Professional Documents
Culture Documents
42 PLACING AND MIXING OF CEMENT INTO 60 days Mon 21/04/14 Fri 20/06/14 40FS+2 days
GRAVEL
43 CURING 75 days Mon 28/04/14 Sat 12/07/14 42SS+7 days
44 BITUMINOUS SURFACE 175 days Wed 16/07/14 Wed 07/01/15
TREATMENT/BITUMINOUS MIXES
45 SPRAYING OF MC 30 21 days W ed 16/07/14 Wed 06/08/14 43FS+4 days
46 SPRAYING OF K1-60 21 days Sun 10/08/14 Sun 31/08/14 45FS+4 days
47 PLACING OF 35 MM APHALT CONCRETE AS 90 days Sun 10/08/14 Sat 08/11/14 46SS
BINDER COURSE
48 PLACING OF 25 MM APHALT CONCRETE AS 90 days Thu 09/10/14 Wed 07/01/15 47SS+60 days
WEARING COURSE
49 ROAD FURNITURE 40 days Sun 11/01/15 Fri 20/02/15
50 PAVEMENT MARKINGS 40 days Sun 11/01/15 Fri 20/02/15 48FS+4 days
51 DAYWORKS 450 days Mon 02/12/13 Wed 25/02/15
52 DAYWORKS 450 days Mon 02/12/13 Wed 25/02/15
53 VAT 450 days Mon 02/12/13 Wed 25/02/15
54 VAT 450 days Mon 02/12/13 Wed 25/02/15
55 CONTIGENCIES 450 days Mon 02/12/13 Wed 25/02/15
56 CONTIGENCIES 450 days Mon 02/12/13 Wed 25/02/15
Page 1