PROGRAMME OF WORKS FOR THE MALINDI AIRPORT APRON AND RUNWAY 08-26 RESURFACING AND OTHER ASSOCIATED WORKS

ID Task Name Duration Start Finish Predecessors 2014 2015


Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
1 MALINDI AIRPORT APRON & RUNWAY 08-26 450 days Mon 02/12/13 Wed 25/02/15
RESURFACING AND OTHER ASSOCIATED WORKS

2 PRELIMINAIES ITEMS 450 days Mon 02/12/13 Wed 25/02/15


3 MOBILIZATION 28 days Mon 02/12/13 Mon 30/12/13
4 SECURITY AND BOUNDARY FENCING WORKS 206 days Wed 01/01/14 Sat 26/07/14
5 SITE CLEARANCE 60 days Wed 01/01/14 Sun 02/03/14
6 BUSH CLEARING 60 days W ed 01/01/14 Sun 02/03/14 3FS+2 days
7 REMOVAL OF EXISTING FENCE 60 days W ed 01/01/14 Sun 02/03/14 6SS
8 DOZING THE AREA TO MAKE IT FLAT 60 days W ed 01/01/14 Sun 02/03/14 7SS
9 EXCAVATION OF HOLES 60 days Wed 15/01/14 Sun 16/03/14
10 EXCAVATION OF HOLES 60 days W ed 15/01/14 Sun 16/03/14 8SS+14 days
11 EXCAVATION FOR GROUND BEAMS 60 days W ed 15/01/14 Sun 16/03/14 10SS
12 INSTALLATION OF PRE CAST CONCRETE 90 days Wed 29/01/14 Tue 29/04/14
POSTS
13 INSTALLATION OF PRE CAST CONCRETE 90 days W ed 29/01/14 Tue 29/04/14 10SS+14 days
POSTS
14 INSTALLATION OF GALVANIZED WIRE MESH 90 days Wed 12/02/14 Tue 13/05/14

15 INSTALLATION OF GALVANIZED WIRE 90 days W ed 12/02/14 Tue 13/05/14 13SS+14 days


MESH
16 CONCRETING OF BEAM 90 days Wed 26/02/14 Tue 27/05/14
17 CONCRETING OF BEAM 90 days W ed 26/02/14 Tue 27/05/14 15SS+14 days
18 INSTALLATION OF SECURITY GATES 30 days Tue 27/05/14 Thu 26/06/14
19 INSTALLATION OF SECURITY GATES 30 days Tue 27/05/14 Thu 26/06/14 17
20 AIRSIDE AND LANDSIDE CONCRETE WORKS 308 days Wed 15/01/14 W ed 19/11/14 4SS
21 SITE CLEARANCE 45 days Wed 15/01/14 Sat 01/03/14
22 SITE CLEARANCE 45 days W ed 15/01/14 Sat 01/03/14 6SS+14 days
23 TERMITES FUMIGATION 45 days W ed 15/01/14 Sat 01/03/14 22SS
24 EXCAVATION AND FILLING FOR STRUCTURES 208 days Wed 29/01/14 Mon 25/08/14

25 EXCAVATIONS AND DISPOSAL 60 days W ed 29/01/14 Sun 30/03/14 22SS+14 days


26 PROVISION OF FILL MATERIAL 90 days W ed 05/02/14 Tue 06/05/14 25SS+7 days
27 HAND PACKING 60 days Thu 05/06/14 Mon 04/08/14 26FS+30 days
28 PROVISION OF QUARRY DUST 14 days Mon 04/08/14 Mon 18/08/14 27
29 ANTI TERMITE TREATMENT 7 days Mon 18/08/14 Mon 25/08/14 28
30 CONCRETE WORKS AND DRAINAGE WORKS 294 days Wed 29/01/14 Wed 19/11/14

31 EXCAVATIONS 60 days W ed 29/01/14 Sun 30/03/14 25SS


32 CONSTRUCTION OF MANHOLES 28 days Mon 25/08/14 Mon 22/09/14 29
33 INSTALLATION OF FORMWORK 60 days Mon 01/09/14 Fri 31/10/14 32SS+7 days
34 LAYING OF CONCRETE AS THE SURFACE 60 days Tue 16/09/14 Sat 15/11/14 33SS+15 days
BED
35 LAYING OF CONCRETE FOR THE 60 days Sat 20/09/14 W ed 19/11/14 34SS+4 days
DRAINAGE STRUCTURES
36 SURFACING ON RUNWAY 308 days Wed 05/03/14 Wed 07/01/15 20SS
37 GRAVEL WEARING COURSE 45 days Wed 05/03/14 Sat 19/04/14
38 PLACING AND MIXING GRAVEL W EARING 45 days W ed 05/03/14 Sat 19/04/14 22FS+4 days
COURSE
39 NATURAL MATERIAL SUB BASE AND BASE 45 days Wed 05/03/14 Sat 19/04/14

40 PLACING AND MIXING OF GRAVEL 45 days W ed 05/03/14 Sat 19/04/14 38SS


41 CEMENT TREATMENT 82 days Mon 21/04/14 Sat 12/07/14

42 PLACING AND MIXING OF CEMENT INTO 60 days Mon 21/04/14 Fri 20/06/14 40FS+2 days
GRAVEL
43 CURING 75 days Mon 28/04/14 Sat 12/07/14 42SS+7 days
44 BITUMINOUS SURFACE 175 days Wed 16/07/14 Wed 07/01/15
TREATMENT/BITUMINOUS MIXES
45 SPRAYING OF MC 30 21 days W ed 16/07/14 Wed 06/08/14 43FS+4 days
46 SPRAYING OF K1-60 21 days Sun 10/08/14 Sun 31/08/14 45FS+4 days
47 PLACING OF 35 MM APHALT CONCRETE AS 90 days Sun 10/08/14 Sat 08/11/14 46SS
BINDER COURSE
48 PLACING OF 25 MM APHALT CONCRETE AS 90 days Thu 09/10/14 Wed 07/01/15 47SS+60 days
WEARING COURSE
49 ROAD FURNITURE 40 days Sun 11/01/15 Fri 20/02/15
50 PAVEMENT MARKINGS 40 days Sun 11/01/15 Fri 20/02/15 48FS+4 days
51 DAYWORKS 450 days Mon 02/12/13 Wed 25/02/15
52 DAYWORKS 450 days Mon 02/12/13 Wed 25/02/15
53 VAT 450 days Mon 02/12/13 Wed 25/02/15
54 VAT 450 days Mon 02/12/13 Wed 25/02/15
55 CONTIGENCIES 450 days Mon 02/12/13 Wed 25/02/15
56 CONTIGENCIES 450 days Mon 02/12/13 Wed 25/02/15

Task Summary External Milestone Inactive Milestone Duration-only Start-only Deadline


Project: NIGHT SHIFT
Split Project Summary Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Date: Tue 27/08/13
Milestone External Tasks Inactive Task Manual Task Manual Summary Progress

Page 1