16. Copyright ASCE. For personal use only; all rights reserved.

mance is assumed among the project activities and a probability National Aeronautics and Space Administration (NASA) in an ef-
distribution is assigned to each activity, all possible project costs will fort to understand the difference between the estimated costs and
be normally distributed with a mean cost similar in value to the one actual costs of software projects. He found that the main factor that
that is calculated by the addition of the activities’ mean costs, and contributed to the increase in the number of successful projects is
the variance of the possible project cost results to be equal to the the improvements in the cost estimation techniques.
accumulation of all activities’ cost variances. The proposed meth- Lhee et al. (2014) proposed a two-step artificial neural network
odology provided the performance status classification, which can (ANN)-based method for estimating the optimal contingency for
be used as a practical guide for the management decision making. construction projects. The model was developed by manipulating
Idrus et al. (2011) proposed a method to estimate cost contin- an intermediate form of contingency (i.e., contingency rate) as
gency using a flexible and rational approach that could accommo- the output variable of the neural network to predict the owner’s
date contractors’ subjective judgment based on risk analysis and the contingency on construction projects. A comparison of the perfor-
fuzzy expert system concept. The proposed method was applied to mances was performed with the one-step ANN-based model. Based
building and infrastructure projects in Malaysia. They applied risk on the net statistics such as average error, mean squared error, cor-
analysis as the main concept to identify and assess the level of risk relation values, and statistical analysis about error rates, the predic-
of each risk factor, while the fuzzy expert system was the method tive performance of the two-step model was shown to be better than
used to assess the level of risk in the risk assessment step. Develop- that of the one-step model. They also claimed that the two-step ap-
ment of the proposed model can be described in the following seven proach has the potential to improve an owner’s budgetary decisions,
stages: development of a conceptual model for cost contingency, reducing the risk of either underutilizing or overcommitting funds.
determination of risk factors for the model, development of the Eldosouky et al. (2014) have done research to trial and put
fuzzy expert system, model testing, tuning, and validation. Project an end to the incorrect opinion that “adding contingency funds
cost contingency was modeled as the function of the level of risk to the tender price of a project may lead to loss of the tender.” They
factors identified as risk magnitude. They found that the predictions proposed an approach for determining and monitoring cost contin-
given by the system were within 20% accuracy compared to actual gency reserve (CCR) for a project. Control of CCR is interfaced
cost contingencies. with earned value management. An application was carried out to
Turskis et al. (2012) reviewed the evolution of concepts, the use real-life projects. The proposed approach for determination of CCR
of reserves, robust itineraries, and contingency of time and cost in for a project with established context for the purpose of tendering
the construction industry. They presented the main trends in differ- includes the following six phases: acquiring project cost estimate
ent approaches to risk management in construction and construc- and high-quality schedule; describing project schedule and cost
tion project processes, such as reliability of production, discount uncertainty; preparing risk register; performing integrated cost/
methods, methods of reporting, and integrated management to- schedule Monte Carlo simulation; determining performance meas-
gether with trends towards standardization of the investment pro- urement baseline (PMB), CCR, management reserve, and nonspe-
cess management. They concluded that the risks can be analyzed cific risk provision; and finally, monitoring and control of project
depending on a context. Risk should be treated as a state, in which PMB and risk budgets. The authors determined that if a contractor
there is a possibility of a loss. One of the most relevant concepts of prepares a detailed cost estimate for the purpose of tendering for a
risk is the dispersion of actual and expected results. This concept certain project accompanied by a high-quality critical path method
leaves room for contingency. They also stated that processes in schedule, then the contractor will be anxious for performing project
construction industry, as well as implementation of construction risk analysis and determining CCR as proposed in this study. On
projects, are governed by specific laws. The need to standardize the other hand, if the contractor does not prepare such information,
legislation results from international cooperation in the execution they will not accept to pay attention to project risk management and
of contracts and requirements of banks. This promotes standardi- the determination of CCR according to the proposed approach or
zation, especially at the stage of preparation for and implementation any equivalent approach.
of investments. In summary, most of the papers found in the literature were
Gharaibeh (2014) investigated the issue of project cost control about estimating cost contingency, with very few about managing
in major power transmission projects, to understand the reasons cost contingency in a project and even fewer about combined the
behind cost overrun. The Delphi method was used to identify prob- cost contingency estimation and management. Touran (2003), Idrus
lems of controlling the project cost, and identifying lessons learned. et al. (2011), Uzzafer (2013), and Lhee et al. (2014) all show differ-
The Delphi study is normally a qualitative research method using ent methods to estimate cost contingency. Some require the project
questionnaires as a research instrument where a panel of experts is manager to have prior knowledge, such as fuzzy logic and artificial
asked to provide feedback and answers on selected questions nor- neural networks, while others require to make assumptions about
mally involving several iterations or rounds of questions (Linstone variables or collecting data. Eldosouky et al. (2014) presented a
and Turloff 1975). A three-round semistructured questionnaire method to manage contingency on a project. This method requires

© ASCE 04016014-2 J. Manage. Eng.

J. Manage. Eng., 04016014


data collection from previous projects and also the use of some approaches discussed in the preceding review. The proposed
subjective opinion. Barraza and Bueno (2007) presented a method method includes estimating, allocating, and managing cost contin-
to calculate and manage cost contingency, based on Monte Carlo gency. First, the proposed method is easy to use as it does not re-
simulation. quire tedious equations or timely data collection (such as interviews
The models proposed by Touran (2003), Idrus et al. (2011), and surveys). It also does not require the project manager to have
Lhee et al. (2014), and Uzzafer (2013) all require extensive data any prior knowledge of ANN, fuzzy logic, or any other simulation.
collections and surveys that need to be undertaken by the project Secondly, the methodology serves as an early warning for activities
manager before starting the project. It would be very difficult to list that are not yet completed by calculating the cost contingency re-
each and every risk for the activities involved in the project, or even serve available to be spent on future activities based on the ongoing
collect accurate data about the impact of each risk on the total cost pattern of spending. This would be an extremely powerful tool to
of the project. These types of models would be more suitable for the project managers because the new metrics are used as a refer-
projects that have been already completed by the project manager ence whenever overspending occurs in the project and to show if
several times, as the collection of inaccurate data will result in in- the overspending is within the acceptable range in the organization.
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 04/29/16. Copyright ASCE. For personal use only; all rights reserved.

correctly calculating contingencies. Idrus et al. (2011) require the The method allows the project manager to carefully plan activities
project manager to have knowledge regarding fuzzy logic, while based on the past and current spending pattern. Thirdly, the pro-
Lhee et al. (2014) require prior knowledge regarding artificial neu- posed method is adaptable and able to accommodate disruptions
ral networks (ANNs). in the project environment by allowing the project manager to se-
The management method provided by Barraza and Bueno lect the required confidence interval.
(2007) can be used in any project, but does not propose how to
allocate contingency to each activity. The management method
provided by Eldosouky et al. (2014) requires identifying all risks Proposed Cost Contingency Management
involved in the project, which can be difficult and very time con- Framework
suming to obtain the required data.
Table 1 shows a summary of all models found regarding con- Very few studies have been conducted on the subject of cost con-
tingencies in project management. In summary, the following is tingency management during project execution; such research is
what differentiates the proposed method from the previous nearly nonexistent. To fill this gap, this paper proposes a new

Table 1. Summary of Contingency Models in the Literature


Developed Type of
Method Purpose Result by research
Probabilistic model that incorporates To consider the random nature of The model provides confidence interval Touran (2003) Contingency
uncertainties in project cost and change orders and their impact on the when the amount of contingency estimation
calculates contingency based on the cost and schedule of a construction deviates from the expected values
level of confidence selected project. This is done by calculating
the probability of cost overrun for a
given contingency level
MCS to estimate and manage To control target cost to maintain The proposed method provided Barraza and Contingency
contingency in a project, and actual costs below the target cost performance status classification which Bueno (2007) estimation and
heuristics to allocate contingency values of the project can be used as practical guide for management
decision making
Estimates cost contingency using a Accommodate contractors’ subjective The predictions given by the proposed Idrus et al. Contingency
flexible and rational approach judgment based on risk analysis and model were within 20% accuracy (2011) estimation
fuzzy expert system concept compared to actual cost contingencies
Implements the Delphi method to To understand the reason behind cost Lack of cost contingency and escalation Gharaibeh Contingency
identify problems of controlling overrun by investigating the issue of of costs in the initial estimate is (2014) management
project costs project cost control in major power considered one of the most important
transmission projects problems in managing projects
A contingency estimation model that To consider the risk tolerance of The main factor contributing to the Uzzafer (2013) Contingency
considers the estimated cost and the software organizations to estimate the increase in the number of successful estimation
risk of software projects to estimate contingency and help decrease the projects is the improvements in the cost
contingency resources maximum impacts of risk events estimation techniques
within the risk tolerance
A two-step artificial neural network To estimate the optimal contingency The proposed method has potential to Lhee et al. Contingency
(ANN)-based method for estimating for funding of transportation improve an owner’s budgetary (2014) estimation
the optimal contingency construction projects decisions, reducing the risk of either
underutilizing or overcommitting funds
Monitors cost contingency reserves To put an end to the incorrect opinion If a contractor prepares a detailed cost Eldosouky Contingency
and controlling them using earned that “adding contingency funds to the estimate for the purpose of tendering et al. (2014) management
value tender price of a project may lead to accompanied by a high quality critical
loss of the tender” path schedule, then the contractor will
be anxious for performing project risk
analysis and determining CCR

© ASCE 04016014-3 J. Manage. Eng.

J. Manage. Eng., 04016014


method of controlling project cost contingency during execution Each and every step of Fig. 1 is described in detail in the fol-
phase of the project. In the approach proposed herein, a prob- lowing (note: any variable with a subscript A refers to the individ-
abilistic method can be adopted to determine the cost contingency ual activity, while a variable with subscript P refers to the total
of the project. This involves assigning a probability distribution project):
function to each activity in the project, and through a summative 1. Record the planned value for each activity (PVA ): this is the
process, developing a probability distribution function for the over- estimated cost for completion of each activity without contin-
all project cost. Subsequently, cost contingencies are calculated us- gency based on experience of similar past projects.
ing MCS and allocated to each activity based on the activity’s 2. Calculate the cost contingency for the entire project (CCP ):
contribution to the overall cost variance of the project. This means this determines the total contingency required for the project.
that activities with large costs, high uncertainty, and high impor- CCP is calculated by assigning a probability distribution for
tance (activities that lie on the critical path) will receive a higher each activity in the project. MCS is run with a large number
cost contingency than activities with low costs, low uncertainty, and of trials; the result obtained from using the simulation is the
do not lie on the critical path. Eldosouky et al. (2014) stated that total cost (TC). The difference between TC and PVP (planned
value of the entire project) is known as CCP
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 04/29/16. Copyright ASCE. For personal use only; all rights reserved.

MCS is more effective compared to other methods as it is an easy-


to-use, understandable, simple, and practical tool. It can easily ac-
commodate estimating uncertainties, threats, and opportunities. CCP ¼ TC − PVP ð1Þ
Fig. 1 shows the steps for the proposed project cost contingency
method. Before using the proposed method, the project cost and 3. Allocate CCP to each activity (CCA ): CCP is allocated to each
the cost for each activity should be calculated and finalized by activity based on the activity’s contribution to the project’s cost
the estimator. The total contingency of the project is calculated variance. The percentage contribution of each activity is ob-
via MCS using the cost estimates prepared by the project man- tained from Oracle Crystal Ball after running MCS. The fol-
ager/owner. The contingency is allocated to each activity and is lowing equation can be used to calculate the contingency for
measured using the new metrics at the end of each reporting period. each activity:

Fig. 1. Steps for estimating and managing project cost contingency

© ASCE 04016014-4 J. Manage. Eng.

J. Manage. Eng., 04016014


CCA ¼ ð1 − αÞ × ð% contribution to variance × CCP Þ activities. On the other hand, a negative CVA indicates that
the project exceeds planned budget, and therefore cost contin-
þ α × ðPVA =PVP Þ × CCP ð2Þ gency will be used.
where α = confidence interval chosen by the project manager 8. Calculate the remaining contingency for each activity (RCA )
to represent an acceptable project risk. Eq. (1) consists of RCA ¼ ECSA þ CVA ð5Þ
two parts
• The first is ð1 − αÞ × ð% contribution to variance × CCP Þ; RCA shows the project manager/owner if the allocated cost
and contingency for an activity, in a given reporting period, is
• The second is α × ðPVA =PVP Þ × CCP . enough to cover the cost overrun. A negative RCA indicates
If the project manager is 100% confident that the project that the activity used more cost contingency than what it
will never experience an overrun, then α is equal to 100% was expected. A positive RCA shows that not all contingency
and hence, only the second part will be considered. In this have been used and there is still some contingency remaining.
case, the cost contingency will be allocated to each activity A zero RCA means that the activity used the entire contingency
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 04/29/16. Copyright ASCE. For personal use only; all rights reserved.

based on the fraction of PVA to PVP , regardless of the uncer- allocated to it for the given reporting period.
tainty, cost, or whether the activity is on the critical path or not. 9. Calculate remaining planned value (RPVA )
On the other hand, if the project manager chooses α to be RPVA ¼ ð1 − % completeÞ × PVA ð6Þ
less than 100%, for instance, a 90% confidence interval, the
first part of the equation will be considered as there is uncer- The RPV calculates how much planned value is remaining
tainty involved. This is where an activity’s contribution to the for the activity to complete. It is calculated by multiplying the
total cost variance is considered. The contribution to variance percentage remaining to complete the activity by the PVA .
answers questions such as “What percentage of the variance or 10. Calculate actual remaining contingency (ARCA )
uncertainty in the target forecast is caused by activity X?” It is
calculated by squaring the rank correlation coefficients and ARCA ¼ CVA þ CCA ð7Þ
normalizing them to 100%. Contribution to variance indicates ARCA is different that RCA because RCA calculated the
the relative importance by showing the percentage of the remaining contingency with respect to a given reporting
forecast variance contributed by each assumption (Oracle period. On the other hand, ARCA calculates how much of
Corporation 2012). The correlation coefficient shows the de- the allocated total cost contingency to each activity is re-
gree to which assumptions and forecasts change together. maining.
Since the project is made up of individual activities that are 11. Determine total remaining cost (TRCA )
connected to each other, the activities that have a significant
impact on the forecast will have a high correlation coefficient. TRCA ¼ ARCA þ RPVA ð8Þ
The higher the absolute value of the correlation coefficient,
the higher the contribution to variance and the stronger the This calculates the total cost (including contingency) re-
relationship. This means that any activity with a high cost maining at the end of each reporting period.
(affecting the budget of the project), or an activity that sits 12. Calculate planned updated remaining contingency for each
on the critical path (affecting the duration of the project), activity (PURCA )
or has a high uncertainty the higher the correlation, then
the stronger the relationship to the target forecast. This will PURCA ¼ CCA − ECSA ð9Þ
allow the project manager to find out which assumptions Calculates the minimum cost contingency for each activity
are influencing the forecasts the least and can pay less atten- that should remain at the end of the reporting period. For ex-
tion or discard them altogether, and focus more on the activ- ample, if an activity is 60% complete, then it is expected that at
ities that will have the most impact on the forecast. least 40% of the contingency is remaining.
4. Determine percentage completion for each activity: each activ- 13. Calculate actual updated remaining contingency for each ac-
ity is evaluated at the end of the reporting period and the per- tivity (AURCA )
centage completion is estimated by the project manager.
5. Record actual cost for each activity (ACA ): this is the cost IF % complete ¼ 100; then AURCA ¼ 0;
spent on an activity during the project execution and is re-
corded at the end of every reporting period. otherwise; AURCA ¼ ðRPVA =RPVP Þ × RCP þ PURCA ð10Þ
6. Calculate the expected contingency spent for each activity
(ECSA ) This means that if the % complete of an activity is 100%, then
the AURC is set to be zero. This is because when an activity is
ECSA ¼ % complete × CCA ð3Þ complete then any remaining contingency (or contingency overrun)
The ECS calculates the maximum amount of cost contin- will be distributed to other activities, either to be used as extra cush-
gency, for each activity, that is expected to be spent at the end ion against future uncertainties (in the case of excess contingency
of the reporting period. For example, if an activity is 60% com- remaining) or to distribute the overrun among other activities (in
plete, then the activity is expected to spend 60% of its allo- the case of spending more contingency than expected). At the end
cated contingency. of the reporting period, the remaining contingency of the project
7. Calculate cost variance for each activity (CVA ) (RCP ) will be distributed to other activities based on the share
of the RPVA of the activity in the RPVP of the project. The project
CVA ¼ ð% complete × PVA Þ − ACA ð4Þ manager should then decide if any further action is required to be
A positive CVA indicates that the activity is under budget, taken to keep the project within the original budget. If PURCP is
and no contingency was required. If the activity has completed greater than AURCP , the project has more cost contingency re-
and the CVA is still positive, then any remaining PVA will be maining than expected. If the PURCA is less than AURCA , the ac-
added to the remaining CCA and used for future remaining tivity has less remaining cost contingency than expected. If PURCP

© ASCE 04016014-5 J. Manage. Eng.

J. Manage. Eng., 04016014


is equal to AURCP , from a financial point of view, the project is internal resources, so there was no need to obtain any contractors.
performing exactly as planned. The total project cost estimation for the project was done by a dif-
ferent department and then sent to the project manager for review.
The total project cost includes a detailed breakdown of the estimates
Case Study (based on experience from similar past project), as well as the
amount of contingency included. Therefore, by removing the con-
In order to demonstrate the use of the proposed cost contingency tingency cost, the total project cost turns out to be $126,500. The
method, the method is applied to a real-life bridge maintenance acceptable risk chosen for this paper is 20% (i.e., 20% of being
project. The project presented in this paper is taken from a recently overrun or 80% of being underrun). After running Monte Carlo sim-
completed Roads and Maritime Services (RMS) maintenance ulation for 10,000 trials and using the 80th percentile, the total cost
project in the state of New South Wales, Australia. The project con- (TC) is calculated to be $131,872. The results obtained from run-
sisted of replacing 730 m of crash barrier as well as cleaning, blast- ning MCS using Microsoft Project 2013 and Oracle Crystal Ball
ing, and painting all bridge bearings, and fabricating and installing are shown in Fig. 2. The CCP (which is the difference between TC
10 new ladders to replace the existing rusted ladders (one on each and PVP ) is $5,372.
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 04/29/16. Copyright ASCE. For personal use only; all rights reserved.

pier). The project also included repairing two major gantries. The Each activity has an influence on the total cost variance of the
bridge project lasted for 21 months with a budget of $3 million, but project; this is used to allocate contingencies to each activity using
for the sake of this research, only the fabrication and installation of Eq. (1). The results for the cost contingency allocation are shown in
three new ladders are studied, which had a planned duration of just Table 2. The cost contingencies are allocated based on activity’s
over 2 months with a budget of $135,652. Since the project dura- contribution to the overall cost variance. This means that an activity
tion is only 39 days, the reporting period is chosen to be 10 days. with a high uncertainty, high cost, and that lies on the critical path,
The following are assumed when calculating cost contingencies will have a high contribution to the cost variance of the project and
for this paper: will therefore have a higher share of the cost contingency, and the
1. All activities are normally distributed to 10% of the mean cost. opposite is true.
To allow for this assumption, according to Barraza and Bueno The following is a detailed demonstration of how cost contin-
(2007), independent performance is to be assumed and probabil- gency is allocated to the activity 1.1, which requires the use of
ity distribution to be assigned to all activities. “Therefore all pro- Eq. (2)
ject costs will be normally distributed with a mean cost similar
in value to the one that is calculated by the addition of the ac- CCA ¼ ð1 − αÞ × ð% contribution to variance × CCP Þ
tivities’ mean costs, and the variance of the possible project cost
results to be equal to the accumulation of all activities’ cost þ α × ðPVA =PVP Þ × CCP
variance (as a result from the central limit theorem)” (Barraza
and Bueno 2007). As mentioned earlier, the project manager has chosen an 80%
2. Any remaining contingency, for say, activity A, should not be confidence interval, α ¼ 80%. The % contribution to variance
transferred to activity B until activity A is 100% complete. This for activity 1.1 was found to be 0.39% (refer to Table 2). The cost
assumption prevents spending the contingency on a first-come, contingency for the project (CCP ) was $5,372 (as discussed ear-
first-served basis, but instead focusing on keeping all activities lier), which is calculated as the difference between the total cost
under the target cost. It also allows identifying which activities of the project (TCP ) and the planned value of the project (PVP ),
are experiencing a cost overrun and requiring to be monitored refer to Eq. (1) and task 1 in Table 2. The planned value for activity
more closely (and in some instances take immediate actions). 1.1 (PVP ) is 4,500 (refer to Table 2), while the planned value for
The PVP for the project was estimated to be $126,500 (without the project (PVP ) is $126,500 (refer to Table 2). Therefore, the CCA
contingency). All work on this project was done in-house using is $155

Fig. 2. Results of total project cost obtained from Monte Carlo simulation

© ASCE 04016014-6 J. Manage. Eng.

J. Manage. Eng., 04016014


Table 2. Allocation of Cost Contingency to Each Activity Table 3). For the activity 1.1, the planned value (PVA ) is $4,500 as
Task Contribution to Planned Cost contingency seen in Table 3 and the actual cost (ACA ) spent on activity 1.1 is
name variance (%) value (CC) Total cost $4,500. Going back to Table 2, the cost contingency assigned for
this activity is $230. Since the activity is 100% and using Eq. (3),
1 100.00 $126,500 $5,372 $131,872
1.1 0.39 $4,500 $230 $4,730 the ESCA is $230 (100% × $230). This means that activity 1.1 was
1.2 94.15 $68,000 $1,690 $69,690 expected to spend $230 of the total $230 contingency assigned to it
1.2.1 93.21 $60,000 $1,228 $61,228 by the end of the first remaining period. The remaining contingency
1.2.2 0.01 $1,000 $226 $1,226 (RCA ) as shown in Table 3 is $230, which is calculated using Eq. 5
1.2.3 0.93 $7,000 $236 $7,236 ($230 + $0). This means that at the end of the first reporting period,
1.3 5.47 $54,000 $3,452 $57,452 activity 1.1 still has $230 remaining not yet used. The total remain-
1.3.1 2.07 $20,000 $1,153 $21,153
1.3.1.1 0.79 $6,000 $235 $6,235
ing contingency (TRCA ) is $230, which is calculated using Eq. (6)
1.3.1.2 0.38 $4,000 $230 $4,230 ($0 + $230). The remaining planned value is $0, since activity 1.1
1.3.1.3 0.64 $5,000 $233 $5,233 has been completed. The total remaining cost (TRCA ) at the end of
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 04/29/16. Copyright ASCE. For personal use only; all rights reserved.

1.3.1.4 0.18 $3,000 $228 $3,228 the first reporting period is $230. This means that there is $230
1.3.1.5 0.08 $2,000 $227 $2,227 remaining (including planned value and contingency), which is cal-
1.3.2 1.06 $14,000 $1,142 $15,142 culated using Eq. (8) ($230 + $0).
1.3.2.1 0.14 $3,000 $228 $3,228 For the activity 1.2.1, the total PV assigned is $60,000 (as seen
1.3.2.2 0.32 $3,000 $230 $3,230
in Table 2), but since the activity is only 20% complete, the amount
1.3.2.3 0.36 $3,500 $230 $3,730
1.3.2.4 0.19 $3,000 $228 $3,228 of PV shown in Table 3 is $12,000 ($60,000 × 20%) while the ACA
1.3.2.5 0.04 $1,500 $227 $1,727 is $15,000. The ECSA is $246, which is calculated using Eq. (3)
1.3.3 2.33 $20,000 $1,156 $21,156 (20% × $1,228). This means that activity 1.2.1 is expected to spend
1.3.3.1 0.92 $6,000 $236 $6,236 a maximum of $246 of the $1,228 (from Table 2) assigned to it
1.3.3.2 0.49 $4,000 $231 $4,231 by the end of the first reporting period. The CVA is –$3,000, which
1.3.3.3 0.53 $5,000 $232 $5,232 is calculated using Eq. (4) (20% × $60,000–$15,000). Since CVA
1.3.3.4 0.36 $3,000 $230 $3,230
1.3.3.5 0.03 $2,000 $227 $2,227
is a negative value, this means that activity 1.2.1 exceed the planned
value and therefore the contingency will be used. The remaining
contingency (RCA ) is −$2,754, which is calculated using Eq. (5)
  ($246–$3,000). This means that activity 1.2.1 used $2,754 more
$4,500 contingency than what it was expected to use by the end of the
0.2 × ð0.39% × $5,301Þ þ 0.8 × × $5,301 ¼ $155
$126,500 first reporting period ($246 was expected). The ARCA is thus
The TCA for activity 1.1 is calculated [using Eq. (1)] as −$1,772, which is calculated using Eq. (7) (–$3,000 þ $1,228).
$4,500 þ $155 ¼ $4,655. This means that the cost overrun for activity 1.2.1 was larger than
For the first reporting period (after 10 days), activity 1.1 is 100% the total contingency assigned to it; $1,228 was originally assigned
complete and only 20% of the activity 1.2.1 is completed (refer to to activity 1.2.1 (refer to Table 2). The RPV is $48,000, calculated

Table 3. Results for the First Reporting Period (after 10 days)


Project Complete
activities PV ($) PURC ($) AURC ($) (%) AC ($) ECS ($) CV ($) RC ($) ARC ($) RPV ($) TRC ($)
1 16,500 4,896 2,372 24 19,500 476 −3; 000 −2;524 −1;542 110,000 112,372
1.1 4,500 0 0 100 4,500 230 0 230 230 0 230
1.2 12,000 1,444 159 16 15,000 246 −3; 000 −2,754 −1,772 56,000 54,690
1.2.1 12,000 982 −119 20 15,000 246 −3,000 −2,754 −1,772 48,000 46,228
1.2.2 — 226 203 0 — — — — — 1,000 1,226
1.2.3 — 236 75 0 — — — — — 7,000 7,236
1.3 — 3,452 2,213 0 — — — — — 54,000 57,452
1.3.1 — 1,153 694 0 — — — — — 20,000 21,153
1.3.1.1 — 235 97 0 — — — — — 6,000 6,235
1.3.1.2 — 230 138 0 — — — — — 4,000 4,230
1.3.1.3 — 233 118 0 — — — — — 5,000 5,233
1.3.1.4 — 228 159 0 — — — — — 3,000 3,228
1.3.1.5 — 227 181 0 — — — — — 2,000 2,227
1.3.2 — 1,143 822 0 — — — — — 14,000 15,143
1.3.2.1 — 228 159 0 — — — — — 3,000 3,228
1.3.2.2 — 230 161 0 — — — — — 3,000 3,230
1.3.2.3 — 230 150 0 — — — — — 3,500 3,730
1.3.2.4 — 228 159 0 — — — — — 3,000 3,228
1.3.2.5 — 227 193 0 — — — — — 1,500 1,727
1.3.3 — 1,156 697 0 — — — — — 20,000 21,156
1.3.3.1 — 236 98 0 — — — — — 6,000 6,236
1.3.3.2 — 231 139 0 — — — — — 4,000 4,231
1.3.3.3 — 232 117 0 — — — — — 5,000 5,232
1.3.3.4 — 230 161 0 — — — — — 3,000 3,230
1.3.3.5 — 227 181 0 — — — — — 2,000 2,227

© ASCE 04016014-7 J. Manage. Eng.

J. Manage. Eng., 04016014


using Eq. (6) (80% × $60,000). The total remaining cost was thus For the third reporting period (after 30 days), as shown in
$46,228, which is calculated using Eq. (8) (−$1,772 þ $48,000). Table 5, all activities under 1.2 is now complete as is all work
The overall project performance for the first reporting period under 1.3.1. The actual cost of the activity 1.2.1 is $62,000
showed that RCP was –$2,524, meaning that the project went over ($2,000 over the PVA ). ECSA is $1,228; this means because ac-
budget and the allocated contingency—for activities in the first re- tivity 1.2.1 is 100% complete, then 100% of the contingency origi-
porting period—was not enough. ARCP was –$1,542, showing that nally allocated to it is expected to be spent. The CVA is –$2,000,
the total contingency assigned for all activities in the first reporting which means that the activity used $2,000 more cost than the
period does not cover the cost overrun. When the AURCP is com- allocated PVA . Given the total amount of contingency allocated
pared with the PURCP , for the first reporting period the actual up- to this activity is $1,228, the actual remaining cost ARCA is
dated remaining contingency (AURCP ) was $2,372 and the –$772 (–$2,000 þ $1,228).
planned updated remaining contingency (PURCP ) was $4,896. All work under 1.3.1 has been completed (refer to Table 5) with
This means that, at the end of the first period, the project was ex- an ACA value of $19,900 and a CVA of $100 (saved $100 on the
pected to have $4,896 of cost contingency remaining, but in reality PVA ). The ECSA was $1,153, while the RCA and ARCA were both
the project had $2,372. This shows that for the first reporting period $1,253, which shows that, not only did the project manager save all
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 04/29/16. Copyright ASCE. For personal use only; all rights reserved.

the project consumed more contingency than expected. of the contingency for activities under 1.3.1, but some of the PVA
For the second reporting period (after 20 days), shown in was also saved. Work under 1.3.2 was 67% complete with ACA of
Table 4, activity 1.2.1 is 87% complete and the ACA was $55,000. $6,200, which is just over the PVA of $6,000; this is shown with a
The amount of contingency expected to be spent (ECSA ) was CVA of –$200. The ECSA is $458, which means that all activities
$1,068, i.e., 87% of the total allocated contingency to the activity under 1.3.2 are expected to spend a maximum of $458 of the total
(refer to Table 2 for total allocated contingency). The CVA for ac- $1,142 (refer to Table 2) allocated to it. The RCA and ARCA for the
tivity 1.2.1 was –$2,800. Since the value is negative, this means that second pier showed a positive value ($258), meaning that the cost
activity 1.2.1 is spending more money than its allocated PV. The overrun (CVA ¼ −$200) had been covered by the contingency and
allocated PVA for activity 1.2.1 in the second reporting period was there is still $258 remaining.
$52,200 (Table 4), while the ACA exceeded this amount and there- Overall, the project in the third reporting period had an AURCP
fore contingency will have to be used to cover the cost overrun. of $3,372 while the PURCP is $1,831. This shows that the project
Looking at the RCA , the results show a negative value (–$1,732) was financially doing much better (1.8 times) than expected.
but with a significant improvement when compared to the RCA The project was supposed to have $1,831 (out of $5,372 originally
value for activity 1.2.1 in the first reporting period (Table 4). The allocated to the project) remaining contingency at the end of
ARCA was –$1,572 (–$2,800 þ $1,228). Since the ARCA is a neg- the third reporting period but actually managed to have $3,372
ative value, this means that the cost overrun could not be covered remaining. This means that for the third reporting period, the
by the total contingency assigned to activity 1.2.1. The RPVA is project is doing better than expected and managed to recover
$7,800 and the total remaining cost (TRCA ) was $6,228. Overall, from the overrun achieved in the first and second reporting
the project had an AURCP at the end of the second reporting period periods.
of $2,572, which was much lower than the PURCP ($4,074). For the fourth and last reporting period (after 39 days), shown in
Again, this shows that the project is still consuming contingency Table 6, all work on the project is now completed. The ACP was
more than expected. $127,500 and the PVP was $126,500, which means that the project

Table 4. Results for the Second Reporting Period (after 20 days)


Project Complete
activities PV ($) PURC ($) AURC ($) (%) AC ($) ECS ($) CV ($) RC ($) ARC ($) RPV ($) TRC ($)
1 56,700 4,074 2,572 42 59,500 1,298 −2,800 −1; 502 −1,342 69,800 72,372
1.1 4,500 0 0 100 4,500 230 0 230 230 0 230
1.2 52,200 622 282 69 55,000 1,068 −2,800 −1,732 −1,572 15,800 14,690
1.2.1 52,200 160 −8 87 55,000 1,068 −2,800 −1,732 −1,572 7,800 6,228
1.2.2 — 226 204 0 — — — — — 1,000 1,226
1.2.3 — 236 85 0 — — — — — 7,000 7,236
1.3 — 3,452 2,290 0 — — — — — 54,000 57,452
1.3.1 — 1,153 723 0 — — — — — 20,000 21,153
1.3.1.1 — 235 106 0 — — — — — 6,000 6,235
1.3.1.2 — 230 144 0 — — — — — 4,000 4,230
1.3.1.3 — 233 125 0 — — — — — 5,000 5,233
1.3.1.4 — 228 163 0 — — — — — 3,000 3,228
1.3.1.5 — 227 184 0 — — — — — 2,000 2,227
1.3.2 — 1,143 842 0 — — — — — 14,000 15,143
1.3.2.1 — 228 163 0 — — — — — 3,000 3,228
1.3.2.2 — 230 165 0 — — — — — 3,000 3,230
1.3.2.3 — 230 155 0 — — — — — 3,500 3,730
1.3.2.4 — 228 163 0 — — — — — 3,000 3,228
1.3.2.5 — 227 195 0 — — — — — 1,500 1,727
1.3.3 — 1,156 726 0 — — — — — 20,000 21,156
1.3.3.1 — 236 107 0 — — — — — 6,000 6,236
1.3.3.2 — 231 145 0 — — — — — 4,000 4,231
1.3.3.3 — 232 124 0 — — — — — 5,000 5,232
1.3.3.4 — 230 165 0 — — — — — 3,000 3,230
1.3.3.5 — 227 184 0 — — — — — 2,000 2,227

© ASCE 04016014-8 J. Manage. Eng.

J. Manage. Eng., 04016014


Table 5. Result for the Third Reporting Period (30 days)
Project Complete
activities PV ($) PURC ($) AURC ($) (%) AC ($) ECS ($) CV ($) RC ($) ARC ($) RPV ($) TRC ($)
1 98,500 1,841 3,372 80 100,500 3,531 −2,000 1,531 1,531 28,000 31,372
1.1 4,500 0 0 100 4,500 230 0 230 230 0 230
1.2 68,000 0 0 100 69,900 1,690 −1,900 −210 −210 0 −210
1.2.1 60,000 0 0 100 62,000 1,228 −2,000 −772 −772 0 −772
1.2.2 1,000 0 0 100 900 226 100 326 326 0 326
1.2.3 7,000 0 0 100 7,000 236 0 236 236 0 236
1.3 26,000 1,841 3,372 60 26,100 1,611 −100 1,511 1,511 28,000 31,352
1.3.1 20,000 0 0 100 19,900 1,153 100 1,253 1,253 0 1,253
1.3.1.1 6,000 0 0 100 6,300 235 −300 −65 −65 0 -65
1.3.1.2 4,000 0 0 100 4,100 230 −100 130 130 0 130
1.3.1.3 5,000 0 0 100 4,000 233 1,000 1,233 1,233 0 1,233
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 04/29/16. Copyright ASCE. For personal use only; all rights reserved.

1.3.1.4 3,000 0 0 100 3,500 228 −500 −272 −272 0 −272


1.3.1.5 2,000 0 0 100 2,000 227 0 227 227 0 227
1.3.2 6,000 685 1,122 67 6,200 458 −200 258 258 8,000 8,943
1.3.2.1 3,000 0 0 100 3,200 228 −200 28 28 0 28
1.3.2.2 3,000 0 0 100 3,000 230 0 230 230 0 230
1.3.2.3 — 230 421 0 — — — — — 3,500 3,730
1.3.2.4 — 228 392 0 — — — — — 3,000 3,228
1.3.2.5 — 227 309 0 — — — — — 1,500 1,727
1.3.3 — 1,156 2,250 0 — — — — — 20,000 21,156
1.3.3.1 — 236 564 0 — — — — — 6,000 6,236
1.3.3.2 — 231 450 0 — — — — — 4,000 4,231
1.3.3.3 — 232 505 0 — — — — — 5,000 5,232
1.3.3.4 — 230 394 0 — — — — — 3,000 3,230
1.3.3.5 — 227 336 0 — — — — — 2,000 2,227

Table 6. Results for the Fourth Reporting Period (after 39 days)


Project Complete
activities PV ($) PURC ($) AURC ($) (%) AC ($) ECS ($) CV ($) RC ($) ARC ($) RPV ($) TRC ($)
1 126,500 0 0 100 127,500 5,372 −1,000 4,372 4,372 0 4,372
1.1 4,500 0 0 100 4,500 230 0 230 230 0 230
1.2 68,000 0 0 100 70,000 1,690 −2,000 −310 −310 0 −310
1.2.1 60,000 0 0 100 62,000 1,228 −2,000 −772 −772 0 −772
1.2.2 1,000 0 0 100 1,000 226 0 226 226 0 226
1.2.3 7,000 0 0 100 7,000 236 0 236 236 0 236
1.3 54,000 0 0 100 53,000 3,452 1,000 4,452 4,452 0 4,452
1.3.1 20,000 0 0 100 19,900 1,153 100 1,253 1,253 0 1,253
1.3.1.1 6,000 0 0 100 6,300 235 −300 −65 −65 0 −65
1.3.1.2 4,000 0 0 100 4,100 230 −100 130 130 0 130
1.3.1.3 5,000 0 0 100 4,000 233 1,000 1,233 1,233 0 1,233
1.3.1.4 3,000 0 0 100 3,500 228 −500 −272 −272 0 −272
1.3.1.5 2,000 0 0 100 2,000 227 0 227 227 0 227
1.3.2 14,000 0 0 100 13,900 1,143 100 1,243 1,243 0 1,243
1.3.2.1 3,000 0 0 100 3,200 228 −200 28 28 0 28
1.3.2.2 3,000 0 0 100 3,000 230 0 230 230 0 230
1.3.2.3 3,500 0 0 100 3,200 230 300 530 530 0 530
1.3.2.4 3,000 0 0 100 3,000 228 0 228 228 0 228
1.3.2.5 1,500 0 0 100 1,500 227 0 227 227 0 227
1.3.3 20,000 0 0 100 19,200 1,156 800 1,956 1,956 0 1,956
1.3.3.1 6,000 0 0 100 6,200 236 −200 36 36 0 36
1.3.3.2 4,000 0 0 100 4,400 231 −400 −169 −169 0 −169
1.3.3.3 5,000 0 0 100 3,500 232 1,500 1,732 1,732 0 1,732
1.3.3.4 3,000 0 0 100 3,000 230 0 230 230 0 230
1.3.3.5 2,000 0 0 100 2,100 227 −100 127 127 0 127

had spent $1,000 more than was planned to be spent. The total re- Discussion
maining cost (TRCP ) at the end of the project was $4,372. This
shows that the cost contingency was enough to cover all cost over- It has been shown that contingency can have a tremendous impact
runs in the project and there was still $4,372 remaining at the end of on project outcome for project participants (Dey et al. 1994;
the project, whereas the expected contingency spent (ECSA ) at the Baccarini 2004) as it provides a buffer against risk development.
last reporting period (end of the project) is $5,372 (as shown in A contingency that is too large can result in poor cost management,
Table 6). uneconomic completion of a project, and a lack of available funds

© ASCE 04016014-9 J. Manage. Eng.

J. Manage. Eng., 04016014


for other organizational activities. On the other hand, a contingency The project used in this paper is a real-life bridge maintenance
that is too low can give rise to inadequate funding for executing project and the reporting period is selected every 10 days.
a project, an unrealistic financial environment, and unsatisfactory
performance outcomes. Performance measures for cost contin-
gency tracks the amount or percentage of contingency included Conclusion
in an estimate for a project (Harper et al. 2013). This allows the
project manager to understand the proper amount of contingency The proposed method considers controlling the actual costs for a
needed for a particular project. Tracking contingency helps to es- project and each activity to be under the target cost value. If the
tablish baseline contingency amount according to project size and original planned goal (of an activity) is not achieved, its contin-
type, and the tracked data are then useful for referencing historical gency reserve will be available for use for the following activities;
data when similar project arise. This research thus has introduced a however, the excess cost contingency allowance for an activity
new methodology to estimate and allocate cost contingency during should not be transferred to any other activity until the former
the planning phase, as well as managing cost contingency during has been fully completed. The original cost contingency estimation
the execution phase of the project. method used in the bridge maintenance presented in this paper was
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 04/29/16. Copyright ASCE. For personal use only; all rights reserved.

based on the experience of the estimator from similar past projects.


The main disadvantage is that this method is subjective and varies
Cost Contingency Estimation and Allocation widely based on the estimator’s skill, knowledge, and experience.
For cost contingency estimation, the project manager estimates the Sometimes, the experience of the estimator may be different from
planned value of each activity based on experience from similar the project being experienced. The method presented in this paper
estimates contingency using Monte Carlo simulation by assigning a
past projects. After running Monte Carlo simulation, the total con-
probability distribution to each activity and selecting an appropriate
tingency is calculated. Cost contingency is allocated to each activ-
confidence interval.
ity based on the activity’s contribution to the overall cost variance
Table 7 is a comparative table showing the differences between
of the project. This means that an activity with high uncertainty,
the actual contingency and estimated contingency using the tradi-
high cost (affecting budget), and that lies on the critical path (af-
tional (original) and proposed method, used in the bridge mainte-
fecting the project’s duration) will contribute more towards the cost
nance project. The results show that applying the new method leads
variance of the project and will therefore have a higher share of the
to a more accurate estimation of the cost contingency. This can be
cost contingency, and vice versa. clearly demonstrated as the cost contingency calculated for the
project using the proposed method is 4.2% of the total project cost,
Cost Contingency Management compared to 7.2% cost contingency actually used for the bridge
maintenance project, which can be the difference between winning
From a financial point of view, a project is considered to be doing and losing a tender.
well when the actual updated remaining contingency (AURCP ) is In summary, the following is what differentiates the proposed
more than or equal to the planned updated remaining contingency method from the ones discussed in the preceding review. The pro-
(PURCP ) of the project. The proposed method is very powerful as it posed method includes estimating, allocating, and managing cost
can show how much of the project is over/under budget and which contingency. First, the proposed method is easy to use as it does not
activities to look out for in the future. The new method also recal- require tedious equations or timely data collection (such as inter-
culates the cost contingency allocated to each activity at the end of views and surveys). It also does not require the project manager to
the reporting period. This will allow project managers/owners to have any prior knowledge such as ANN, fuzzy logic, or any other
keep track more frequently and accurately of the total cost of the simulation. Complex models would never be the solution to man-
project. The contingency budget should not be used to cover age cost contingency especially on a construction project. Any
changes in scope; rather, its purpose is to cope with cost increases complex or time-consuming methods will have little added value
resulting from the uncertain nature of some construction activities. for the construction industry. Secondly, the proposed method acts

Table 7. Comparative Table between the Actual and Proposed Method


Items Original method Proposed method
Total project cost excluding contingency $126,500
Total project cost including contingency $135,652 $131,872
Amount of contingency included $9,152 $5,372
Amount of contingency consumed $4,301
Cost contingency estimation method Based on professional experience from similar past Using MCS
projects
Cost contingency allocation method The contingency is used as a global contingency Contingency assigned to each activity individually
(placed at the end of the project) based in the activity’s contribution to the project
variance. The more the activity affects the project,
the higher the amount of contingency assigned to it
Cost contingency management method There is no one particular way for managing cost Managed based on Fig. 1. This method takes into
contingency. The cost contingency is used to any account the complexity of the project and its effect
activity that requires it based on first-come, first- on the total project
used basis. This method does not take into account
the complexity of the activity and how it affects the
total project

© ASCE 04016014-10 J. Manage. Eng.

J. Manage. Eng., 04016014


as an early warning for activities going over budget. It allows to Barraza, G. A., and Bueno, R. A. (2007). “Cost contingency manage-
carefully planning activities based on the past and current spending ment.” J. Manage. Eng., 10.1061/(ASCE)0742-597X(2007)23:3(140),
pattern. Thirdly, the proposed method is adaptable enough to ac- 140–146.
commodate disruptions in the project environment. The project Burroughs, S., and Juntima, G. (2004). “Exploring techniques for
manager can select the required confidence interval. contingency setting.” AACE Int. Transactions, Association for the Ad-
Given the preceding discussion and the results obtained in this vancement of Cost Engineering (AACE), Morgantown, WV, EST3-1–
EST3-6.
paper, our new understanding about cost contingency management
Dey, P., Tabucanon, M. T., and Ogunlana, S. O. (1994). “Planning for
is that there is no particular way assigned for managing cost con-
project control through risk analysis: A petroleum pipeline-laying
tingency. The authors are not claiming that this is the only method project.” Int. J. Project Manage., 12(1), 23–33.
to estimate, allocate, or manage cost contingency in a project, nor Eldosouky, I. A., Ibrahim, A. H., and Mohammed, H. E. (2014). “Manage-
are they claiming that because of the proposed method the pre- ment of construction cost contingency covering upside and downside
sented project the case study finished without using the entire con- risks.” Alexandria Eng. J., 53(4), 863–881.
tingency allocated to it. Gharaibeh, H. M. (2014). “Cost control in mega projects using the Delphi
As a future work, the proposed method can be extended for
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 04/29/16. Copyright ASCE. For personal use only; all rights reserved.

method.” J. Manage. Eng., 10.1061/(ASCE)ME.1943-5479.0000218,


schedule contingency and tested on a real-life project. Another fu- 04014024.
ture objective is combining the proposed cost contingency method Günhan, S., and Arditi, D. (2007). “Budgeting owner’s construction con-
with a new schedule contingency method to create a total contin- tingency.” J. Constr. Eng. Manage., 10.1061/(ASCE)0733-9364(2007)
gency estimation, allocation, and management frameworks. Other 133:7(492), 492–497.
distributions should be examined and its effect on the estimating Harper, C. M., Molenaar, K. R., Anderson, S., and Schexnayder, C. J.
and managing contingency should be closely observed. (2013). “Synthesis of performance measures for highway cost estimat-
ing.” J. Manage. Eng., 10.1061/(ASCE)ME.1943-5479.0000244,
04014005.
Notation Idrus, A., Fadhil Nuruddin, M., and Rohman, M. A. (2011). “Development
of project cost contingency estimation model using risk analysis and
The following symbols are used in this paper: fuzzy expert system.” Expert Syst. Appl., 38(3), 1501–1508.
AC = actual cost; Lhee, S. C., Flood, I., and Issa, R. R. A. (2014). “Development of a two-
ARC = actual remaining contingency; step neural network-based model to predict construction cost contin-
AURC = actual updated remaining contingency; gency.” J. Inf. Technol. Constr., 19, 399–411.
CC = cost contingency; Linstone, H. A., and Turoff, M. (1975). The Delphi method: Techniques
CV = cost variance; and applications, Addison-Wesley, Reading, MA.
ECS = expected contingency spent; Microsoft Project 2013 [Computer software]. Microsoft, Redmond, WA.
PURC = planned updated remaining contingency; Oracle Corporation. (2012). “Sensitivity chart views.” 〈http://docs.oracle
PV = planned value; .com/cd/E17236_01/epm.1112/cb_user/frameset.htm?ch07s04s03
.html〉 (Jul. 9, 2015).
RC = remaining contingency;
Oracle Crystal Ball [Computer software]. Oracle, Redwood Shores,
RPV = remaining planned value;
CA.
TC = total cost; Project Management Institute. (2013). A guide to the project management
TRC = total remaining cost; and body of knowledge (PMBOK guide), Newton Square, PA.
α = confidence interval chosen to represent an acceptable Smith, G. R., and Bohn, C. M. (1999). “Small to medium contractor con-
project risk. tingency and assumption of risk.” J. Constr. Eng. Manage., 10.1061/
Note: All of the aforementioned notations, with the exception of (ASCE)0733-9364(1999)125:2(101), 101–108.
α, should be followed with a subscript either A or P. Any variable Terje Karlsen, J., and Lereim, J. (2005). “Management of project contin-
with a subscript A refers to the individual activity, while a variable gency and allowance.” Cost Eng., 47(9), 24–29.
with subscript P refers to the total project. Touran, A. (2003). “Probabilistic model for cost contingency.” J.
Constr. Eng. Manage., 10.1061/(ASCE)0733-9364(2003)129:3(280),
280–284.
References Turskis, Z., Gajzler, M., and Dziadosz, A. (2012). “Reliability, risk
management, and contingency of construction processes and projects.”
Baccarini, D. (2004). “Accuracy in estimating project cost construction J. Civ. Eng. Manage., 18(2), 290–298.
contingency—A statistical analysis.” Int. Construction Research Conf., Uzzafer, M. (2013). “A contingency estimation model for software
RICS Foundation, Headingley Stadium, U.K. projects.” Int. J. Project Manage., 31(7), 981–993.

© ASCE 04016014-11 J. Manage. Eng.

J. Manage. Eng., 04016014

You might also like